Udine - April 19th 2004 1
Data Check for MAGIC
Raquel de los ReyesUniversidad Complutense de
Madrid(U.C.M.)
Udine - April 19th 2004 2
Contents The program Central control data check DAQ data check Conclusions
Udine - April 19th 2004 3
Program
Group of scripts and Root macros to check the subsystems and the data taken at the end of each night shift.
Two scripts: CCDataChecking & DAQDataChecking
Two macros: CCDataCheck.C & DAQDataCheck.C
Thanks to F. Goebel and R. Wagner
http://www.magic.iac.es/operations/datacheck
Udine - April 19th 2004 4
Central control data checkDrive systemGeneral camera statusCamera HVCamera DCCamera LVCooling systemTrigger systemTrigger macro cellsWeather station
Udine - April 19th 2004 5
Drive system(CC_2004_02_15.ps)
CrabNebula
OffMrk421-1Mrk42
1
OffCrab4
21:58 & 03:22 :Cosy crashed
no reported
Thanks to T. Bretz and D. Dorner
Udine - April 19th 2004 6
General camera status (CC_2004_02_15.ps)
21:35: Guagua crashed
Change source: OffCrab4 – Mrk421
Move to CrabNebula
End shift
Udine - April 19th 2004 7
Camera High Voltages (HV)
(CC_2004_02_15.ps)
Failure of master voltage regulator boards and the six adc boards
monitoring HV y DC in sectors 3-5
no reported
21:35: Guagua crashed
21:35: Guagua crashed
Thanks to J.Flix
Udine - April 19th 2004 8
Camera Direct Currents (DC)
(CC_2004_02_15.ps)
21:35: Guagua crashed
no reported
Udine - April 19th 2004 9
Camera Low Voltages (LV)(CC_2004_02_15.ps)
21:35: Guagua crashed
no reported
Udine - April 19th 2004 11
Trigger system(CC_2004_02_15.ps)
21:26: ZetaTauri
Pedestal runs(PED)/calibration runs(L1_5NN:L2_DEFAULT)
Thanks to R. Paoletti and A. Stamerra
Calibration runs
Firing macrocells 2 and 7
Low threshold pixels 3, 9 and 21
Udine - April 19th 2004 12
Trigger macro cells(CC_2004_02_15.ps)
UMa51 in pixels 3, 9 and 21: Macrocells 2 and 7
Fire not reported:
Pixels(HW) 88, 89, 123, 124, 125, 165, 166
Udine - April 19th 2004 14
DAQ data check
PedestalCalibration
Conversion factorDefect pixelsFitted chargesReduced sigma per chargeAbsolute arrival times
Timing
Udine - April 19th 2004 16
Calibration (I): Conversion factor
(IFAE sample C (on): 15/02 - 17031-17123)
Thanks to J. Cortina and M. Gaug
Udine - April 19th 2004 18
Calibration (III):Fitted charges
(IFAE sample C (on): 15/02 - 17031-17123)
Udine - April 19th 2004 19
Calibration (IV):Reduced sigma per charge
(IFAE sample C (on): 15/02 - 17031-17123)
Udine - April 19th 2004 20
Calibration (V):Absolute arrival times
(IFAE sample C (on): 15/02 - 17031-17123)
Udine - April 19th 2004 22
ConclusionsThe CC check plots will allow us to take a look to night conditions and hardware problems.The DAQ check plots will make a preliminar analysis of night data.In the future these scripts could interact with the DataBase to collect the hardware problems.STATUS:
CC data check runningDAQ data check in tests.