Presentation Outline
• Introduction to Strathcona County
• Types of Projects We Do
• Types of Consulting Assignments
• Heartland Industrial Area
• Emerging Issues
• Questions?
2
Who and Where Are We?
1/18/2018 3
Strathcona County:
• is a specialized municipality east of Edmonton
• includes an urban services area (Sherwood Park) and 8 rural hamlets
• specializes in agriculture and petroleum
• has a population of 100,000• occupies 1182 km2
• includes 75% of western Canada’s refining capacity
• 1308 kms Rural Roads• 403 kms Urban Roads
What We Do..
1/18/2018 7
And where we most often work with consulting specialists in the fields of engineering, landscape architecture, and planning…
Recreation and Open Space Development
Recreational Space Development Boulevard Enhancement
1/18/2018 11
Type of Assignments
Transportation Planning
• Functional Planning Studies
• Traffic Impact Assessments
• Transportation Master Plans
Transportation and Open Space Construction
• Preliminary Engineering (Surveying, Geotechnical Investigation, Etc.)
• Detailed Design and Tender Preparation
• Contract Administration
1/18/2018 14
Types of Assignments (Cont’d)
Planning and Development
• Area Concept Plans
• Area Structure Plans
• Growth Management Studies
• Land Procurement
Underground Utilities
• Water, sewer, and storm engineering, design and contract administration
• Water, sewer, and storm Master Plans
Facilities
• Building engineering, design and contract administration
1/18/2018 15
TPE Projects (Expected Assignments)
• 2018:
– Twp Rd 550, from Rge Rd 221 to Hwy 830, Widening
– Annual Missing Links Sidewalk Program
• 2019-2022:
– Hwy 15S Service Road, from Rge Rd 231 to Rge Rd 212, New Construction
– Rge Rd 232, from Wye Road to Estate Drive, Widening
– Rge Rd 231, from Wye Road to Hillshire Blvd, Widening
– Rge Rd 233, from Fountain Creek Way to Hwy 628, Widening
– Sherwood Drive/Broadmoor Roundabout, Reconstruction
– 34th Street from Sherwood Park Freeway to Baseline Rd, Widening
1/18/2018 16
1/18/2018 17
TPE PROJECTS (Cont’d)
• 2019-2022 (Cont’d):
– Broadmoor Blvd, from Baseline Rd to Pembina Rd, Widening
– Baseline Rd and Broadmoor Blvd Intersection Improvements FPS
– Class 1 Grid Rd Improvement (Locations TBD)
– Missing Sidewalk Links Program (Annually)
Utilities Projects
• 2018:
– Ardrossan Water Supply New Main (from Sherwood Park) – Design, and Land
• 2019-2022:
– Ardrossan Water Supply New Main - Construction
1/18/2018 20
Facilities Projects
• 2018:
– Kinsmen Leisure Centre Pool Family Change Rooms
– Annual Facility Lifecycle Program
• 2019-2022:
– Public Transit ‘Bus Barn’ Expansion
– Annual Facility Lifecycle Program
– Community Hub (FCS)
1/18/2018 21
Heartland Industrial Area
• Canada’s Largest Hydrocarbon Processing Region
• Over $12 Billion of New Projects Announced, Under Construction, or Recently Completed
1/18/2018 22
Recent Projects
• Air Products – Hydrogen Production Plant
• Atco Power – Scotford Cogeneration Plant
• CNR – Oil and Gas Distribution Centre
• Heartland Sulfur Transfer Terminal
• Keyera Josephburg Rail Terminal – propane loading facility
• Shell Scotford Upgrader and Manufacturing Facility
• Shell QUEST project – carbon capture and sequestration
1/18/2018 24
Proposed Projects
• ATCO Heartland Generating Station -proposal to build and operate a 400 MW natural gas power generating station
• Gibson Energy – crude and Natural Gas Liquids (NGL) Terminal
• Inter Pipeline–propane dehydrogenation and polypropylene facility~$3.5B
• TransCanada Pipelines Ltd – TransCanada Terminals Project
1/18/2018 25
Heartland Activity
• Requires:
– Potable Water
– Rail Facilities
– General Access Roads
– Heavy Haul Roads
• Strathcona County is a partner in infrastructure improvements through CIAC Agreements (Contribution in Aid of Construction), or site specific contribution agreements; these projects often require the assistance of consulting engineers to help us implement the work.
1/18/2018 26
Emerging Issues
• Procurement Changes (goods, services, construction)
– Adjusting to CFTA and CETA Requirements – longer tender periods for major construction; requirement to post bid results (including consulting RFP’s) on APC
– No longer having public tender openings (at Strathcona County)
– Cannot accept “free” advice in preparing scope or terms of reference for an RFP – if that consultant wants to propose;
– Negotiated format RFP’s (BAFO or ‘Best and Final Offer’ - similar to Quality Based Selection)
– Considering Pre-Qualification for Construction Contractors
• Updating Design and Construction Standards – in review with UDI
• Redesigned Strathcona County Website – more user friendly – topic based