US Army Corps of Engineers
BUILDING STRONG®
JOINT FEDERAL PROJECTUPDATE for SAFCA Board
US Army Corps of Engineers
Pam Amie
19 May 2011
BUILDING STRONG®2
PROJECT OVERVIEW
Phase 3: Construction of the Control Structure is currently underway
Phase 4: Chute/Stilling Basin and Approach Channel Designs are
currently underway
Schedule Optimization: Schedule Optimization Task Force (SOTF)
has currently met for three 3-day group sessions to further refine the
auxiliary spillway completion schedule
BUILDING STRONG®3
CONTROL STRUCTURE Granite is currently excavating common
material from the left side (Monolith 5)
and the right side (Monoliths 1 and 2)
To date approximately 65,000 cubic
yards of common material has been
excavated at the site
Production blasting continues 3 to 5
days per week
Blasting and excavation program
currently anticipated to be complete late
Nov of this year
BUILDING STRONG®4
On-Going Construction
BUILDING STRONG®5
Designs for Chute/Stilling Basin and Approach Channel are currently underway
Design teams are looking at strategies to accelerate the designs for earlier award; including the design for the cofferdam
URS completed Phase I barge drilling in the reservoir; Phase II confirmatory drilling under rock plug in support of the construction of the cofferdam for the approach channel excavation is scheduled to start in Nov
Chute/SB and AP Channel
BUILDING STRONG®6
REVISED SCHEDULE
The Schedule Optimizing Task Force completed it's third round of meetings and has given an update briefing to Corps Sacramento District, BoR, and sponsor leadership. The Task Force is continuing to revise the schedule, with risks and costs for each and the team will deliver a final recommendation to Corps, Reclamation and sponsor leadership on 1 June 11. Fully vetted schedule will be completed by 30 June 11.
BUILDING STRONG®7
Points of Contact Beth Salyers, Senior PM for JFP
Pam Amie, PM for JFP
Jerry Hasty, PM Forward for Construction
Angela De Paoli, PM for Permanent Operations Study
Nikole May, PM for Dam Raise