update no 1 report
TRANSCRIPT
Update No 1 Report
for the
Supplemental Site Characterization Report
Tier 1 Risk Assessment
Columbia Missouri FMGP Site
December 2013
Prepared for:
AMEREN SERVICES COMPANY
St. Louis, Missouri
Update No 1 Report
for the
Supplemental Site Characterization Report
Tier 1 Risk Assessment
Columbia Missouri FMGP Site
December 2013
Prepared for:
AMEREN SERVICES COMPANY
St. Louis, Missouri
PSC INDUSTRIAL OUTSOURCING, LP
210 West Sand Bank Road
Columbia, Illinois 62236-0230
Project 624-1302-0002
i Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
TABLE OF CONTENTS
EXECUTIVE SUMMARY ........................................................................................................ 1
1.0 INTRODUCTION ................................................................................................................ 2
2.0 UPDATES TO THE SUPPLEMENTAL SITE CHARACTERIZATION REPORT ... 3
3.0 UPDATES TO THE TIER 1 RISK ASSESSMENT – SITE CONCEPTUAL MODEL 4
3.1 Distribution of COCs in Soil ....................................................................................... 4
3.2 Current/Future Land and Groundwater Use ............................................................ 5
3.3 Known or Proposed Land or Water Use Restrictions .............................................. 5
3.4 Chemicals of Concern .................................................................................................. 6
3.4.1 Chemicals Retained / Excluded for Evaluation ..............................................6
3.5 Exposure Model ............................................................................................................ 7
3.5.1 Domestic Use of Overburden Groundwater ...................................................7
3.5.2 Site Surficial Soil ...............................................................................................9
3.5.3 Site Subsurface Soil ...........................................................................................9
3.6 Saturated Soil Concentration ...................................................................................... 9
3.7 Representative Concentration Calculations .............................................................. 9
3.8 Individual or Representative Concentration Exceedances and Planned Removal
Summary ..................................................................................................................... 10
3.8.1 Evaluation of Exposure Domain and Exclusion Considerations ................10
3.8.2 Exposure Pathway Scenario Evaluation Results ..........................................11
3.8.3 Exposure Scenario Evaluation Summary vs. Planned Removal ................12
4.0 POST-PLANNED REMEDIAL ACTION RISK EVALUATION (TOTAL AND
CUMULATIVE SITE-WIDE) .......................................................................................... 13
4.1 Carcinogenic Risk Evaluation (D)(1) ....................................................................... 13
4.2 Non-Carcinogenic Risk Evaluation (D)(2) ............................................................... 13
4.3 Individual Residual Borehole Risk Evaluation ....................................................... 14
5.0 SUMMARY AND CONCLUSIONS ................................................................................. 15
ii Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
LIST OF FIGURES
1 Site Location Map
2 Site Base Map
3 Soil Analytical Sample Depths and Total Borehole Depths
4 Groundwater Monitoring Well Locations
5 Groundwater Results – Benzene, Naphthalene, Benzo(a)Pyrene
6 Soil RBTL Exceedance Summary (0-3’ Interval)
7 Soil RBTL Exceedance Summary (3-10’ Interval)
8 Soil RBTL Exceedance Summary (10-15’ Interval)
9 Soil RBTL Exceedance Summary (15-20’ Interval)
10 Soil RBTL Exceedance Summary (20-25’ Interval)
11 Soil RBTL Exceedance Summary (Planned Removal Area/Depth 0-15’)
LIST OF TABLES
1 Soil–Default Target Level Comparison (ND@1xDL)
2 Soil–Default Target Level Comparison ([email protected])
3 Exposure Model–Complete Pathway(s)/Exposure Media-Future Non-Residential Use
4 Groundwater Results: All COC – EOI 2005-2011
5 Groundwater Results: Detected COC Only – EOI 2005-2011
6 Soil RBTL Comparison: Construction Worker Combined Exposure (0-10’)
7 Soil RBTL Comparison: Non-Residential Combined Exposure (0-3’)
8 Soil RBTL Comparison: Non-Residential Indoor Vapor Inhalation Exposure (3-25’)
9 Acceptable Risk Evaluation Summary
LIST OF ATTACHMENTS
1 MDNR Letter Dated June 18, 2013, Re: Columbia FMGP
2 PSC Borehole Logs (SB-19 to SB-28) – 2013 Supplemental Soil Investigation
3 Laboratory Analytical Soil Report – 2013 Supplemental Soil Investigation
4 City of Columbia, MO Zoning District Map (8/17/2012)
5 MDNR Letter Dated November 8, 2013, Re: Columbia FMGP 2013 Borehole Sealing
1 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
EXECUTIVE SUMMARY
Soil remediation at the Columbia [MO] Coal Gas-East Parcel located in Columbia, Missouri is
targeted for the first half of 2014. In preparation for the pending soil remediation, Ameren
Services desires Missouri Department of Natural Resources (MDNR) approval of this
submittal, along with a PSC risk management plan provided separately, that covers soil
characterization and interim risk assessment updates developed since the MDNR letter dated
June 18, 2013. Following soil remediation, and subsequent groundwater confirmation
sampling activities, a closeout report will be provided for final project closure approval by
MDNR. Future site use will be suitable for non-residential purposes with a non-domestic use
groundwater activity use limitation.
2 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
1.0 INTRODUCTION
On behalf of Ameren Services (Ameren), PSC Industrial Outsourcing, LP (PSC) has
prepared this submittal for the Columbia [MO] Coal Gas-East Parcel (MGP) located in
Columbia, Missouri (Site). This submittal has been prepared to provide the results of
soil characterization and risk assessment activities performed by PSC in 2013, which
update the Supplemental Site Characterization Report (SSCR) and Tier 1 Risk
Assessment by Civil & Environmental Consultants, Inc. (CEC) dated August 2007 and
February 2008, respectively. The Missouri Department of Natural Resources (MDNR)
Brownfields/Voluntary Cleanup Program approved the CEC submittals in a letter dated
June 18, 2013.
The Site location in Columbia, Missouri and the current site conditions are illustrated on
two attached figures: Figure 1 (Site Location Map); and Figure 2 (Site Base Map).
3 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
2.0 UPDATES TO THE SUPPLEMENTAL SITE CHARACTERIZATION REPORT
Additional characterization of soil was performed during the June 2013 Supplemental
Soil Investigation (SSI) per the SSI Work Plan dated June 5, 2013, with the following
exception. In accordance with comment #6 in the June 18, 2013 MDNR letter (see
Attachment 1), the background arsenic soil sampling locations were eliminated and the
MDNR-provided background concentration for arsenic of 18.1 mg/kg was utilized. The
text below briefly outlines the work performed during the SSI.
Ten (10) direct-push probe locations, SB-19 to SB-28, were completed by Brotcke Well
& Pump, Inc. on June 24-25, 2013. Direct-push probe refusal depths ranged between
14 and 16.5 feet below ground surface (bgs). Soil samples for analysis were collected
as follows:
• 2-3 feet bgs: Six (6) locations - (SB-19, 20, 21, 22, 23, 24, and 26); and
• >3 feet bgs: Ten (10) locations - (seven locations where two samples were
collected for laboratory analysis and three locations where one sample was
collected).
PSC’s borehole logs and the laboratory soil sample analysis report are included as
Attachments 2 and 3, respectively. The soil samples were analyzed for Site chemicals
of concern (COCs) including volatile organic compounds (VOCs), semi-volatile organic
compounds (SVOCs) and inorganic compounds. The new borehole locations, sample
depths, and total borehole depths are summarized on Figure 3, along with those from
the previous (1990-91 and 2007) site investigations. The boreholes were backfilled
with bentonite chips, as documented on the well plugging registration record (ref no.
487067; included in Attachment 2), which was submitted to the MDNR. A letter from
the MDNR dated November 8, 2013 confirmed that these boreholes were plugged
according to Missouri Well Construction rules (Attachment 5).
4 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
3.0 UPDATES TO THE TIER 1 RISK ASSESSMENT – SITE CONCEPTUAL
MODEL
Based on the findings from the June 2013 SSI, updates to the Site Conceptual Model
(SCM) in the Tier 1 Risk Assessment are outlined in the following subsections.
3.1 Distribution of COCs in Soil
The soil Type 2 classification determined in the CEC Tier 1 Risk Assessment was
observed in direct-push probe holes SB-19 through SB-28. PSC concludes that the
soil Type 2 classification remains applicable for the Site. Probe refusal depths were
similar to those encountered during the previous site investigations. The general
findings suggest the following:
• Soil samples for SB-19, 20, and 26, in or adjacent the west edge of the
central Metal Storage Building, have impact at levels that indicate soil
remediation beneath the building is not required;
• Subsurface impact extends toward the southwest corner of the property
(as far as SB-23);
• Subsurface impact extends northwest of the slab-at-grade foundation of
Gas Holder GH-3; and,
• Soil impacts extend below the storm water sewer that is present on the
southern one-third of the property (along the south side of Gas Holder
GH-2). Historic photographs of the Site suggest that the storm water
sewer (concrete box culvert) apparently was constructed along the
approximate path of an historic creek, resulting in a suspected
preferential migration pathway.
5 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
3.2 Current/Future Land and Groundwater Use
Current and potential future land and groundwater use assumptions for the Site are
discussed below:
Current Land Use
Ameren currently owns the Site property. Zoning reference records for the
property are provided in Attachment 4. The property is located in City Zoning
Map Grid F7, and is zoned as M-1 (General Industrial). The properties
surrounding the Site are zoned either M--1 or C-2 (Central Business).
As of October 2013, Ameren operations have been permanently relocated
from the Site to new facilities. The property is currently vacant and paved
with four slab-on-grade building structures, and is fenced at the property
boundary to limit third party access.
Private utilities on-site (Figure 2) include overhead electric and
communications, and subsurface water, sanitary sewer, storm water, natural
gas, and electric utilities. Public subsurface utilities traversing the site include
sanitary and storm water sewers.
Future Land Use
Ameren intends to make the property available for sale after the completion of
the planned 2014 remedial actions. PSC assumes that Site redevelopment will
be consistent with the current zoning for the Site as General Industrial or
Central Business use, which is consistent with the surrounding property use.
The RMP will include a condition that the Activity Use Limitations (AULs)
will be placed on the property title, limiting future site use to non-residential
use because of the soil remediation objectives planned as part of the RMP.
Groundwater Use
Groundwater is not used at the Site, and the area is supplied by City water for
domestic use purposes currently, which is also the anticipated future status.
3.3 Known or Proposed Land or Water Use Restrictions
Domestic groundwater use is not currently prohibited by City Ordinance or the
property deed. For purposes of site closure and property transfers after the
Remedial Action, an AUL for groundwater use restriction prohibiting the
domestic use of the groundwater within the property boundary will be placed on
the property deed.
6 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
3.4 Chemicals of Concern
This section provides an update for the screening of chemicals below the default
target levels (DTLs), including the addition of the June 2013 SSI data.
3.4.1 Chemicals Retained / Excluded for Evaluation
Comment #2 of the MDNR letter dated June 18, 2013, MDNR requested Total
Petroleum Hydrocarbon-Gasoline Range Organics (TPH-GRO) be included in
future evaluations of Site soil although TPH-GRO was not part of the Tier 1
Risk Assessment data comparison set. The 2013 soil sampling TPH-GRO
results exceeded the DTL, so the parameter has been retained in our revised
evaluation as noted below.
Table 1 includes a comparison of the Missouri Risk-Based Corrective Action
(MRBCA) Default Target Levels to maximum and individual COC
concentrations for the selected soil evaluation depth interval. Table 2 presents
the same comparison as Table 1 but presenting one-half the detection limit for
non-detects. There are a total 49 unique COC on each table (Naphthalene was
analyzed by both VOC/SVOC methods).
Two (2) of the 49 parameters historically included with the 1990-1991, 2007,
and 2013 site data sets are considered common laboratory contaminants, and are
not typically associated with coal gasification processes. Therefore, the two
parameters listed below were not deemed necessary to be retained for further
soil evaluation.
- Acetone - 2-Butanone (MEK)*
Of the remaining 47 parameters from the combined soil analysis data sets of the
1990-1991, 2007, and 2013 site investigations, twenty two (22) parameters
listed below had maximum concentrations below the DTL, and were eliminated
from further evaluation.
- 1,2,3-Trimethylbenzene
- 2-Methylphenol
- 2,4-Dimethylphenol
- 3&4-Methylphenol*
- Anthracene
- Barium
- Benzo(g,h,i)perylene
- Benzo(k)fluoranthene
- Cadmium
- Chromium
- Chrysene
- Fluoranthene
- Isopropyl benzene
- Mercury
- n-Propyl benzene
- Phenol
- Pyrene
- p-Isopropyl toluene
- Sec-Butyl benzene
- Styrene
- Total Cyanide
- TPH - Oil Range Organics
*COC excluded because only an elevated detection limit exceeded the DTL
7 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
The remaining twenty five (25) COCs with DTL exceedances retained for further
evaluation included:
- 1,2,4-Trimethylbenzene
- 1,3,5-Trimethylbenzene
- 2-Methylnaphthalene
- Acenaphthene
- Acenaphthylene
- Arsenic
- Benzene
- Benzo(a)anthracene
- Benzo(a)pyrene
- Benzo(b)fluoranthene
- Biphenyl
- Carbazole
- Dibenzofuran
- Dibenzo(a,h)anthracene
- Ethylbenzene
- Fluorene
- Indeno(1,2,3-cd) pyrene
- Lead
- Naphthalene
- Phenanthrene
- Selenium
- Toluene
- TPH Diesel Range Organics
- TPH Gasoline Range Organics
- Xylenes
3.5 Exposure Model
This section includes an updated exposure pathway evaluation (summarized in
Table 3), and discusses pathways eliminated or retained for pathway and soil type-
specific risk-based target level (RBTL) comparisons to applicable soil and
groundwater data for the assumed non-residential future land use scenario to be
used for the property.
3.5.1 Domestic Use of Overburden Groundwater
As acknowledged in comment #4 of the June 18, 2013 MDNR letter, MRBCA
RBTL criteria comparisons for the domestic groundwater use exposure pathway
for groundwater in the overburden have been excluded. As requested in
comment #4, additional detail supporting the exclusion of the domestic
groundwater use exposure pathway for overburden groundwater is discussed
below.
As part of the demonstration for the exclusion of the domestic use of the
overburden groundwater pathway, a groundwater plume stability demonstration
is provided below. Figure 4 illustrates the locations of 11 groundwater
monitoring wells (MW-series) associated with the Site and the 1994 remediation
area west of the Site. Seven (7) of the wells (MW-1, 2, 3B, 4, 5, 6, 8) remain
available for sampling. The remaining four wells were abandoned either during
the 1994 remediation (MW-3), or since the 1994 remediation (MW-7, MW-9,
and MW-10). MW-1 to MW-4 were installed in 1990, and MW-5 to MW-7
were installed in 1991 (Atlantic, 1992). MW-3 was abandoned as part of the
1994 remediation activities, as it was within the excavation area, and was since
replaced by monitoring well MW-3B. Monitoring well MW-8 replaced
monitoring well MW-7, which was damaged and subsequently abandoned.
Monitoring wells MW-9 and MW-10, installed at the same time as MW-8,
8 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
were abandoned in 2006 at the request of the property owner when the land on
which they were located (formerly part of an abandoned railroad right-of-way)
was acquired for property expansion.
Groundwater monitoring at the Site was required by an Administrative Order on
Consent (AOC) for the Remedial Action that Union Electric (now Ameren)
entered into with the United States Environmental Protection Agency (USEPA)
Region VII on February 14, 1994. During the biannual sampling events from
2005-2011, which were performed by Environmental Operations Inc. (EOI) on
behalf of Ameren and reported to the MDNR by Ameren, only four (4) of the
remaining monitoring wells (MW-1, MW-4, MW-6, and MW-8) were sampled
in accordance with an approved groundwater sampling plan. Well MW-3B has
not been sampled because of the presence of MGP process residual free product
in the well (which was removed during monitoring events and has diminished to
less than one inch or material). Flow in the overburden groundwater in the
vicinity of the Site has been to the west-northwest (as reported by EOI). MW-1
is the only on-site well, and MW-4 is considered the key down-gradient well for
the Site. Potential off-site COC sources include, but may not be limited to, the
former western MGP area and a former fuel station up-gradient of MW-6 and
MW-8.
Polycyclic Aromatic Hydrocarbon (PAH) and Volatile Organic Compound
(VOC) groundwater results for wells MW-1, 2, 4, 6, & 8 tested during the EOI
2005-2011 biannual monitoring events, are presented on Table 4. Seven (7)
PAH and fourteen (14) VOC COCs were detected at least once, as presented on
Table 5. Groundwater data for the three primary soil COCs, (benzene,
naphthalene, and benzo(a)pyrene) are presented for the 2005-2011 biannual
events on Figure 5. The groundwater concentration trends with time appear to
be stable or decreasing, which suggests that the groundwater use exposure
pathway exclusion for the overburden groundwater is suitable.
Reports referenced for the groundwater exposure pathway exclusion
demonstration included:
• Remedial Investigation Report (Atlantic Environmental - 3/1992);
• 2005 Groundwater Monitoring Event Results (EOI - 8/2005);
• 2007 Groundwater Monitoring Event Results (EOI - 8/2007);
• 2009 Groundwater Monitoring Event Results (EOI - 9/2009); and
• 2011 Groundwater Monitoring Event Results (EOI - 9/2011).
The RMP for the Site remedial actions indicates that Ameren will submit a
groundwater monitoring plan for post-remedial action groundwater monitoring
at the Site.
9 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
3.5.2 Site Surficial Soil
Surficial soil exposure pathways deemed complete for non-residential land use
evaluation included:
• Non-Residential Combined* (0 - 3 feet below ground surface) -
*“Combined” refers to the direct contact pathway for outdoor inhalation
(vapors and particulates), ingestion, and dermal exposure pathways in
combination; and
• Construction Worker Combined (0 - 10 feet below ground surface) –
This depth interval is a modification from the 0 - 3 foot interval
considered in the CEC report, and reflects potential future subgrade
construction (e.g. underground parking level).
3.5.3 Site Subsurface Soil
Subsurface soil exposure pathways deemed complete for non-residential land
use evaluation included:
• Non Residential Indoor Inhalation of Vapor Emissions (3 - 25 feet) –
This pathway comparison depth interval was selected assuming
groundwater was not applicable within the overburden.
3.6 Saturated Soil Concentration
As indicated in comment #8 of the June 18, 2013, MDNR letter, MRBCA RBTL
criteria comparisons for saturated soil exposure pathways have been excluded.
3.7 Representative Concentration Calculations
This section includes updated representative concentration considerations based
on the sample location population and exposure pathway route comparison being
considered.
For the COCs retained following the DTL comparison screening, representative
concentrations were calculated for the COCs in an exposure pathway comparison
scenario if the maximum concentration was above the comparison RBTL. The
representative concentration was calculated as the arithmetic average for the
sample population groupings comprising individual sample locations marked as
“Y” below the sample identifications on Tables 6, 7, and 8 (collectively referred to
as “comparison tables” hereafter), which means the result is retained for the
evaluation scenario). The concentration used in the arithmetic average
calculation was the result for detected or estimated results, or one-half the
detection limit if the result was non-detect.
10 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
On the comparison tables, the representative concentrations and individual sample
results are color highlighted if they exceed their respective RBTL. Individual
sample results are also underlined if the concentration exceeds 10 times its
calculated representative concentration.
3.8 Individual or Representative Concentration Exceedances and Planned
Removal Summary
This section summarizes the locations with individual sample or representative
concentration-based exceedances of the RBTL or threshold criteria.
3.8.1 Evaluation of Exposure Domain and Exclusion Considerations
For each exposure pathway scenario discussed below, select samples were
excluded from the evaluation set, leaving a grouping of locations to remain
following remediation, which constitute the exposure domain. The exposure
domain is defined by 10 CSR25-18(1)13 as “the area that can result in a
particular receptor being exposed to COCs by a specified exposure pathway”.
Potential exposure across the entire property for future uses is considered likely,
so no specific subarea of interest was evaluated.
Besides sample locations not being applicable for the exposure pathway depth
interval of interest on a specific basis, there were other samples excluded from
the evaluations including:
• Locations not included in the Tier 1Risk Assessment data sets (1990-
1991 & 2007) and those without analytical results (B-3 to B-7, B-9 to B-
13, B-22, B-24 to B-32, SB-9);
• Locations outside the property boundaries (B-1, B-2, SB-13, SB-14, and
SB-22);
• Locations at the property boundaries believed to have been remediated in
1994 (B-8);
• Sample duplicates that would bias representative concentration/risk
results; and
• Locations and depths planned for removal during the 2014 Remedial
Action due to direct RBTL, 10x representative concentration
exceedances, or otherwise on a voluntary or as-desired/needed basis (e.g.
un-impacted intervals above impacted intervals, excavation slope
stability requirements, gross visible impact, etc.).
Sample locations and depths retained as part of the exposure domain for the
evaluation scenarios discussed below are marked by “Y” on the comparison
tables, meaning the soil will be left in-place as part of the “residual” exposure
11 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
domain. Sample locations and depths excluded from the evaluation tables for
the reasons noted above are marked as “N” on the evaluation tables.
3.8.2 Exposure Pathway Scenario Evaluation Results
Exposure pathway scenario evaluation results are discussed below:
Surficial Soil: Construction Worker Combined (0 - 10 foot interval) – As shown
on Table 6 and Figure 6 (for the 0 - 3 foot interval), the individual
results/maximum and representative concentrations were below the RTBL.
As shown on Table 6 and Figure 7 (for the 3 - 10 foot interval), the individual
naphthalene results for B-14(5-6) and B-16(5-5.7) exceeded the RBTL. The
representative concentration with the individual exceedances excluded was
below the RBTL.
Surficial Soil: Non-Residential Combined (0 - 3 foot interval) – As shown on
Table 7 and Figure 6, the individual results/maximum and representative
concentrations were below the RTBL.
Surficial Soil: Non-Residential Indoor Vapor Inhalation (3 - 25 foot interval) –
The evaluation for this exposure pathway interval is shown on Table 8, and on
Figures 7 through 10. The figures cover the 3 - 10, 10 - 15, 15 - 20, 20 - 25 foot
depth intervals, respectively, as discussed below.
• 3 - 10 Foot Depth Interval (Figure 7) – Individual result or 10x
Representative Concentration exceedances of the RBTL for benzene or
naphthalene occurred at three locations within the planned soil
remediation interval: SB-11(5-7), B-14(5-6), and B-16(5-5.7).
• 10 - 15 Foot Depth Interval (Figure 8) – Individual result or 10x
Representative Concentration exceedances of the RBTL for benzene or
naphthalene occurred at nine locations (not including excluded locations
B-8 and SB-22) within the planned soil remediation interval:
SB-11(12-14), SB-12(10-12), SB-18(11-13), B-16(13.8-14.2), B-
20(13.5-14.5), B-21(12.7-13.2), SB-24(13-14), SB-25(13-14), and SB-
27(13-14).
• 15 - 20 Foot Depth Interval (Figure 9) – Individual result exceedances or
10x Representative Concentration exceedances of the RBTL for
naphthalene occurred at two locations outside the planned soil
remediation interval: B-18 (16.2-16.5) and SB-21(15-16).
• 20 - 25 Foot Depth Interval (Figure 10) – No individual result
exceedances or 10x Representative Concentration exceedances of the
RBTL occurred for this interval.
12 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
3.8.3 Exposure Scenario Evaluation Summary vs. Planned Removal
A summary of the benzene and naphthalene RBTL exceedances versus the
planned soil remediation area is shown on Figure 11. RBTL exceedance
locations other than those listed below fall within the planned soil remediation
area/interval (0 - 15 feet):
• B-8(10–11) is at the property boundary where the 1994 remediation
activities ended. It has a benzene non-residential indoor vapor inhalation
exceedance concentration less than 10 times the exposure domain
representative concentration. In addition, construction of a building
would not be anticipated in the vicinity of this location, so receptor
exposure for the non-residential indoor vapor inhalation RBTL
exceedance would not be considered complete regardless;
• B-18(16.2-16.5) has a naphthalene exceedance greater than 10 times the
exposure domain representative concentration, but the cumulative site-
wide risk for naphthalene is within the acceptable risk. This area of the
Site will not be excavated in order to avoid disturbing the sanitary sewer
in this area of the Site;
• SB-21(15-16) has a naphthalene non-residential indoor vapor inhalation
exceedance concentration less than 10 times the exposure domain
representative concentration. This area of the Site will not be excavated
in order to avoid disturbing the sanitary sewer in this area of the Site; and
• SB-22 is located off the property. The sample from a depth of 11-12’
has exceedances of the non-residential indoor vapor inhalation exposure
pathway RBTL for benzene, naphthalene, and 1,3,5-trimethylbenzene.
A building would not be anticipated in the vicinity of this sample
location so receptor exposure for the non-residential indoor vapor
inhalation RBTL exceedance would not be considered complete;
With the planned 2014 Remedial Action, the maximum or representative
concentrations of the exposure domain are less than the RBTL.
13 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
4.0 POST-PLANNED REMEDIAL ACTION RISK EVALUATION (TOTAL AND
CUMULATIVE SITE-WIDE)
A description of the total risk and cumulative site-wide risk calculation updates conducted
pursuant to 10 CSR25-18(D)(1,2) are discussed for carcinogenic and non-carcinogenic
scenarios below. These updates pertain to Sections 8.0 and 9.0 of CEC’s Tier 1 Risk
Assessment Report.
4.1 Carcinogenic Risk Evaluation (D)(1)
On Tables 6, 7, and 8, each retained carcinogenic COC has its total risk
calculated. The contributing risk was calculated as either the maximum or
representative concentration times 10-5
and divided by the comparison RBTL. If
the maximum concentration for a retained COC was less than the comparison
RBTL, then the maximum concentration was used to calculate the retained
carcinogenic COC risk. Otherwise, if the maximum concentration for a retained
carcinogenic COC was greater than the comparison RBTL or threshold criteria
concentration, then the representative concentration was used to calculate the
retained carcinogenic COC risk.
Table 9 summarizes the total risk for each retained carcinogenic COC. The total
risk is the sum of all the complete individual exposure risks, which was compared
to the acceptable Individual Excess Lifetime Cancer Risk (IELCR) of 10-5
. The
cumulative site-wide risk was calculated as the sum of the total risks for all
retained carcinogenic COCs, which was compared to the acceptable risk threshold
of 10-4
.
For the planned removal scenario, the only parameter with a total risk above the
acceptable threshold of 10-5
was arsenic, with a value of 1.025x10-5
. This very
slight exceedance is conservative when taking into consideration the planned
removal of the side wall slopes, and is therefore deemed insignificant. The
removal of the 0 - 3 foot soil interval will be greater than the assumed residual
locations evaluated, since an additional perimeter area of 18 feet outside the
planned 15-foot deep removal area will also have the 0 - 3 foot interval removed.
4.2 Non-Carcinogenic Risk Evaluation (D)(2)
On Tables 6, 7, and 8, each retained non-carcinogenic COC has its hazard quotient
calculated. The contributing hazard quotient for a retained non-carcinogenic COC
was calculated as either the maximum or representative concentration divided by
the comparison RBTL. If the maximum concentration for a retained non-
carcinogenic COC was less than the comparison RBTL, then the maximum
concentration was used to calculate the retained non-carcinogenic COC hazard
quotient. Otherwise, if the maximum concentration for a retained non-
carcinogenic COC was greater than the comparison RBTL or threshold criteria
concentration, then the representative concentration was used to calculate the
retained non-carcinogenic COC hazard quotient.
14 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
Table 9 summarizes the retained non-carcinogenic COC hazard quotients, the
individual COC-specific hazard index, and the site-wide hazard index. The hazard
quotients were transferred from each complete exposure pathway evaluation. The
COC-specific hazard index (total risk) is the sum of the complete exposure
pathway hazard quotient on an individual basis for each COC. The site-wide
hazard index is the sum of COC-specific hazard indexes. The total risk and site-
wide hazard indexes were compared to the acceptable risk of 1 for both cases. All
non-carcinogenic risk concentrations were below their acceptable risk thresholds.
4.3 Individual Residual Borehole Risk Evaluation
Tables 9-1 to 9-4 of CEC’s Tier 1 Risk Assessment report calculate the
carcinogenic and non-carcinogenic risks by individual location to remain outside
the exposure domain. Tables 6, 7, and 8 of this report calculate these risks using
the parameter groupings indicated below:
COCs Used For Location Risk Calculation (See table COC highlighting)
Carcinogenic (yellow highlight) Non-carcinogenic (blue highlight)
Benzene Ethylbenzene
Naphthalene Toluene
Benzo(a)Anthracene 1,2,4-Trimethylbenzene
Benzo(b)Fluoranthene 1,3,5-Trimethylbenzene
Benzo(a)Pyrene Xylenes
Carbazole Acenaphthene
Dibenzo(a,h)Anthracene Acenaphthylene
Indeno(1,2,3-c,d)Pyrene Fluorene
Arsenic 2-Methylnaphthalene
Phenanthrene
Lead
Selenium
TPH – Gasoline Range Organics
TPH – Diesel Range Organics
COCs Not Used in Grouping For Location Risk Calculation (No highlight)
Biphenyl
Dibenzofuran
None of the individual borehole carcinogenic and non-carcinogenic risks exceeded their
individual acceptable risk criteria of 10-5
and 1, respectively.
15 Columbia FMGP Site Update No. 1 Report
PSC Project 624-1302-0002 December 2013
5.0 SUMMARY AND CONCLUSIONS
The PSC 2013 soil characterization update identified additional impact beyond that
covered in the CEC2007 report. The PSC 2013 Tier 1 risk assessment identified soil
impact risks to be addressed under a separate risk management plan (RMP). The soil
remediation of interest based on this risk assessment update consists of subsurface soil
(primarily 3-15 feet) around the vicinity of Gas Holder #2 and #3, and the concrete box
culvert.
Following soil remediation activities, a final groundwater sampling event will be
performed, and a final remediation/risk assessment close out report will be submitted to
MDNR for site closure. The close out report will provide an overview of the
performance based remediation activities and confirmation results, the groundwater
results, and the post-remediation final risk assessment.
Based on the post-remediation cumulative site-wide risk, the residual impact will be
proposed to remain in place for a MDNR-approved closure that will allow for future
non-residential site use and include a non-domestic groundwater activity use limitation.
LIST OF FIGURES
1 Site Location Map
2 Site Base Map
3 Soil Analytical Sample Depths and Total Borehole Depths
4 Groundwater Monitoring Well Locations
5 Groundwater Results – Benzene, Naphthalene, Benzo(a)Pyrene
6 Soil RBTL Exceedance Summary (0-3’ Interval)
7 Soil RBTL Exceedance Summary (3-10’ Interval)
8 Soil RBTL Exceedance Summary (10-15’ Interval)
9 Soil RBTL Exceedance Summary (15-20’ Interval)
10 Soil RBTL Exceedance Summary (20-25’ Interval)
11 Soil RBTL Exceedance Summary (Planned Removal Area/Depth 0-15’)
LIST OF TABLES
1 Soil–Default Target Level Comparison (ND@1xDL)
2 Soil–Default Target Level Comparison ([email protected])
3 Exposure Model–Complete Pathway(s)/Exposure Media-Future Non-Residential Use
4 Groundwater Results: All COC – EOI 2005-2011
5 Groundwater Results: Detected COC Only – EOI 2005-2011
6 Soil RBTL Comparison: Construction Worker Combined Exposure (0-10’)
7 Soil RBTL Comparison: Non-Residential Combined Exposure (0-3’)
8 Soil RBTL Comparison: Non-Residential Indoor Vapor Inhalation Exposure (3-25’)
9 Acceptable Risk Evaluation Summary
LIST OF ATTACHMENTS
1 MDNR Letter Dated June 18, 2013, Re: Columbia FMGP
2 PSC Borehole Logs (SB-19 to SB-28) – 2013 Supplemental Soil Investigation
3 Laboratory Analytical Soil Report – 2013 Supplemental Soil Investigation
4 City of Columbia, MO Zoning District Map (8/17/2012)
5 MDNR Letter Dated November 8, 2013, Re: Columbia FMGP
Attachment 1
MDNR Letter Dated June 18, 2013, Re: Columbia FMGP
Attachment 2
PSC Borehole Logs (SB-19 to SB-28) – 2013 Supplemental Soil Investigation
Attachment 3
Laboratory Analytical Soil Report – 2013 Supplemental Soil Investigation
Attachment 4
City of Columbia, MO Zoning District Map (8/17/2012)
Attachment 5
MDNR Letter Dated November 8, 2013 Re: Columbia, MO FMGP Site