uta airport trax line north temple viaduct & construction phasing

12
UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

Upload: eddie-burchell

Post on 31-Mar-2015

215 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

UTA Airport TRAX LineNorth Temple Viaduct &

Construction Phasing

Page 2: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

North Temple Viaduct Detours

North Temple viaduct closure and construction begins April 18. Construction will take 18 months

Alternative A• Westbound detour – 300 West to 600 North to 900 West

Alternative B• Eastbound detour – 900 West to 400 South to 300 West

Page 3: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

UTA Bus Routes

UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com

Page 4: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

When Is the Airport Line Being Built?

Page 5: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

North Temple Construction - Phases

Phase 1Phase 2

Phase 3Phase 4

Phase 5

Page 6: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

North Temple Phasing – Spring 2010

North Temple Phasing – Spring/Summer 2010

Page 7: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

North Temple Phasing – Summer/Fall 2010

North Temple Phasing – Spring 2011

Page 8: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

North Temple Phasing – Summer 2011

Page 9: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

Downtown Phasing – Spring 2012 – Fall 2012

Page 10: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

Communications and Marketing

• Weekly construction updates• Regular one-on-one visits to corridor properties• Comprehensive marketing plan

• Milestone events • Direct mail• Radio• Billboards• Print

• Looking for others ways to communicate construction information

Page 11: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

Airport Construction & Viaduct Open House

Thursday, March 185 p.m. to 7 p.m.

UTA FrontLines Headquarters669 West 200 South

Page 12: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

Thank youMatt Sibul, UTA Airport TRAX Project Manager: 801-236-4731

Chad Saley, UTA Public Involvement: 801-287-2290Bill Knowles, Downtown Salt Lake Ombudsman: 801-580-2626

24-Hour Construction Issue Hotline: 1-888-800-8854www.rideuta.com