ucg eskom’s experience and future projects · 2016-05-13 · ucg – eskom’s experience and...
TRANSCRIPT
UCG – Eskom’s Experience and Future Projects
Shaun Pershad
11 May 2016
FFF Workshop to present Updates on the Developments in South Africa – Is there Gas?
Content
1. Eskom’s UCG Strategic Drivers
2. Current Status of Eskom UCG Pilot Project Development
3. Risks for UCG Development
4. Summary of Eskom UCG Project Mandate
2
Disclaimer
This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or
invitation of any offer to buy or subscribe for or underwrite or otherwise acquire, securities of Eskom Holdings Limited
(“Eskom”), any holding company or any of its subsidiaries in any jurisdiction or any other person, nor an inducement to
enter into any investment activity. No part of this presentation, nor the fact of its distribution, should form the basis of, or
be relied on in connection with, any contract or commitment or investment decision whatsoever. This presentation does
not constitute a recommendation regarding any securities of Eskom or any other person or technology.
Certain statements in this presentation regarding Eskom’s business operations may constitute “forward looking
statements.” All statements other than statements of historical fact included in this presentation, including, without
limitation, those regarding the financial position, business strategy, management plans and objectives for future
operations of Eskom are forward looking statements.
Forward-looking statements are not intended to be a guarantee of future results, but instead constitute Eskom’s current
expectations based on reasonable assumptions. Forecasted financial information is based on certain material
assumptions. These assumptions include, but are not limited to continued normal levels of operating performance and
electricity demand in the Distribution and Transmission divisions and operational performance in the Generation and
Primary Energy divisions consistent with historical levels, and incremental capacity additions through our Group Capital
division at investment levels and rates of return consistent with prior experience, as well as achievements of planned
productivity improvements throughout our business activities.
Actual results could differ materially from those projected in our forward-looking statements due to risks, uncertainties and
other factors. Eskom neither intends to nor assumes any obligation to update or revise any forward-looking statements,
whether as a result of new information, future events or otherwise.
In preparation of this document we used certain publicly available data. While the sources we used are generally
regarded as reliable we did not verify their content. Eskom does not accept any responsibility for using any such
information.
3
1. Eskom’s UCG Strategic Drivers
Why is Eskom, an electricity utility, working on a mining technology ?
• SA mining houses were approached before Eskom started our UCG project, but they declined to participate. PetroSA and Sasol have displayed collaboration interest.
• Coal is South Africa’s largest fuel resource, but three quarters of it is unminable with conventional mining technology (due to economics, poor quality, geology etc.). Eskom has proven that UCG can unlock this potential.
• UCG offers an indigenous fuel that is shielded from international commodity prices.
• Eskom is leading UCG development, so can be an energy price-setter.
• The availability of an alternative energy resource for co-firing in Eskom’s stations provides future primary energy options.
2016-05-11 4
UCG Strategic Drivers Research Achievements
• Independent, long-term fuel source Proven at Concept level
• Total Environmental footprint (including Carbon) In progress
• Low cost energy source In progress
• Mining efficiency Proven at Pilot level
• Security of supply – baseload or mid-merit option
In progress
• Technology transfer In progress
• Mining safety Proven at Pilot level
• Broader geographic distribution for new
generating capacity Proven at Concept level
• Job creation in rural locations Proven at Pilot level
• Valuable by-products Proven at Pilot level
• Ash left underground Proven at Pilot level
1. Eskom’s UCG Strategic Drivers
5
1. Opportunities for UCG in South Africa
2. Current Status of Eskom UCG Pilot Project Development
3. Key Risks to UCG Project Development
2016-05-11 8
Risk Description Root Cause of Risk Consequences Mitigations/
Controls
Environmental
Contamination
UCG industrial process leaks and
contaminates surrounding
environment.
• Gasifier
• Wells
• Surface infrastructure (will not go
further on this one as it is
duplicated all over the world –
nothing new here)
-Cannot operate and business terminates
-Prosecution, penalties
-Non existent social license, permitting &
funding to exist and operate non existent.
……………..
Project
Economics
• Project costs
• Market demand
• Competing energy prices
Permitting &
Licensing
-Limited UCG Knowledge by
regulators to grant licenses.
-Unforeseen/additional studies
required by authorities.
-Public appeals
-Delays by the authorities
-Negative international
environmental incidents from UCG
operations
-
• Technology selection*
• Site selection*
• Site characterization*
• Piloting*
• Specialist studies for EIA
• Design
• Operational Controls
• Monitoring*
• Decommissioning
• Rehabilitation & Containment * Described in more detail
= No
Business
Case
= No
Project !!
• Design and integration
• Stakeholder engagement
• Published regulations
• Controlled Timelines
3. Mitigation/Control: Technology Selection IS KEY !!!!
2016-05-11 9
Activities:
• End-user needs analysis
• Technology match analysis
• Technology selection
• Technology provider capability assessment
• Engage UCG users worldwide
• Visit UCG reference plants
• Evaluate technology provider credentials
and guarantees
• Select and appoint technology provider
• Compile pre-feasibility level study with
technology provider
• Motivate project
Objectives:
• Match needs to technology
• Identify technology, and providers thereof
• Rank technology providers
• Appoint technology provider
• Motivate project
Outputs:
• Technology selection
• Technology provider tender evaluation matrix
• Commercial process
• Tender evaluation
• Technology provider appointment
• Technology provider review of project, and pre-feasibility report
• Stakeholder approval of project
•
3. De-risking technology development
2016-05-11 10
From : AACE 18R-97 International Costing Practice
Applies to
cost,
performance
guarantees,
regulatory
compliance
etc.
Screening/Conceptual
Feasibility/Preliminary
Budget, Authorisation
Control, bid\tender
Check or bid\tender
FS
U
UC
G
US
A/E
U U
CG
Austr
ali
an U
CG
?
?
?
?
?
?
Eskom
UC
G
DESCRIPTION of UCG - known for 100 years.....as opposed to
QUANTIFICATION of UCG (through actual demonstration) – still to be largely done
3. Description of UCG
2016-05-11 11
3. Quantification of UCG
2016-05-11 12
Carefully consider how
each of these criteria
affect your project.
3. Quantification of UCG – Confidence…….Beyond Costs ……..
13
3. Mitigation/Controls : How to set up for SUCCESS !
2016-05-11
Science:
• The UCG technology basic science derived from prior UCG operations must be combined with the site-specific topography, geotechnics, surface features and infrastructure, geology, hydrogeology, rock mechanics, drilling/well completion etc. in order to confirm a site.
• The site must be characterised for UCG suitability with drilling, well completion, water & air injection tests that evaluate the likely impact and success of UCG.
• Specialist studies are completed for the EIA
Wrong site =
HIGH
ENVIRONMENTAL
RISK
Engineering:
• Technology components are selected/designed based on the science and regulatory requirements
• Piloting
Legal & Regulatory
Operations & closure:
Successful operations, monitoring, decommissioning & rehabilitation = multi-disciplinary, skilled team
Incorrect
Engineering =
HIGH
ENVIRONMENTAL
RISK
Poor operation
& closure =
HIGH
ENVIRONMENTAL
RISK
See later
Class 5
Class 4
Class 3
Narrow the
Uncertainty !!
Commercial Process Class 2
Commercial Process Class 1
3. Mitigation/Control : Site Selection
2016-05-11 15
Activities:
• Shortlist potential locations and resources
• Evaluate available and required regulatory
and stakeholder approvals on all locations
• Evaluate available and required scientific
information on all locations
• Quantify resources as per SAMREC code
• Analyse end-user needs
• EIA & Public Participation.
• Evaluate potential commercial application
performance and cost
Objectives:
• Confirm suitable site(s)
• Confirm UCG technology potential at site(s)
• Confirm stakeholders
• Confirm needs analysis
• Confirm regulatory requirements
• Confirm gaps in scientific knowledge for
the site(s)
Outputs:
• Preferred location selection
• Potential sites at preferred location
• Regulatory and social approvals required
• Specialist studies required
• Gap analysis
• Fatal flaw analysis
• Risk assessment & mitigation strategy
• Technical performance model
• Financial model
3. Mitigation/Control : Site Characterisation
2016-05-11 16
Activities:
• Regulatory and stakeholder approvals
• Prospect to SAMREC code for measured
coal resources
• Evaluate and optimize drilling methods
• Analyse and test core samples, eg.
Chemical analyses, bench scale
gasification etc.
• Conduct permeability & air injection tests
• Bury instrumentation in & above resource
• Model coal resource attributes
• Design pilot plant to prove technology
• Evaluate commercial equipment selection
Objectives:
• All regulatory and social approvals in place
• Baseline pre-UCG site conditions for EIA
• Specialist studies for EIA
• Build comprehensive databases and
models of resource background science
• Model concept-level (AACE Class 5) UCG
performance, longevity and economics of
commercial UCG application
• Risk assessment & mitigation strategy
• Confirm site suitability !!
Outputs:
• Regulatory approvals
• Risk assessment & mitigation strategy matrix
• AACE Class 5 UCG costs, timescales and performance for commercial UCG application (incl.
mining plan, power generation costs etc.)
• AACE Class 3 UCG costs and timescales for UCG pilot plant
• Approved business case for pilot plant investment
• UCG pilot plant test plan
• Hydrogeological, geological, rock mechanic and UCG models
• Financial model
• Power plant performance model (equipment selection, economics, emissions etc.)
3. Mitigation/Control : Piloting
2016-05-11 17
Activities:
• Site establishment
• Injection and production well completions
• Gas pipeline, treatment plants and flare
design and construction
• Regulatory and stakeholder approvals
• Prospecting continued to SAMREC code
• Initiate and operate UCG in a 2-dimensional
gasifier cavity
• Measurement and monitoring
• Geology, hydrogeology, rock mechanic and
UCG Process modelling
• Shutdown, gasifier sampling & rehab
Objectives:
• Qualify that the technology works, and
quantify key parameters
• Inform regulators and stakeholders
• Secure enough information for commercial
regulatory applications
• Build comprehensive databases and
models
• Risk assessment & mitigation strategy
• Staffing requirements & recruitment plan
• Lodge regulatory applications
Outputs:
• Pilot plant performance
• Specialist studies, including Environmental Management Plan
• AACE Class 3 UCG costs, timescales and performance for commercial UCG application (incl.
mining plan, power generation costs etc.)
• Gap analysis
• Fatal flaw analysis
• Risk assessment & mitigation strategy
• Technical performance model
• Financial model
• Regulatory reporting
• Regulatory applications for the next phase
3. Mitigation/Control : Monitoring
2016-05-11 18
Activities:
• Baseline environmental sampling PRIOR to
any UCG activity.
• Set up instrumentation on the site, above
and below ground
• Model process, hydrogeology etc.
• Routine monitoring – 3 zones (see
following diagram)
• Long term monitoring post closure
Objectives:
• Monitor and compare to baseline
• Alert exceedances
• Action correction or remediation
Outputs:
• Monitoring plan
• Exceedance response plan
• Remediation plan
• Rehabilitation plan
• Routine reports to regulator and management
19
3. UCG Water Monitoring Strategy - Zones
Production zone • Equivalent to
underground mine
workings or open
pit – “process
water”
• Operational area
• Monitoring purpose:
to observe “process
water” against
operations
summary
Process Control
zone • Safety zone around
mine workings or open
pit
• Buffer zone for early
warning of potential
problems
• Monitoring purpose:
monitor significant
changes in early
warning indicators
Compliance zone • Equivalent to external
environment of
conventional mine
• Area expected to be
unaffected by UCG
operation
• Compliance required
against agreed WUL
quality standards
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 20
Hydrogeology
Geology
Rock Mechanics
Drilling
&
Well Completion
Disciplines Involved
in Design of
Underground
Activities Only :
UCG
Engineer
Geology
Rock Mechanics
Drilling
&
Well Completion
UCG
Engineer
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 21
Hydrogeology
Disciplines Involved
in Design of
Underground
Activities Only :
Responsible for : • Part of multi-
disciplinary team
• Reviewing
background
hydrogeology data
• Commissioning test
work
• Modelling
• Recommending
hydrogeology control
philosophy
• Designing
underground aquifer
monitoring system
• Monitoring (incl. post
UCG)
• Participating in
remediation activities
• Regulatory
applications &
reporting
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 22
Hydrogeology
Rock Mechanics
Drilling
&
Well Completion
Disciplines Involved
in Design of
Underground
Activities Only :
UCG
Engineer
Responsible for : • Part of multi-
disciplinary team
• Reviewing
background
geology data
• Prospecting
• Modelling
• Recommending
mining philosophy
• Pre-production
prospecting
• Participating in
remediation
activities
• Regulatory
applications &
reporting
Geology
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 23
Hydrogeology
Geology
Rock Mechanics
Drilling
&
Well Completion
Disciplines Involved
in Design of
Underground
Activities Only :
UCG
Engineer
Responsible for : • Part of multi-
disciplinary team
• Reviewing
background RM
data
• Prospecting
participation
• Modelling
• Site subsidence
monitoring
• Recommending
subsidence
management
philosophy
• Monitoring (incl.
post UCG)
• Participating in
remediation
activities
• Regulatory
applications &
reporting
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 24
Hydrogeology
Geology
Rock Mechanics
Drilling
&
Well Completion
Disciplines Involved
in Design of
Underground
Activities Only :
UCG
Engineer
Responsible for : • Part of multi-
disciplinary team
• Reviewing
background
drilling data
• Designing drilling
& well
completion
philosophy
• Controlling all
drilling activities
• Participating in
remediation
activities
• Reporting
3. Mitigation/Control: UCG Discipline Roles & responsibilities
2016-05-11 25
Hydrogeology
Geology
Rock Mechanics
Drilling
&
Well Completion
Disciplines Involved
in Design of
Underground
Activities Only :
UCG
Engineer
Responsible for : • Integrating all
activities
• Leading multi-
disciplinary team
• Reviewing all
background data
• Prospecting
participation
• Modelling
• Mining
philosophy &
plan
• Monitoring (incl.
post UCG)
• Leading
remediation
activities
• Regulatory
applications &
reporting
3. Mitigation/Control: Example of UCG
Disciplines Integration in Hydrogeological Model
3. Mitigation/Control: Project Economics
2016-05-11 27
Carefully consider how
each of these criteria
affect your project.
Quantification as opposed to Description
3. Mitigation/Control: Project Economics
• Capex : Design : Mine including initial wells, piping (gas and oxidant), surface infrastructure (gas and liquid treatment), end product (power generation, fuels, chemicals)
• Opex : Replenishment Well drilling & completion, piping, manpower, input energy, royalties/taxes, shutdown, decommissioning, rehabilitation.
• Permitting & Licensing : Timelines & currently unknown specific design requirements.
• Products : Raw gas, Electricity Fuels/Hydrocarbon/chemical byproducts
• Target price benchmarks are freely available to determine business case viability.
• Benchmarks and thus business case are thus “quantified” in specific detail and NOT “described” generally. Margin for error is very small in a competitive energy pricing business.
2016-05-11 28
Costs Income
Design & Integration are thus
critical !
3. Mitigation/Control: Project Economics Risk - Design & Integration
2016-05-11 29
Activities –
Class 3
• Engineering is 10-40% complete for
established technologies – UCG being “FOAK
“will require more activity.
• PFD’s, UFD’s, Plot Plan, Developed Layouts,
Utility equipment lists
Class 2
• Engineering 30% to 75% complete.
• High degree of deterministic estimating
methods
• In addition to above Class 3, Heat & material
balances, final plot plan, final layout drawings,
complete engineered process and utility
equipment lists, single line diagrams for
electrical, electrical equipment and motor
schedules, vendor quotations, detailed project
execution plans, work force plans.
• Prepared in great detail, involving tens of
thousands of unit cost line items
Objectives –
Class 3
• Support full project funding requests.
• Class 3 is often the last estimate required and
could very well form the only basis for
cost/schedule control – this is however for
established mature technologies – care to be
taken with First of a Kind (FOAK) projects.
Need for greater depth.
• Referred to as : Budget, Scope, Sanction,
Concept Study, Basic Engineering phase
estimate. Target estimate
Class 2
• Used by contractors to establish contract value
and detailed contractor baseline (and update
the owner control baseline)
• Referred to as Detailed control, forced detail,
execution phase, Master control, Engineering,
Bid, Tender, Change order estimate
3. Mitigation/Control: Project Economics Risk - Design & Integration
2016-05-11 30
Outputs:
• Piping & instrumentation diagrams issued for design.
• Class 3 = 10-40% of full project definition. Class 2 = 30-75%.
• Ranges could exceed those shown if there are unusual risks !
3. Mitigation/Control: Project Economics Risk - Design & Integration
31
?
Detailed Cross Comparison of Deliverables Maturity Level
3. Mitigation/Control: Project Economics Risk - Design & Integration
32
?
3. Mitigation/Control: Project Economics Risk - Design & Integration
• The UCG mine is ultimately about fuel production, but even more so about the optimum gas specification. Operational Trade-offs possible, e.g. CO2 emissions vs maximum mining efficiency. Gas spec is site, technology and process specific/unique. Piloting is critical
• Gas specification: What is in the gas ? Specifications, tolerances and margins are key. Detailed down to trace elements for Class 3/2 work. If not, assumptions and tolerance stack
up will occur.
• Business case will depend on gas specification certainty. The class 3/2 technical work must be the basis to reduce risk. This includes the gasifier upon which the surface infrastructure is dependant on.
33
Raw gas specification
dependencies
Risk Background: Permitting/Regulatory Processes
2016-05-11 34
Research/Science
-Quantification
Permit/Regulations
Quantification
The dilemma…….. Piloting follows full/normal permitting process !
Research/Science
Quantification
2001 t
o 2
016 P
roje
ct
tim
eli
ne
Sig
nif
ican
t ch
an
ges i
n P
erm
itti
ng
&
Lic
en
sin
g –
Mu
ch
mo
re q
uan
tifi
cati
on
deta
il n
ow
Req
uir
ed
!
3. Mitigation/Control: Permitting & Licensing
2016-05-11 35
2014 – Scoping & Environmental Impact Reporting Process (S&EIR)
3. Mitigation/Control: Permitting & Licensing
2016-05-11 36
3. Mitigation/Control: Permitting & Licensing
2016-05-11 37
3. Mitigation/Control: Permitting & Licensing -Water Use Licensing (IWULA)
2016-05-11 38
• A UCG Site will typically trigger the following
sections for an IWULA Section 21 (e) – Engaging in a Controlled Activity for the UCG process
Triggers in terms of the Traditional Water uses:
S21(a) – Abstraction of Water from Groundwater during UCG Process
S21(b) – Water Storage Dam
S21(c) – Impeding or Diverting the flow of water in a watercourse for
the construction of roads and bridges over watercourses
S21(g) – Disposing of waste that may impact on a water resource.
S21(h) – Disposing of waste from a power generation process for re-
injection of treated process water
S21(i) – Altering the bed, banks, course or characteristics of a
watercourse for the construction of roads and bridges over
watercourses
S21(j) – Removing and disposing of groundwater from the UCG
process
• UCG Declared a controlled activity in October 2015.
• Awaiting :
Draft control guidelines for public comment.
Final control guidelines.
Application format.
WU
L C
loc
k f
or
UC
G a
pp
licati
on
s n
ot
yet
ab
le t
o
sta
rt t
ickin
g t
o 3
00 d
ays.
Until the above process is finalised, the 300 days
(excl appeal period of 90 days) cannot start
ticking and no project WUL can be granted !
3. Key Insights from IBM FOAK Research Program
• Partnership is essential !
• Process of partnering in any context - be it business, community, government, or just plain ordinary people is never easy to define, much less document. Partnering is more art than science, more passion than intellect, and, ideally, more oriented toward giving than getting.
• Needs for partnering must be clear and complementary.
• Researchers are the creative catalysts of FOAK: no researchers = no projects.
• Must have the ability to imagine how technologies might be used & to consolidate ideas, capabilities, resources
• Successful innovation depends on having the right people - those with a commitment to innovation and the skills to help move an idea into the marketplace.
• While not every skill may be available, basic resources and capabilities should be in place before an innovation project begins.
• Because innovation may be difficult to explain, may payoff only in the long term, and may carry higher risk, setting expectations with partners is a critical success factor.
• FOAK contracts uses nonstandard T&Cs. Prolonged contracting process not best for FOAK & Partners who cannot work with non-standard T&C’s are not desired.
• FOAK projects suffered from reprioritizing human resources not long after the projects began.
• Project must be aligned with real business value.
2016-05-11 39
• IBM Research program since 1996
• Only allocated part funding from
internal budget.
• Funding model still in place today
(2010)
• 200 projects completed
• 15 projects completed from 20-25
approved for funding annually
• 70% successful asset transfer for
reuse from projects completed.
Eskom’s Intent : to develop an independent, long term, lower cost, market
immune, primary fuel source for South Africa
How ?
Why?
Whom?
Where?
When?
Majuba
Eskom
2018
Majuba or Elsewhere
Eskom+ Partner/s
2018
• Demonstrate safe environmental operation
& shutdown/decomissioning practice &
compliance
• Quantify long term environmental &
geological impacts
• Provides key information for permit and
licensing processes
• Allows for future growth of technology &
Majuba coalfield.
• Integrate and share resources to leverage
existing assets and knowledge
• Provide an execution structure that
addresses previous & current piloting
difficulties
• Deliver the original objectives & benefits
4. Summary of Eskom UCG Project
Thank You
2016-05-11 41