Update on MC-04(05) New interaction region Attenuation lengths vs endcap module numbers Regeneration and nuclear interaction EMC time resolution generator – Trigger Additional generators lsb insertion code Energy scale calibration DC tracking resolution Correlated noise in DC for charged kaons Fix discrepancy in SQZ library LNF-6-May-05 Offline Meeting

Upload: sharleen-morris

Post on 14-Jan-2016

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Update on MC-04(05)

– New interaction region– Attenuation lengths vs endcap module numbers– Regeneration and nuclear interaction– EMC time resolution– generator– Trigger– Additional generators– lsb insertion code– Energy scale calibration– DC tracking resolution– Correlated noise in DC for charged kaons– Fix discrepancy in SQZ library

LNF-6-May-05Offline Meeting

Page 2: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Layout of the presentation for Capri

• Data Reconstruction • Computing Farm and Tape storage• MonteCarlo:

– Production for 2001-02 data– Upgrade for 2004-05 data

• Reprocessing of 2001-02 data• False dead wires problem• Short and long term Plans

Page 3: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

• Integrated Luminosity in 2004-05; size of the reconstructed data

• Quality of the reconstruction vs run number (few plots from datarec)

• Datarec version (19-20-21-22) vs run number• Status of dst’s production

Data Reconstruction

Page 4: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Monte Carlo production for 2001-02 data completed in 2004

Program LSF

ee 6e+e (ISR only) 6 rad 5ee ee 0.15 all 0.2 all (21 pb-1 scan) 1KSKL 1 KK 1

Total 1527 Mev 6890 B80CPU days 40.5 TB

Page 5: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

ProgramEvents(106)

LSFTime

(B80 days)Size(TB)

KSKL rare 62 20* 320 1.7 est.

62 20* 320 est. 1.7 est.

To be updated with last production (gg, charged kaons)

Monte Carlo production for 2001-02 data completed in 2004-05

Page 6: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Update of the Monte Carlo for 2004-05 data

• Effort to produce a Monte Carlo simulation for 2004/05 data

• Tasks:– New interaction region– Attenuation lengths vs endcap module numbers– Regeneration and nuclear interaction– EMC time resolution– generator– Trigger jitter– Additional generators– lsb insertion code– Energy scale calibration– DC tracking resolution– Correlated noise in DC for charged kaons

Page 7: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Monte Carlo Production for 2004-05 data

• Final goal :

– Simulation of a sample corresponding to 1.7 fb-1 (estimated by the end of 2005)

– 20 % all phys + 100% neu Kaon +100% Kpm +500% radiative +...

– Extrapolating from 2001/02 ->280 days on 100 B80 CPU

Production schedule would be driven by analysis needs.

Page 8: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Reprocessing of 2001-02 data

• Motivation

• more compact sample and with refined selection/reconstruction routines.

• Sample: 420 pb-1 of data • Estimate time: 8000 CPU days • Schedule:

– Depends on the offline activities

• Current situation: 30 Cpu with dst’s and reconstruction running (1.4pb-1/day)

• First Part: 40 pb-1. Expected to finish in one month from now

Page 9: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Problem of false dead wires

• Description of the problem• Affected : MC2001-02, data 2004• Needs to:

– Redo the correct list for 2001/02 and 2004– Re-reconstruct the MC for a sub-sample of 2001/02 data (30

pb-1)

• Time scale:– Correct list for 2001-02 data done (1 month/24CPU)– Correct list for 2004 data: to be done (estimate time 45

days for 650 pb-1) – MC re-reconstruction: to be done (estimate time 15 days

for 30 pb-1)

Page 10: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

fibm Ktest KMC Krec Datarec DST Repro13 4 114 4 115 4 117 4 118 4 119 4 120 4 121 4 122 4 123 4 1 1 2 224 4 1 1 2 225 4 1 1 2 226 4 1 2 227 4 1 2 228 4 1 2 229 4 1 1 330 4 1 1 331 4 1 1 332 4 1 1 333 4 1 1 334 4 1 1 335 2 436 2 437 2 438 2 439 2 440 2 441 2 442 2 443 2 444

Offline resources and activities

Page 11: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

Offline Plans

• Short term (before the end of the year):– Reprocessing 2001/02 – Re-reconstruction of MC 2001/02 (at least 30pb-1)– Correct list of dead wires for 2004– MC 2004/05

• Long term list (probably from next year):– Reprocessing 2004 data– …

Page 12: Update on MC-04(05) –New interaction region –Attenuation lengths vs endcap module numbers –Regeneration and nuclear interaction –EMC time resolution –

2

0

0

5

Reconst

DST

(120 CPU)

Reproc.

(30 CPU)

Recons. MC01/02

(30 CPU)

Dead Wires

2004

(24 CPU)

MC04

(30 CPU)

May 40pb-1

Jun 15 days (30pb)

45days

July

Sep20% all

Oct

Nov

Dec