united states ** nuclear regulatory commission · -2-march 21, 2000 by the same approach under 10...

65
UNITED STATES ** NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 21, 2000 LICENSEE: Baltimore Gas and Electric Company FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 SUBJECT: SUMMARY OF THE DECEMBER 14,1999, MEETING REGARDING CORROSION BEHAVIOR OF FUEL CLADDING AT CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 (TAC NOS. MA6875 AND MA6876) On December 14, 1999, the Nuclear Regulatory Commission (NRC) staff held a meeting at the NRC offices in Rockville, Maryland with representatives from Baltimore Gas and Electric Company (BGE) the licensee for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 and their consultants ABB - Combustion Engineering Nuclear Power, Inc. (ABB - CENP) to discuss corrosion behavior of fuel cladding at Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2. Enclosure 1 is a list of attendees. Enclosure 2 is a copy of the nonproprietary viewgraphs distributed at the meeting. The licensee stated that an inspection was performed on fuel that had been discharged from Unit 2 at the end of Cycle 12 and on a lead assembly. As part of the inspection, visual examinations were performed on several high duty fuel assemblies, assemblies that had seen a high rate of burnup in the two cycles in which they were in the core. The visual examinations resulted in the observation that some fuel rods exhibited blistering of the oxide layer, and some fuel rods showed evidence of early stages of spalling. Based on these observations, several assemblies were taken apart for more detailed inspection of individual fuel rods. The fuel rods were visibly examined and the oxide layer thickness were measured on some of the rods. Some fuel rods, particularly peripheral fuel rods, had measured oxide thicknesses that were higher than predicted by the vendor's corrosion model. The licensee then described the immediate actions taken which included a voluntary Licensee Event Report (LER), initiating a root cause evaluation and performing an operability evaluation to support current cycles operation. The root cause evaluation concluded that the factors affecting fuel duty are the primary contributors to the unexpected behavior. These factors include: improved operating history, reduced reactor coolant system flow due to plugged steam generator tubes, rod location within the assembly, rod power and adjacent rod power, subcooled boiling and thermal hydraulics effects due to geometry. The operability evaluation determined that there was no concern for normal operation. In addition, it addressed accidents and transients. A preliminary fuel duty model was developed by ABB CENP which uses an improved corrosion model. A fuel duty index was evaluated which is a function of time and temperature. Fuel duty comparisons were made between CC2N and past and current batches which showed fuel duties for current cycles and CC2N are similar. Based on these comparisons, the licensee concluded that the current cores are operable. Finally, the licensee indicated that near term cores (up to and including Unit 2 Cycle 14 (U2C14)) will be evaluated SFo;

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

UNITED STATES ** NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

March 21, 2000

LICENSEE: Baltimore Gas and Electric Company

FACILITY: Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2

SUBJECT: SUMMARY OF THE DECEMBER 14,1999, MEETING REGARDING CORROSION BEHAVIOR OF FUEL CLADDING AT CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 (TAC NOS. MA6875 AND MA6876)

On December 14, 1999, the Nuclear Regulatory Commission (NRC) staff held a meeting at the NRC offices in Rockville, Maryland with representatives from Baltimore Gas and Electric Company (BGE) the licensee for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 and their consultants ABB - Combustion Engineering Nuclear Power, Inc. (ABB - CENP) to discuss corrosion behavior of fuel cladding at Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2. Enclosure 1 is a list of attendees. Enclosure 2 is a copy of the nonproprietary viewgraphs distributed at the meeting.

The licensee stated that an inspection was performed on fuel that had been discharged from Unit 2 at the end of Cycle 12 and on a lead assembly. As part of the inspection, visual examinations were performed on several high duty fuel assemblies, assemblies that had seen a high rate of burnup in the two cycles in which they were in the core. The visual examinations resulted in the observation that some fuel rods exhibited blistering of the oxide layer, and some fuel rods showed evidence of early stages of spalling.

Based on these observations, several assemblies were taken apart for more detailed inspection of individual fuel rods. The fuel rods were visibly examined and the oxide layer thickness were measured on some of the rods. Some fuel rods, particularly peripheral fuel rods, had measured oxide thicknesses that were higher than predicted by the vendor's corrosion model.

The licensee then described the immediate actions taken which included a voluntary Licensee Event Report (LER), initiating a root cause evaluation and performing an operability evaluation to support current cycles operation. The root cause evaluation concluded that the factors affecting fuel duty are the primary contributors to the unexpected behavior. These factors include: improved operating history, reduced reactor coolant system flow due to plugged steam generator tubes, rod location within the assembly, rod power and adjacent rod power, subcooled boiling and thermal hydraulics effects due to geometry. The operability evaluation determined that there was no concern for normal operation. In addition, it addressed accidents and transients. A preliminary fuel duty model was developed by ABB CENP which uses an improved corrosion model. A fuel duty index was evaluated which is a function of time and temperature. Fuel duty comparisons were made between CC2N and past and current batches which showed fuel duties for current cycles and CC2N are similar. Based on these comparisons, the licensee concluded that the current cores are operable. Finally, the licensee indicated that near term cores (up to and including Unit 2 Cycle 14 (U2C14)) will be evaluated

SFo;

Page 2: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

-2-March 21, 2000

by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement of steam generators (greater flow), use of the TURBO assembly design and use of an advanced cladding alloy. In addition, the licensee stated its intention to continue to examine the fuel and to keep the NRC informed of its findings.

/RA/

Alexander W. Dromerick, Sr. Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Docket Nos. 50-317 and 50-318

Enclosures: 1. List of Attendees 2. Licensee's Handout

cc w/encls: See next page

DISTRIBUTION:

E-Mail (w/encl.1) J. Zwolinski/S. Black E. Adensam (e-mail) M. Gamberoni (A) S. Little A. Dromerick S. Wu M. Chatterton H. Scott M. Tschiltz M. Oprendek, RGN-I

-S-, i.

DOCUMENT NAME: G :\PDI-1\CC1-2\MTS121499.wpd

Hard Copy (w/all encls.) File Center PUBLIC PDI-1 R/F A. Dromerick OGC ACRS

cc: Licensee & Service List

r -�'.1 �

To receive a copy of this with attachment/enclosure

OFFICE PDY-l/,''

NAME mi k&.-cc DATE 1,., ?-a _AA

document, indicate in the box: "C' = Copy i ut attachment/enclosure "IE" = Copy "IN" = No copy A

i PDI-/LLAk0( i PDI-l/

SLittl• -- MGambe

OFFICIAL RECORD CO'PYII

I .

/Vz-k -65Y

Page 3: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

-2-

by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement of steam generators (greater flow), use of the TURBO assembly design and use of an advanced cladding alloy. In addition, the licensee stated its intention to continue to examine the fuel and to keep the NRC informed of its findings.

Alexander4W. Dromerick, Sr. Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Docket Nos. 50-317 and 50-318

Enclosures: 1. List of Attendees 2. Licensee's Handout

cc w/encls: See next page

Page 4: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Nuclear Power Plant Unit Nos. 1 and 2

President Calvert County Board of

Commissioners 175 Main Street Prince Frederick, MD 20678

James P. Bennett, Esquire Counsel Baltimore Gas and Electric Company P.O. Box 1475 Baltimore, MD 21203

Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge 2300 N Street, NW Washington, DC 20037

Mr. Bruce S. Montgomery, Director NRM Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685

Mr. Richard I. McLean, Manager Nuclear Programs

Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401

Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Mr. Joseph H. Walter, Chief Engineer Public Service Commission of

Maryland Engineering Division 6 St. Paul Centre Baltimore, MD 21202-6806

Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631

Patricia T. Birnie, Esquire Co-Director Maryland Safe Energy Coalition P.O. Box 33111 Baltimore, MD 21218

Mr. Loren F. Donatell NRC Technical Training Center 5700 Brainerd Road Chattanooga, TN 37411-4017

Mr. Charles H. Cruse Vice President, Nuclear Energy Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657

Page 5: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

LIST OF ATTENDEES

BALTIMORE GAS AND ELECTRIC COMPANY

DECEMBER 14, 1999

NAME Alexander W. Dromerick Norton Shapiro Zeser Karoutas John Osborne Matthew Kattic Penney File Ian Rickard George Smith, Jr. Muffet Chatterton Shih-Liang Wu Jeff Isakson Harold Scott

ORGANIZATION NRC/DLPM ABB CENP ABB CENP BGE BGE BGE ABB CENP ABB CENP NRC/SRXB NRR/SRXB ABB CENP NRC/RES

Enclosure 1

Page 6: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Corrosion Behavior of OPTIN Cladding at Calvert Cliffs

Presented by Penney File

BGE December 14, 1999

ABB Combustion Engineering Nuclear Power Inc

Page 7: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Purpose

* Describe Inspections and Observations

* Summarize Evaluation Supporting Operability of Current Cores

* Describe Approach for U1C 15

2 ABB Combustion Engineering Nuclear Power Inc

Page 8: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Outline

• Describe Inspections and Observations

• Describe Immediate Actions

* Describe Longer Term Actions

• Summarize

3 ABB Combustion Engineering Nuclear Power Inc

Page 9: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Background

* 24 Month Cycles

650EFPD * Tcold - 546.5

*Thot- 592

* Average LHGR - 6.25 Kw/Ft

*Tech Spec Fr- 1.65

* High Duty- 2 24 Month Cycles

* Low Duty -3 24 Month Cycles 4

ABB Combustion Engineering Nuclear Power Inlc

Page 10: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Fuel Assembly Schematic Upper End Fitting Serial Number Side

0'1234567 8 9 10 11 12 13 14

000000000001000 00000000000000 00 000000000 00 000000.00 00000000000000 00000000000000 000000(000000 000000 O000000 0000ooo0000000 00000000000000 00 000000 00 00 000000 00 000000000000000 0000000000000

1800

5ABB Combustion Engineering Nuclear Power Inc

270°

A

B

C

D

E

F G 900 H

J

K

L

M

N

Page 11: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Outline

SDescribe Inspections and Observations

• Describe Immediate Actions

• Describe Longer Term Actions

• Summarize

6 ABB Combustion Engineering Nuclear Power Inc

Page 12: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

July 1999 Initial Inspection Scope

* C2NT Test Assemblies Discharged in Spring 1999

9 4 Assemblies Visually Examined 0 1 Assembly Reconstituted to Allow ECT and

Oxide Thickness Measurement [ ] * Visual Examination of Discharged Assemblies to

Characterize the Effects of Duty

SClI Batch N and P (4 total, Assembly Average Bumups [ ] GWD/MTU)

• C2 Batch M and N (4 total, Assembly Average Burnups [ ] GWD/MTU)

7 ABB Combustion Engineering Nuclear Power Inc

Page 13: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

High Duty Fuel Observations

•Oxide[ ]

•No Evidence of[ ]

* More Detailed Examination Required

8 ABB Combustion Engineering Nuclear Power Inc

Page 14: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Expanded Examination Scope • 2 High Duty and 1 Low Duty Assembly

Reconstituted to Allow Single Rod Exams

[ ] Measured to Characterize Oxide Thickness

[ ] Visually Examined to Characterize Appearance

0 Visual Examination of [ ] High DutyAssemblies to Quantify Population of

I I

9ABB Combustion Engineering Nuclear Power Inc

Page 15: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Cladding Oxide Thickness Determination * ECT Technique Used to Measure Liftoff From Base Metal

* Measurements Performed on Individual Rods After Removal From Assembly

"* Four Full Length Axial Traces Performed at 900 Azimuthal Orientations

"* Thickness Data for Each Trace Stored Digitally as a Function of Elevation (0.050 Inch Intervals)

* Data Reduction

e Axial Traces Combined to Generate Composite

Maximum Circumferentially Averaged Oxide Thickness Calculated From Digital Composite as Running Average Over 1 Inch Interval (80 Measurements)

10 ABB Combustion Engineering Nuclear Power Inc

Page 16: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Low Duty Observations

Three Cycle Assembly

]I* Measured Oxide [

* No Blistering/Spalling

11

ABB Combustion Engineering Nuclear Power Inc

Page 17: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

High Duty Observations

• Two Cycle Assemblies

• Accuracy of Oxide Predictions Dependent onL I

* Blistering/Slight Spalling Observed,

12

ABB Combustion Engineering Nuclear Power Inc

Page 18: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

B listering/Spalling

• Spalling Is a Process That Begins [ ] S[ ] Progresses To Blistering

* Blistering Progresses To "Spallation"

13 ABB Combustion Engineering Nuclear Power Inc

Page 19: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Photograph not provided in handout

14 ABB Combustion Engineering Nuclear Power Inc

Page 20: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

High Duty Corrosion Results

15ABB Combustion Engineering Nuclear Power Inc

Page 21: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Oxide Traces for Adjacent CC2N [ ] Rods

16ABB Combustion Engineering Nuclear Power Inc

Page 22: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Fuel Assembly Schematic Upper End Fitting Serial Number Side

001 2 3 4 5 6 7 8 9 10 11 12 13 14

00000000000000 00000000000000 00 000000000 00 000000 00 00000000000000 00000000000000 000000 000000 000000 O000000 00000000000000 00000000000000 00 000000 00 000000000 00 00000000000000 00000000000000

180°

ABB Combustion Engineering Nuclear Power Inc

270*

A

B

C

D

E

F

G H

J

K

L

M

N

90

17

Page 23: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

OPTIN Corrosion Performance in Calvert Cliffs-I & 2

18

ABB Combustion Engineering Nuclear Power Inc

Page 24: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

High Duty Blistering/Spalling

• Blistering/Spalling [ ]

• Behavior Observed on Rods With 57 Microns of Oxide at 51 GWD/MTU

19

ABB Combustion Engineering Nuclear Power Inc

Page 25: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Fuel Assembly Schematic Upper End Fifting Serial Number Side

0°1234567 8 9 10 11 12 13 14

00000000000000 001000000000000. 000000000000 O0 000000000

00000000000000 00000000000000, 00000000000000 0010000 000000 O0000000000000

000000000000 00000000000000 0100010000000100

1800o

A

B

C

D

E

F

G

H

J

K

L

M

N

90

20ABB Combustion Engineering Nuclear Power Inc

2700

Page 26: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Observed Blisters on [ ] Rods

21ABB Combustion Engineering Nuclear Power Inc

Page 27: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Fuel Assembly Schematic

Upper End Fitting Serial Number Side

0'

1234 56 7 8 9 10 11 12 13 14

000000000000000 000000000000000 00 000000 001 00• 000000 _s00 00000000000000 00000000000000

000000)000000 000000 000000 01000-001010000,000 010000 00100001000 00 0010000/" 00 000 00!0000000

00000000000000 1800

A B

C

D

E

F

G

H

J

K

L

M

N

90

22

ABB Combustion Engineering Nuclear Power Inc

2700

Page 28: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Fraction of Examined [ I

23ABB Combustion Engineering Nuclear Power Inc

I

Page 29: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Corrosion Performance of C2N High Duty Fuel Rods

24ABB Combustion Engineering Nuclear Power Inc

Page 30: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Comparison of Measured to Predicted Oxide Using Current Model

25ABB Combustion Engineering Nuclear Power Inc

Page 31: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Summary Of Observations

* Low Duty Fuel Exhibits Expected Corrosion Behavior

* High Duty Fuel Exhibits Variable Behavior

* Some Populations of Rods Exhibit Higher Than Expected Corrosion and Blistering/ Spalling Behavior

26

ABB Combustion Engineering Nuclear Power Inc

Page 32: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Outline

* Describe Inspections and Observations

• Describe Immediate Actions

* Describe Longer Term Actions

* Summarize

27 ABB Combustion Engineering Nuclear Power Inc

Page 33: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Immediate Actions Taken

• Voluntary LER

• Root Cause Evaluation Initiated

* Operability Evaluation Performed to Support Current Cycles of Operation

28

ABB Combustion Engineering Nuclear Power Inc

Page 34: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Root Cause Conclusions

"• Factors Such as [ ] Not Identified as Primary Contributors

"• Factors Affecting Fuel Duty (Time and Cladding Temperature) Are Primary Contributors

29

ABB Combustion Engineering Nuclear Power Inc

Page 35: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Factors Affecting Fuel Duty

* Improved Operating History

° Reduced RCS Flow Due to Plugged Steam Generator Tubes

" Rod Location Within The Assembly

° Rod Power and Adjacent Rod Power

* Subcooled Boiling

* T-H Effects Due to Geometry

* Others 30

ABB Combustion Engineering Nuclear Power Inc

Page 36: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Operability Evaluation

• No Concern For Normal Operation

• Addressed Accidents and Transients

31

ABB Combustion Engineering Nuclear Power Inc

Page 37: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Operability Evaluation - Accidents and Transients

• Effect of[ ] * Effect of[ ] 0 Effect of[ ]

• Bottom Line Operability Issue - [ ]

32 ABB Combustion Engineering Nuclear Power Inc

Page 38: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

PROTOTYPE Test Rods * Test Rods With High Tin Zr-4 Clad/Modified Pellet Designs

Irradiated for 5 Cycles, Discharged 1988

* Subset of Rods Examined in Hot Cell (Rod Average Bumups

of[ ] GWD/MTU)

* Mechanical Property Tests Indicate

33

ABB Combustion Engineering Nuclear Power Inc

Page 39: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Photograph not provided in handout

34

ABB Combustion Engineering Nuclear Power Inc

Page 40: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

] Evaluation for Operability

35

ABB Combustion Engineering Nuclear Power Inc

Page 41: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Operability - Accidents and Transients

o [ ] Demand Calculated at [ I• Even Heavily Spalled Prototype Rod [

] * CC2N Rod Capability [ I

36ABB Combustion Engineering Nuclear Power Inc

Page 42: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

] in CClI Prototype and CC2N Models

37

ABB Combustion Engineering Nuclear Power Inc

Page 43: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

I ] for Prototype and CC2N Spalled Rods

38 ABB Combustion Engineering Nuclear Power Inc

Page 44: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

[ ] in CClI Prototype and CC2N Models

39ABB Combustion Engineering Nuclear Power Inc

Page 45: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Clad _

40

ABB Combustion Engineering Nuclear Power Inc

Page 46: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Total [ ] due to Spalling

41ABB Combustion Engineering Nuclear Power Inc

Page 47: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Operability (Continued)

"• Current Cycles - U1C 14 and U2C 13

"* CC2M Fuel- 580/638 EFPD (U2C10/1 1)

* CC2N Fuel - 63 8/640 EFPD (U2C11/12)

* U1C13/C14 Fuel - 590/620 EFPD

• U2C12/C13 Fuel - 640/658 EFPD

* Key Parameters- [ ]

42 ABB Combustion Engineering Nuclear Power Inc

Page 48: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

43 ABB Combustion Engineering Nuclear Power Inc

Page 49: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

44 ABB Combustion Engineering Nuclear Power Inc

Page 50: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Fuel Duty Comparisons

0 Fuel Duty Comparisons Were Made Between CC2N and.Past & Current Batches

* A Preliminary Fuel Duty Model Was Developed by ABB CENP Which Uses-an Improved Corrosion Model

" A Fuel Duty Index Was Evaluated Which is an [ I Temperature and Time

" Results Show That Fuel Duties are Similar to CC2N for Current Cycles

45

ABB Combustion Engineering Nuclear Power Inc

Page 51: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

46 ABB Combustion Engineering Nuclear Power Inc

Page 52: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Fraction of Examined [ ]

47

ABB Combustion Engineering Nuclear Power Inc

Page 53: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Unit 2 Cycle 12 Core Schematic

m. LJ

K Lii

KTT*' 1-,1-

- it-11. i.."i ... , 1. 1 1 1 . - 1. ., .- 1 ., 1 ., i -

High Duty Assembly (Second Cycle of Operation)

ABB Combustion Engineering Nuclear Power Inc

N

-. .*15 i. S. t. - i.o.i." , i.- t. - t. 1.121 i 12w 1iw-

- i I I • "' I' .. . I'

48

S... . • . ... ... .. gA . b• . .... ....

• i1 •o,2 o+J +14 • os o|+ 1-'o7 •ol °i, ° • s

• o • s• ,• os •|• a 1 "-" F " , -6 -l5 -, , +

m I

4|I 1ý "Im

• 137

P-17.1

Page 54: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Calvert Cliffs Fuel Assembly Schematic

49

ABB Combustion Engineering Nuclear Power Inc

Page 55: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Summary of Operability Evaluation

0 [ ] Demand Evaluated

*PROTOTYPE[ Spalled Rod [

] Show Heavily ] Matches Demand

or * Current Operating Cores Projected to Have

Similar Fuel Duty to CC2N

* Conclusion - Current Cores are Operable

I

50ABB Combustion Engineering Nuclear Power Inc

Page 56: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Outline

* Describe Inspections and Observations

* Describe Immediate Actions

• Describe Longer Term Actions

* Summarize

51

ABB Combustion Engineering Nuclear Power Inc

Page 57: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

1OCFR50.59 Approach for

U1C15/U2C14

* Assess Fuel Duty Based on [ ]

* Evaluate Impact of Incremental Increase in Duty

on Anticipated Corrosion Behavior Including

Blistering/Spalling

*Ensure [ ]

* Acquire Data on CC 1R Fuel at EOC 14 (Spring

2000) to Further Characterize Phenomenon

52

ABB Combustion Engineering Nuclear Power Inc

Page 58: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Beyond U2C 14

• Replacement Steam Generators

* Evaluate TURBO Assembly Design

* Pursue Advanced Cladding Alloy

53 ABB Combustion Engineering Nuclear Power Inc

Page 59: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Summary

• Current Cores Operable

* Subsequent Cores Will Be Handled Under

10CFR50.59

* Longer Term Actions Expected To Mitigate

Problem

54

ABB Combustion Engineering Nuclear Power Inc

Page 60: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Questions

55

ABB Combustion Engineering Nuclear Power Inc

Page 61: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Typical Lamination of ZrO2 Layer[P I

C ,gz00 6,: ; 2^ -fa -rlv , e

I

Photo 1

Page 62: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

C/ oo6 -I t"PRoOTy•- / ?oD

Typical Appearance of Region IPhoto 2

Page 63: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

0104d

160).1"Powbpoolo,-4, h1H

Page 64: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

Cc2 ~V3954/4' ~e

Photo 4

e) f1A X1

Page 65: UNITED STATES ** NUCLEAR REGULATORY COMMISSION · -2-March 21, 2000 by the same approach under 10 CFR 50.59. Beyond U2C14 fuel behavior is expected to be different due to replacement

/8600 SP4A( 7

Photo 5

18 14'"•