uncertainty in transport modelling; the four-stage næstved
TRANSCRIPT
Uncertainty in transport modelling; the four-stage Næstved model case study
Stefano Manzo Otto A. Nielsen Carlo G. Prato
DTU Transport, Technical University of Denmark
Rationale
• An extensive literature has demonstrated that there is a considerable and almost systematic inaccuracy between forecasted and observed traffic flows
• One of the reason of this inaccuracy can be traced in the complexity of systems generating traffic. Complex systems generate unpredictable output (emerging behaviour)
• Whenever a model is created to reproduce a complex system the output it generates will invariably be unpredictable because affected by uncertainty
• If not properly understood and quantified, the uncertainty inherent in transport models makes analyses based on their output highly unreliable
2 25-09-2012
DTU Transport, Technical University of Denmark
Outline
• Introduction
• Case study and methodology • Results
• Conclusions
3 25-09-2012
DTU Transport, Technical University of Denmark
Introduction • Ideally we would like to build deterministic models; in this way modelled
output would be perfectly accurate. Uncertainty and ignorance prevent from making this possible, originating the modeller inability to model a complex system with a deterministic approach
• Ignorance refers to a complete absence of awareness of some model components or their dynamics
• Uncertainty instead refers to limited knowledge (epistemic) or stochasticity (ontological) of some model components and the way they interact
– “Everything we do not know to a full extent” (Van Zuylen 1999)
– “Any departure from the unachievable ideal of complete deterministic
knowledge of the relevant system” (Walker 2003)
4 25-09-2012
DTU Transport, Technical University of Denmark
Introduction
5 25-09-2012
DTU Transport, Technical University of Denmark
Introduction • Transport model point output only represents one of the possible output
generated by the model
• “(...) modelled output is better expressed as a central estimate and an overall range of uncertainty margins articulated in terms of values and likelihood of occurrence” (Boyce 1999)
• Uncertainty analysis pertains to:
– how uncertainty in each model component affects the model output – how to express the model output as a distribution, so as to reflect the
overall uncertainty in the model
6 25-09-2012
DTU Transport, Technical University of Denmark
Case study and methodology
7
• Næstved model (Traffic Analyst)
– 106 zones – 315 links – low congestion – four-stage model (3 overall iterations) – 2 modes: private and public transport – 2 categories: home/work and
business trips – traffic is modelled on 24H time interval
25-09-2012
DTU Transport, Technical University of Denmark
Case study and methodology
8 25-09-2012
DTU Transport, Technical University of Denmark
Case study and methodology
9 25-09-2012
Model (Parameters) Type Category 1 Category 2
Assignment
Length 0.350 0.350
Free TT 0.520 1.300
Congested TT 0.820 1.300
Error Term 0.000 0.000
Price 1.000 1.000
Type Name Value
Small road Alpha 0.800
Large road Alpha 0.500
Highway Alpha 0.450
Small road Beta 1.500
Large road Beta 2.500
Highway Beta 4.000
Small road Gamma 0.150
Large road Gamma 0.100
Highway Gamma 0.000
Model (Parameters) Name Category 1 Category 2
Trip generation
WP_PRIM 1.061 0.118 WP_SEC 1.432 0.159
Workplaces 0.005 0.001 Workers 1.342 0.149
Gravity model GravAlpha 0.052 0.052 GravBeta 0.043 0.043
Mode Split Beta 0.060 0.060
Model (Input) Name
Trip Generation
Production Workers
Workplaces
Attraction WP_PRIM
WP_SEC
Assignment
FreeSpeed
QueueSpeed
LaneHCFor
LaneHCBack
DTU Transport, Technical University of Denmark
Case study and methodology
• This study investigates uncertainty in model input and parameters through stochastic sampling technique combined with sensitivity analysis
– Latin hypercube sampling simulation (100 draws) – Input (Triangular) Parameters (Lognormal) – Model sensitivity analysis (100 runs)
• Uncertainty is quantified in terms of Coefficient of Variation (CV)
10 25-09-2012
DTU Transport, Technical University of Denmark
Case study and methodology • Different scenarios are analysed
– three uncertainty locations (input, parameters and total) – two levels of uncertainty (CV 0.1 and 0.3) – three levels of congestion (1,1.5 and 3 times the base traffic)
• Analysis focuses on:
– uncertainty propagation pattern – effects on output uncertainty of uncertainty location – effects on output uncertainty of network congestion
11 25-09-2012
DTU Transport, Technical University of Denmark
Results
12 25-09-2012
Correlation Model Pearson Spearman
Workers (Input) Generation 0.24021 0.21905
Workers (Parameter) Generation 0.86464 0.85929
Beta (Parameter) Mode split 0.22432 0.20462
DTU Transport, Technical University of Denmark
Results
13 25-09-2012
Generation Distribution Mode Assignment
Total 0.366 0.487 0.511 0.366
Parameters 0.282 0.348 0.455 0.224
Input 0.241 0.323 0.364 0.300
DTU Transport, Technical University of Denmark
Results
14 25-09-2012
Generation Distribution Mode Assignment
CV 0.3 0.366 0.487 0.511 0.366
CV 0.1 0.119 0.162 0.294 0.136
DTU Transport, Technical University of Denmark
Results
15 25-09-2012
Generation Distribution Mode Assignment
SUE 0.366 0.487 0.511 0.366
UE 0.366 0.490 0.510 0.422
DTU Transport, Technical University of Denmark
Results
16 25-09-2012
Not ready yet
Generation Distribution Mode Assignment
Cong 3 0.365 0.594 0.668 0.371
Cong 1.5 0.366 0.487 0.511 0.366
Cong 1 0.371 0.500 0.436 0.361
DTU Transport, Technical University of Denmark
Results
17 25-09-2012
DTU Transport, Technical University of Denmark
Results
18 25-09-2012
DTU Transport, Technical University of Denmark
Results
19 25-09-2012
DTU Transport, Technical University of Denmark
Conclusions • In terms of propagation pattern and uncertainty location
– uncertainty increases throughout the first three model stages to then
reduce in the assignment model; this pattern is irrespective to uncertainty location, level of network congestion and base CV
– trip generation stage seems to define the level of final model uncertainty
– SUE reduces final uncertainty more than UE
– input uncertainty appears to have an higher influence on final model
uncertainty than parameters uncertainty
20 25-09-2012
DTU Transport, Technical University of Denmark
Conclusions • In terms of network congestion
– different levels of congestion do not seem to result in significant
differences in terms of final model uncertainty – with regard to traffic volume the dispersion around the CV mean
value reduces at increasing level of veh/cap ratio and traffic volumes – with regard to travel time, the level of dispersion around the CV
mean value appear to be stable, irrespective to travel time length
21 25-09-2012
DTU Transport, Technical University of Denmark
Perspective • The method illustrated requires many repeated simulations. Is it possible
to reduce the number of model runs without losing information?
• Correlation between parameters in the sampling procedure? In case of forecasts, which values should be used for the parameters?
• How big is the cost of inaccurate forecasts and how time-consuming and effective is the implementation of uncertainty analyses?
• How does transport model uncertainty affect new infrastructure?
22 25-09-2012
DTU Transport, Technical University of Denmark
Thanks for the attention
23 25-09-2012
DTU Transport, Technical University of Denmark
Break in case of emergency 1
24 25-09-2012
Uncertainty matrix
Location
Context (system modeled)
Model (structure/methodology)
Input (from the system)
Parameters (calibrated/assumed)
Model output (propagated)
Level
Stat
istic
al
unce
rtain
ty
Scen
ario
un
certa
inty
Rec
ogni
zed
igno
ranc
e
Stat
istic
al
unce
rtain
ty
Scen
ario
un
certa
inty
Rec
ogni
zed
igno
ranc
e
Stat
istic
al
unce
rtain
ty
Scen
ario
un
certa
inty
Rec
ogni
zed
igno
ranc
e
Stat
istic
al
unce
rtain
ty
Scen
ario
un
certa
inty
Rec
ogni
zed
igno
ranc
e
Stat
istic
al
unce
rtain
ty
Scen
ario
un
certa
inty
Rec
ogni
zed
igno
ranc
e
Nat
ure Epistemic
Ontological
Modified after Walker et al. (2003)
DTU Transport, Technical University of Denmark
Break in case of emergency 2
25 25-09-2012
Socio-economic analyses in perspective: Uncertainties and bias in decision support
Associate Professor, PhD Kim Bang Salling DTU Transport Traffic days in Aalborg 2012 – Special session: “Uncertainties in Transport Project Evaluation (UNITE)”
DTU Transport, Technical University of Denmark 2
Project Plan of UNITE
Uncertainties in Transport Project Evaluation (UNITE): the five Work-Packages
(5) Evaluation methodologyWP5 project leader: Steen Leleur (DMG)
(4) Uncertainty calculation in transport modelsWP4 project leader: Otto Anker Nielsen (TMG)
(2) Organizational context of Modelling, an empirical study
WP2 project leader: Petter Næss (AAU)
(3) Uncertainty calculation of cost estimates
WP3 project leader: Bo Friis Nielsen (DTU Informatics)
(1) Systematic biases in transport models (recognized ignorance), an empirical studyWP1 project leader: Petter Næss (AAU)
DTU Transport, Technical University of Denmark 3
How do we evaluate transport projects?
• Various existing guideline report: –Denmark, Sweden, UK, European Union, ....
• Socio-economic analysis by the use of Cost-Benefit
Analysis (CBA)
• Produces single point estimates such as Net Present Values (NPV), Benefit Cost Ratios (BCR), etc
• However, no common rule have been set in order to acommodate the uncertainties in CBA!
–Recent conducted PhD dissertation proved this point
DTU Transport, Technical University of Denmark 4
Background & Motivation
• The Manual for socio-economic analysis in the transport sector (2003)
–Unique guidelines for evaluating transport infrastructure projects
–Lack of uncertainty handling –Expected revision 2012-2013
DTU Transport, Technical University of Denmark 5
How do we evaluate transport projects?
• However, no common rule have been set in order to acommodate the uncertainties in CBA!
–Recent conducted PhD dissertation proved this point
DTU Transport, Technical University of Denmark 6
The Case Study: HH-Connection • Connecting Denmark with Sweden: Scandinavian link
–Currently, close to the capacity limit on Oresund
HH-Connection (alternatives*)
Description (Alignment of connection)
Cost (million DKK)
Alternative 1 Tunnel for rail (2 tracks) person traffic only 7,700
Alternative 2 Tunnel for rail (1 track) goods traffic only 5,500
Alternative 3 Bridge for road and rail (2x2 lanes & 2 tracks) 11,500
Alternative 4 Bridge for road (2x2 lanes) 6,000
* Larsen, L.A. & Skougaard, B.Z. (2010). Vurdering af alternativer for en fast forbindelse Helsingør-Helsingborg, M.Sc. thesis, Department of Transport, Technical University of Denmark (in Danish)
DTU Transport, Technical University of Denmark 7
The UNITE-DSS Modelling Framework Todays Outline
DTU Transport, Technical University of Denmark 8
Results: Cost-Benefit Analysis
• Construction costs – by far the largest contributor of costs
• User Benefits – by far the largest contributor of benefits – Consists of Ticket revenue and time savings – Relies on the prognosis of future number of passengers i.e.
demand forecasts
HH-Connection (alternatives)
Cost (million DKK)
BCR NPV (million DKK)
Alternative 1 7,700 1.50 5,530
Alternative 2 5,500 0.16 -6,640
Alternative 3 11,500 2.71 28,240
Alternative 4 6,000 3.08 17,860
DTU Transport, Technical University of Denmark 9
Are we telling the truth?!?!
Construction cost overruns
0%
200%
400%
600%
800%
1000%
1200%
1400%
1600%
1800%
2000%
Suez
Can
al
Sydn
eyO
pera
Hou
se
Con
cord
eSu
pers
onic
Aero
plan
eBo
ston
'sAr
tery
/Tun
nel
Proj
ect,
USA
Hum
ber
Brid
ge, U
K
Bost
on-
Was
hing
ton-
New
Yor
kG
reat
Bel
tR
ail T
unne
l,D
KA6
Mot
orw
ayC
hape
l-en-
le-
Frith
/Wha
ley
Shin
kans
enJo
etsu
Rai
llin
e, J
apan
Was
hing
ton
met
ro, U
SA
Cha
nnel
Tunn
el, U
K &
Fran
ceKa
rlsru
he-
Bret
ten
light
rail,
Ger
man
yØ
resu
ndAc
cess
link
s,D
K &
Swed
enM
exic
o ci
tym
etro
line
,M
exic
oPa
ris-A
uber
-N
ante
rre
rail
line,
Fra
nce
Cos
t Ove
rrun
s (%
)
Q: Have we learned anything from history?
”Chunnel” in 1987 £2,600 million (’85 prices) Completion 1994 £4,650 million (’85 prices) Total cost overrun of approx. 80%
”Øresund access link” in 1991 3.2 billion DKK (’90 prices) Completion 1998 5.4 billion DKK (’90 prices) Total cost overrun of approx. 68%
DTU Transport, Technical University of Denmark 10
Theoretical anchoring The Transport Planning Phase: Adapted from the British Department for Transport (DfT) (2004)
Reference Class Forecasting: Optimism Bias
Inside View Outside View
”Uniqueness” of Project
”The Planning Fallacy”
Reference Class Forecasting
Forecasting of particular projects
Forecasting from a group of projects
(1) Identification of relevant reference
classes
(2) Establishing probability distribution
(3) Placing and comparing the
project
Optimism Bias UpliftsCurrent Situation
DTU Transport, Technical University of Denmark 11
Optimism Bias and uplifts
• Deriving uplifts is highly dependet on large data-sets –Flyvbjerg from (AAU) has since 2003 developed a large
database –Unfortunately, it looks upon mega-projects
• The basis is Reference Class Forecasting i.e. statistical measurements on various project pools
Source: Flyvbjerg and COWI (2004)
DTU Transport, Technical University of Denmark 12
Results : Optimism Bias Uplifts
• The BCR are lower, however, still point estimates towards DM –Moreover an advanced form of sensitivity analysis
• Imply to introduce risk analysis and Monte Carlo simulation
HH-Connection (alternatives)
Cost (uplifted) (million DKK)
BCR (orig.) (from slide 8)
BCR (uplifts): 80% uplift
Alternative 1 12,090 1.50 0.97
Alternative 2 8,640 0.16 0.10
Alternative 3 15,180 2.71 1.75
Alternative 4 7,920 3.08 1.98
DTU Transport, Technical University of Denmark 13
The UNITE Project Database (UPD)
• The convention used is as follows: ( )( )
forecasted
forecastedactual
XXX
U100×−
=
Over estimation of Demand
DTU Transport, Technical University of Denmark 14
• Demand forecasts (user benefits) are derived: – U is percent inaccuracy, – Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build
• Combination of two database samples
0
5
10
15
20
25
30
(-12
0;-1
00)
(-10
0;-8
0)
(-80
;-60)
(-60
;-40)
(-40
;-20)
(-20
;0)
(0;2
0)
(20;
40)
(40;
60)
(60;
80)
(80;
100)
(100
;120
)
(120
;140
)
(140
;160
)
(160
;180
)
(180
;200
)
(200
;220
)
(220
;240
)
Freq
uenc
y of
occ
uren
ce (%
)
Inaccuracies in demand forecasts (%)
Inaccuracies in demand forecasts (road projects)
Salling et al. (2012)
Flyvbjerg et al. (2003)
Nicolaisen et al. (2012)
DTU Transport, Technical University of Denmark 15
The UNITE Project Database (UPD)
• The convention used is as follows: ( )( )
forecasted
forecastedactual
XXX
U100×−
=
Under estimation of costs
DTU Transport, Technical University of Denmark 16
• Construction costs bias derived similarly: – U is percent inaccuracy, – Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build
• Combination of two database samples
0
10
20
30
40
50
(-10
0;-8
0)
(-80
;-60)
(-60
;-40)
(-40
;-20)
(-20
;0)
(0;2
0)
(20;
40)
(40;
60)
(60;
80)
(80;
100)
(100
;120
)
(120
;140
)
(140
;160
)
(160
;180
)
(180
;200
)
(200
;220
)
(220
;240
)
Freq
uenc
y of
occ
uren
ce (%
)
Inaccuracies in construction costs (%)
Inaccuracies in construction cost (road projects)
Salling et al (2012)
Flyvbjerg et al. (2003)
Nicolaisen et al. (2012)
DTU Transport, Technical University of Denmark 17
Results (RCF): Monte Carlo simulation
DTU Transport, Technical University of Denmark 18
Conclusions
• Feasibility risk assessment can be carried out by using historical experience stemming from RCF in order to obtain interval results
• An important aspect in RCF and UNITE is to set and validate input parameters. Hence, empirical data enter the assessment.
• The RCF approach has been illustrated on a case example concerning the construction of a new fixed link, the HH-Connection, between Denmark and Sweden.
• Clearly vital to include uncertainties within socio-economic analyses in order to validate results
DTU Transport, Technical University of Denmark 19
Perspectives
• Recovering of further data (UPD) with regard to both the demand forecast uncertainty as well as the construction costs through large-scale research study
• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)
• More info on UNITE can be found: (www.transport.dtu.dk/unite)
• An international conference on the topic is scheduled in September 2013 – a specific call will be posted in the upcoming month.
DTU Transport, Technical University of Denmark
SIMSIGHT: Decision Conferencing (DC)
20
• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model
• Enables to include Stakeholders and Decision-makers in an early stage, i.e. to include experts opinion on MIN and MAX values as entries to the Monte Carlo simulation
DTU Transport, Technical University of Denmark 21
Results from DC and RSF
DTU Transport, Technical University of Denmark
SIMSIGHT: Overconfidence
22
DTU Transport, Technical University of Denmark 23
Perspectives
• Recovering of further data (UPD) with regard to both the demand forecast uncertainty as well as the construction costs through large-scale research study
• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)
• More info on UNITE can be found: (www.transport.dtu.dk/unite)
• An international conference on the topic is scheduled in September 2013 – a specific call will be posted in the upcoming month.
DTU Transport, Technical University of Denmark 24
Thank you for your attention!
Affiliation:
Associate Professor, PhD Kim Bang Salling
Department of Transport Technical University of Denmark
Introduktion af beslutningskonferencer - Vurderinger af usikkerheder i beslutningsgrundlaget for samfundsøkonomiske analyser Trafikdage, 28-08-2012 Michael Bruhn Barfod Adjunkt, DTU Transport
DTU Transport, Technical University of Denmark
Introduktion
• Beslutningstagning inden for transportplanlægning – Ofte kompleks proces – Mange interessenter involveret
• Fokus på mangler og usikkerheder ifm. samfundsøkonomiske analyser
• UNITE
– Fastlæggelse af trafikprognoser – Fastlæggelse af anlægsoverslag – Evalueringskriterier som punktestimater
• Hvordan kan beslutningstagerne/interessenterne involveres i analysen af
usikkerhederne?
28-08-2012 Trafikdage, Aalborg Universitet 2
DTU Transport, Technical University of Denmark
SIMDEC beslutningsstøttesystemet • SIMDEC tilgangen har til formål at udføre omfattende vurderinger af
infrastrukturprojekter, hvor der kan tages højde for en lang række af kriterier og synspunkter
Vurdering
Beslutningskonference
SIMDEC tilgangen
28-08-2012 3 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
SIMDEC tilgangen
• Flere forskellige metoder kombineres:
– Feasibility risk assessment: • Cost-benefit analyse • Monte Carlo simulering
– Multi-kriterie analyse: • REMBRANDT • SMARTER
• Formålet er at benytte SIMDEC til vurderingen og allokere passende scorer til alternativerne og vægte til kriterierne
28-08-2012 4 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Overblik over SIMDEC tilgangen
(Leleur og Ambrasaite, 2012) 28-08-2012 5 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Beslutningskonference • En beslutningskonference kan ses som et strategisk værktøj, der kan
benyttes til interaktion med beslutningstagere/interessenter
• Set-up’et afhænger af diverse faktorer (type, tid, deltagere, etc.)
• 3 elementer interagerer
Gruppe processer
IT
Beslutnings-analyse
28-08-2012 6 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Beslutningsprocessen
28-08-2012 Trafikdage, Aalborg Universitet 7
The preliminary problem structuring phase
The five steps of the decision conference
Step 2-Definition of the
criteria/impacts that are to be assessed
(possibility to include more or omit some)
Step 3-Scoring of
alternatives within each criterion/impact
Step 4-Weighting of criteria
-Trade-off considerations
Step 5-Results
-Sensitivity analysis-Validation
Step 1-Introduction to the
concepts and techniques to be used
in the process
Possibility for revising assessments in order to accomplish shared understanding
Identify the problem Select an appropriate analytic approach
Develop a detailed analytic structure
Possible decision
Focus on the problem
Focus on the alternatives
Problem formulation
Generate relevant criteria (workshops etc.)
Select one or more assessment techniques
Division of problem into simple judgments
Division of criteria if defined too broad
DTU Transport, Technical University of Denmark
Case studie
• Forbindelse mellem Helsingør og Helsingborg (HH) – 3 alternative løsningsmuligheder
• Samfundsøkonomi
– CBA alle 3 alternativer rentable – Riskoanalyse rentabilitet ikke sikker
28-08-2012 Trafikdage, Aalborg Universitet 8
B/C rate
NPV (mio. DKK)
Certainty Value
Alt 1 1.23 2657 27 %
Alt 2 2.38 40506 77 %
Alt 3 1.99 38518 69 %
CV = 77%
DTU Transport, Technical University of Denmark
Strategiske kriterier
• Kriterier identificeret og fundet relevante for valget af alternativ
– Samfundsøkonomisk robusthed – Forbedringer for passagerbiler og offentlig transport – Effekt på byer og arealanvendelse – Effekt på regional økonomi – Effekt på logistisk fleksibilitet – Bidrag til EU’s grønne korridorer
28-08-2012 Trafikdage, Aalborg Universitet 9
DTU Transport, Technical University of Denmark
Scorer for alternativer Intensitet Definition
0 Ens
2 Svag
4 Klar
6 Stærk
8 Meget stærk
1, 3, 5, 7 Kompromis
Kriterium: Samfundsøkonomisk robusthed
A1 A2 A3 Score
A1 0 -6 -4 0,10
A2 6 0 3 8,00
A3 4 -3 0 1,26
Samfundsøkonomisk robusthed
28-08-2012 10 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Kriterievægte
Kriterier Rangorden Bæredygtighed
Bussines-as-usual
Samfundsøkonomisk robusthed 2 (0.24)
Forbedringer for passagerbiler og offentlig transport 3 (0.19)
Effekt på byer og arealanvendelse 6 (0.04)
Effekt på regional økonomi 1 (0.30)
Effekt på logistisk fleksibilitet 5 (0.09)
Bidrag til EU’s grønne korridorer 4 (0.14)
Deltagerne kan opdeles / prædefineret rangorden til diskussion
28-08-2012 11 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Resultater
28-08-2012 Trafikdage, Aalborg Universitet 12
DTU Transport, Technical University of Denmark
Fordele ved beslutningskonferencer
• Er en beslutning, som tages på baggrund af konsensus ved en beslutningskonference, mere eller mindre valid end vurderinger og løsninger, som findes uden hjælpemidler?
• En beslutningskonference giver følgende fordele:
– Bedre kommunikation imellem grupper – Fælles forståelse af strategiske mål – Dedikeret indsats for at nå målet/målene – Forbedret teamwork – Større viden om og relation til diverse usikkerheder – Beslutninger som kan forsvares
28-08-2012 13 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Konklusion og perspektiv
• Ved at benytte SIMDEC tilgangen i en planlægningsproces kombineret med en beslutningskonference får man mulighed for at vurdere et beslutningsproblem på en helhedsorienteret måde
• Det fulde potentiale vil først blive tydeligt når tilgangen benyttes i en fuld beslutningskonference med deltagelse af rigtige interessenter
• Det er nødvendig at undersøge potentialet af denne tilgang videre i rigtige beslutningssituationer og teste dens brugbarhed
• Applikationer af beslutningskonferencer
– Lokalisering i Øresundsregionen (STMØ, 2008) – Udvælgelse af jernbanekorridor – Ostlänken (Vinnova, 2009) – Udvælgelse af cykelprojekter (Cykelpuljen, 2009-2010) – Vurdering af alternativer til HH-forbindelse (EcoMobility, 2011) – UNITE, 2012 (oktober)
28-08-2012 14 Trafikdage, Aalborg Universitet
DTU Transport, Technical University of Denmark
Tak for opmærksomheden!
28-08-2012 Trafikdage, Aalborg Universitet 15