update on tbl status ctf3 committee 17.09.2009

7
Update on TBL status CTF3 committee 17.09.2009 • Several runs with beam, slowly increasing the current Arrived at 10 A beam current and 20 MW 12 GHz power extracted • Got experience with beam optics and handling for TBL • Commissioning of instrumentation, BPM’s, BPS’s, RF-diagnostics for amplitude and phase, movers Conclusion so far: • 12 GHz production in good agreement with theoretical predictions PETS is well behaved so far, transmission, vacuum • Beam handling rather simple • Some problems with BPM electronics

Upload: gene

Post on 06-Jan-2016

21 views

Category:

Documents


0 download

DESCRIPTION

Update on TBL status CTF3 committee 17.09.2009. Several runs with beam, slowly increasing the current Arrived at 10 A beam current and 20 MW 12 GHz power extracted Got experience with beam optics and handling for TBL - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Update on TBL status CTF3 committee 17.09.2009

Update on TBL statusCTF3 committee 17.09.2009

• Several runs with beam, slowly increasing the current Arrived at 10 A beam current and 20 MW 12 GHz power extracted

• Got experience with beam optics and handling for TBL

• Commissioning of instrumentation, BPM’s, BPS’s, RF-diagnostics for amplitude and phase, movers

Conclusion so far:• 12 GHz production in good agreement with theoretical predictions PETS is well behaved so far, transmission, vacuum• Beam handling rather simple• Some problems with BPM electronics

Page 2: Update on TBL status CTF3 committee 17.09.2009

0 100 200 300 400 500 600-10

-8

-6

-4

-2

0

2

Time (ns)

Bea

m c

urre

nt (

A)

BPM0150

BPS0210

BPS0250BPS0310

BPM0310

-100 0 100 200 300 400 5000

1

2

3

4

5

6

Time (ns)

RF

pow

er (

MW

)

Pout left

Pout right

Pref leftPref right

P predict

TBL run with 7 A but long bunches suspected

-100 0 100 200 300 400 5000

1

2

3

4

5

6

Time (ns)

RF

pow

er (

MW

)

Pout left

Pout right

Pref leftPref right

P predict

BPM 150 to predict

BPM 310 to predict

Page 3: Update on TBL status CTF3 committee 17.09.2009

0 100 200 300 400 500 6000

0.2

0.4

0.6

0.8

1

1.2

1.4

Time (ns)

RF

pow

er (

MW

)

Pout left

Pout right

Pref left

Pref right

P predict

0 100 200 300 400 500 600-5

-4

-3

-2

-1

0

1

Time (ns)

Bea

m c

urre

nt (

A)

BPM0150

BPS0210

BPS0250BPS0310

BPM0310

BPS 210 to predict

TBL run with 4 A and good agreement

Page 4: Update on TBL status CTF3 committee 17.09.2009

TBL run 15.9. with 10 A into the PETSForm factor 0.9

0 50 100 150 200 250 300 350 400 450 500-100

-80

-60

-40

-20

0

20

40

60

80

100

Time (ns)

RF

pha

ses

(deg

)

Pout left

Pout right

0 100 200 300 400 500 600-16

-14

-12

-10

-8

-6

-4

-2

0

2

Time (ns)

Bea

m c

urre

nt (

A)

BPM0150

BPS0210

BPS0250BPS0310

BPM0310

-100 0 100 200 300 400 500-1

0

1

2

3

4

5

6

7

8

9

Time (ns)

RF

pow

er (

MW

)

Pout left

Pout right

Pref leftPref right

P predict

Good transmission but noisy signals from the BPS’s

Page 5: Update on TBL status CTF3 committee 17.09.2009

-100 0 100 200 300 400 5000

2

4

6

8

10

12

14

Time (ns)

RF

pow

er (

MW

)

Pout left

Pout right

Pref leftPref right

P predict

0 50 100 150 200 250 300 350 400 450 500-150

-100

-50

0

50

100

150

Time (ns)

RF

pha

ses

(deg

)

Pout left

Pout right

TBL run 15.9. with 10 A into the PETSOptimized for peak power, Form factor

= 1

0 100 200 300 400 500 600-25

-20

-15

-10

-5

0

5

10

Time (ns)

Bea

m c

urre

nt (

A)

BPM0150

BPS0210

BPS0250BPS0310

BPM0310

Page 6: Update on TBL status CTF3 committee 17.09.2009

Next steps

Commissioning:• Higher current : 20 A, 100 MW (delay loop needed)• Better BPS performance to measure resolution and to play alignment games with the movers

Finishing TBL:• Finishing the beam line in the next shutdown 21.9 – 16.10 (all Quads, BPS, vacuum system and spectrometer)• Series production of tanks launched ( Two tanks expected to be installed during the winter shutdown )• Norwegian collaborators expected to work on TBL commissioning in 2010

Page 7: Update on TBL status CTF3 committee 17.09.2009

Status on BPS’s from IFIC ValenciaAngeles Faus-Golfe

Status:• BPS finished, calibration measurements ongoing• Electronic droop compensation by Gabriel Montero next week (week 39)• Juanjo will come to CERN week 41 and 42 to help with the installation