USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26 th July to 8 th August, 2010 Central Institute for Rural Electrification of Rural Electrification Corporation Ltd (A Govt. of India) Hyderabad, Andhra Pradesh, India

Upload: duongthuan

Post on 08-Apr-2018

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY

(SARI/ENERGY)

26th July to 8th August, 2010Central Institute for Rural Electrification of

Rural Electrification Corporation Ltd(A Govt. of India)

Hyderabad, Andhra Pradesh, India

Page 2: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

DISTRIBUTION SYSTEM PLANNING

Page 3: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Distribution System

• substations• transformers• circuit breakers• feeders• sectionalizing switches• capacitor banks• voltage regulators• DSGs• customers

- HT customers- LT customers

Generation System

Transmission System

Primary circuits

Generating Plant

Step-up transformers

Circuit breakers

Transmission System

Transformers in Bulk power substations

Solar orWind Sources(100KW to 1MW)

One-phaselateral feeder

DistributionTransformer

DispersedStorage and generation (DSG)

VoltageRegulator

Capacitorbank

Sub-transmissionsystem

Distributionsubstation

Three-phasePrimary feeders

Battery orFuel cells,1 to 25 MW

DSG Sectionalizing switch

DSG PhotovoltaicPower supply, up to 100 KW

Home

Typical Power System

Page 4: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Power System connectivity

33 kV lines

220kV Lines

EHV substations

Distributionsubstations

17.6/220 kVSub-station

220/33 kVSub-station

33/11 kVSub-station

Industry at 33 kV

11 kV lines (feeders)

DistributionTransformer

11/ 0.4 kV

Industry at 11 kVCustomers(Domestic, Commercial, Agricultural)

Page 5: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

STRUCTURE OF POWER SYSTEM

Power System Components: Grid substation(GSS): The power from Transmission

network is delivered to Sub-Transmission networkafter stepping down the voltage to 66 kV or 33kVthrough220/110/66/33 kV Grid substation

Sub-transmission Network: Power is carried at 66 kVor 33 kV by Overhead lines or Underground cables

Primary Substation(PSS): Power is stepped down by66/11 kV or 33/11 kV transformersto11kv.In somecases power is stepped down from 132/110 kV to11kV

Page 6: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

STRUCTURE OF POWER SYSTEM (CONTD…)

Primary Distribution Feeders: Power isdelivered from PSS through primary feedersmainly at 11kV to Various DistributionTransformers

Distribution Substation(DSS): Power isfurther stepped down by DistributionTransformers to utilisation Voltage 400 V

Secondary Distribution network:It carriespower from DSS at 400V(230V single phase)to various consumers through overheadlines/UGcables/service wires

Page 7: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING OBJECTIVES Planning and design of distribution system

to meet load growth and to ensure Voltage conditions to be within

permissible levels Optimum energy losses Least overall cost system

Improvement in reliability/security of power supply

Improvement in quality of power supply Safety of operation Evolving a scientific automation and load

management system Better customer service

Page 8: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING PHILOSOPHY The approach for planning of distribution

system should be based on the following Delivering bulk supply of electricity

as near to the load centres as possible Consumers affected due to outage to

be few in the area, if at all it becomesinevitable

Formation of ring circuit and radialcircuit or combination of bothdepending on the technical andeconomic requirement of the systemto enhance reliability of powersupply.

Page 9: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING PROCESSSTRATEGY

Short Term PlanLong Term Plan

Page 10: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

SHORT TERM PLAN In the prevaling situation of mounting losses,

priority attention to be given to reduction oflosses- technical & commercial

Short term plan shall cover the measuresrequired for immediate improvements andreduction of losses

Works identified as short term shall be completedwithin1-2 years period

Page 11: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

WORKS UNDERSHORT TERM PLAN Network reconfiguration Network Reconductoring Installation of LT & 11 kV Capacitors Installation of Voltage Boosters Additional DTRs(DSS) Shifting DTRs to Load Centres Load Balancing ON ALL Three Phases Improvement of joints in the network Refurbishment/replacement of old/obsolete

Equipment

Page 12: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LONG TERM PLAN-Area for planning purposes may be circle or district• Steps involved in preparation of the plan:1. Data collection/compilation of existing system.- Category wise number of consumers and

connected load - Peak demand MW/VAR- simultaneous and non

simultaneous- Annual energy consumption - Geographical map of the area depicting T&D

system(GIS Mapping)

Page 13: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

DATA COLLECTION/COMPILATION OFEXISTING SYSTEM.(CONTD..)

- Sub-transmission system- Distribution system- Operational parameters- Electrical network details- Single line diagrams and equipment parameter

data- Load Data- System load factor and Loss load

factor(LF&LLF)- Data validation

Page 14: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LONG TERM PLANNING (CONTD…)

2. Analysis of existing Transmission, sub-transmission and Distribution systems

Voltage variation - Voltage at each node/bus section- % voltage variation w.r. t rated input voltage- Whether Voltage variation within permissible

limit Peak power loss/Energy loss of each system

element for arriving at total technical losses in the circle

Page 15: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LONG TERM PLANNING (CONTD…)

Computation of commercial losses Assessment of inadequacies of the existing ST& D

system along with the identification of - Overloading of transformers- Overloading of lines- Requirement of reactive compensation Inadequacy of the back up transmission system Security and reliability of power supply

Page 16: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LONG TERM PLANNING (CONTD…)

3. Existing T&D Losses:The technical losses are obtained from thesimulation and analysis of the network elementwise. From the total losses obtained from theenergy balance sheet, technical losses obtainedabove will be subtracted to find the commerciallosses of the area under study.

Page 17: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LONG TERM PLAN (CONTD…)4. Load Forecast As the long term plan caters to the load growth of

5-7 years, The important step in the planningprocess is LOAD FORECAST.

The Distribution System planning Involves sitingof substations, routing of feeders and many otherdecisions relating to both locations and amountsof capacity additions

Therefore Distribution Load forecast refers toforecast of geographical locations as well asquantum of future load growth.

Page 18: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAST(CONTD….) The Distribution Load forecast of urban areas is

relatively more complex due to:- high density-high growth rates-Variation in density in a small

geographical area -Rapid transition of suburban area from Rural

to urban Characteristics

Page 19: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAST(CONTD….) Three step procedure involved in entireload

Forecast are:-Analysis of past trends of growth in

Electricity Demand and EnergyConsumption

- System load Forecast for the entire study area

- Spatial or small area load forecas viz.,Divide the utility service area into sufficiently

large number of small areas and forecast for eachsmall area

Page 20: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAST(CONTD….)Trend Analysis

Data Required: Category wise number of services Connected Load Energy consumption for the last 5-10 Yrs

Page 21: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAST(CONTD….)

Trend Parameters Evaluated from analysis of load growth:

Growth rate of energy year wise and cumulative growth rate of energy for the period

Share of electrical energy consumption among different sectors year wise and the average for the period

Energy consumption per service year wise and the average for the period

Page 22: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAST(CONTD….) Growth rate of service connections year wise and

the cumulative growth rate for the period Connected load per service connection year wise

and the average during the period

Page 23: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…) System Load Forecast Techniques Techniques Based on Extrapolation

This technique involves fitting a trend curve to the basic historical data, using method of least squares

Techniques Based on Co-relationThis technique relates the system demand to various demographic and economic factors such as population, value added, net domestic product, etc

`

Page 24: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…) Enduse Method

In this method the demand of each category ofconsumer is assessed and summed up to arrive atthe total consumption

Power utility may adopt end-use technique tocompute the demand projection of eachdistribution circle for horizon year(say 5 years).The demand for energy is estimated for eachcategory of consumption taking into accountrelevant parameters such as

Page 25: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)number of consumers, connected load, annualrate of energy consumption per consumer or perkW of connected load, past trends etc. The peakdemand is worked out from the totalconsumption adopting appropriate annual loadfactors keeping in view the nature andcomposition of loads and also considering the lossfigures.

Page 26: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)Estimation of Agricultural consumption/Rural load :The agricultural consumers are largely unmetered and a correct assessment of energy consumption is difficult. The agricultural consumption depends on three factors:-

Number of pump sets Capacity of pump Number of working hours in a day

Page 27: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)Methods used to assess the agricultural consumption:

Sampling:Average consumption per H.P. is calculated from sampling techniques

Annual consumption:Average load factorX total connected kW of pump sets X8760 units

Consumption/irrigation/hectare as per studies byindependent agencies:

Total consumption per year=Consumption for one irrigation perHectare X number of irrigations peryear X total land under irrigation in hectares

Total consumption per year = Consumption for oneirrigation per hectare x number of irrigations peryear x total land under irrigation in hectares.

Page 28: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)Spatial load forecast: The forecast of loads and their locations, known as

spatial or small area load forecast, is very important forDistribution system planning. For optimal sitting of newsubstation/augmentation of capacity of existing S/S andeconomical reinforcement of existing networks, thespatial load forecast has to be adopted

For this purpose, the total area is divided into a numberof small areas and the loads in each area are forecasted.How these small areas are

Page 29: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)Constituted, is very important because it forms the basis

for codification of customer and distribution systemequipment like transformers, capacitors, boosters forthe purpose of proper operation and maintenance ofrecords.

One of the widely used method is to divide the area intosquares of 0.5 or 1 km size, known as grid co-ordinatesystem. The main advantage of this method is thatapplication of optimization techniques for distributionsystem planning is relatively simple, as the area of cellis constant

Page 30: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)The disadvantage of this method is that the areas do notcoincide with administrative units of governmentagency and collection of economic and general data isdifficult

The other method is known as random area methodwhere each small area constitutes an administrativeunit of Government agencies. Hence, the economic andgeneral data for the small area will be readily availablefrom data records maintained and collected byGovernment. The main advantage of this method is thateach area is clearly identified and

Page 31: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)with administrative unit of Government. Thedisadvantage of the method is the application ofoptimization techniques is complex. Considering thedata availability etc., it is suggested to adopt uniformarea model for urban areas and random area model forsuburban or rural area around the town.

The small area forecasting can be broadly classified astrend, multivariate and land use based simulationmethods. The objective of spatial load forecast is toallocate among the small areas the growth of demand or

Page 32: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

LOAD FORECAT (CONTD…)energy consumption/the number of customers computedin system forecast for the total area. The load forecastsmade for small areas have to be adjusted taking intoaccount the specific growth rates and othercharacteristics of each small area.

Page 33: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

5.PLANNING CRITERIA 1. The voltage variations in 33 kV and 11kV feeders should

not exceed the following limits at the farthest end underpeak load conditions and normal system operationregime.

Above 33kV (-) 12.5% to (+) 10%Up to 33kV (-)9.0% to (+)6.0%Low voltage (-)6.0% to (+) 6.0%

In case it is difficult to achieve the desiredvoltage especially in Rural areas, then11/0.433kV distribution transformers(in place ofnormal 11/0.4kV DT’s) may be used in theseareas

Page 34: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)Adequate power supply at normal voltage shall beavailable at main grid sub-stations to meet thesystem demand. The transformation capacity at theGrid-substations shall be such that the systemdemand shall be met even with the outage of thelargest capacity transformer.

2. Every primary Receiving sub-station, subject to spaceconstraints shall be provided with at least twotransformers having either sufficient cyclic loadingcapacity to supply the sub-station maximum demandor sufficient 11kV system inter-connections to enablethe maximum demand in the area to be met in theevent of outage of single largest capacity transformer.

Page 35: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)3. Every 33/11 kV substation should preferably

have at least two incoming feeders from twodifferent sources from reliability considerations.If both the 33kV incoming feeders to 33/11 kVsub station(s/s) emanate from the samesource(sub-station) then each feeder shouldsupply independent sections of 33/11 kV s/s, thetwo sections being isolated from each other bybus coupler or isolators. This results in increasedreliability. However, if one of 33kV feeders hasmuch longer route, the shorter feeder maynormally feed the 33/11 kV s/s and the other onemay be called upon to supply in emergency

Page 36: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)4. The sitting of primary substation i.e.

33/11 kV substation should be on thebasis of spatial load forecast,demographic factors, space availability,right of way considerations, existingnetwork configuration etc.

5. Power transformers: The preferredtransformer capacities for Primary sub-stations(i.e. 66/11 kV or 33/11 kV)should be of 6.3,8,10,16 MVA for urbanareas and 1.6,3.15,5 MVA for rural areas

Page 37: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)6. Distribution transformers: The distribution transformers to

be installed in the circle should preferably have standardrating of 25,50,63,100,250,315,400,500 and 630 kVA. Thehigher capacity(i.e. larger than 250 kVA) shall be used forconcentrated load or area with high load density and lowercapacity(less than 100 kVA) may be used for Rural areas.In high rise building having concentrated loads, highercapacity distribution transformers such as 1000kVA maybe use. 33/0.415 kV distribution transformer of appropriateratin-630kVA,1000kVA,2000kVA,may also be used basedon techno-economic considerations. Lower ratings could beused for rural areas/far flung urban areas. Standardizationof ratings would help in achieving reduction in inventoryfor purposes of procurement & maintenance and reductionin price on account of bulk purchases.

Page 38: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)The distribution transformers in urban areasshould operate at an initial capacity factor ofabout 65%-75% of their rated capacity andwould have to be augmented when themaximum demand on the transformer is nearits rating. In case of Rural areas, a higherloading based on the assessment of loadgrowth could be considered for adoption.

7. Choice of conductor: Standard conductor sizesshould be adopted for 66kV,33kV,11kV and LT(400 V)

Page 39: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

PLANNING CRITERIA (CONTD…)lines. ACSR and AAC conductors foroverhead lines and XLPE and PVC/PILCcables can be used. Most power utilitiesuse ACSR on account of priceconsiderations although AAAC conductorsare lighter in weight, have a longer life onaccount of higher resistance to corrosion.The characteristics of conductors/cablesbeing used in distribution systems aredetailed. As a guideline the sizes ofconductors/cables indicated below could bepreferred:

Page 40: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Rated System Voltage Conductor Type33 Kv ACSR panther, wolf, Dog or

equivalent AAC, 3 core XLPE cables of 150,185,240,300 and 400 sq.mm

11kV ACSR Dog, Racoon, Rabit or equivalent AAC, Equivalent aerial Bunched cables(ABC)3-core XLPE cables of sizes 120,150,185,240 & 300 sq.mm

LT ACSR Dog, Racoon, RabbitAAC, ant, Grass hopper, wasp or equivalent AAAC.Equivalent aerial Bunched cales(ABC) 3 ½ core or 4-core PVC cables of 95,120,150,185,240 & 300 sq.mm

Page 41: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

In the choice of conductor size, the parameters to beconsidered are the thermal limit, voltage regulation andeconomic loading based on capitalized cost of losses. Thefirst two parameters are technical requirements and haveto be ensured. The loading of the lines should preferably bekept as near to the economic loading level of the conductoras feasible. This approach could lead to requirement ofhuge capital cost. Therefore optimization of conductor sizeafter ensuring voltage regulation and Thermal limits hasto be done considering the cost of decremental losses vis-athe incremental cost involved.

Till computer software facilities are established in thecircle, KVA-km concept may be used to decide the size ofconductor and length of feeder. However, it would bedesirable to limit length of LT feeder to a minimum.

Page 42: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Based on the experience and condition prevailing,the length of LT feeder should not exceed about 400meters. For higher voltage levels, feeder lengthshould be decided based on studies.

8. The 11kV feeders shall generally not be long undernormal conditions and shall as far as possible feedonly local areas. The 11 kV feeders shall be soplanned that wherever the size of the conductor isinadequate or the voltage drop exceed theprescribed limit, the existing conductors shall eitherbe replaced by higher size conductor or load on thefeeder shall be reduced by addition of new feeders.Existing.. Lines should be utilized to the maximumextent.

Page 43: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

9. Selection of voltage vis a vis size of conductor:Most of the power utilities use 0.4kV,11kV and33kV as distribution voltages depending uponquantum and location of load. The higher thevoltage more expensive is the system in terms ofinvestment cost. However, it would be less interms of total owning cost by way of capitalizationof losses. The most economic voltage level wouldhave to be determined through tech-economicstudies from voltage regulation considerations,loading limit of conductor, cost of losses andinvestment cost consideration.

Page 44: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

In order to avoid proliferation of 66kV or 33kVsub-stations, overloading of network, poorvoltage regulation etc. the following criteria issuggested for releasing new bulk loads.

However, the same can be modified by theconcerned utility as per the loading condition inthe network.

o Maximum Demand of upto 70kVA to besupplied at low voltage.

o Maximum Demand of between 70 kVAand 1500 kVA to be supplied at 11kV

Page 45: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

o Maximum Demand between 1.5 MVA and 5MVA to be supplied at 33kV

o Maximum Demand of more than 5 MVA to besupplied at 66kV(or higher voltage)Separate 33kV/11 kV feeders shall be laid formajor industrial consumers, In case or ruralareas, separate feeders, as far as possible, shallbe provided

11. Customer Substation:- A large customer(generally over 5MW) may request specialservice for his needs. In such a case.a) one source feed and the standard substationdesign(not including switch gear) shall beprovided

Page 46: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Enhanced power options should be atcustomers expense. These include alternatefeeds and any additional equipment, such asCBs/switches, additional redundanttransformers etc. These options require acontract that must be coordinated with bothDistribution Services and Electric planning

12.The power factor of the system wouldpreferably be not less than 0.95 at 11 kVlevel.

Page 47: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

13. The level of security of supply to be providedis a matter of subjective judgment for thepower utility. Higher the level of security,higher would be the cost. The highest degreeof security is obtained when a sub-transmission system is operated in closedring but this method requires an expensiveprotection system. Operation is morecomplicated and this system should berestricted to very densely loaded city centresor VIP areas where security of supply isessential. More common arrangementrequiring less of investment would be anopen ring system.

Page 48: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

For industrial consumers, it may be appropriateto provide an alternatives source of supply byusing an open ring circuit for 66/33kV and 11kVconsumers with the least possible restorationtime. In case of important low voltageconsumers, it may be proposed to providealternate source of supply from adjacentDistribution transformer.

14 Technical loss levels: Acceptable technical losslevels are subject to the economic factors suchas costs of power and energy, cost of equipmentand discount rates rather than purely ontechnical factors.

Page 49: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

However target levels and maximum tolerable loss levels foreach voltage level on the system with a view to meet theeconomic loss performance may be taken as shown below.

System components Level for peak power losses Target level %

Maximum tolerable %

(i) Step up transformer and EHV transmission system

0.50 1.00

(ii) Transformation to inter- mediate voltage level, transmission system & step down to sub-transmission voltage level.

1.50 3.00

(iii) sub-transmission system and step-down to distribution voltage level

2.25 4.50

(iv) Distribution lines and service connection

4.00 7.00

Total power losses 8.25 15.50

Page 50: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

15. Maximum fault levels: The three phase fault levels maynot exceed the following except where the system isnearer to the generating source where actual shortcircuit value may be used to decide switchgearspecifications:

i) 33kV systems 750MVAii) 11kV system 350 MVA(urban areas)

250 MVA(rural areas)

16. Harmonic distortion: Harmonic distortion is causeprincipally by non-linear loads such as rectifiers and arcfurnaces and can effect the operation of a supply systemand can cause overloading of equipments such ascapacitors, or even resonance with the system leading tooverstressing(excessive voltage& current).Other effectsare interference with telephone circuits andbroadcasting, metering errors overheating of rotatingmachines due to increased iron losses(eddy currenteffects),

Page 51: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

overheating of rotating machines due to increasediron losses(eddy current effects), overheating ofdelta connected winding of transformer due toexcessive third harmonics or excessive excitingcurrent.

The suggested total harmonic voltage distortionand individual harmonic voltage distortion atpoint of common coupling areTotal Harmonic Distortion(THD) =

9% in 0.4 ≤45kV4% in 45<U ≤ 220kV3% in U>220kV

Page 52: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

17. Sub-station layout: Before deciding the rating of theequipment in a sub-station it is necessary to prepare aschematic/lay out diagram of the substation. Thereare a number of arrangements dependent uponsystem voltage, position of the sub-station in thesystem, flexibility, reliability of supply and cost. Thefactors to be considered while deciding the layout are

o It shall be possible to carry out equipmentmaintenance without interrupting the entiresupply

o As far as possible there should be alternatearrangements in the event of outage of any oneimportant item of equipment

o The layout should be economical and should nothinder future expansion.

Page 53: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

single bus bar, single bus bar with bus sectionalizer,double busbar. Double bus bar with double breakerscheme and mesh scheme and mesh scheme are thevarious types of layouts being adopted. A layoutwhich is most economical, satisfies technicalrequirements as per actual site conditions may beadopted. Generally 33/11 kV s/s with single busbsrand sectionalizer in between on the 33 kV as well as11kV sides is being adopted.

18. To improve the operational flexibility, minimizerestoration time of power supply and to preventoverloading of lines and transformers in real timemode, modern features such as DistributionAutomation may be incorporated.

Page 54: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

19. A mobile substation could be used as backup ofdistribution substation in the event of a transformerfailure. Where a mobile substation cannot be provided tofeed the total normal load of the failed transformer, theremust be adequate tie capacity available to serve theremainder of the transformers normal load form othersources. The service by back up means must be capable ofmaintaining normal voltage levels at the load forindefinite lengths of time

20. The overall planned system subject to meeting thetechnical requirement for supplying quality and reliablepower supply to the consumers should be the leastcost(considering the capital cost of proposed works andcapitalizing the cost of losses over the life of theequipment out of the various alternatives considered.

Page 55: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

6. UPGRADATION/STRENGHENING OF THE SUB-TRANSMISSION AND DISTRIBUTION SYSTEMSWith substantial increase in load demand expected inthe plan period, the system would needstrengthening and augmentation to ensure deliveryof power to the consumers at proper voltage and forreduction of losses to a reasonable level. For thedevelopment of the system, the spatial load demandare worked out and imposed on the existing system toassess the inadequacy of the system for meeting thedemand in the horizon year. This systemaugmentation/strengthening is then worked out tocover the inadequacy of the existing system to meetthe proposed demand as well as to identify theconstraints in the back up system.

Page 56: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

TRANSMISSION (BACK UP SYSTEM)The existing distribution network is supplied by 220,132,66and 33 KV substations. For Sub-transmission &Distribution study, it may be considered that adequatepower supply at normal voltage shall be available formmain Grid sub-stations to meet the system demand.Further, transformation capacity at the Grid sub-stationshall be such that the system demand shall be met evenwith the outage of one of largest capacity transformers.However, if there are any constraints/inadequacy in backup transmission system, the same may be clearly identifiedin the Project report.

Sub –Transmission:The sub –transmission and Distribution system would haveto be expanded to meet the growth in demand. Thefollowing options for expansion of sub-transmission systemwould have to be considered:-

Page 57: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

SUB –TRANSMISSION (CONTD…)i. Augmentation of the transformation capacity at

the existing 66 or 33/11 kV substation.,rearranging/reconfiguring the 66/33 kV feedersby using higher size conductors and orincreasing the number of feeders.

ii. Establishing new 66/11 kv or 33/11 kV sub-stations nearer to the load centres andredistribution the loads between existing andnew sub-stations and feeder strengthening.

iii. Augmenting the transformer capacities at someof the existing sub-stations and establishingnew sub-stations so as to have an evendistribution of load on the substations andcorresponding strengthening and addition offeeders.

Page 58: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

SUB –TRANSMISSION (CONTD…)The location for augmentation/new substations haveto be worked out on the basis of assessment of thearea wise power demand potential. In theory thearea supplied by individual Power sub-station variesas a function of distribution system voltage and loaddensityOnce the radius of operation of the sub-station hasbeen determined from these two factors, new sub-station have to be planned to cater to the loads notcovered by the existing sub-stations. The proposedlocations of the new primary sub-station have to bechosen considering the proximity to the load centreand availability of suitable and adequate site. In thecase of augmentation of existing sub-stations, theavailability of land and feasibility of adding

Page 59: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

SUB –TRANSMISSION (CONTD…)

new transformer/additional lines have to kept inview.planning for sitting of S/S and 11kV trunk and spurfeeder in Rural area should be based on the loadsurvey, and load centres in the village. Thegeographical maps of village/Taluka showing thelocation of well, village streets, clusters, existingdiesel based on industry/cold storage etc. would haveto be plotted ultimately for optimal planning ofnetwork for the rural area.The various options for the sub-transmission systemare evaluated on techno-economic considerations todecide on the final alternative.

Page 60: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

SUB –TRANSMISSION (CONTD…)The load flow studies would give the losses for thevarious alternatives and total cost of eachalternative would then be worked out on the basisof capital cost of each alternative and the cost oflosses.

Evaluation of Various AlternativesThe study of each alternative should be analysedunder normal condition as well as outagecondition. It should be ensured that the networkdoes not experience overloading and the voltagevariation in all the alternatives is withinpermissible limit as indicated in the planningcriteria.

Page 61: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

EVALUATION OF VARIOUS ALTERNATIVES (CONTD…)To evolve the least cost alternative, subject totheir meeting the technical requirements, thetotal owning cost of the various alternativesshould be estimated.After identifying the scope of works andestimation of losses under various alternativesfor Sub-Transmission system, the least costoptimal solution may be worked outconsidering the capital cost of proposed worksand net present worth of peak & energy lossesover the expected life of the equipment.

Page 62: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

EVALUATION OF VARIOUS ALTERNATIVES (CONTD…) Transmission and sub-Transmission system

RequirementThe proposed system details would be indicated asbelow:

• Back up Transmission systema) Augmentation of EHV sub-stationsb) New EHV sub-stationc) Transmission linesd) Reconductoring of EHV lines

Page 63: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

EVALUATION OF VARIOUS ALTERNATIVES (CONTD…) Sub-Transmission system requirement

a) Augmentation of sub-stationb) New Sub-stationc) Sub-transmission line(new)d) Reconductoring of sub-transmission lines

Page 64: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

DISTRIBUTION SYSTEM

Once the sub-transmission system has beenfinalized, the upgradation requirements ofdistribution system have to be identified. Thepeak demand at 66 or 33/11 kV sub-stationwould have to be disaggregated to work out thepeak demand in each feeder and the allocationof demand on the distribution transformerswould be made on the basis of actual loadconnected to the distribution transformer.The voltage regulation and power losses alongeach feeder section up to Distributiontransformer would have to be worked out.Based on the results of studies(using thesoftware),

Page 65: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

DISTRIBUTION SYSTEM (CONTD…)The feeder section requiring reconductoring /additionof new feeder and its conductor size may be Decided. Itmay be ensured that the voltage is within the limit ateach node/distribution transformer.

In addition some new transformers would be requiredand some would have to be augmented. Attemptsshould be made to locate the distribution transformeras near to the load centre as possible. It may notpossible to determine the actual locations where theseare to be installed. However, for the purpose of thescheme expected load growth indications would haveto be considered of determining the number andlocation of the distribution transformers.

Page 66: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

DISTRIBUTION SYSTEM REQUIREMENTThe proposed distribution system details shall coverthe following

i) Augmentation of distribution sub-stationsii) New 11 kV linesiii) Reconductoring 11kV linesiv) New Distribution Sub-stationsv) Reconductoring of LT feedersvi) New LT lines

The requirement of LT line may be worked out onthe basis of detailed study network emanating fromvarious distribution transformers. However, in thebegin the requirement of LT lines may be workedout on the basis of extrapolation results fromstudies of typical distribution transformers

Page 67: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

INSTALLATION OF CAPACITORS

Shunt capacitors are the simplest andcheapest way of managing the reactivepower Agricultural pump sets & LT motiveload are operating at very low power factor(0.6 to 0.7) causing reactive powermanagement and voltage profile problemsin the Systems and thereby increasingsystem losses. It has been realized that theinstallation of LT capacitors close to theconsumer load would-(i) reduce loadcurrent in the LT feeders(ii) reduceoverloading of distribution transformersand 11 kV lines& Backup system.

Page 68: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

INSTALLATION OF CAPACITORS (CONTD…)It is therefore recommended to install:

LT fixed capacitors on Lt side ofdistribution transformer

Pole mounted 11 kV of suitable rating(autoswitchable) capacitorsThe requirement of additional switchedreactive compensation at 220/ 132/66/33/11kV may be decided on system studies

Page 69: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

The proposed system would have to beanalyzed for meeting the load demand inhorizon year so that:

i) Voltages are within permissible limitii) Adequacy of system is establishediii) Losses are within limitsiv) Choice of least cost alternatives

For the analysis of the system, the entiresystem in horizon year would have to bedetailed with load transfers and load sharingso that peak loading of each elements isknown

Analysis of proposed system

Page 70: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Evaluation of technical losses(for proposed systems)

The studies by simulation of the proposedsystem would facilitate in identifying theelement wise losses in the system. The totaltechnical annual average energy losses of theproposed system would be computed usingappropriate load factors at different voltagesin the system and corresponding load lossfactors

Page 71: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

7. Reliability AnalysisIn order to demonstrate the improvement inquality and reliability of supply with theimplementation of project, reliability indicesof power supply in the circle shall beestimated before and after ‘implementationof the project’. These reliability indices canbe assessed as under

Customer Interruption Frequency Index=Total number of Customer InterruptionsTotal number of customers served

Page 72: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

Reliability Analysis (CONTD…)Total number of customer interruption =Sum of no. of customers having no powersupply in each interruption

Customer Interruption Duration Index=Sum of customer Interruption DurationTotal no. of customers served

Sum of customer interruption Duration = sumof No. of customers not having power supplyduration of interruption

Page 73: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

8. TECHNOLOGICAL OPTIONS

Long term proposal should be based on latesttechnology such as:

o Adoption of High voltage Distribution systemo Standardization of construction practices and

operation and maintenance of procedureso Adoption of Distribution Automation

techniques, so as to improve the reliability andsecurity of power supply

o Adoption of Demand side Managementmeasures

o Use of modern and effective equipments likeelectronic meters with remote meter readingsystems, prepayment meters etc..

Page 74: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

TECHNOLOGICAL OPTIONS (CONTD…)o Use of all aluminum alloy conductors, Aerial

bunched/partial insulted LT lines in theft pronearea, XLPE cables

o Low loss transformers viz amorphous coretransformers, Hi-B steel core transformerscompletely self protected transformers, cast resintransformers dry type transformers etc..

o Ring main units, Automatic sectionaliser,autoreclosers, load break switches etc.

o Adoption of management Information systems,Customer relation ship management system etc..

Page 75: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

9. SCOPE OF WORKS AND COST ESTIMATES

o The various works as evolved from system studies as perthe planning criteria as detailed above, which constitutethe long term plan, should be formed up and summarized.

o Detailed Cost estimates should be prepared based on theprevailing market rates both for the material and labour.

o Abstract of cost estimates covering each item of work maybe prepared

o The works have to be phased year-wise as per thecapability of the utility to execute the works and thefinance available.

o The phasing of works shall be decided on the priorityaccorded to a various sub-works depending on the benefitsform each sub-work

Page 76: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

10. FINANCIAL ANALYSIS

o The design and sustainability of projects is to takeinto account the level of incentive for undertaking andmaintaining a project investment. The financialincentive takes the form of the increased income theinvestment generates with the executive of project.

o The following methods are adopted to check thefinancial viability of the projects/schemes

o Benefit cost Ratio: The method is based on lifecycle(25-30 years period) cost benefits.

o The financial analysis is usually done for thelifetime of the project considering the year-wise costsincluding

Page 77: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

FINANCIAL ANALYSIS (CONTD…)o interest, depreciation, operation and maintenance

charges, and the expenditure on additional sale ofenergy ant the year-wise gross benefits including therevenue from additional energy, and cost saving dueto saving in losses. The year-wise net present valueof the net benefits is calculated an the cumulativenet present value of the net benefits is evaluated.

o Internal Rate of Return(IRR): This method calculatesthe rate of interest needed for the present value ofthe returns to be the same as the present value of theinvestment needed. i.e net present value to be zero.This is the point at which the project breaks even.REC specifies the IRR as 15 percent whilesanctioning short-term(seven-year repayment) loanscheme

Page 78: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

FINANCIAL ANALYSIS (CONTD…)o Pay back period: It is the ratio of the

investment to the monetary value of benefitsexpected due to the execution of project. Thismethod does not consider the time value ofmoney and the life of investment after the payback period but this measure used as anindication of the amount of investment’s risk.Acceptable payback period for power utilityprojects range from 1-5 years.

Page 79: USAID / SOUTH ASIA REGIONAL INITIATIVE FOR ... / SOUTH ASIA REGIONAL INITIATIVE FOR ENERGY (SARI/ENERGY) 26th July to 8th August, 2010 Central Institute for Rural Electrification of

11. IMPLEMENTATION OF THE PROJECTS UNDER LONG

TERM PLAN

The project reports prepared for implementationfor long term plans should clearly bring out thevarious preliminary investigation carried outincluding route survey, land acquisition, etc.,

The works proposed under project may be notifiedas per the statutory requirement.

The bar/per-chart for each activity/work involvedfor timely implementation of project may befurnished

The availability/tie-up of funds for implementationof report may be given.