uk link programme dashboard report change overview board 4/8/14

2
UK Link Programme Dashboard Report Change Overview Board 4/8/14 •RAG status remains at amber •Detailed Design to complete at the end of September; is challenging but achievable •Priority remains to make file formats available in draft format as early as possible •Functional fit remains positive at approx. 77-80% •Good attendance at UKLIEF and broad engagement by individual organisations in the Programme Executive summary Industry Engagement Comms IE Comms. Key Milestone High Level Design Complete Detailed Design Complete Xoserve UAT Complete Industry Testing Start Cutover & Implementation Baseline Date 18/04/14 29/08/14 28/05/15 01/06/15 01/10/15 Current Planned Date Complete 30/04/14 26/092014 28/05/15 01/06/15 01/10/2015 Programme Milestones Supply Point Transfer End to End To Be Process published and presented at UKLIEF on 22 nd July Data Mapping overview presented to UKLIEF on 22 nd July. Functional Specifications continue to be developed as per the Detailed Design plan Significant progress has been made in the development of the Logical Design Model and Physical Design Model mapping Recent Achievements Prepare and publish the End to End To Be Process for AQ (19 th August) Confirmation to Industry of the to-be process communication schedule and scope Continuation of Design Workshops to develop Functional Specifications Agree the approach for the early delivery of draft file formats with the industry Agree UKLIEF Stakeholder Readiness Measurement approach and begin population Future Priorities Key Dependencies Reporting Date 01/06 Start of Market Trials, L/L Cutover Plan 30/09 Interface Inventory & File Formats, Transition Plan 28/08 End of Market Trials Risk Risk Summary Impact Date Mitigation Industry readiness: Risk that some industry stakeholders have a low level of understanding of Nexus requirements due to lack of attendance at industry forums 01/06/15 UKLIEF established need for Stakeholder Readiness Framework to monitor industry readiness. Scope: Raising of new mods which impact the baselined requirements will impact Oct 2015 delivery. On-going UKLP baselined scope now communicated Change control process now in place to manage scope Market Testing: Risk that Market Trials is insufficient in length, too late within the programme, and participants may not be ready in time to take part. Q4 2014 Xoserve to consider mitigating actions i.e. dummy test files in advance while preparing Market Trials Aggregated Programme RAG Q1 2015 Mkt Test Approach & Registration Process ~31/03 Transition Mods Approved Dependency Date Required Impact if missed Status Industry participants to cleanse data by December 2014 to feed into UAT 31/12/14 UAT timelines may increase due to increased number of data issues, leading to an overall delay to the implementation. Industry agreement of process change to adopt SAP ‘Out of the Box’ May 14 September 14 Delays in confirmed changes to industry stakeholder systems with follow on impacts on market test and implementation readiness Industry agreement of file formats. Oct 14 Delay in approving file formats may lead to design rework which will impact programme build and testing timescales. 12/5 Test Strategy 18/6 Transition Strategy 22/7 Data Mapping Presentation To-Be Processes

Upload: kalei

Post on 06-Jan-2016

24 views

Category:

Documents


0 download

DESCRIPTION

UK Link Programme Dashboard Report Change Overview Board 4/8/14. Executive summary. RAG status remains at amber Detailed Design to complete at the end of September; is challenging but achievable Priority remains to make file formats available in draft format as early as possible - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: UK Link Programme Dashboard Report  Change Overview Board 4/8/14

UK Link Programme Dashboard Report Change Overview Board 4/8/14

•RAG status remains at amber•Detailed Design to complete at the end of September; is challenging but achievable•Priority remains to make file formats available in draft format as early as possible•Functional fit remains positive at approx. 77-80%•Good attendance at UKLIEF and broad engagement by individual organisations in the Programme

Executive summary

Industry Engagement Comms

IE Comms.

Key Milestone High Level DesignComplete

Detailed DesignComplete

Xoserve UATComplete

Industry TestingStart

Cutover & Implementation

Baseline Date 18/04/14 29/08/14 28/05/15 01/06/15 01/10/15

Current Planned DateComplete 30/04/14

26/092014 28/05/15 01/06/15 01/10/2015

Programme Milestones

• Supply Point Transfer End to End To Be Process published and presented at UKLIEF on 22nd July• Data Mapping overview presented to UKLIEF on 22nd July.• Functional Specifications continue to be developed as per the Detailed Design plan • Significant progress has been made in the development of the Logical Design Model and Physical

Design Model mapping

Recent Achievements

• Prepare and publish the End to End To Be Process for AQ (19th August)• Confirmation to Industry of the to-be process communication schedule and scope• Continuation of Design Workshops to develop Functional Specifications• Agree the approach for the early delivery of draft file formats with the industry• Agree UKLIEF Stakeholder Readiness Measurement approach and begin population

Future Priorities

Key Dependencies

Reporting Date

01/06Start of

Market Trials,L/L Cutover Plan

30/09Interface Inventory & File Formats, Transition

Plan

28/08End of

Market Trials

Risks

Risk Summary Impact Date Mitigation

Industry readiness: Risk that some industry stakeholders have a low level of understanding of Nexus requirements due to lack of attendance at industry forums

01/06/15

UKLIEF established need for Stakeholder Readiness Framework to monitor industry readiness.

Scope: Raising of new mods which impact the baselined requirements will impact Oct 2015 delivery.

On-going

UKLP baselined scope now communicatedChange control process now in place to manage scope

Market Testing: Risk that Market Trials is insufficient in length, too late within the programme, and participants may not be ready in time to take part.

Q4 2014

Xoserve to consider mitigating actions i.e. dummy test files in advance while preparing Market Trials Approach.

Aggregated Programme RAG

Q1 2015Mkt Test

Approach & Registration Process

~31/03Transition Mods

Approved

DependencyDate

RequiredImpact if missed Status

Industry participants to cleanse data by December 2014 to feed into UAT

31/12/14UAT timelines may increase due to increased number of data issues, leading to an overall delay to the implementation.

Industry agreement of process change to adopt SAP ‘Out of the Box’

May 14 September1

4

Delays in confirmed changes to industry stakeholder systems with follow on impacts on market test and implementation readiness

Industry agreement of file formats.

Oct 14Delay in approving file formats may lead to design rework which will impact programme build and testing timescales.

12/5Test Strategy

18/6Transition Strategy

22/7Data Mapping Presentation

To-Be Processes

Page 2: UK Link Programme Dashboard Report  Change Overview Board 4/8/14

Change Portfolio: Programme Dashboards

EU Reform – EU Phase 2 and Gas Day Changes

Smart Portfolio – DCC Day 1 & DCC Gateway

Aggregated Programme RAG

Key MilestoneAnalysisComplete

Detailed Design

Complete

Xoserve UAT

Complete

Cutover & Imp.

Baseline Date 07/04/2014 30/05/14 17/10/14 07/11/14

Current Planned Date07/04/2014Complete

30/05/14Complete

17/10/14 07/11/14

Recent Achievements:

• Build and Unit Test activities have been completed• System testing has commenced and progressing to plan

Priorities For Next Month:

• Continue with System Testing• Continue with UAT preparation activities• Issue External communications on the handling of transition and cutover scenarios

Risks:• Increased efforts in testing as Faster Switching functionality is to be delivered in

Legacy and new world UKL.

Dependencies: • None – relevant Mod now approved for implementation

Faster Switching (Mod 477)

*Cutover to be planned alongside UKLP

Key MilestoneAnalysisComplete

Detailed Design

Complete

Xoserve UAT

Complete

Cutover & Imp.

Baseline Date 30/06/14 15/08/14 31/07/15 01/10/15

Current Planned Date30/06/14Complete

20/08/14 15/07/15 01/10/15*

Aggregated Programme RAG

Recent Achievements:

• DCC Day 1 went live successfully on 28th June.• Delta files are being received on a daily basis

Priorities For Next Month:

• Commence Build phase for DCC Gateway project• Provide SEC 4 response• Complete RDP consultation on baselined SIT Approach document for the DCC

Risks:

• Uncertainty over revised DCC go-live • Late delays to UKLP or DCC implementation would impact DCC Gateway cutover• There is a risk of a large number of record rejections if Supplier IDs are not correctly

set up on iGT systems by DCC Day 1

Dependencies:• DCC Gateway deployment approach is dependent upon the sequencing of DCC and

UKLP go live dates.

Key MilestoneDCC

Day 1 Impl.HLD

Complete

Detailed Design

Complete

Xoserve OAT

Complete

Cutover & Imp.

Baseline Date 29/06/14 n/a 05/09/14 24/10/14 13/12/14

Current Planned Date29/06/14Complete

n/a 23/10/14 31/12/14 18/01/15

Aggregated Programme RAG

Recent Achievements:

• Application Design phase is progressing to plan• Greater understanding is developing of the dependencies between UKLP and EU

Reform and development of options to mitigate the delivery risks.

Priorities For Next Month:

• Start Application Build• Upgrade test environments to accommodate EU Changes

Risks:• Adjacent Transmission System Operators may use data exchange tools that are not

compatible with Gemini’s data exchange tool• High risk of change due to unapproved EU Codes and mods

Dependencies: • Baselining and approval of modifications is required.