    COLLEGE OF ENGINEERING

    PUTRAJAYA CAMPUS

    Test No. 1

    1stSemester, Year 2015 / 2016

    PROGRAMME : Bachelor of Civil Engineering (Honours)

    SUBJECT CODE : CEPB 323

    SUBJECT : Project Management and Construction

    DATE : 31stJuly 2015

    TIME : 3.003.45 p.m. (45 min.)

    INSTRUCTIONS TO CANDIDATES:

    1. This paper contains THREE (3)questions in THREE (3)pages.

    2. Answer ALLquestions in the answer sheets that are provided.

    3. Total marks = 45 marks

    THIS QUESTION PAPER CONSISTS OF FOUR (4) PRINTED PAGES

    INCLUDING THIS COVER PAGE.

  • 7/24/2019 Understanding the project management principe through question

    2/3

    CEPB 323 Project Management & Construction Test 1

    Page 2 of 3 1stSemester, Year 2015/16

    Question 1 (15 marks)

    The activities, immediate predecessors and activity duration for a project are listed in Table 1

    below.

    Table 1: Project data for question 1

    ActivityImmediate

    Predecessor

    Duration

    (month)

    A NONE 4

    B A 4

    C A 8

    D A 8

    E B 6

    F D 4

    G C,E,F 4

    H G 10

    a)

    Constructa CPM precedence (AON) diagram based on the data in Table 1.

    [8 marks]

    b) Determinethe project duration [1 mark]

    c) Determine and list the critical activities in the project. [1 mark]

    d) Draw the critical path(s) in the CPM precedence (AON) diagram using either bold,

    highlighted or double arrows. [1 mark]

    e)

    Determine the total float for activity B and show your calculations. [1 mark]

    f) Determinethe earliest time that activity C can start. [1 mark]

    g) Determine the free float for activity E with respect to activity G and show your

    calculations. [2 marks]

  • 7/24/2019 Understanding the project management principe through question

    3/3

    CEPB 323 Project Management & Construction Test 1

    Page 3 of 3 1stSemester, Year 2015/16

    Question 2 (15 marks)

    The activities, immediate predecessors and activity duration for a project are listed in Table 2

    below.

    Table 2: Project data for question 2

    ActivityImmediate

    Predecessor

    Duration

    (month)

    A None 4

    B A 6

    C A 4

    D B 4

    E C 6

    F A, E 2

    G C, D, F 4

    a)

    Construct a CPM arrow (AOA) diagram based on the data in Table 2. [10 marks]

    b) Draw the critical path(s) in the CPM arrow (AOA) diagram using either bold,

    highlighted or double arrows. [2 marks]

    c) When is the earliest duration that the project can be completed? [1 mark]

    d)

    What is the latest time that activity D must start to avoid any delay in the project?

    [2 marks]

    Question 3 (15 marks)

    Discuss about the meaning and basic relationships between scope, budget, schedule and

    quality for a construction project. Please support your answer with giving an example.

    End of questions