upper ohio-shade nonstructural stakeholder meetings · certified floodplain manager; licensed...

52
September 2016 UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS FLOOD RISK MANAGEMENT USACE Huntington District USACE Nonstructural Flood Proofing Committee Federal Emergency Management Agency Region III Mid-Ohio Valley Regional Council Ohio Silver Jackets

Upload: others

Post on 08-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

September 2016

 

 

UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS

FLOOD RISK MANAGEMENT

USACE Huntington District USACE Nonstructural Flood Proofing Committee Federal Emergency Management Agency Region III Mid-Ohio Valley Regional Council Ohio Silver Jackets

Page 2: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms
Page 3: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

UPPER OHIO-SHADE STAKEHOLDER MEETINGS FOR FLOOD RISK MANAGEMENT

Parkersburg, Wood County, West Virginia; September 14, 2016

Ripley, Jackson County, West Virginia; September 15, 2016

Local Stakeholder Meetings; 2:00PM-3:30PM

Public Workshops / Open House; 4:00PM-7:00PM

Stakeholder meetings conducted by the Ohio Silver Jackets team including, U.S. Army Corps of Engineers (USACE), Huntington District, USACE National Flood Proofing Committee (NFPC), Federal Emergency Management Agency (FEMA) Region III, and Mid-Ohio Valley Regional Council (MOVRC) will provide an overview of various agency programs and authorities and individual risk reduction techniques. These techniques include elevation, wet flood proofing, dry flood proofing, acquisition, relocation, and individual berms and floodwalls. These meetings will also allow for the needs of the Upper Ohio-Shade Watershed to be expressed by local stakeholders in order to identify specific needs and potential opportunities within the watershed.

Topic Time (Minutes) Presenter 1. Silver Jackets Program 15 USACE Huntington 2. USACE Programs and Authorities 15 USACE Huntington 3. Flood Risk and Nonstructural Measures 15 USACE NFPC 4. FEMA Programs and Missions 15 FEMA 5. Overview of MOVRC 15 MOVRC 6. Open Discussion with Q&A 15 All 7. Public Workshop / Open House 180 All

Page 4: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

PRESENTER BIOGRAPHIES STEPHEN O’LEARY, AIA, CFM US Army Corps of Engineers, Huntington District

Mr. O’Leary serves as an Architect/Planner and Project Manager with the Huntington District USACE. Mr. O'Leary's duties include USACE Nonstructural Flood Risk Management SME; USACE Nonstructural Flood Proofing Committee Member; West Virginia Silver Jackets Lead, project manager/team member on the Levee Safety Policy and Procedures Team (LSPPT), developing the new Levee Safety Program Engineering Circular (EC 1110-2-6072); Course owner for the USACE Planning Associates FRM course; Served 15 years in the Planning Branch and 10 years in Engineering and Construction Division as the District's Senior Architect. The majority of his USACE Career has focused on flood risk management studies/reports, implementation of FRM projects and mitigation of flood prone structures. Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms. Combs serves as an Economist and Project Manager with the Huntington District USACE. Ms. Combs’ duties include performing economic analysis on USACE studies; reviewing/ updating levee screening consequences; Ohio and West Virginia Silver Jackets team Co-Lead and LRH representative on the Kentucky Silver Jackets team; provide technical assistance on Floodplain Management Services requests; works with GIS and HAZUS programs; outreach for various USACE programs and authorities including Floodplain Management services, Planning Assistance to States, and Continuing Authorities Program; serves on the Special Emphasis Committee. Ms. Combs has served 8 years with the Huntington District USACE; 4 years in Project Management and 4 years in Planning Branch. Certified Floodplain Manager; Masters in Project Management. ASHLEY STEPHENS, CFM US Army Corps of Engineers, Huntington District Ms. Stephens serves as a Community Planner with the Huntington District USACE. Ms. Stephens’ duties include Ohio Silver Jackets Co-Lead, Lead Planner on Continuing Authorities Program projects, and preparing documentation for assessment of environmental impacts in accordance with the National Environmental Policy Act. Ms. Stephens has served 7 years in the Planning Branch and is a Certified Floodplain Manager. Ms. Stephens obtained her Masters of Science in Geography.

Page 5: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

MATTHEW MCCULLOUGH Federal Emergency Management Agency, Region III Matt McCullough is a Community Planner with FEMA Region III; where he has worked in Mitigation’s Risk Analysis Branch since 2010. He has technically assisted and approved multiple Local and State Hazard Mitigation Plan’s throughout Region III. He gained his first hazard mitigation planning field experience during the Severe Storms, Flooding, Landslides and Mudslides of WV-DR 1696. He has also assisted in the RiskMAP process during Discovery and Action Collection. FRED RADER Community Development Director, Mid-Ohio Valley Regional Council Fred has been with the Mid-Ohio Valley Regional Council since 1983 and has been Community Development Director for over twenty years. He has a Bachelor’s Degree (1981) and a Master’s Degree (1982) from Marshall University in Huntington, WV.

Page 6: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms
Page 7: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

1

US Army Corps of Engineers

BUILDING STRONG®

U.S. Army Corps of Engineers Silver Jackets Program

Presented By:JoAnn Combs, CFM, MPMAshley Stephens, CFM

BUILDING STRONG®

Silver Jackets Program Program Description

► Collaborative interagency approach to flood risk management and hazard mitigation

Program Objectives► Integrate hazard planning and mitigation with emergency

response and recovery

► Leverage resources and information among state and federal agencies

► Define interagency communication and roles

► Improve public outreach in risk management

Example Activities► HAZUS Analysis

► Flood mapping update

► Nonstructural Workshops

► Multimedia Products

2

Page 8: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

2

BUILDING STRONG®

Program Overview State-led Interagency approach to sharing knowledge, leveraging

resources, and collaboratively reducing flood risk► Develop cohesive solutions for effectively managing the floodplain

► Focus hazard planning and mitigation on state priorities

► Enhance response and recovery efforts following natural disasters

► Follow life-cycle risk management

► Watershed perspectives

Various Federal, State, and local Agency Involvement (Examples)► EMA, DNR, USGS, NWS/NOAA, FEMA, NRCS, Regional Planning Councils,

Local Conservancy Districts, Many Others

Combines available agency resources► Funding

► Programs

► Technical expertise

Huntington District is the Lead for Ohio and

West Virginia► Pittsburgh and Baltimore Districts provide

support to West Virginia

Website: http://silverjackets.nfrmp.us/

3

BUILDING STRONG®

Types of Efforts / Funding

USACE participation funded through its National Flood Risk Management Program

►Nonstructural • Flood Warning System• Floodplain Mapping• Flood Emergency Preparedness Plans• Evacuation Plans

►Levee Safety Risk Communication• Workshops with communities explaining risk with local

USACE levees• Meetings with local officials to discuss levee risk

4

Page 9: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

3

BUILDING STRONG®

Silver Jackets Ohio Program

Ohio was the first state to establish a Silver Jackets team by signing a charter in 2005

Top Three Priorities ► Support the State Hazard Mitigation

Plan objectives and updates► Flood Risk Awareness Efforts► Implementation of projects funded

through the Silver Jackets initiative

Program Status► Program has supported seven

interagency projects within Ohio since 2011 – providing over $550K in Federal funds and leveraging over $700K in in-kind contributions

BUILDING STRONG®

Silver Jackets West Virginia Program

West Virginia Silver Jackets team was established by signing a charter in 2013

Key Goals► Assist in identifying actions to reduce

the threat, vulnerability, and consequences of flooding

► Foster leveraging of available resources and information among agencies

► Develop regional flood risk reduction strategies

Program Status► Program has supported two interagency

projects within West Virginia since 2014 – providing $230K in Federal funds and leveraging over $160K in in-kind contributions

Page 10: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

4

BUILDING STRONG®

Example Completed Silver Jackets Interagency

Projects

7

BUILDING STRONG®

Flood Inundation Warning System Ohio and Lower Muskingum Rivers, City of Marietta, and Washington and Morgan Counties

Flood Inundation Warning System► Reduces flood risk by providing

flood inundation maps ► Allows for early flood warning ► Accurately predict where flooding

will occur Partners

► U.S. Geological Survey (Project Lead)

► National Weather Service► U.S. Army Corps of Engineers► Muskingum Watershed

Conservancy District► Ohio Department of Natural

Resources► Ohio Emergency Management

Agency► Housing and Urban Development► City of Marietta► Washington and Morgan County

Commissioners► Local flood mitigation committee► RFG Associates, Inc.

8

Page 11: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

5

BUILDING STRONG®

NWS Stage Predictions Internet Application

USGS Streamgage Modeling and Mapping

Components of a Flood Warning System

9

BUILDING STRONG®

Flood Inundation Warning System Ohio and Lower Muskingum Rivers Continued

Objectives► Improve public information and

early earning systems

► Support efforts to enhance the early flood warning system along the Muskingum River

► Support efforts to implement an early flood warning system along Duck Creek

► Improve flooding emergency response systems

Outcomes► Predict the date and time for the

crest of the flood and generate Flood Inundation Mapping

► Input data into new Washington County ALERT System

10

Page 12: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

6

BUILDING STRONG®

NWS Flood Inundation Mapping Water Alert http://maps.waterdata.usgs.gov/mapper/wateral

ert/

USGS Report

http://pubs.usgs.gov/sir/2014/5195/

USGS Flood Inundation Mapping

http://wimcloud.usgs.gov/apps/FIM/FloodInundationMapper.html

Additional Information

11

http://water.weather.gov/ahps2/index.php

BUILDING STRONG®

Flood of 1913 – Ohio Silver Jackets Public Awareness Campaign

Year-long flood awareness campaign

100th anniversary of the Great Ohio Flood

Campaign Focus ►Flood Safety

►Preparedness

►Mitigation

12

Page 13: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

7

BUILDING STRONG®

Flood of 1913 Team Activities Silver Jackets participation and

press event at OSU Weather Symposium

Presented at ASFPM Conference Articles in Silver Jackets Newsletter Twitter, Facebook, and business

cards with QR codes Website Flood awareness brochurehttp://ema.ohio.gov/Documents/SilverJackets/Silver%20Jackets%201913%20Flood%20brochure.pdf

Press releases by multiple agencies 1913 Flood Miami Conservancy

District (MCD) Facebook page U.S. Geologic Survey 1913 Flood

videoMCD Facebook Page

13

BUILDING STRONG®

HAZUS Level 1 Analysis In 2008, Silver Jackets

conducted the analysis in support of the Statewide Hazard Mitigation Plan

Uses the Federal Emergency Management Agency’s HAZUS program and methodology to calculate damages to structures in the Special Flood Hazard Area

Analysis was conducted on 47 counties

Level 3 Floodplain

specific data

Level 2 Combination of local

and default flood hazard, building, and

damage data

Level 1 Default flood hazard, inventory,

and damage information

14

Page 14: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

8

BUILDING STRONG®

Example CurrentSilver Jackets Interagency

Projects

15

BUILDING STRONG®

HAZUS Level 2 Analysis FEMA’s HAZUS program and

methodology to calculate damages to structures in the Special Flood Hazard Area

Level 2 analysis for 25 counties ► Flood analysis for the 25- and

100-year frequency based on a four square mile drainage area

► Created depth grids

► User Defined Facilities (UDF)• Ohio Emergency

Management Agency worked with counties to gather tax parcel information required for UDF process

Level 3 Floodplain

specific data

Level 2 Combination of local

and default flood hazard, building, and

damage data

Level 1 Default flood hazard, inventory,

and damage information

16

Page 15: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

9

BUILDING STRONG®

Loss Avoidance Study The study will assess the

performance of implemented mitigation projects in Findlay and Ottawa

Ohio Emergency Management Agency (Partner) has completed Phase 1 Initial Project Selection and has collected required data components

U.S. Army Corps of Engineers Buffalo District is currently working on► Phase 2 – Physical Parameter

Analysis

► Phase 3 – Loss Estimation Analysis

17

BUILDING STRONG®

Marion County Floodplain Mapping

Conducting a flood study along the Scioto River through Marion County as current maps are unverified

Completed ► Bridge/Culvert Information – provided by Ohio Department of

Transportation and Marion County

► Generated inundation limits and floodway profile

► Incorporated USGS model of La Rue into study

► Ohio Emergency Management Agency worked with Marion County Commissioners and the key Villages of La Rue, Prospect, and Green Camp to sign a resolution to adopt the results of this study as best available data until a physical map revision is completed by FEMA

18

Page 16: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

10

BUILDING STRONG®

Mahoning County Nonstructural Flood Risk Management Meeting

The Mahoning River is a tributary to Beaver River which runs into the Upper Ohio River

Background► Chronic Flooding, siltation, and standing

flood risks at multiple sites in Poland Township located in Mahoning County, Ohio

Purpose ► Present Federal and state programs that

may be of assistance to Mahoning County► Create brochure and media product

Meeting held August 16, 2016 in Lowellville, Ohio► Led by Pittsburgh District ► Ohio EMA, ODNR, NWS, and other

partners presented

Product ► Create video from digitally recorded

meeting to share with other Ohio municipalities that experience similar flood risks

Mahoning County Meeting

19

BUILDING STRONG®

Multimedia Outreach Project will develop videos for distribution to

bring flood risk awareness to the general public, as well as, local officials regarding flood risk management, and the positive impacts of nonstructural mitigation

Ohio Silver Jackets team is currently developing storyboards for videos

Once completed videos will be distributed and placed on partner websites, YouTube, and social media

20

Page 17: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

11

BUILDING STRONG®

WV Levee Outreach

West Virginia and FEMA have proposed an effort to certify all levees within the State► This project focuses on levees

inspected by the Corps and have available inspection reports

Several workshops will be held across the state to:► Inform local stakeholders about their

levee(s)

► Promote flood risk management and awareness

► Educate stakeholders on each agencies various programs and authorities

► Identify future Silver Jackets opportunities

21

BUILDING STRONG®

Upper Ohio-Shade Regional Nonstructural Workshop

FEMA’s Discovery process not deployed for this watershed

Nonstructural workshops will be held in Ohio and West Virginia to achieve flood risk reduction and awareness

► Overview of flood risk

► Benefits of proper floodplain management

► Education about effective nonstructural measures

► Mitigation

Upper Ohio-Shade Watershed

Upcoming Ohio WorkshopsSeptember 12, 2016Meigs County Public Library, Pomeroy, Ohio Local Stakeholder Presentations: 2:00pm to 3:30pmPublic Workshop Session: 4:00pm to 7:00pm

September 13, 2016Marietta Public Library, Marietta, OhioLocal Stakeholder Presentations: 2:00pm to 3:30pmPublic Workshop Session: 4:00pm to 7:00pm

22

Page 18: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

12

BUILDING STRONG®

USACE Silver Jackets Contact Information

Lead District for Ohio

HUNTINGTON DISTRICT

Ashley Stephens

[email protected]

JoAnn Combs

[email protected]

Lead District for West Virginia

HUNTINGTON DISTRICT

Steve O’Leary

[email protected]

Joe Trimboli

[email protected]

23

USACE Silver Jackets Website:http://silverjackets.nfrmp.us/

Page 19: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

1

US Army Corps of Engineers

BUILDING STRONG®

USACE Programs and Authorities

Presented by:JoAnn Combs, CFM, MPMAshley Stephens, CFM

September 2016

BUILDING STRONG®

USACE Missions Navigation

Flood Risk Management

Ecosystem Restoration

Regulatory

Recreation

Emergency Management

International and Interagency Support

Water Supply

2

Page 20: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

2

BUILDING STRONG®

Getting Started Authorization – Permission to undertake a study

or project► Water Resource Development Act (WRDA) ► Study Resolution► Special Authorizations

Appropriation – Funding to conduct an authorized study or project► President’s Annual Budget► Energy & Water Development Appropriations Act► Continuing Resolution Act (CRA)► Work Plans

3

BUILDING STRONG®

Feasibility

24 – 36 months

Preconstruction, Engineering &

Design

12 – 24 months

Construction

Varies with Complexity

Operation & Maintenance by

Sponsor

Life of Project

Civil Works Timeline

4

Page 21: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

3

BUILDING STRONG®

What will be accomplished?• Execute Feasibility Cost Share Agreement (FCSA)• Develop Project Management Plan (PMP)• Employ six step planning process • Obtain public input for project formulation• Formulate and evaluate alternative measures• Perform preliminary design• Conduct environmental analyses• Identify and recommend tentatively selected plan (TSP)• Determine necessary real estate acquisitions and utility relocations• Develop baseline cost estimate and detailed schedule• Conduct external peer review• Produce a Feasibility Report

Cost• Varies with project complexity (Up to $3M without waiver)• 50% Federal, 50% sponsor cost share• Entire non-Federal share can be in-kind services

Feasibility Phase (24-36 months)

5

BUILDING STRONG®

SMART Feasibility Study Process

6

SpecificMeasurableAttainableRisk-InformedTimely

Page 22: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

4

BUILDING STRONG®

Pre-Construction, Engineering, and Design (12-24 months)

What will be accomplished?• Execute Design Agreement• Complete detailed studies and designs needed for plans and

specifications• Prepare plans and specifications for the first construction contract• Produce Design Documentation Report (DDR)• Develop Project Partnership Agreement (PPA)

Cost• Varies with project complexity• Non-Federal cost share is determined by program and project

purpose• Entire non-Federal share can be in-kind services

7

BUILDING STRONG®

Construction (Varies)

What will be accomplished?• Execute Project Partnership Agreement (PPA)• Acquire real estate and complete relocations (if applicable)• Initiate and complete first construction contract• Continue design and preparation of plans and specifications for

subsequent contracts• Complete all construction activities• Develop Operations & Maintenance manual

Cost• Varies with project complexity• Non-Federal cost share is determined by program and project

purpose

8

Page 23: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

5

BUILDING STRONG®

Operation and Maintenance (Life of Project)

9

What will be accomplished?• Operate and maintain newly constructed project

including any repair, rehabilitation, or replacement

Cost• Varies with project complexity• 100% non-Federal

BUILDING STRONG®

Other Programs and Authorities

10

Page 24: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

6

BUILDING STRONG®

Continuing Authorities Program (CAP)Authorities Section 14, 1946 FCA, as amended

► Emergency streambank protection

Section 107, 1960 Rivers & Harbors Act, as amended► Small navigation projects

Section 205, 1948 FCA, as amended► Flood damage reduction

Section 206, WRDA 1996, as amended► Aquatic ecosystem restoration

Section 208, 1954 FCA, as amended► Snagging and clearing for flood control

Section 1135, WRDA 1986, as amended► Ecosystem restoration at Federal projects

Cost Share Study Phase

► Initial $100K full Federal

► 50% / 50% after initial $100K

Construction Phase► 65% Federal, 35% Sponsor

Section 14 Examples

11

Section 206 Examples

Section 205 Example

BUILDING STRONG®

Planning Assistance to States (PAS) andFloodplain Management Services (FPMS)

Planning Assistance to States (PAS –Section 22)► Technical assistance to support state

comprehensive water and related land resource development plans

► Studies are planning level of detail and do not include detailed design for project construction

► Cost Share (50% Federal, 50% Sponsor)

Floodplain Management Services (FPMS)► Information, technical planning assistance,

and guidance in identifying the magnitude and extent of flood hazards and planning appropriate use of the floodplains

► Cost Share (100% Federal)

12

PAS Example

FPMS Example

Page 25: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

7

BUILDING STRONG®

Section 729 Watershed Planning

Watershed planning is a collaborative process of developing a holistic plan for addressing watershed needs► Flood risk reduction

► Aquatic ecosystem restoration

► Stormwater management solutions

► Sedimentation and water quality improvements

► Clean water and sanitary sewer (environmental infrastructure)

► Recreation opportunities

► Emergency preparedness plans

Example Section 729 ProjectMuskingum Basin and Nimishillen Creek

13

BUILDING STRONG®

Section 729 Watershed Planning

Nimishillen Creek Watershed Final Watershed Assessment Great success thanks to our

engaged stakeholders

Resulted in a Watershed Management Plan for sustainability of the watershed

Some outcomes being implemented:► Installation of additional rain/stream

gages

► Hydrologic and hydraulic modeling update

► Consolidation of floodplain management duties

Muskingum River Basin

Final Watershed Assessment Initial stakeholder meetings in June 2016

Inventory problems, opportunities, and needs within the Basin► Continued focused outreach to local

stakeholders

► Form technical working and advisory groups

Establish baseline condition

Develop and prioritize strategies for addressing needs throughout the Basin

14

Page 26: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

8

BUILDING STRONG®

WV Environmental Infrastructure

Section 340 – Southern WV Section 571 – Central WV

► Huntington District manages both of these programs in WV

Design and/or construction assistance to non-Federal interests for carrying out water-related environmental infrastructure and resource protection and development projects► Wastewater treatment and related

facilities► Combined sewer overflow► Water supply, storage, treatment and

related facilities► Surface water resource protection

and development

15

BUILDING STRONG®

USACE District Contact Information

16

BALTIMORE DISTRICT

HUNTINGTON DISTRICT

PITTSBURGH DISTRICT

Amy GuiseChief, Planning Division

(410) [email protected]

Rebecca Albert Acting Chief, Planning Branch

(304) [email protected]

Ryan FisherChief, Plan Formulation and Economics

Section(412) 395-7588

[email protected]

Page 27: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

1

US Army Corps of Engineers

BUILDING STRONG®

Flood Risk, Nonstructural Measures, The National Flood Proofing Committee (NFPC)

Presented by:Stephen O’Leary, AIA, CFMUSACE Huntington District / NFPC

September 2016

BUILDING STRONG®

Flood Risk Risk = f [(Probability of Flooding) x (Consequences)]

(Probability of Flooding) is the frequency of flooding or how often does flooding occur in a particular location. Reduce the frequency of flooding and risk is reduced.

(Consequences) are the potential damages and life loss associated with flooding. The structures (critical, residential, commercial, public, and industrial), land use (agricultural, urban, public) , and infrastructure (highways, roads, rail, utilities) make up the potentially damageable assets. Reduce the consequences of flooding and risk is reduced.

Note: If critical facilities become inoperative during a flood event the area of impact extends beyond the area of flooding (i.e. electrical service, communications, water and wastewater, etc).

2

Page 28: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

2

BUILDING STRONG®

Nonstructural Flood Risk Management Definition

Nonstructural flood risk management can be categorized as a set of physical or nonphysical measures utilized for mitigating loss of life as well as existing and future flood damages.

The physical measures adapt to the natural characteristics of the floodplain without adversely affecting or changing those natural flood characteristics. These measures are generally compliant with the NFIP and cause no adverse affects to the floodplain, flood stages, velocities, or the environment.

Because of their ability to adapt to flood risk, these measures may also be referred to as Flood Risk Adaptive Measures and can be incorporated into existing or new structures to mitigate for potential future flood damages and life loss.

3

BUILDING STRONG®

Nonstructural Flood Risk Adaptive Measures

The most common physical FRAM measures implemented for flood damage and life loss reduction are:

Acquisition Relocation Elevation

Dry Flood Proofing Wet Flood Proofing Basement Removal

Nonphysical measures can be considered separately or as a combination of floodplain management and planning functions. Representative nonphysical measures are:

Floodplain Mapping Land Use Flood Insurance

Evacuation Plans Flood Warning Zoning

Operational Changes Floodplain Management Plans

4

Page 29: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

3

BUILDING STRONG®

Acquisition and Demolition

Acquire the structure(s) as well as the land

Demolish structure(s) or sell and remove

5

BUILDING STRONG®

Elevation

Elevation is one of the most common and effective methods used to prevent flooding of living space

Recommend design and construction by reputable/qualified professionals and contractors

Not permitted in regulatory floodway

Acceptable in A Zones

6

Page 30: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

4

BUILDING STRONG®

Dry Floodproofing

• Flood depths of 3 feet or less

• Structurally sound buildings

• New construction

• Retrofitting existing buildings

• No basement or crawl space

7

BUILDING STRONG®

Wet Floodproofing

City of Sacramento Fire Station 43 (Natomas, CA)

Town Hall (Prestonsburg, KY)Church (Grundy, VA)

8

Page 31: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

5

BUILDING STRONG®

RelocationIndividual Relocations Redevelopment Site Relocation

9

BUILDING STRONG®

Berms, Walls, and Barriers

*Not FEMA Accredited

10

Page 32: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

6

BUILDING STRONG®

Assessing the Situation Flood Characteristics

► Flood depth, Flood velocity, Flood duration, Rate of rise, Debris/Ice flows, Wave action, Floodway, Other

Site Characteristics► Location, Soil type, Topography, Site size,

Urban/Rural, Other

Building/Structure Characteristics► Type of construction, Foundation, Condition of the

building, Lower levels (Basement), Historical Significance, Other

Other Considerations► Building Occupancy, Building Codes, Zoning

Ordinances and Local Restrictions, Other Agencies (Local / State / Federal), Aesthetics, Public Heath/Safety/Welfare, Other

11

BUILDING STRONG®

Flood Damage Reduction Matrix

12

Page 33: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

7

BUILDING STRONG®

USACE National Nonstructural Flood Proofing Committee (NFPC)

The National Nonstructural Flood Proofing Committee (NFPC) functions under the general direction of the Chief, Planning Community of Practice, Directorate of Civil Works, HQUSACE. The objectives of the NFPC are to:

Promote the development and use of all nonstructural flood risk reduction measures.

Risk expertise on all aspects of nonstructural flood risk reduction and associated opportunities.

Disseminate nonstructural flood reduction information.

Partner with Planning Centers of Expertise in all aspects of nonstructural flood risk reduction and associated opportunities.

Provide leadership in all aspects of floodplain management.

http://www.usace.army.mil/Missions/CivilWorks/ProjectPlanning/nfpc.aspx

14

BUILDING STRONG®

NFPC Activities

• Support for Field Assessments, Plan Formulation, and Project Review

• Nonstructural and Floodplain Management Training

• Publications of Nonstructural Mitigation Measures

• Collaboration with ASFPM and FM Approvals on National Flood

Barrier Testing and Certification Program

• Collaboration with FEMA on Technical Bulletin Revisions

• NFPC Web Site

• Inventory of USACE Nonstructural Flood Risk Management Activities

• nServo – Nonstructural mitigation costing tool

16

Page 34: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

8

BUILDING STRONG®

Questions?

15

Page 35: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

1

USACE Upper-Ohio ShadeWatershed WorkshopFEMA REGION IIISeptember 14-15th

1

Overview

▸ Basics of Discovery

▸ Goal of Data Development

▸ Planning for Risk

▸ Actionable Outcomes

Page 36: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

2

2

Purpose of Discovery:Information Sharing

▸ Share your concerns about flood risk

▸ Share any additional flood data you may have• Areas of recent or proposed development near floodplains or areas of

historical flooding

• Areas of historical flooding or flooding not shown on map

• Possible areas of mitigation interest

• Risk communication needs

▸ Share your thoughts on which FEMA flood risk products or mitigation projects you would like in your community

3

Discovery: Engagement & Collaboration

▸ Cooperating Technical Partnership

▸ GIS capabilities

▸ Public/private partnerships

▸ Education and outreach• Strategic communication plan

development

• Information materials development and dissemination

• Media relations

• Training

• Website and social media links

Community Engagement

Assessment

Building Relationships

Communication

Page 37: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

3

4

Discovery: Data Collection and Collaboration

▸ Process of data mining, collection, and analysis

▸ Investigating current and potential flood risk, and existing mitigation projects, within a watershed

▸ Data gathered and analyzed before meeting includes:

• Boundaries: Watershed and Jurisdiction• CRS Participation• Comprehensive Plan Summary• Dams• Declared Disasters• Effective Floodplains: Special Flood

Hazard Areas• Hazard Mitigation Assistance Grants• Identified Mitigation Actions• Individual Assistance• Letters of Map Change

• Levee Inventory• Mitigation Plan Status and Summary• NFIP Participation• Population• Public Assistance• Stream Data• Stream Gages • Study Needs: FEMA• Topography• Total Exposure in Floodplain• Transportation: Roads and Railroads

5

Information We Need from You

▸ Completed Discovery data questionnaire, with GIS contact

▸ Areas of Concern• Areas of recent or planned development

• Areas of high growth or other significant land changes

▸ Areas of historical flooding and other flood risks

▸ Mitigation projects that address flood risks

▸ Your ideas about other ways to increase your community’s resilience to flooding

Page 38: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

4

6

Reducing Risk in Communities

7

Risk Communication

▸ Federal/State/Local goals:• To reduce risk to life and property and ensure safer, sustainable

communities

• To effectively communicate risk and increase public awareness, leading citizens to make informed decisions regarding their risk

• To have an open dialogue throughout the Discovery process

▸ Key factors contributing to successful achievement of these goals:• Whole Community engagement and exchange of flood risk information

• Effective collaboration through partnerships

• Strategic communication plan development

• Local understanding and implementation of mitigation action and strategies

Page 39: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

5

8

What Are We Building Towards?

RESILIENCY

9

What is Resilience?

(rəˈzilyəns/)noun1. The ability of a substance or

object to spring back into shape; elasticity.

2. The capacity to recover quickly from difficulties; toughness.

A resilient community:

▸ Prepares for, withstands, and rapidly recovers from disruptions

▸ Adapts to changing conditions and environments

▸ Withstands the economic and social impacts of hazards

▸ Protects what is important to the community

Page 40: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

6

10

What is the Path to Resilience?

Know Your Risk

▸ Understand the hazard risk equation

▸ Communicate risk to property owners and the general public

▸ Understand the stresses risks can put on: • Residents

• Community

• Infrastructure

• Economy

Reduce Your Risk

▸ Data, tools, and resources

▸ State Mitigation Plan

▸ Other planning efforts

▸ Disaster declarations

▸ Online resources

▸ Technical assistance

▸ Studies and reports

Reduce Your Risk

Insure Your Risk

Know Your Risk

11

Resilient and Sustainable Communities

▸ Sustainability• “Meets the needs of the present without

compromising the ability of future generations to meet their own needs.”

• Traditional indicators of sustainability are social, economic, and environmental health

▸ Resilient and Sustainable Communities Take Action to Reduce Risk and Mitigate Hazards• By mitigating against the risks posed by natural

hazards, and reducing vulnerability to them

• Sustainable communities minimize exposure of people and property to natural disasters; sustainable communities are disaster-resilient communities

Page 41: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

7

12

PlanningReducing Risk in Communities

13

Hazard Mitigation

Hazard Mitigation: Hazard mitigation is the effort to reduce loss of life and property by lessening the impact of disasters

▸ Occurs before, during, and after disasters and serves to break the cycle of damage and repair

▸ Long-term risk reduction

▸ Essential part of community resilience

Page 42: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

8

14

Hazard Mitigation

Hazard Mitigation: Hazard mitigation is the effort to reduce loss of life and property by lessening the impact of disasters

▸ Occurs before, during, and after disasters and serves to break the cycle of damage and repair

▸ Long-term risk reduction

▸ Essential part of community resilience

15

Planning Cycle and Key Planning Factors

ENGAGE

ENHANCE

INTEGRATE

IMPLEMENT

Ensure all participants

adopt the plan

Start conducting

annual meetings

and tracking actionsStart the

process to secure

funding for the plan update

Begin planning process, determine the planning lead

(or consultant) and convene planning

team

Finalize risk and vulnerability

assessment, develop mitigation

strategies, and finish writing the

plan

Page 43: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

9

16

Building a Mitigation Planning Routine

Incorporation of enhancements into the day-to-day responsibilities

▸ How can the planning components become a part of the normal operating functions of a community?

▸ Make risk reduction part of the normal functions of the community

17

Connecting Planning and Mitigation

▸ Plan integration is a process where communities look critically at their existing planning framework and align hazard mitigation principles with other local planning mechanisms• Transportation planning

• Comprehensive planning

▸ This two-way exchange of information supports community-wide risk reduction, both before and after disasters occur

▸ Supports a holistic approach to building resiliency

Page 44: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

10

18

Resiliency Opportunities in Planning

▸ Define risk and vulnerabilities

▸ Identify priorities that cross multiple interests

▸ Prioritize critical infrastructure

▸ Creative incentives to promote use of resilience measures

▸ Use a collaborative regional governance structure

▸ Public-Private Partnerships

▸ Encourage flexibility and adaptive management

▸ Consider a combination and blend of measures to customize solutions

19

Identifying and Advancing Action

Reducing Risk in Communities

Page 45: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

11

20

What is a Hazard Mitigation Action?

▸ Any sustained action taken to reduce or eliminate the long-term risk to human life and property from hazards

▸ Communities sustain action by building the capacity, knowledge, and understanding necessary to successfully advance action

21

Why Engage in Mitigation Planning and Action Advancement?

▸ Creates safer communities by reducing loss of life and damage to property and the environment

▸ Minimizes post-disaster disruption, allowing communities to recover more quickly

▸ Allows communities to respond and adapt to changing conditions

▸ Generates secondary economic, environmental, and public health benefits

▸ Empowers individuals to act as agents of change in their communities

▸ Lessens financial impacts on individuals, communities, and society as a whole

Page 46: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

12

22

Implementing Action:Mitigation Grant Programs

▸ Pre-Disaster Mitigation (PDM)• Funds cost-effective, comprehensive mitigation activities that reduce

injuries, loss of life, and property damage

▸ Flood Mitigation Assistance (FMA)• Provides funding to assist states and communities in implementing

measures to reduce or eliminate the long-term risk of flood damage to buildings, manufactured homes, and other structures insured under the NFIP

▸ Hazard Mitigation Grant Program (HMGP)• Available after a major disaster declaration – the amount of funding is

15% of the total federal assistance provided by FEMA for disaster recovery under the major disaster declaration

23

Resources

▸ FEMA: www.fema.gov

▸ Floodsmart, the official site of the NFIP: www.floodsmart.gov

▸ Map Service Center: https://msc.fema.gov/portal

▸ NFIP Reform: www.fema.gov/flood-insurance-reform

Page 47: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

13

24

Contact Information

▸ FEMA Region III• Matt McCullough, FEMA Region III Community Planner

[email protected]

25

Page 48: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms
Page 49: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

1

UPPER OHIO – SHADEWATERSHED MEETING

SEPTEMBER 2016

FRED RADER,COMMUNITY DEVELOPMENT DIRECTOR

MID-OHIO VALLEY REGIONAL COUNCIL

www.movrc.org

WHAT IS MOVRC?

• ONE OF 11 REGIONAL COUNCILS COVERING ALL 55 COUNTIES IN WV

• MOVRC INCLUDES EIGHT COUNTIES AND 22 MUNICIPALITIES

• BOARD IS COMPRISED OF A COUNTY COMMISSIONER FROM EACH COUNTY, THE MAYOR OF

EACH CITY OR TOWN, ECONOMIC DEVELOPMENT AUTHORITY REPRESENTATIVES AND PRIVATE

SECTOR MEMBERS

• PROVIDE PLANNING AND DEVELOPMENT ASSISTANCE TO LOCAL GOVERNMENTS – SUCH AS

REGIONAL HAZARD MITIGATION PLAN

Page 50: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

2

WV REGIONAL COUNCILS

HAZARD MITIGATION PLAN

• IDENTIFY RISKS FROM NATURAL HAZARDS

• ESTIMATE EXTENT OF RISK AND PRIORITIES FOR ACTION

• IDENTIFY MITIGATION MEASURES THAT WILL LESSEN HARM FROM FUTURE EVENTS

Page 51: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

3

214

311

177

230

258

221

178

349

0 50 100 150 200 250 300 350 400

Calhoun

Jackson

Pleasants

Ritchie

Roane

Tyler

Wirt

Wood

Total NCDC Events Recorded in the Mid-Ohio Valley 1950-September 2015

County Total Events Property Damage Average Yearly Property Damage

Calhoun 31 $3,319,029.83 $174,685.78

Jackson 42 $3,748,078.52 $197,267.29

Pleasants 19 $2,783,038.93 $146,475.73

Ritchie 27 $4,494,817.51 $236,569.34

Roane 39 $16,356,529.43 $860,869.97

Tyler 39 $4,076,290.44 $214,541.60

Wirt 16 $3,454,125.55 $181,796.08

Wood 32 $11,843,683.20 $623,351.75

Summary Statistics for Flooding by County (adjusted for inflation)

Page 52: UPPER OHIO-SHADE NONSTRUCTURAL STAKEHOLDER MEETINGS · Certified Floodplain Manager; Licensed Architect. JOANN COMBS, CFM, MPM US Army Corps of Engineers, Huntington District Ms

4

MITIGATION MEASURES

• ENHANCED FLOODPLAIN ORDINANCES AND CONSISTENT ENFORCEMENT ARE FIRST LEVEL

MITIGATION MEASURES – SUSTAINABLE DEVELOPMENT

• HISTORICALLY ACQUISITION AND DEMOLITION: HAPPY VALLEY, REEDY, CALHOUN COUNTY

• STATE HAS RECENTLY ADDED “COMPLIANT” RECONSTRUCTION AS AN ELIGIBLE ACTIVITY

CONCLUSION

• FLOODING IS A SIGNIFICANT RISK IN THE MID-OHIO VALLEY AND THIS WATERSHED

• SUSTAINABLE DEVELOPMENT PRACTICES REDUCE ADDING TO THE RISK

• MID-OHIO VALLEY REGIONAL COUNCIL IS HERE TO HELP WITH APPLICATIONS FOR FUNDING

ASSISTANCE FOR RISK REDUCTION ACTIVITIES