uk link programme dashboard report change overview board 4/8/14
DESCRIPTION
UK Link Programme Dashboard Report Change Overview Board 4/8/14. Executive summary. RAG status remains at amber Detailed Design to complete at the end of September; is challenging but achievable Priority remains to make file formats available in draft format as early as possible - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: UK Link Programme Dashboard Report Change Overview Board 4/8/14](https://reader036.vdocuments.us/reader036/viewer/2022062321/56813b1d550346895da3d204/html5/thumbnails/1.jpg)
UK Link Programme Dashboard Report Change Overview Board 4/8/14
•RAG status remains at amber•Detailed Design to complete at the end of September; is challenging but achievable•Priority remains to make file formats available in draft format as early as possible•Functional fit remains positive at approx. 77-80%•Good attendance at UKLIEF and broad engagement by individual organisations in the Programme
Executive summary
Industry Engagement Comms
IE Comms.
Key Milestone High Level DesignComplete
Detailed DesignComplete
Xoserve UATComplete
Industry TestingStart
Cutover & Implementation
Baseline Date 18/04/14 29/08/14 28/05/15 01/06/15 01/10/15
Current Planned DateComplete 30/04/14
26/092014 28/05/15 01/06/15 01/10/2015
Programme Milestones
• Supply Point Transfer End to End To Be Process published and presented at UKLIEF on 22nd July• Data Mapping overview presented to UKLIEF on 22nd July.• Functional Specifications continue to be developed as per the Detailed Design plan • Significant progress has been made in the development of the Logical Design Model and Physical
Design Model mapping
Recent Achievements
• Prepare and publish the End to End To Be Process for AQ (19th August)• Confirmation to Industry of the to-be process communication schedule and scope• Continuation of Design Workshops to develop Functional Specifications• Agree the approach for the early delivery of draft file formats with the industry• Agree UKLIEF Stakeholder Readiness Measurement approach and begin population
Future Priorities
Key Dependencies
Reporting Date
01/06Start of
Market Trials,L/L Cutover Plan
30/09Interface Inventory & File Formats, Transition
Plan
28/08End of
Market Trials
Risks
Risk Summary Impact Date Mitigation
Industry readiness: Risk that some industry stakeholders have a low level of understanding of Nexus requirements due to lack of attendance at industry forums
01/06/15
UKLIEF established need for Stakeholder Readiness Framework to monitor industry readiness.
Scope: Raising of new mods which impact the baselined requirements will impact Oct 2015 delivery.
On-going
UKLP baselined scope now communicatedChange control process now in place to manage scope
Market Testing: Risk that Market Trials is insufficient in length, too late within the programme, and participants may not be ready in time to take part.
Q4 2014
Xoserve to consider mitigating actions i.e. dummy test files in advance while preparing Market Trials Approach.
Aggregated Programme RAG
Q1 2015Mkt Test
Approach & Registration Process
~31/03Transition Mods
Approved
DependencyDate
RequiredImpact if missed Status
Industry participants to cleanse data by December 2014 to feed into UAT
31/12/14UAT timelines may increase due to increased number of data issues, leading to an overall delay to the implementation.
Industry agreement of process change to adopt SAP ‘Out of the Box’
May 14 September1
4
Delays in confirmed changes to industry stakeholder systems with follow on impacts on market test and implementation readiness
Industry agreement of file formats.
Oct 14Delay in approving file formats may lead to design rework which will impact programme build and testing timescales.
12/5Test Strategy
18/6Transition Strategy
22/7Data Mapping Presentation
To-Be Processes
![Page 2: UK Link Programme Dashboard Report Change Overview Board 4/8/14](https://reader036.vdocuments.us/reader036/viewer/2022062321/56813b1d550346895da3d204/html5/thumbnails/2.jpg)
Change Portfolio: Programme Dashboards
EU Reform – EU Phase 2 and Gas Day Changes
Smart Portfolio – DCC Day 1 & DCC Gateway
Aggregated Programme RAG
Key MilestoneAnalysisComplete
Detailed Design
Complete
Xoserve UAT
Complete
Cutover & Imp.
Baseline Date 07/04/2014 30/05/14 17/10/14 07/11/14
Current Planned Date07/04/2014Complete
30/05/14Complete
17/10/14 07/11/14
Recent Achievements:
• Build and Unit Test activities have been completed• System testing has commenced and progressing to plan
Priorities For Next Month:
• Continue with System Testing• Continue with UAT preparation activities• Issue External communications on the handling of transition and cutover scenarios
Risks:• Increased efforts in testing as Faster Switching functionality is to be delivered in
Legacy and new world UKL.
Dependencies: • None – relevant Mod now approved for implementation
Faster Switching (Mod 477)
*Cutover to be planned alongside UKLP
Key MilestoneAnalysisComplete
Detailed Design
Complete
Xoserve UAT
Complete
Cutover & Imp.
Baseline Date 30/06/14 15/08/14 31/07/15 01/10/15
Current Planned Date30/06/14Complete
20/08/14 15/07/15 01/10/15*
Aggregated Programme RAG
Recent Achievements:
• DCC Day 1 went live successfully on 28th June.• Delta files are being received on a daily basis
Priorities For Next Month:
• Commence Build phase for DCC Gateway project• Provide SEC 4 response• Complete RDP consultation on baselined SIT Approach document for the DCC
Risks:
• Uncertainty over revised DCC go-live • Late delays to UKLP or DCC implementation would impact DCC Gateway cutover• There is a risk of a large number of record rejections if Supplier IDs are not correctly
set up on iGT systems by DCC Day 1
Dependencies:• DCC Gateway deployment approach is dependent upon the sequencing of DCC and
UKLP go live dates.
Key MilestoneDCC
Day 1 Impl.HLD
Complete
Detailed Design
Complete
Xoserve OAT
Complete
Cutover & Imp.
Baseline Date 29/06/14 n/a 05/09/14 24/10/14 13/12/14
Current Planned Date29/06/14Complete
n/a 23/10/14 31/12/14 18/01/15
Aggregated Programme RAG
Recent Achievements:
• Application Design phase is progressing to plan• Greater understanding is developing of the dependencies between UKLP and EU
Reform and development of options to mitigate the delivery risks.
Priorities For Next Month:
• Start Application Build• Upgrade test environments to accommodate EU Changes
Risks:• Adjacent Transmission System Operators may use data exchange tools that are not
compatible with Gemini’s data exchange tool• High risk of change due to unapproved EU Codes and mods
Dependencies: • Baselining and approval of modifications is required.