udot i-15 the point design-build project using an ‘independent quality firm’ to verify...
TRANSCRIPT
UDOT I-15 The Point Design-Build ProjectUsing an ‘Independent Quality Firm’ to Verify Conformance to
Contract Requirements
July 20, 2015
1
Tim Rose, PE – Utah Department of TransportationDavid Brown, PE – ParsonsMatt Wildauer, PE - Parsons
Introduction
• Project Overview• Measuring Quality and Approach to Quality Management• IQF Methodology and Reporting• Conclusions/Take-Away• Questions
2
Project Overview
3
Project scope is to reconstruct I-15 from SR-92 to 12300 South
4
Construction will be phased through two seasons
5
Complex phasing allows four lanes to be maintained in each direction
6
Phase 2 : April – June 2015 Phase 3 : June – September 2015
New pavement will be utilized for Phase 4 MOT
7Phase 4: September – November 2015
Mainline construction will extend through 2015 and 2016
8
• Independent Quality Firm is involved in the project from selection through closeout.
Goals and objectives provide focus to the project
9
Goals and objectives provide focus to the project
10
Goals and objectives provide focus to the project
11
Project Highlights
12
East Jordan Canal box culvert installation Segment 3 near Lehi
Project Highlights
13
Grading in Segment 3 Retaining wall along Pony Express Rd
Project Highlights
14
Placement of lean concrete pavement Girder setting at 14600 South bridge
Measuring Quality and Approach to Quality Management
15
Performance measurement roles depend on delivery method
16
Traditional - Project Delivery - Alternative Changing Roles & Responsibilities
DOT Maintenance
Fix the pot-hole quickly.
Ensure Quality
Design-Bid-Build
Inspect and test materials
Verify Quality
Design-Build
Design Builder follows QMP
Validate Quality
P3
Oversight of Developer
Due Diligence
Various projects use different measures of quality
• Set a high expectation – “We want a ‘high quality’ project.”• Inspect everything until it is right.• “If all the material tests pass then the work is good.”
17
To measure QUALITY – we need DATA
Quality measurement on I-15 The Point project is based on performance and conformance rates
18
# of CONFORMING observations
TOTAL # of observationsPerformance Rate =
PERFORMANCE rate CONFORMANCE rate
Conformance Rate MUST 100%
Requirements management uses verification to determine performance
• A way to measure PERFORMANCE• All Work is defined by distinct requirements.• Isolate KEY requirements – in a searchable database.• Apply attributes to requirements (risk, owner, phase, performance).• Verify requirements are fulfilled.• Update requirements in database as scope evolves.
19
The Project Management
‘Trinity’
Requirements management is a component of overall performance measurement
20
SCOPETechnical
Requirements
BUDGETDollars
SCHEDULETime
PerformanceMeasurement
Requirements management is a component of performance measurement
21
SCHEDULEManagement
Time Remaining 0%100%Th
e W
ork
BUDGETManagement
Dollars Remaining 0%100%
The
Wor
k
REQUIREMENTManagement
Requirements Remaining 0%100%
The
Wor
k
Data allows performance to be measured and reported
22
Observed Performance Rate ~97%
Acceptance Data Points
~ 1700
Similar project
in Ohio
IQF Methodology and Reporting
23
A customized database provides an efficient platform for verifying requirements
• At the beginning of the project, team will extract requirements from Contract documents, standards, and special provisions.
• This provides an organized, customizable, searchable requirement database for use by the project team.
• Requirements are updated as scope evolves.
24
Contract requirements are imported to the database at the beginning of the project
25
Requirement Description
Each applicable requirement is verified based on objective evidence
• Verifications of the design to determine conformance with Contract requirements are completed at each submittal. Requirements populated using checklists.
• Verifier provides objective evidence and location for observations on each requirement along with a result code.
26
Objective evidence is provided for each requirement verified.
Each observation is assigned a result – “C” or “RD”
Objective evidence for construction verifications are based on inspection and testing
• Construction verifications are based on inspection and testing – hard data from the field.
• Test results are referenced in objective evidence for verification.• Results that do not pass are marked as RD or NCR.
27Result Code
IQF monthly report measures and tracks project performance
• The IQF monthly report provides measurement and tracking of the design-build team’s performance on the project.
• The report presents results of verifications and tracks trends throughout the project.
• IQF staff work with the Department to capture results of Department audits in the report.
• Material testing results are gathered and summarized each month.
28
Design Discipline Latest Issue Date
RD's Opened During Reporting Period
Open RD's Carried Forward
RD's Closed During Reporting Period
RD's Remaining Open
ATMS, Lighting, Traffic Signals 5/29/2015 4 11 2 13
Drainage 5/7/2015 2 3 0 5MOT 5/14/2015 1 0 1 0
Roadway 5/20/2015 9 0 3 6Structures 5/30/2015 4 13 3 14
Utilities 5/27/2015 8 3 0 11Walls 5/20/2015 5 0 0 5TOTAL 33 30 9 54
Design performance is measured continuously and reported monthly
• Monthly design performance has ranged from 75%-89% conforming observations, with an average of 85% conforming observations.
• Conformance rate must equal 100% prior to RFC.
29
Design Performance
Jun-15 Project Average
0%
20%
40%
60%
80%
100%
86% 85%
Design Performance
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15Jul-1
5
Aug-15
Sep-150
200
400
600
800
1000
1200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
440
242 231
556
803
531
309 329 277
563
112
48 79
76
150
84
60 4333
891
22
80%83%
75%
88%84% 86%
83%88% 89% 86%
Monthly Design Performance Activity
Conforming Observations Requirement Deficiencies (Issued)Nonconformance (Issued) Monthly Performance Rate
Requ
irem
ents
Ver
ified Perform
ance Rate
Construction performance is measured and reported in a similar manner to design
• Construction performance rate is near 98% conforming.• Higher performance rate is due to larger sample size and backup of
material testing data for verifications.
30
ConstructionPerformance
Jun-15 Project Average0%
20%
40%
60%
80%
100%98% 98%
ConstructionPerformance
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15Jul-1
5
Aug-15
Sep-150
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 640 35
447 534 926 953 1107 17801
8
17 12
16
19
1
24
7 84
12
100%95%
100% 98% 97% 98% 98% 98%
Monthly Construction Performance Activity
Conforming Observations Requirement Deficiencies (Issued)
Nonconformance (Issued) Monthly Performance Rate
Requ
irem
ents
Ver
ified
Performance Rate
Observed performance rates are similar between projects
31
Conclusion/Take-Away
• A requirements based quality program provides a comprehensive approach to quality. The process provides an opportunity to measure performance, not just progress.
• This process collects data – from design and construction – and provides objective evidence of conformance to requirements.
• Success depends on having good people with a focus on meeting requirements the first time, allowing projects to be completed with greater speed and efficiency, and saving money.
32
Questions
33