us cms silicon tracker : overview j. incandela university of california santa barbara us cms silicon...
Post on 20-Dec-2015
220 views
TRANSCRIPT
US CMS Silicon Tracker : Overview
J. Incandela
University of California Santa Barbara
US CMS Silicon Tracker Project Manager
Fermilab PMG
April 9, 2004
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 2
Squarks and Gluinos
•SUSY could be discovered in one good month of operation …
The figure shows the q, g mass reach for various luminosities in the inclusive ET + jets channel.
~ ~
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 3
Gluino reconstruction
M. Chiorboli
~
p
p
g~
b~
b
b
l
l
01
~
02
~ l~
Event final state:• 2 high pt isolated leptons OS• 2 high pt b jets• missing Et
~ bb g pp
b~02
01
~
(26 %)
(35 %)
(0.2 %)
llll 01
~ ~
(60 %)
ll
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 4
Tracking
• Efficient & robust• Fine granularity to resolve nearby tracks
• Fast response time to resolve bunch crossings
• Radiation resistant devices
• Reconstruct high PT tracks and jets• ~1-2% PT resolution at ~ 100 GeV
• Tag b jets• Asymptotic impact parameter d ~ 20 m
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 5
Silicon Strips
6 layers of 500 m sensorshigh resistivity, p-on-n
4 layers of 320 m sensorslow resistivity, p-on-n
Blue = double sided
Red = single sided
9+3 disks per end
Strip lengths range from Strip lengths range from 10 cm10 cm in the inner layers to in the inner layers to 20 cm20 cm in the outer layers. in the outer layers.
Strip pitches range from Strip pitches range from 8080mm in the inner layers to near in the inner layers to near 200200mm in the outer layers in the outer layers
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 6
Some Tracker Numbers
• 6,136 Thin wafers 320 μm• 19,632 Thick wafers 500 μm
• 6,136 Thin detectors (1 sensor)• 9,816 Thick detectors (2 sensors)
• 3112 + 1512 Thin modules (ss +ds)• 4776 + 2520 Thick modules (ss +ds)
• 10,016,768 individual strips and readout electronics channels
• 78,256 APV chips• ~26,000,000 Bonds
• 470 m2 of silicon wafers • 223 m2 of silicon sensors
• (thick = 175 m2 + thin= 48 m2)
FE hybrid FE hybrid with FE with FE ASICSASICS
Pitch adapterPitch adapter
Silicon sensorsSilicon sensors
CF frameCF frame
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 7
Our Responsibility
5.4 m
2.4
m
Outer Barrel (TOB)
~105 m2
NEW:End Caps (TEC)
50% Modules for Rings 5 and 6 and
hybrid processing for Rings 2,5,6
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 8
Efficiency, Purity, Resolution
ROD INTEGRATION
AachenKarlsruheStrasbourgZurichWien
PETALS INTEGRATION Aachen
Brussels Karlsruhe
Louvain
Lyon Strasbourg
BrusselsWien Lyon
TEC assemblyTEC assembly
CERN
Frames:
BrusselsSensors:factories
Hybrids:Strasbourg
Pitch adapter:Brussels
Hybrid:CF carrier
TK ASSEMBLYAt CERN
LouvainStrasbourg
Pisa Perugia Wien
BariPerugia
Bari FirenzeTorinoPisaPadova
TIB-TID INTEGRATION
FNAL
UCSB
TOB assembly TIB-ID assemblyAt CERN Pisa Aachen Karlsruhe. --> Lyon
Karlsruhe
Pisa
Sensor QAC
Moduleassembly
Bonding &testing
Sub-assemblies
FNAL
US in the tracker
Integrationinto mechanics
KSU
US carries roughly half of the total production load
FNAL UCSB
UCSB
UCSB
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 10
Outer Barrel Production
• Outer Barrel • Modules
• 4128 Axial (Installed)
• 1080 Stereo (“ “)
• Rods
• 508 Single-sided (“ “)
• 180 Double-sided (“ “)
• US Tasks • All hybrid bonding & test
• All Module assembly & test
• All Rod assembly & test
• Joint Responsibilities with CERN• Installation & Commissioning
• Maintenance and Operation
~20 cm
Modules Built & Tested in US
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 11
Rods & Wheels
0.9 m1.2 m
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 12
End Cap Construction
• Central European Consortium requested US help
• With consent of US CMS and DOE, we agreed to produce up to 2000 R5 and R6 modules
• After 10 weeks UCSB successfully built the R6 module seen above.
• We’re nearly ready to go on R5
First TEC Module Built at UCSB
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 13
The Group• Fermilab (FNAL)
• M. Demarteau, A. Ronzhin, K. Sogut, L. Spiegel, S. Tkaczyk + technicians
• Kansas State University (KSU)• T.Bolton, W.Kahl, R.Sidwell, N.Stanton
• University of California, Riverside (UCR)• Gail Hanson, Gabriella Pasztor, Patrick Gartung
• University of California, Santa Barbara (UCSB)• A. Affolder, S. Burke, C.Campagnari, D. Hale, (C. Hill), J.Incandela, S.
Kyre, J. Lamb, S. Stromberg, (D. Stuart), R. Taylor, D. White + techs.• University of Illinois, Chicago (UIC)
• E. Chabalina, C. Gerber, T. Ten• University of Kansas (KU)
• P. Baringer, A. Bean, L. Christofek, X. Zhao • University of Rochester (UR)
• R.Demina, R. Eusebi, E. Halkiadakis, A. Hocker, S.Korjenevski, P. Tipton• Mexico:3 institutes led by Cinvestav Cuidad de Mexico• Brown is also planning to join
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 14
Recap of this past year
• Problems continued to plague components• US contributions have been critical
• US played major role in finding and fixing a series of flaws• In some cases these problems would have been fatal
• Problems for module components have been addressed (see talks by R. Demina and E.Chabalina)
• Frames and hybrids: Yield and rates are high and rising• Sensors and US involvement
• US identified CM Noise problem with STM sensors• Advocated shifting order to HPK:
• Provided funds for procuring the masks• Insisted order be placed with HPK by end of February –
beyond which we would have delayed HPK deliveries• CMS is Re-qualifying STM now
• Either STM quality reaches HPK standards or remainder of order will be shifted to HPK
• Upshot: no matter what, we achieve very high delivery rates by July
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 15
Adapting to Delays
• But these issues have meant that the schedule has slipped again!• We have lost 6-8 months in FY04 due to this last round of problems
• In parallel with our work to resolve component problems• We underwent a major upgrade of the US production lines in order to
achieve significantly higher production capacity to allow us to recover lost schedule time.
• New and better methods
• More and better tooling and hardware
• Better software and Quality Control
• Both FNAL and UCSB production lines have demonstrated more than 100% increases in stable, high quality module production
• Our production capacity is unprecedented:• CDF Run 2 silicon detector = 750k channels:
• We can produce this many channels in 10 weeks without overtime or extended working weeks.
With overtime we could do this in 6 weeks
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 16
Productivity Enhancements(see talks by White and Spiegel)
• Gantry (robotic) module assembly• Redesigned: more robust, flexible,
easily maintained
• Surveying and QA• Automated use of independent
system (OGP)
• More efficient, accurate, fail-safe
•Module Wirebonding• Fully automated wirebonding
• Faster and more reliable bonding
• Negligible damage or rework
•Taken together:• Major increase in US capabilities
• Higher quality
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 17
Testing & QA (see talk by E. Chabalina)
• US has led in many respects • US testing macros and test stand
configurations now used everywhere
• Critical contributions• Discovered and played lead role in
solution of potentially fatal problems!
• Defective hybrid cables
• Vibration damage to module wirebonds
• Common Mode Noise problem - traced it to ST sensors
• Other Important contributions;
• Problem of Faulty pipeline cells
• Led to improved screening
•Taken together• Averted a disaster
• Resulted in higher quality
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 18
Rod Assembly, Test, Transport(See talks by P. Tipton and J. Lamb)
• US contributions• Designed and built module
installation tools
• Built single rod test stands
• Designed and built and multi-rod burn-in stands
• Will lead in the definition of tests and test methods
• Transportation boxes
• Production• Will build and test ~350 rods
(+10% spares) at each site
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 19
Summary
• CMS is designed to maximize LHC physics• The tracker is one of the main strengths of CMS
• US is making critical contributions• We have (unfortunately) proven to be far more essential to the
success of the CMS tracker project than anticipated
• We have uncovered serious problems• Huge US effort to help find good solutions as quickly as possible.
• Module component problems have been solved
• Sensor issue is dynamic but we have a solution
• We’ve accumulated more delays!
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 20
Upshot
• Schedule has slipped and the project has evolved:• Increased US capacity from 15 modules per day to > 30
• Complete all deliverable modules before the end of FY05
• Delivery of parts crucial
• Rod assembly to keep pace with module assembly
• Final assembly of the wheels at CERN slipping into FY06.
• The costs of an unexpectedly prolonged module and rod production period are being partially offset by use of funds originally allocated for I&C in FY04-05
• Parts are the issue
UCSB CMS Silicon Tracker PMG April 9, 2004, J. Incandela - Overview 21
Schedule of Presentations
1:00 pm Project Overview J. Incandela (UCSB)1:15 pm Fermilab Production Line L. Spiegel (FNAL) 1:35 pm UCSB Production Line D. White (UCSB) video1:55 pm Results from Module Testing E. Chabalina (UIC)2:20 pm Module Components R. Demina (U. Rochester)2:50 pm Coffee Break 3:00 pm Rods J. Lamb (UCSB) video3:20 pm Long-term testing and transportation of rods
P. Tipton (U. Rochester) video3:40 pm Schedule J. Incandela (UCSB)4:00 pm Executive Session E. Temple4:40 pm Closeout5:00 pm Adjourn