University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
![Page 2: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/2.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Substantial completion is scheduled for April 15, 2011.
Move in is scheduled for July 1st – July 15th, 2011
![Page 3: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/3.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
* 30kW bifacial photovoltaic solar panels system functional in the process of commissioning.
![Page 4: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/4.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Interior finishes: •Drywall is almost complete and painted. •Resilient flooring and carpeting is almost complete. •Ceramic tiling of the washrooms is complete. •Terrazzo work on the ground floor is ongoing. •Installation of T-bar ceiling tiles and fixtures is ongoing. •The contractor is currently working on the feature stair glazing, balustrades, vestibules, and doors.
![Page 5: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/5.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Feature staircase
![Page 6: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/6.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Building interior furnishings, Audio Visual and lighting installation is 95% complete
![Page 7: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/7.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
500, 350, 150, 100, lecture theaters complete with fixed seating and acoustical paneling in place
![Page 8: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/8.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
•Envelope: Glazing and stainless steel fins are installed.
•Installation of stainless steel V panels is almost complete on the 2nd floor and progressing on the other floors.
•The glazing of the bridge is yet to be installed.
![Page 9: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/9.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
![Page 10: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/10.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Lab benches are installed.
![Page 11: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/11.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Termination and tie-in activities are ongoing. Millwork installation is ongoing.
![Page 12: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/12.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
Lecture theatres are installed.
![Page 13: University of Toronto Mississauga Campus Capital Projects University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9,](https://reader030.vdocuments.us/reader030/viewer/2022020417/56649e705503460f94b6e9a9/html5/thumbnails/13.jpg)
University of Toronto Mississauga CampusCapital Projects
University of Toronto Mississauga Campus: Capital Projects Erindale College Council | March 9, 2011
M&E equipment start-up, verification and balancing are ongoing. Weekly meetings with consultants and contractors to ensure timely and successful commissioning process.