UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012. Agenda. Outline UFRAS Develop a brief understanding of how to use UFRAS Develop an understanding of what to do with output from UFRAS Go through each sheet of UFRAS Explain input/results - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

UFRASUniversity Facilities Risk Assessment

Spreadsheet25 April 2012

Page 2: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Agenda• Outline UFRAS

o Develop a brief understanding of how to use UFRAS

o Develop an understanding of what to do with output from UFRAS

• Go through each sheet of UFRASo Explain input/resultso Instruct users’ on how to input datao Present a synopsis of the function of each sheet

Page 3: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

UFRAS• Objectively and consistently

quantifies a risk index for facilities via a matrix

Page 4: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

UFRAS• Facilitates quick and efficient

comparison of risk across facilities• Conducts a hazard assessment and

vulnerability assessment• Output highlights areas of weakness• Reinforces the suggestion for mitigation

measures

Page 5: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Hazard Assessment• Evaluates the probability and intensity of

the 9 potential hazards that could affect a campus

• Data comes from reputable sourceso ASCE 7-05o NOAAo County flood maps

• Inputs are normalized relative to hazard intensities across the continental United States

• Inputs are largely static for each campuso Reference data unlikely to change; thus

campuses should not need to adjust these inputs for future use

Page 6: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Hazard Assessment

Page 7: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Vulnerability Assessment• Conducted via site visits, discussion with

facility personnel, review of drawings/documents

• Inspection checklist is completed while conducting inspection

• 1-5 hours to complete, depending on size/complexity of facility

• Facility conditions change over time, thus the need to reevaluate facilities periodically

Page 8: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Inspection Checklist• Divided into 5 sections—based on facility

components; it is the first 5 sheets in UFRAS• 92 total questions/statements • 910 permutations to produce final matrix• Inspector assigns ratings (usually 1-4) for

each question/statement which are input for risk calculation

• Unanswered questions/statements are omitted from risk index calculation

Page 9: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Results

• 1 represents lowest risk• 10 represents highest risk• Matrix is normalized by campus

Page 10: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Results

Page 11: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Analysis• Based on output from UFRAS:

o Highlights areas of weakness in facility components relative to hazards

o Mitigation measures can be tailored for the weaker areas in the facility

• Once mitigation measures are suggestedo Inspection checklist may be modified to reflect

lower vulnerability−Second matrix is concurrently produced projecting

new lower risk

Page 12: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Overview of UFRAS sheets• 11 Total sheets

o 5 sheets make up the inspection checklisto 1 sheet makes up the hazard assessmento 1 sheet concisely summarizes input datao 1 sheet allows users to modify ratings to reflect

proposed mitigation measureso 1 sheet produces normalized outputo 2 sheets produce raw output

Page 13: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 1: Site/General Checklist

• 31 questions/statements pertaining to:o General facility design parameterso Site geographyo Vegetationo Site improvements

−Streets/roads−Fencing−Drainage infrastructure

o Utilities on siteo Storage tankso Secondary/support structures

Page 14: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 2: Envelope Checklist

• 19 Questions/statements pertaining to:o Windows and doors

−Flashing−Closing mechanisms−Material

o Veneer−Attachment, configuration, material

o Foundation plane/lowest level floor planeo Building geometryo Roof system

−Coping−Drainage

Page 15: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 3: Structure Checklist

• 15 Questions/statements pertaining to:o Geometry of structure (plan and elevation)o Design loadso Structural system

−Redundancies−Hybrid−Design era

o Connectionso Foundationo Construction type/materials

Page 16: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 4: Utilities Checklist• 14 Questions/statements pertaining to:

o All utility systems within the facility−Telecommunications−Power−Gas−Water (potable, wastewater, roof drain lines)−Fire safety systems−Computing systems−Building controls−Security systems

Page 17: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 5: Contents Checklist

• 13 Questions/statements pertaining to:o Occupantso Corridors, stairwells, exit routeso Furnitureo Interior (non-structural) partition walls, flooring,

doors, windowso Specialized equipmento Light fixtureso Elevators

Page 18: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 6: PI Input Values

Page 19: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 7: Final Output• Presents normalized risk index matrices

o First set presents normalized relative to facility−As Inspected (AI) Matrix−Mitigation Measures (MM) Matrix—calculates new

risk index with updated inputs that assume suggested mitigation measures are implemented

o Second set presents normalized relative to campus

−AI Matrix−MM Matrix

o Third set presents normalized relative to sample space

−AI Matrix−MM Matrix

Page 20: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 8: Summary of EV Inputs

• Lists all 92 questions/statements with respective ratings in one place for ease of referenceo 4 page printouto For review only; no modifications can/need to be

made

Page 21: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 9: Insert Updated EV Values

• Identical layout to Sheet 8o Modify ratings in this sheet to reflect the lower

vulnerability based on suggested mitigation measures

o Anytime a rating is modified, an (*) appears to the right of the updated rating

o This input is used to produce the “MM” matrix

Page 22: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 10: Output Printout (AI)

• Displays the raw output from the input ratingso Contents of this sheet have minimal applicable

useo Summarizes the hazard informationo Presents an exposure and vulnerability matrixo Presents a raw risk index matrix

−Range 0-1 where 0 is lowest risk; 1 is highest risko All of which is used to produce normalized risk

index matrices• Error message at the bottom of sheet is only

item needed from this sheeto Error count tallies the number of times a rating

outside range limits is input in sheets 1-5

Page 23: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Sheet 11: Output Printout (MM)

• Identical in layout and function to Sheet 10o Uses data from Sheet 9 (Updated EV Inputs) to

produce a risk index matrix reflecting lower risk (assuming mitigation measures are implemented)

o This data is used to produce the “MM” set of matrices

• Error message at the bottom of sheet is only item needed from this sheeto Error count tallies the number of times a rating

outside range limits is input in Sheet 9

Page 24: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

IMPORTANT – Sheet 11:Output Printout (AI)

• Cell F54 controls campus normalization o Set this cell equal to the maximum value within

the cell range B43:S47−Can be done with a master spreadsheet that links

to other facilities on campus• Cell F55 controls sample space

normalizationo Set this cell equal to the maximum value within

the sample space of raw risk index matrices−If the sample space is the campus, use the same

value that was used in F54

Page 25: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Results• Output can be combined with UFIS results

o Composite of objective importance and risk scores

• Output can be combined with any measure of facility value/importanceo Facilitates a better understanding of the results

−Incorporates a loss measure−Combines risk and importance into one result

• Must use raw risk scoreso Raw risk scores present the most accurate resulto Normalized risk scores do not have enough

resolution to provide clear delineation of results

Page 26: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Exercise• Facility “A” has a raw risk score of 0.020

o Insured value of $4.8 milliono UFIS score of 0.680

• Facility “B” has a raw risk score of 0.045o Insured value of $3.5 milliono UFIS score of 0.580

• Which facility should take priority in receiving mitigation measures?

Page 27: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Exercise• Facility “A”

o 0.020 x $4.8 million = $0.096 million (Insured value)o 0.020 x 0.680 = .0136

(UFIS results)

• Facility “B”o 0.045 x $3.5 million = $0.158 million (Insured value)o 0.045 x 0.580 = 0.0261

(UFIS results)

• Facility “B” takes priority for mitigation measures based on composite score

Page 28: UFRAS University Facilities Risk Assessment Spreadsheet 25 April 2012

www.zapatainc.com

Questions/ContactBrian Zapata6302 Fairview Road, Suite 600Charlotte, NC 28210(704) 358-8240 - Phone(704) 358-8342 - Fax(888) [email protected]://www.zapatainc.com