1 GUJART STATE ELCTRICITY CORPORATION LTD UKAI THERMAL POWER STATION UKAI DAM–TAPI TENDER COPY RFQ NO-30597 WT-2752 TENDER DOCUMENT FOR Job work to Gear box commissioning related work at bucket wheel platform of Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS ESTIMATED COST: Rs. - 04, 07,301=00 EMD DEPOSIT : Rs. 4075=00 TENDER FEE : Rs. 500=00 TIME LIMIT : Six month. DEPARTMENT : Coal Plant-6

Upload: hoangliem

Post on 21-Aug-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

1

GUJART STATE ELCTRICITY CORPORATION LTD

UKAI THERMAL POWER STATION

UKAI DAM–TAPI

TENDER COPY

RFQ NO-30597

WT-2752 TENDER DOCUMENT

FOR

Job work to Gear box commissioning related work

at bucket wheel platform of Stacker cum Reclaimer

in Unit-6 coal handling plant

at UKAI TPS

ESTIMATED COST: Rs. - 04, 07,301=00

EMD DEPOSIT : Rs. 4075=00

TENDER FEE : Rs. 500=00

TIME LIMIT : Six month.

DEPARTMENT : Coal Plant-6

2

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

Tender for the Job work to Gear box commissioning related work at bucket wheel platform of

Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS

SR NO. INDEX PAGE NO 1 Tender notice

03

2 Condition of tender & special notes

04

3 Schedule-A & scope of work

05 to 09

5 Prequalification criteria

10

7 Safety circular

11 to 13

8 Schedule-B 14

3

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

RFQ NO-30597

WT-2752

TENDER NOTICE LIMITED TENDER NOTICE Sealed percentage rate tenders are invited form experienced, Registered and approved contractor

for the work Job work to Gear box commissioning related work at bucket wheel platform of

Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS

1) Estimated cost:- : Rs-04,07,301=00

2) Date for submission of tender. :19-12-2014 ( 15=30 Hour )

3) Date of opening of Tender : 19-12-2014 ( 15=30 Hour )

if possible

5) Earnest Money: - : Rs- 4075/- 6) Security Deposit : 5%-of the order value.

7) Tender Fee: - : Rs- 500=00

8) Time limit: - : 06=00(Six) Month

The full particulars can be had in the tender, which can be obtained from the office of the Chief

Engineer (Gen), GSECL, UGBPS, TPS, Ukai Dam, Dist:-Tapi, Pin-394680.

Earnest money deposit will be accepted only by cash or demand draft of any nationalize bank in

favor of GSECL payable on Bank of Baroda at Ukai Dam, Cheques are not accepted. The tenders

may be opened in the presence of contractor who wishes to remain present at the time of opening.

The undersigned reserves the right to reject any or all tenders without assigning any reason

thereof.

N.B:-1) Tender will be accepted only by RPAD. It is necessary to produce the experience, income

tax clearance & solvency certificates for the work carried out in past at the time

submitting of tender copy.

2) The tenderer should quote the DD/BG No on tender cover for payment of EMD.

3) The tender without payment of EMD & Tender fee will not be opened/considered.

Chief Engineer (Gen)

G.S.E.C.L, TPS, Ukai Dam

4

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

Name of the work:- Job work to Gear box commissioning related work at bucket wheel platform

of Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS

SPECIAL NOTE:-

Contractor has to submit his tender copy along with relevant documents in view of following points

of this special notes:-

1) Detail of similar job/jobs carried out during last 3 years along with documentary evidence.

2) Bank solvency certificates of about 20% value of the contract.

3) Details of skilled/semiskilled persons presently employed by the contractor for similar

contract going on elsewhere if any, having sufficient knowledge of similar job.

4) Copy of contractor’s registration with GSECL.

5) Detail of partnership deed in case it is a partnership firm.

6) Detail of performance certificate for satisfactory executed order from GSECL, Semi Govt

organization or reputed organization.

7) Provident fund no.

Full Address:-

---------------------

--------------------- Signature of contractor

------------------------------------------------------------------------------------------------------------

NOTICE

1) All the columns in schedule should be filled in ink.

2) Rates quoted include clearance certificate of site (prier to commencement of work and

after completion of work) in all respects & hold good for work under all condition, site

moisture weather etc.

3) The quantities given above are approximate.

4) Certain minor changes may be incorporated during construction and as a result there may be

increase or decrease in the above stated quantities. In such on event it should be noted

that contractor should not claim any thing extra. Those will be paid on the basis of actual

quantities executed.

5) The rates shall be quoted both in words & figures as per unit specified in the schedule-B

should there be any discrepancy between rate quoted in words & figure, rates quoted in

words shall prevail.

6) Further if there should be any discrepancy between rate and amount the rate will be

considered for awarding the contract.

Chief Engineer (Gen)

G.S.E.C.L, TPS, Ukai Dam

5

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

Sub: - Job work to Gear box commissioning related work at bucket wheel platform of Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS Scope of work for item no-1

1. The Job involves receipt of material from main store/site store & shift the same at

working place by contractor/or staff & truck/tractor as per instruction of EIC.

2. The job work involves arrangement of all consumable required for the work. I.e.-Cutting

gas, welding rod, Hardware material etc relevant to job.

3. The job work involves fabrication of temporary structure {as per inst. of EIC} for work to

be carried out above ground level at an average Height of 05 meter approximately.

4. The job work involves cutting & removing of existing failed shrink disk from bucket wheel

solid shaft by gas cutting or cut rod welding process.

5. It is sole responsibility of contractor to keep close watch on cutting process so that

bucket wheel shaft damage can be avoided.

6. The Job work involves cleaning of complete shaft of bucket wheel by cleaner & remove

burrs from the shaft.

7. The job work involves opening of both side plumber block of bucket wheel solid shaft &

checking of bearing along with replacement of required grease.

8. The job work involves filling of machineble welding material {CGS-680} on bucket wheel

solid shaft by welding process.

9. It is sole responsibility of party to arrange sufficient labor force to rotate bucket wheel

manually during the welding process.

10. The job work involves preparing of tool post nearby bucket wheel solid shaft as per

requirement of machinist/turner for the machining process.

11. The job work involves arrange sufficient labor force to rotate bucket wheel manually

during the machining process without major break.

12. It is sole responsibility of party to continuously in touch with machinist & EIC & take

measurement of shaft for the required dimension of shaft.

13. It is sole responsibility of party to safe guard the material procured by them or issued to

them for work till completion of work & handing over same to GSECL.

14. The job involves crediting of excess material from the job work to main store/Site store.

6

15. The contractor will have to bring all the consumables like gas, welding rod, nut bolt etc at

his own cost.

16. The contractor has to credit the all type of welding rod in site store prior start of work.

[Qty-CGS/680--10 Kg, Cutrod--20 Kg & Gen purpose rod--10 Kg. respectively

].

17. The contractor has to credit welding from L&T/Bob-shell/Diffusion/D&H make in main

store prior to start of welding job.

18. The Workshop facility for drilling of holes etc. (for minor work only) will be provided by

the GSECL, FREE OF COST if available.

19. The welding machine & cable etc shall have to be arranged by the Contractor and GSECL

will not pay any Extra charges for the same.

20. Electrical connection & water connection shall be supplied, FREE OF COST by the GSECL

21. Hydra crane facility for the work shall be provided free of cost{if available}

22. No Extra charges will be paid by the GSECL for Loading, Unloading & carting of the

materials as rates are all inclusive.

23. For any dispute, the decision of the Chief Engineer shall be final and binding to the

contractor.

24. The work will have to be completed within Six Month; However contractor will have to

start the work immediately on getting intimation from GSECL.

25. Payment :-

• 100% job work cost shall be made on completion of work & satisfactory trial of gear

box after joint verification & as per GSECL terms and conditions.

26. VAT, other Govt. taxes etc will be born by the contractor.

27. The contractor has to observe all the safety rules for the safety of himself, his labors,

Plants etc.

28. Contractor has to submit the daily work progress report on his letter head to EIC & get

certified by them.

29. The contractor has to observe all the labor law/rules during the work.

SIGNATURE CHIEF ENGINEER

NAME & ADDRESS OF CONTRACTOR GSECL: UTPS: Ukai

7

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

Sub: - Job work to Gear box commissioning related work at bucket wheel platform of Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS

Scope of work for item no-2

1. The Job involves receipt of material [gear box or spares etc.] from main store/site store

& shift the same at working place by contractor/or staff & truck/tractor as per

instruction of EIC.

2. The job work involves arrangement of all consumable required for the work. I.e.-Cutting

gas, welding rod, Hardware material etc relevant to job.

3. The job work involves fabrication of temporary structure {as per inst. of EIC} for work to

be carried out above ground level at an average Height of 05 meter approximately.

4. The job work involves servicing of complete gear box at tool room of coal handling plant &

replaces the necessary required spares as per instruction of service engineer of supplier.

5. It is sole responsibility of contractor to arrange visit of service engineer of supplier for

the said work. GSECL shall co-operate in the matter positively.

6. It is sole responsibility of contractor to arrange lodging/boarding & transportation of

service engineer.

7. The Job work involves cleaning of base frame of gear box at site

8. The Job work involves shifting of complete gear box from tool room to site safely &

installs the same at position approximately five meter heights.

9. The job work involves installation of hollow shaft in position, alignment of all parts of

bucket wheel shaft.

10. The job work involves fixing/installation of shrink disk in position.

11. It is sole responsibility of party to arrange sufficient labor force to rotate bucket wheel

manually {if required} during the installation/commissioning process of gear box..

12. It is sole responsibility of party to safe guard the material procured by them or issued to

them for work till completion of work & handing over same to GSECL.

13. The job involves crediting of excess material from the job work to main store/Site store.

8

14. The contractor will have to bring all the consumables like gas, welding rod, nut bolt etc at

his own cost.

15. The Workshop facility for drilling of holes etc. (for minor work only) will be provided by

the GSECL, FREE OF COST if available.

16. The welding machine & cable etc shall have to be arranged by the Contractor and GSECL

will not pay any Extra charges for the same.

17. Electrical connection & water connection shall be supplied, FREE OF COST by the GSECL

18. Hydra crane facility for the work shall be provided free of cost{if available}

19. No Extra charges will be paid by the GSECL for Loading, Unloading & carting of the

materials as rates are all inclusive.

20. For any dispute, the decision of the Chief Engineer shall be final and binding to the

contractor.

21. The work will have to be completed within Six Month; However contractor will have to

start the work immediately on getting intimation from GSECL.

22. Payment :-

• 100% job work cost shall be made on completion of work & satisfactory trial of gear

box after joint verification & as per GSECL terms and conditions.

23. VAT, other Govt. taxes etc will be born by the contractor.

24. The contractor has to observe all the safety rules for the safety of himself, his labors,

Plants etc.

25. Contractor has to submit the daily work progress report on his letter head to EIC & get

certified by them.

26. The contractor has to observe all the labor law/rules during the work.

SIGNATURE Chief Engineer (Gen)

NAME & ADDRESS OF CONTRACTOR G.S.E.C.L, TPS, Ukai Dam

9

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM–TAPI

Schedule-A

Sub: - Job work to Gear box commissioning related work at bucket wheel platform of Stacker cum

Reclaimer in Unit-6 coal handling plant at UKAI TPS

Terms & Conditions:-

1. The party has to arrange Consumable for the work along with Hardware item up to site.

2. All the loading/unloading/shifting of material & job work of commissioning along with testing

shall be supervised by party’s supervisor only.

3. As the power station is restricted area party has to approach to C.I.S.F section for

necessary permit/gate pass to staff.

4. The job work for commissioning, testing of the system shall be carried out in Ukai Dam

premises only.

5. No other taxes levies or octroi / duties shall be payable to the party.

6. Service Tax if any shall be paid extra as per GSECL rules.

7. The necessary tool/Tackles/ welding rod/Gas shall be arranged by party.

8. Payment shall be made only after commissioning, testing of the system at site/complete

erecting & certified by EIC as per GSECL standard payment terms.

9. The rates quoted shall be firm till completion of the work and valid up to three month from

the date of opening of tender.

10. The successful tenderer shall require executing the agreement as per GSECL rule before

commencement of work. The cost of the stamp paper shall be born by the party.

11. The time limit for the work is kept for Six (06) months from the date of written

instruction to commence work by GSECL.

12. The successful tenderer shall have to pay Security Deposit of 5 % of the order value within

10 Days by D.D or bank guarantee from the date of issue of work order/LOI in favor of

GSECL Payable at Bank of Baroda-Ukai branch/State bank of India –Ukai branch. The S.D

will be released after one month (30 Days) from the completion of work order.

13. The offer received without Tender fee & EMD will not be considered.

14. Chief Engineer reserves the right to accept or reject any or all offers without assigning any

reason thereof.

15. The party shall have to follow all safety rules and compliances to appropriate authority on

default party shall be responsible.

Chief Engineer

G.S.E.C.L, TPS, Ukai Dam

10

U]HZFT ZFHI lJn]T SM5M"Z[XG ,LDL8[04

SMg8=FS8ZMV[ 5F/JFGF “;,FDlTGF ;FDFgI lGIDM”

lJHDYSDF\ SFI"ZT NZ[S SMg8=FS8ZMV[ GLR[ H6FJ[, ;,FDlTGF ;FDFgI lGIDMG] \ R]:T56[ 5F,G SZJFG] \ ZC[X[P T[DGF JS"SMg8=FS8 C[9/ SFI" SZTL NZ[S V[Hg;LqSFDNFZM G[ ;NZC]\ lGIDM YL ;\5}6"56[ JFS[O SZJFGL VG[ SFI" NZdIFG VF lGIDM G] \ 5F,G SZFJJFGL HJFANFZL H[ T[ SMg8=FS8ZGL ZC[X[P p5ZF\T4 NZ[S SMg8=FS8Z[ T[DG] \ SFI" RF,] SZTF\ 5C[,F ;\AlWT lJEFULI J0Fq.HG[ZG[ AF\C[WZL VF5JFGL ZC[X[ S[ T[D6[ GLR[ H6FJ[, ;]Z1FFGF ;FDFgI lGIDM AZFAZ JF\R[, K[4 T[DG[ D/[, JS" SMg8=FS8G] \ SFI" SZTLqSZFJTL JBT[ ;NZC] \ lGIDMG] \ ;\5}6"56[ 5F,G SZX[ VG[ VFD SZJFDF\ lGQO/ UI[YL S[ T[G]\ p<,\WG SZJFYL Ô[ SM5M"Z[XGGL SM.56 DF,vlD,STG[ G]SXFG YX[ VYJF TM T[DGFqSM5M"Z[XGGF SM.56 :8FOG[ .ÔqVS:DFT G0X[ TM T[GL ; \5}6" HJFANFZL T[DGL 5MTFGL ZC[X[P H[GL T[VMV[ T[DGF\ ,[8ZC[0 p5Z ,[BLTDF\ BF+L VF5JFGL ZC[X[P

s!f NZ[S SFI" DF8[ SFDG[ VG]~5 IMuI ,FISFT WZFJTF\ VG]EJL VYJF H[ T[ SFI" DF8[ BF; TF,LD V5FI[, DF6;MG[ H SFD 5Z ,[JFGF q ZFBJFGF ZC[X[ H[YL VS:DFTM lGJFZL XSFIP

sZf EIHGS 5NFY"4 DXLGZL TYF lJ:TFZ S[ H[GF p5Z R[TJ6L NXF"J[, CMI VYJF GM8L; D]S[, CMI tIF\ VYJF T[GF 5Z SFD SZTF\ 5C[,F\ ;\5}6" ;,FDlTGF 5U,F\ ,[JF VG[ H~ZL ,F.G S,LIZ VYJF “5ZDL8 8] JS"” ;\ \A\lWT ;[SXG q 0L5F8"D[g8DF\YL VYJF T[DGF âFZF lGI]ST ;1FD VlWSFZL 5F;[YL D[/JL ,LWF AFN H SFD RF,] SZJ] \P

s#f J[<0ÄU4 S8ÄU4 CL8ÄU TYF VgI CM8JS" Ô[[A sS[ H[DF\ VFU4 :5FS"4 UZDL lJP 5[NF YFIf SZTF\ 5C[,F SFDGL HuIFGL VFH]AFH] SM. VFU 5S0L ,[ T[J] \ D8LZLI, 50[, CMI TM B;[0L GFBJ] \ VG[qVYJF -F\SL N[J] \P 8]\SDF\4 VFJF SFIM" RF,] SZTF\ 5C[,F\ VFUGF ;\ElJT pNŸEJ :YFGMGM GFX SZJM VYJF VFJF SFIM" äFZF VFU G ,FU[ T[ DF8[GF ;\5}6" ;,FDlTGF 5U,F\ ,[JFP p5ZF\T4 VF 5|SFZGF CM8JS" HF[A RF,] SZTF\ 5C[,F\ ;\A\lWT ;[SXGq0L5F8"D[g8G[ Ô6 SZJL VG[qVYJF ;1FD VlWSFZL 5F;[YL “CM8JS"

5ZDL8” D[/JL ,[JLP VFJF SFI" NZdIFG SFI":Y/ 5ZqGÒS VFU lGI \+6GF ;FWGM H[JF S[ VluGXFDS I \+M4 5F6LqZ[TLGL AF,NLVM lJP p5,aW ZFBJFP VFUGL XSITFVM JWFZ[ H6FI TM VUFpYL H OFIZ ;[SXGG[ HF6 SZJL H[YL IMuI 5U,F\ ,. XSFI VYJF OFIZvJMR CFHZ ZFBL

XSFIP

s$f SM.56 SgOF.G :5[;s;F\S0L HuIF4 A\WLIFZ HuIF VYJF TM T[JL HuIF S[ HIF\ CJFGL VJZHJZ

GlCJT CMIqTNŸG G CMIfGL V \NZ S[ J[;<;GL V \NZ SFD SZJF DF8[GL H~ZL “SgOF.G :5[;qJ[X<; V[g8=L 5ZDL8” ;\,uG BFTF TZOYL D[/JL ,[JL VG[ tIFZAFN H SFD DF8[ V \NZ HJ]\P VFJL HuIFDF\ 5|SFX DF8[ Z$ JM<8GM sBIS 5|DF6LT4 UF0" JF/Mf C[g0,[d5 H JF5ZJMP C[g0,[d5 DF8[ p5IMUDF\ ,LW[, JFIZsS[A,f ;FZL l:YlTGM4 ;F\WF\ZCLT VG[ H~ZLIFT D]HAGL ÙDTFGM CMJM H~ZL K[P VFJL :5[;qJ[;<;GL V\NZ SFD SZTF\ DF6;MG] \ wIFG ZFBJF ACFZ V[S DF6;G[ VJxI ZFBJM H[ V\NZ SFI" SZTF\ DF6;MG] \ ;TT ACFZYL wIFG ZFB[ VG[ .DZHg;LDF \ T[DGL DNN[ VFJ[qDNN SZ[ VG[ qVYJF DNN DF8[ jIJ:YF SZ[P U8Zq8=[gRGF -F\S6F BM,L V\NZ SFD SZFJTL JBT[ T[GL VFH]AFH]YL VJZHJZ SZTF\ VgI SFDNFZMqDF6;MG[ R[TJJF DF8[ SM. DF6; ZFBJM VYJF TM T[ lJ:TFZGL VFH]AFH] NMZL AF\WL ,F, S50]\ VYJF R[TJ6LGL GM8L; ,UFJLG[ VgI 8=FOLSG[ R[TJJMP VFJF SFIM" 5]ZF YIF AFN BM,[, -F\S6F\ SFI" 5C[,F CMI T[JL ZLT[ H A\W CF,TDF\ OZL UM9JJF VG[qVYJF ;NZC] \ :Y/G[ ;J" 5|SFZ[ ;]Z1FLT CF,TDF\ H KM0J] \P

s5f %,Fg8DF\ HJFGF Z:TFVM4 ;L0LVM4 NFNZ4 ,LO84 5[;[H S[ VgI U[ \UJ[.H VG[ Z:TFVM S[ H[GF p5Z DF6;MGL VJZHJZ ZC[TL CMIq.DZHg;LDF\ VJZHJZGL XSITFVM CMI T[GF p5Z SM. SFD G SZJ] \

11

S[ T[GF p5Z D8LZLI<;4 :5[Z5F8";4 8]<;8[S<;4 .SJL5D[g84 lJP D]SL Z:TFVM a,MS G SZJFP VFJL HuIF 5Z SFD SZJ] \ VlGJFI" CMI TM ;1FD VlWSFZLGL VYJF H[ T[ BFTFGF .HG[ZGL 5ZJFGUL D[/jIF AFN H SFD SZJ]\P VlGJFI" ;\HF[UMDF\ VFJL HuIFV[ SFD SZTF\ 5C[,F T[ lJ:TFZG[ NMZL T[DH ,F, S50]\qGM8L; D]SL T[ Z:TFG[qHuIF G[ VJZHJZ DF8[ V;,FDT ÔC[Z SZJL VYJF V[S DF6; pEM ZFBL VJZHJZ V8SFJL N[JLq0FIJ8" SZJLP

s&f SM.56 JLH/LYL RF,TF I \+s5FJZ VM5Z[8[0 .SJL5D[g8 q C[g0 8]<;f H[JF\ S[ J[<0L\U DXLG4 C[g0 U|F.0L\U DXLG4 C[g0 0=L,L\U DXLG lJP p5IMUDF\ ,[TF\ 5C[,F\ T[ JF5ZL XSFI T[D K[ S[ S[D T[ T5F;L4 JF5ZJF DF8[ ;,FDT H6FI TM H T[GM p5IMU SZJMP BM8SFJF/F4 AU0L UI[, VYJF AZFAZ DZFDT G YI[,F ;FWGM JF5ZJF GCL\P p5ZMST ;FWGM JF5ZJF DF8[G] \ H~ZL lJHvHF[0F6 VF5 D[/[ G SZTF\ ;\,uG ;[SXG âFZF VYJF TM T[DGF DFU"NX"G C[9/ H IMuI HF[0F6 SZJ] \ q SZFJJ] \P H[ T[ .,[S8=LS, lJEFU âFZF SMg8=FS8ZG[ C\UFDL JLHvHF[0F6 T[DGF s9[S[NFZGFf D[.G AM0" ;]WL VF5JFDF\ VFJX[P H[GF p5Z D[.G :JLR4 .PV[,P;LPALP TYF OI]h CMJF H~ZL K[P p5ZMST ;FWGM âFZF .,[S8=LS, XMS G ,FU[ VYJF :5FS"4 XM8" ;ZSL8 lJP G YFI T[ DF8[ VFJF NZ[S ;FWGMG[ VYL" \U D/L ZC[ T[ BF; H~ZL K[P VFJF ;FWGM DF8[GM JFIZs5FJZ SM0"f ;F\WF JUZGM ;\/U VG[ 5]ZTL 1FDTFGM JF5ZJM4 S[ H[DF\ VYL"\UGM JFIZ 56 CMJM BF; H~ZL K[P T[YL ;L\U,O[.h DF8[ #s+6f VG[ Y|LO[.h DF8[ 5s5F\Rf JFIZJF/M IMuI S[5[;L8LGM H SM0" JF5ZJMP %,U4 ZL;[%8[S<;4 5LG CM<0Z lJP ;FZL CF,TDF\ TYF IMuI 1FDTFJF/F CMI TM H JF5ZJFP

s*f NZ[S SFI" DF8[ H~ZL VG[ IMuI ;,FDlTGF :JZ1F6FtDS ;FWGMGM VJxI p5IMU SZJMP VFJF ;FWGMGF p5IMU lJGF SFD SZJ] \ GlCP H]NF H]NF SFI"DF\ q SFI" :Y/M p5Z JF5ZJF DF8[GF ;,FDlTGF ;FWGMGL IFNL GLR[ D]HA K[P

! .g0:8=LI, ;[O8L C[,D[8P DFYFGF Z1F6 DF8[P

Z ;[O8L UMU<;sU|F.g0L\UqJ[<0;"q,[WZ DF:Sq5[GMZDF UMU<; lJPf

VF\BGF Z1F6 DF8[P

# O[.; XL<0 sCF<O q O],f RC[ZFGF Z1F6 DF8[P

$ .IZ %,U q .IZ DO;P SFGGF Z1F6 DF8[P

5 V[5|MG sZaAZ4 5LJL;L4 V[:A[:8Mh4 ,[WZ4 SM8G lJPfP XZLZGF Z1F6 DF8[P & u,Mh sZaAZq5LJL;L4 V[:A[:8Mh4 ,[WZ4SM8G4 XMS5|]O

lJPf CFYGF Z1F6 DF8[P

* .g0:8=LI, ;[O8L;]h4 UDA]84 ,[WZ X]h4 V[:A[:8Mh X]hP

5UGF Z1F6 DF8[P

( ;[O8L A[<84 ;[O8L ZM54 ,F.O ,F.G lJP p \RF.qp \0F.qSgOF.G:5[;q J[;<;DF\ SFD JBT[ Z1F6 DF8[P

) 0:8 Z[:5LZ[8Z4 :SFO"P 0:8 ;FD[ `J;GT \+GF Z1F6 DF8[P

!_ S[DLS, SF8L"h Z[:5LZ[8ZP S[DLS, OI]d; q J[5Z ;FD[ Z1F6 D[/JJF DF8[P !! S[GL:8Z U[; DF:SP h[ZL U[; ;FD[ Z1F6 DF8[P

!Z V[Z ;%,FI Z[:5LZ[8;"P 5|F6JFI]GL T \ULJF/F SFI"1F[+DF\ SFI" SZTL JBT[

s(f JHG p\RSJF DF8[GF ;FWGMs,LO8L\U 8[S<;fGM T[DH T[GL ;FY[ ;\S/FI[, J:T]VM H[JL S[ OLSR;"4 :,L\U4 I]vS,[d54 VF.vAM<84 lJU[Z[GM p5IMU SZTF\ 5C[,F\ T[ ;,FDT K[ S[ S[D VG[ T[GL ;1FD jIlST âFZF SZJFDF\ VFJTL JFlQF"S RSF;6L q 8[:8L\U GL SFIN[;ZTFsJ[,L0L8Lf K[ S[ S[D T[ T5F;L BF+L SZL ,[JLP p5ZF\T4 JHG p \RSTF\ 5C[,F\ T[G[ AZFAZ OLS; SZJ] \P

s)f p \RF. p5Z SFD SZJF DF8[GF DF\R0Fs:S[OM<0f 5]ZTF DF5 TYF S[5[;L8LGF\ AF\WJFP VFJF :S[OM<0 p5Z R0TF\ ;DI[ VYJF TM p \RF. 5ZGF SM.56 :8=SRZ p5Z SFD SZTL JBT[ ;[O8L A[<8 TYF C[<D[8GM VJxI p5IMU SZJMP p5ZF\T4 5C[Z[, C[<D[8GM RLGv:8=[5 AF\WJM 56 H~ZL K[P

s!_f JS"VM0"Z D]HAG]\ SFI" SZFJJF DF8[ H~ZL NZ[S .,[S8=LS, TYF DLS[GLS, ;FWGM q p5SZ6M H[JF S[ J[<0L\U DXLG4 S8L\U DXLG4 U|F.g0Z4 0=L,4 R[.G 5],L a,MS4 C]S R]S TYF VgI ;FWGM lJP VF.PV[;PVF.P 5|DF6LT H JF5ZJFGF ZC[X[P p5ZF\T4 V[JF ;FWGM S[ H[G[ RMSS; ;DI DIF"NFDF\

12

JF5ZJFGF CMI NFPTP U|F.g0L\U JL, q 0L:S4 J[<0L\U .,[S8=M0 lJPGL V[S:5FIZL TFZLB HTL ZCL CMI TM T[ JF5ZJF GCL\P

s!!f SMg8=FS8ZMV[ T[DH T[DGF DF6;MV[ T[DG[ V5FI[, JS" SMg8=FS8 l;JFIGF %,Fg8DF\ RF,TF\ ZMÒ\NF SFDDF\ NB,~5 YJ] \ GlC4 HIF\ tIF\ CZJ] \vOZJ]\ GCL T[DH DXLGZL .SJL5D[g8 TYF VgI ;FWGM ;FY[ R[ \0F SZJF GlCP p5ZF\T4 T[DGF SD"RFZL q SFDNFZM4 ZL;[; NZdIFG S[ VgI ;DI[4 RF,] %,Fg8 q ;L:8LD q DXLGZL q VgI HuIF S[ HIF \ HF[BDM CMI tIF\ G A[;[4 G HD[ S[ G VFZFD SZ[ T[GL ;]RGF VF5JLP

s!Zf SFI" NZlDIFG VFU S[ W]DF0M 5[NF YFI TM TFSLN[ A]hFJJF 5|ItG SZJM VG[ T]T"H OFIZ :8[XGDF \ HF6 SZJLPsOFIZ :8[XGGM OMG G\AZ Z__ VG[#__ K[Pf

s!#f h[[ZL TYF W0FSF ;FY[ ;/UL p \9[ T[JF U[;GF AF8,FVM sH[JF S[ VMS;LHG4 V[;L8L,LG4 V[,P5LPÒP4 CF.0=MhG4 V[DMGLIF4 S,MZLG4 SFA"G 0FIMS;F.0 lJU[Z[f G[ BF; SF/Ò ,.G[ ;,FDT ZLT[ B;[0JFP VF DF8[ BF; 8=M,LGM p5IMU SZJMP VFJF U[; ;L,Lg0ZM ;FY[ SFD SZTF\ 5C[,F\ VG[ NZlDIFG BF; ;,FDlTGF 5U,F\ ,[JFP

s!$f SFI" 5]~ SIF" 5KL SFDGL HuIFV[YL SM8GJ[:84 -/[, VM., q U|L;4 J[<0L\U ZM0GF 8]S0F4 VgI GSFD]\ D8LZLI<; q RLHJ:T]VM C8FJL ,[JL VG[ HuIF jIJl:YT ZLT[ ;FO SZL q SZFJL VF5JLP

s!5f SM.56 SFI" NZdIFG HF[ SM. VS:DFT G0[ TM T[GM ZL5M8" TFlSN[ T[GF BFTFSLI J0F DFZOT ;,FDTL

VlWSFZL4 p+F6G[ SZJMP VF ZL5M8" DF8[GF D]SZZ SZ[,F OMD" G\P Z! H[ T[ BFTFDF\YL VYJF TM ;[O8L ;[SXGDF\YL D/L ZC[X[P

s!&f 9[S[NFZ[ SFI" NZlDIFG4 SFI"GF HF[BDM ;FD[ 5ZT] \ Z1F6 VF5L XS[ T[JF :8Fg00" AGFJ8GF sVF.PV[;PVF.P 5|DF6LTf :JZ1F6FtDS ;FWGM T[DGF :8FOG[ 5]ZF 5F0JFGF\ ZC[X[ VG[ SD"RFZL q SFDNFZ T[ ;FWG JF5ZLG[ SFI" SZ[ T[ wIFG ZFBJFGL HJFANFZL 9[SNFZGL ZC[X[P

s!*f p5ZMST lGIDM p5ZF\T ;]Z1FFG[ ,UTL ;ZSFZzL âFZF W0JFDF\ VFJ[, NZ[S SFINFSLI HF[UJF.VMG] \ 56 T[VMV[ ;\5}6"56[ 5F,G SZJFG]\ ZC[X[P BF; SZLG[4 SFZBFGF WFZMv!)$( TYF SFZBFGF lGIDv!)&# sK[<,F ;]WFZFVM ;lCTfDF \ SZJFDF\ VFJ[, NZ[S HF[UJF.VMG]\ R]:T56[ 5F,G SZJFG] \ ZC[X[P p5ZF\T4 :YFlGS ;1FD VlWSFZL äFZF D]SZZ SZJFDF \ VFJ[, ;]Z1FFG[ ,UTF lGIDMq;]RGMq5wWlTVMG] \ 56 5F,G SZJFG] \ ZC[X[P

s!(f p5ZMST lGIDM G] \ R]:T56[ 5F,G SZJ] \P SM.56 lGIDM DF\ ;DHF6 G 50[ VYJF DFU"NX"GGL H~Z H6FI TM ;,FDlT VlWSFZL GM ;\5S" SZJMP

D]bI .HG[Z U]PZFPlJPSMP,LP4

13

GUJARAT STATE ELECTRICITY CORPORATION LIMITED

UKAI THERMAL POWER STATION, UKAI DAM, DIST: TAPI

Name of work: - Job work to Gear box commissioning related work at bucket wheel platform of

Stacker cum Reclaimer in Unit-6 coal handling plant at UKAI TPS.

-: SCHEDULE - “B” :-

Name of Party: - __________________________________________________________

Sr.

No.

Description of work Qty

Rate in

Rs.

Unit Amount in Rs.

1 Dismantling of existing shrink

disk from solid shaft of bucket

wheel by gas/cut rod electrode

cutting process, Filling of

Machine able welding material on

solid shaft of bucket wheel &

machining of Shaft as per

dimension of shrink disk at site

of Ukai TPS as per scope of

work & schedule-A.

1 3,48,083/- Complete

Job work

3,48,083.00

2 Job work of Assembly of hollow

shaft with gear box, shifting to

site, Installation, commissioning

& testing trial run there off as

per scope of work & schedule-A.

1 59,218/- Complete

Job work

0, 59,218.00

Total 04,07,301.00

In words Rs Four Lakh Seven Thousand Three Hundred One only

Note: - 1] The rates are Exclusive of Service tax & shall be paid as per GSECL rules.

2] Payment shall be made for the actual quantity executed.

Chief Engineer (Gen)

GSECL, UTPS, Ukai Dam

My offer is _______ % higher or _______ % lower than estimated cost of Schedule-B

(Percentage should be written in figure as well as in words).

(Rs.______________________________________________________).

Signature of Contractor