typical horizontal - chicago international … d - construction...standard. b tia-569...
TRANSCRIPT
PART 1 GENERAL
1.1. PROJECT DESCRIPTION;
A. PROVIDE AND INSTALL A COMPLETE
STRUCTURED CABLING SYSTEM (SCS) FOR CICS
WRIGHTWOOD ELEMENTARY SCHOOL, 8130
SOUTH CALIFORNIA AVE. CHICAGO IL, 60652. THE
CABLING SYSTEM SHALL INCLUDE, BUT NOT BE
LIMITED TO HORIZONTAL AND BACKBONE CABLE
DISTRIBUTION, CABLE SUPPORT, TERMINATION
AND LABELING COMPONENTS. AS WELL AS THE
BUILD OUT OF TELECOMMUNICATIONS
EQUIPMENT ROOM WITH WIRE MANAGEMENT
AND CONVEYANCE COMPONENTS.
B. THE CONTRACTOR SHALL TRACE, TEST AND
LABEL ANY CABLES THAT ARE NOT PROPERLY
LABELED.
C. THE PRINCIPAL BID FOR THIS PROJECT SHALL BE
BASED ON A CATEGORY 5E AND/OR CATEGORY 6
STRUCTURED CABLING SYSTEM MANUFACTURED
BY:
MATCH EXISTING CABLE AND TERMINATION
MANUFACTURER.
D. THE PRINCIPAL BID FOR THIS PROJECT SHALL BE
BASED ON HARDWARE COMPONENTS
MANUFACTURED BY:
MATCH EXISTING CABLE AND TERMINATION
MANUFACTURER.
E. REFERENCED STANDARDS AND CODES
1. AUTHORITY HAVING JURISDICTION.
2. NFPA 70 "NATIONAL ELECTRIC CODE" (NEC); TO
INCLUDE ALL LOCAL AMENDMENTS TO THE
NEC
3. CHICAGO ELECTRIC CODE
4. ALL LOCAL AND STATE BUILDING CODES.
5. THE LATEST REVISION OF ALL AMERICAN
NATIONAL STANDARDS INSTITUTE /
TELECOMMUNICATIONS INDUSTRY
ASSOCIATION STANDARDS (ANSI/TIA)
INCLUDING ASSOCIATED ADDENDA.
6. ALL CURRENT REVISIONS OF AMERICAN
NATIONAL STANDARDS INSTITUTE /
TELECOMMUNICATIONS INDUSTRY
ASSOCIATION / ELECTRONIC INDUSTRIES
ALLIANCE - ANSI/TIA/EIA STANDARDS AND
BULLETINS. TO INCLUDE:
a ANSI/TIA-568- COMMERCIAL BUILDING
TELECOMMUNICATIONS CABLING
STANDARD.
b TIA-569 TELECOMMUNICATIONS
PATHWAYS AND SPACES.
c ANSI/TIA-606 - ADMINISTRATION
STANDARD FOR TELECOMMUNICATIONS
INFRASTRUCTURE.
d ANSI/TIA-607 - GENERIC
TELECOMMUNICATIONS BONDING AND
GROUNDING (EARTHING) FOR
CUSTOMER PREMISES.
e ANSI/TIA-1152 - REQUIREMENTS FOR
FIELD TEST INSTRUMENTS AND
MEASUREMENTS FOR BALANCED
TWISTED-PAIR CABLING.
f TIA TSB-162 - TELECOMMUNICATIONS
CABLING GUIDELINES FOR WIRELESS
ACCESS POINTS.
g TIA TSB-184 - GUIDELINES FOR
SUPPORTING POWER DELIVERY OVER
BALANCED TWISTED-PAIR CABLING
h TIA TSB-190 - GUIDELINES ON SHARED
PATHWAYS AND SHARED SHEATHS
7. ANSI/NECA/BICSI 568-2006 - STANDARD FOR
INSTALLING COMMERCIAL BUILDING
TELECOMMUNICATIONS CABLING.
8. NECA/BICSI 607-2011 - STANDARD FOR
TELECOMMUNICATIONS BONDING AND
GROUNDING PLANNING AND INSTALLATION
METHODS FOR COMMERCIAL BUILDINGS
9. NATIONAL ELECTRICAL MANUFACTURERS
ASSOCIATION (NEMA).
10. AMERICAN SOCIETY FOR TESTING MATERIALS
(ASTM).
11.INSTITUTE OF ELECTRICAL AND ELECTRONIC
ENGINEERS (IEEE).
1.2. CONTRACTOR QUALIFICATIONS / REQUIREMENTS:
A. THE CONTRACTOR SELECTED FOR THIS
PROJECT SHALL BE CERTIFIED BY THE SCS
MANUFACTURER, ADHERE TO THE DESIGN
ENGINEERING, INSTALLATION AND
CERTIFICATION PROCEDURES AND UTILIZE THE
AUTHORIZED MANUFACTURER COMPONENTS IN
COMPLETING THIS PROJECT.
B. THE CONTRACTOR SHALL:
1. HAVE A BICSI CERTIFIED RCDD ON STAFF AND
READILY AVAILABLE FOR THIS PROJECT. A
COPY OF THE BICSI CERTIFICATE OR STAMP
SHALL BE PROVIDED. LEAD INSTALLER
SHALL HAVE A MINIMUM OF 5-YEARS OF
INSTALLATION WORK EXPERIENCE RUNNING
PROJECTS.
2. BE EXPERIENCED IN ALL ASPECTS OF THE
WORK REQUIRED TO COMPLETE THIS
PROJECT AND SHALL BE REQUIRED TO
DEMONSTRATE DIRECT EXPERIENCE ON
RECENTLY INSTALLED SYSTEMS OF SIMILAR
SIZE AND TYPE.
3. CAREFULLY EXAMINE THE CONTRACT
DOCUMENTS AND MAKE ARRANGEMENTS TO
VISIT THE SITE, AND THOROUGHLY BECOME
FAMILIAR WITH THE BUILDING STANDARDS
AND LOCAL CONDITIONS RELATING TO THE
WORK. FAILURE TO DO SO WILL NOT RELIEVE
THE CONTRACTOR OF THE OBLIGATIONS OF
THE CONTRACT.
4. OWN AND MAINTAIN EQUIPMENT AND TOOLS
REQUIRED FOR THE INSTALLATION AND
TESTING OF THE SPECIFIED STRUCTURED
CABLING SYSTEMS. THE CONTRACTOR
SHALL ALSO EMPLOY PERSONNEL WHO ARE
ADEQUATELY TRAINED IN THE USES OF
REQUIRED TOOLS AND EQUIPMENT.
C. THESE DOCUMENTS DETAIL THE COMPONENTS
AND INSTALLATION GUIDELINES THAT NEED TO
BE INCLUDED FOR THE PROJECT. THESE
DOCUMENTS CONTAIN WORK THAT IS THE
RESPONSIBILITY OF MULTIPLE CONTRACTORS
I.E. COMMUNICATION CONTRACTOR, ELECTRICAL
CONTRACTOR, GENERAL CONTRACTOR ETC. IT
IS NOT THE INTENT OF THESE DOCUMENTS TO
DICTATE WHICH CONTRACTOR IS RESPONSIBLE
FOR EACH TASK; THE PRIME
CONTRACTOR/CONSTRUCTION MANAGER SHALL
DELEGATE THE WORK TO THE APPROPRIATE
SUB-CONTRACTORS.
1.3. PROPOSAL REQUIREMENTS:
A. CONTRACTOR SHALL PROVIDE A PROPOSAL FOR
ALL LABOR AND MATERIAL TO INSTALL A
COMPLETE STRUCTURED CABLING SYSTEM
(SCS), INCLUDING BUT NOT LIMITED TO ALL
REQUIRED CABLING, RACKS, PATCH PANELS,
SUPPORT HARDWARE, CROSS CONNECTS,
PATCH CORDS, RACEWAYS,
TELECOMMUNICATIONS OUTLETS, ETC. SCS
SHALL BE INSTALLED AND CONFIGURED TO
PROVIDE VOICE AND DATA CONNECTIVITY FROM
EACH TELECOMMUNICATIONS OUTLET TO THE
VOICE NETWORK/SWITCH OR DATA
NETWORK/SWITCH DESIGNATED AS THE SERVICE
POINT OF THE COMMUNICATIONS NETWORK.
B. UNIT PRICING: CONTRACTOR SHALL PROVIDE
ADD/DEDUCT UNIT PRICES AS FOLLOWS:
1. TYPICAL COMMUNICATIONS OUTLET, EACH
CONFIGURATION, COMPLETE INCLUDING
CABLE, JACK(S), FACEPLATE, APPORTIONED
PATCH PANEL OR OTHER TERMINATION
HARDWARE, INSTALLATION AND
CERTIFICATION. UNIT COST SHALL ASSUME
A 200FT CABLE LENGTH AVERAGE.
2. TYPICAL PATCH CORD ASSEMBLY, EACH TYPE
AND LENGTH. INSTALLATION AS SPECIFIED.
C. SUBMITTALS:
1. CUT SHEET SUBMITTALS: CONTRACTOR SHALL
PROVIDE MANUFACTURER PRODUCT DATA
SUBMITTALS, WITH THE INTENDED PART
NUMBER(S) AND USE CLEARLY INDICATED,
FOR THE FOLLOWING:
a ALL CABLE AND WIRE INCLUDING
PREMISES CABLES, BACKBONE CABLES,
PATCH CABLES AND CROSS CONNECT
WIRE.
b ALL CONNECTORS AND REQUIRED
TOOLS.
c ALL TERMINATION SYSTEM COMPONENTS
FOR EACH CABLE TYPE.
d ALL EQUIPMENT ROOM AND
TELECOMMUNICATIONS ROOM
EQUIPMENT RACKS, CABINET
ENCLOSURES, HORIZONTAL CABLE
MANAGEMENT, VERTICAL CABLE
MANAGEMENT AND CABLE TRAY AND
ASSOCIATED HARDWARE.
e ALL COMMUNICATIONS GROUNDING
SYSTEM COMPONENTS.
f ALL TEST EQUIPMENT TO BE USED FOR
COPPER AND OPTICAL FIBER
CERTIFICATION, INCLUDING CURRENT
CERTIFICATES OF CALIBRATION.
2. SHOP DRAWING SUBMITTALS: CONTRACTOR
SHALL SUBMIT SHOP DRAWINGS CLEARLY
INDICATING THE FOLLOWING, BUT NOT
LIMITED TO:
a EXACT CONDUIT, PULL BOX AND
RACEWAY LAYOUTS.
b WORK AREA OUTLET LABELING PLAN.
c CONTRACTOR SHALL COORDINATE WITH
APPROPRIATE TRADE CONTRACTORS
AND EOR.
3. SAMPLES AND MOCK-UPS: CONTRACTOR
SHALL SUBMIT SAMPLE PRODUCT MOCK UPS
FOR REVIEW BY OWNER AND EOR. DIGITAL
PHOTOS ARE ENCOURAGED. SAMPLES
SHALL INCLUDE BUT NOT BE LIMITED TO:
a FACEPLATES: PROVIDE A SAMPLE OF
EACH TYPE OF FACEPLATE USED ON
THE PROJECT. SAMPLE SHALL INCLUDE
JACK INSERTS AND SAMPLE LABEL
(TEXT, FONT AND SIZE).
b CABLE: PROVIDE A 3FT LONG SAMPLE OF
EACH CABLE BEING INSTALLED WITH A
SAMPLE LABEL (TEXT, FONT AND SIZE)
c PATCH PANELS: PROVIDE A SAMPLE OF
PLANNED PATCH PANEL LABELING
(TEXT, FONT AND SIZE)
d EQUIPMENT RACK/CABINETS: PROVIDE A
SAMPLE OF PLANNED EQUIPMENT
LABELING (PLACEMENT, TEXT, FONT
AND SIZE)
4. CLOSE OUT SUBMITTALS:
a CONTRACTOR SHALL PROVIDE
ELECTRONIC FORMATTED AS-BUILT
DRAWINGS TO OWNER AND ENGINEER
OF RECORD (EOR) IN AN ELECTRONIC
FORMAT AS DETERMINED BY OWNER
UPON COMPLETION OF PROJECT.
b THE CONTRACTOR SHALL PROVIDE A
ONE (1) YEAR GENERAL CONSTRUCTION
WARRANTY.
c THE CONTRACTOR SHALL SUPPLY AN
EXTENDED LIFE (20+ YEARS)
MANUFACTURER WARRANTY FOR THE
ENTIRE STRUCTURED CABLING SYSTEM.
THE MANUFACTURER WARRANTY MUST
ENSURE THAT THE STRUCTURED
CABLING SYSTEM (SCS) WILL BE FREE
FROM PRODUCT DEFECTS IN MATERIAL
AND WORKMANSHIP, WILL EXCEED
APPLICABLE TIA/EIA AND ISO/EIC
SPECIFICATIONS IN FORCE AT THE TIME
OF INSTALLATION AND WILL COMPLY
WITH DESIGN AND PERFORMANCE
REQUIREMENTS FOR RECOGNIZED
CABLING MEDIA INSTALLED IN THE
STRUCTURED CABLING LINK/CHANNEL.
ALL CABLE SHALL SUPPORT ALL
CURRENT OR FUTURE APPLICATIONS
THAT ARE DESIGNED FOR
TRANSMISSION OVER ITS RESPECTIVE
CABLING CLASSIFICATION AS DEFINED
IN ANSI/TIA-568.
d THE CONTRACTOR SHALL MOUNT A
LAMINATED 1/2-SIZED AS-BUILT
DRAWING IN THE TR (IDF). THE
CONTRACTOR SHALL SUBMIT A PHOTO
OR OWNER SIGN-OFF OF THE AS-BUILT
DRAWING FOR PROJECT CLOSE-OUT.
e THE CONTRACTOR SHALL PROVIDE A
WRITTEN SIGN-OFF VERIFICATION THAT
THE SPECIFIED OWNER
TRAINING/ORIENTATION WAS
COMPLETED.
f THE CONTACTOR SHALL PROVIDE A
WRITTEN SIGN-OFF VERIFICATION OF
THE COMPLETION OF THE PATCH CABLE
INSTALLATION AND HAND-OVER OF
PATCH CABLES SPECIFIED FOR OWNER
INSTALLATION.
PART 2 PRODUCTS
2.1. TWISTED PAIR CABLE
A. JACKET RATING: ALL INSTALLED CABLES SHALL
BE RATED FOR THE ENVIRONMENT FOR WHICH
THEY ARE INSTALLED PER THE NEC.
B. VERIFICATION: ALL INSTALLED CABLES SHALL BE
INDEPENDENTLY VERIFIED BY AN NRTL FOR
COMPLIANCE.
C. CATEGORY 5E UTP (CAT 5E): 4-PAIR UTP CABLES
SHALL CONSIST OF 4-PAIR, 24 GAUGE, UTP.
D. CATEGORY 6 UTP (CAT 6) 4-PAIR UTP CABLES
SHALL CONSIST OF 4-PAIR, 24 GAUGE, UTP.
2.2. TERMINATION HARDWARE:
A. PATCH PANELS:
1. COPPER PATCH PANELS SHALL BE:
a BE HIGH DENSITY SUCH THAT 24 PORTS
OCCUPY 1 RACK SPACE AND 48 PORTS
OCCUPIES 2 RMU.
b PATCH PANEL CABLE TERMINATIONS
SHALL BE 110 TYPE INSULATION
DISPLACEMENT CONTACT PRINTED
CIRCUIT BOARD UNO.
c HAVE A CABLE MANAGEMENT BAR TO
ENSURE PROPER BEND RADIUS AND
STRAIN RELIEF
d FLAT.
e COMPLY WITH ANSI/TIA-606 LABELING
STANDARDS.
2. JACK PANELS SHALL BE
a BE HIGH DENSITY SUCH THAT 24 PORTS
OCCUPY 1 RACK SPACE AND 48 PORTS
OCCUPIES 2 RMU.
b SHALL INCLUDE BLANK INSERTS FOR ANY
UNUSED PORTS.
c HAVE A CABLE MANAGEMENT BAR TO
ENSURE PROPER BEND RADIUS AND
STRAIN RELIEF
d FLAT
e COMPLY WITH ANSI/TIA-606 LABELING
STANDARDS.
B. WORK AREA OUTLETS:
1. JACKS SHALL:
a MEET OR EXCEED ALL TRANSMISSION
REQUIREMENTS FOR THE SPECIFIC
CATEGORY RATING OF THE INSTALLED
CABLE.
b WIRING TERMINATION SEQUENCE FOR
T-568-A OR 568-B WIRING SCHEME
c MEET THE ELECTRICAL, MECHANICAL
AND CLEARANCE SPECIFICATIONS IN
FCC RULES AND REGULATIONS, PART
68, SUBPART F.
d UL LISTED AND CSA CERTIFIED
2. FACE PLATES SHALL:
a POSSESS DESIGNATION WINDOWS TO
FACILITATE LABELING AND CONFORM
TO ANSI/TIA-606 LABELING STANDARDS
b BE AVAILABLE IN A VARIETY OF
CONFIGURATIONS AND PORT
CAPACITIES TO SATISFY THE DESIGN
REQUIREMENTS.
c BE AVAILABLE IN A VARIETY OF COLORS
TO MATCH THE DESIGN. COORDINATE
FACEPLATE COLORS WITH ARCHITECT,
EOR AND OTHER TRADES PRIOR TO
ORDERING MATERIALS.
d BE AVAILABLE IN FLUSH AND SURFACE
MOUNT TO ACCOMMODATE WALL
BOXES AND FURNITURE RACEWAYS.
e BE UL LISTED AND CSA CERTIFIED
2.3. PATCH CORDS
A. COPPER PATCH CORDS ARE REQUIRED AS
NOTED IN PATCH CORD TABLE IN DRAWINGS.
2.4. PATHWAY SYSTEMS
A. SHALL BE LISTED BY THE NRTL FOR THE
INSTALLED APPLICATION.
B. CONTRACTOR SHALL USE EXISTING PATHWAYS
WHEN POSSIBLE AND MATCH EXISTING WHEN
INSTALLING ADDITIONAL PATHWAYS.
C. CONDUIT
1. CONTRACTOR SHALL PROVIDE A COMPLETE
EMPTY METAL RACEWAY SYSTEM
CONSISTING OF ALL CONDUIT, CABLE TRAY,
LADDER TRAY, FITTINGS, BUSHINGS, PULL
BOXES (PLENUM APPROVED AS REQUIRED),
OUTLET BOXES, ETC. FOR A FULLY
FUNCTIONAL SYSTEM.
2. THE MINIMUM CONDUIT SIZE ALLOWED FOR
TELECOMMUNICATIONS PATHWAYS SHALL
BE 1”.
D. TELECOMMUNICATION BOXES
1. WALL BOXES SHALL BE 4 11/16” X 4 11/16” X 2
1/2” DOUBLE GANG BOXES (11B) DEEP
JUNCTION BOX WITH A SINGLE-GANG
OPENING PLASTER RING OPENING UNO.
2. SURFACE BOXES SHALL MATCH EXISTING
TELECOMMUNICATIONS BOXES.
E. CABLE TRAY SYSTEMS
1. WIRE BASKET TRAY WILL CONSIST OF
CONTINUOUS, STEEL WIRE MESH CABLE
MANAGEMENT SYSTEM TO ALLOW
CONTINUOUS VENTILATION OF CABLES AND
MAXIMUM DISSIPATION OF HEAT. TRAY
SHALL BE INSTALLED IN COMPLIANCE WITH
MANUFACTURER AND NRTL BONDING
REQUIREMENTS.
F. LADDER RACK
1. LADDER RACK SHALL BE MANUFACTURED
FROM 3/8” (9.5 MM) WIDE BY 1-1/2” (38 MM)
HIGH TUBULAR STEEL WITH .065” (1.65 MM)
WALL THICKNESS.
2. LADDER RACK (SIDE STRINGERS) WILL BE
9'-11½“(3.0 M) LONG. CROSS MEMBERS WILL
BE WELDED IN BETWEEN STRINGERS ON 12”
(300 MM) INTERVALS/CENTERS BEGINNING
5-3/4” (146 MM) FROM ONE END SO THAT
THERE ARE 10 CROSS MEMBERS PER
LADDER RACK SECTION. THERE WILL BE
10-1/2” (267 MM) OF OPEN SPACE IN
BETWEEN EACH CROSS MEMBER.
3. EACH LADDER RACK SECTION SHALL BE
BONDED TO THE TGB OR TMGB WITH A #6
AWG STRANDED COPPER CONDUCTOR,
UTILIZING 2-HOLE COMPRESSION LUGS.
4. FINISH SHALL BE EPOXY-POLYESTER HYBRID
POWDER COAT (PAINT).
2.5. HARDWARE COMPONENTS:
A. SHALL BE LISTED BY THE NRTL FOR THE
INSTALLED APPLICATION.
B. WIRE MANAGERS SHALL MEET THE FOLLOWING
CRITERIA UNLESS NOTED OTHERWISE IN THE
EQUIPMENT SCHEDULE
1. VERTICAL WIRE MANAGERS SHALL BE:
a SINGLE SIDED, FULL HEIGHT.
b DOUBLE-HINGED, REMOVABLE DOORS
SHALL BE PROVIDED
c METAL FINGERS
d SEE DRAWINGS FOR SPECIFIC WIDTHS.
2. HORIZONTAL WIRE MANAGERS SHALL:
a MOUNT IN A STANDARD 19” WIDE RACK.
b COVERS SHALL BE PROVIDED FOR THE
FRONT CHANNELS OF THE WIRE
MANAGERS.
3. SEE THE DESIGN DRAWINGS TO DETERMINE
THE RMU OF THE REQUIRED HORIZONTAL
CABLE MANAGERS.
PART 3 EXECUTION
3.1. GENERAL
A. THE CONTRACTOR SHALL PROVIDE A COMPLETE
AND FUNCTIONAL STRUCTURED CABLING
SYSTEM (SCS).
B. THE SCS INSTALLATION SHALL FOLLOW ALL
RECOGNIZED INDUSTRY BEST PRACTICES AND
SHALL BE PERFORMED IN A NEAT AND WORKMAN
LIKE MANNER.
3.2. CABLE INSTALLATION:
A. TWISTED PAIR CABLE (INCLUDES ALL
CATEGORIES):
1. CABLE DISTANCES
a CATEGORY RATED CABLES SHALL NOT
EXCEED 295FT OF INSTALLED LENGTH IN
THE PERMANENT LINK.
2. THE MAXIMUM PULLING TENSION OF 4-PAIR
UTP CABLES SHALL BE NO GREATER (25LBF).
FOR MULTI-PAIR BACKBONE CABLES,
MANUFACTURERS PULLING TENSION
GUIDELINES SHALL BE FOLLOWED.
3. CABLES SHALL NOT BE ATTACHED TO CEILING
GRID SUPPORTS AND SHALL NOT BE LAID
DIRECTLY ON THE CEILING GRID.
4. CABLES SHALL NOT BE ATTACHED TO OR
SUPPORTED BY FIRE SPRINKLER SYSTEMS
COMPONENTS OR ANY ENVIRONMENTAL
SENSOR LOCATED IN THE CEILING SPACE.
5. ALL CABLE RUNS BETWEEN THE TERMINATION
HARDWARE AND THE
TELECOMMUNICATIONS OUTLET SHALL BE
CONTINUOUS WITHOUT ANY SPLICES.
6. ALL TELECOMMUNICATIONS CABLING
INSTALLED WITHIN OPEN CEILING SPACES
SHALL BE ROUTED THROUGH THESE
SPACES PERPENDICULAR TO AND A
MINIMUM OF 12 INCHES FROM ELECTRICAL
CIRCUITS AND DEVICES. THE PROXIMITY OF
CABLING TO SOURCES OF RFI AND EMI
SHALL BE CONSIDERED WHEN INSTALLING
CABLE.
7. THE MINIMUM BEND RADIUS, UNDER NO-LOAD
CONDITIONS, FOR 4-PAIR UTP CABLES SHALL
BE 1 INCH OR 4 TIMES THE CABLE DIAMETER,
WHICHEVER IS GREATER. FOR MULTI-PAIR
BACKBONE CABLE THE MINIMUM BEND
RADIUS SHALL BE 10 TIMES THE CABLE
DIAMETER. THE MINIMUM BEND RADIUS,
UNDER NO-LOAD CONDITIONS, FOR
HORIZONTAL OPTICAL FIBER CABLE SHALL
BE 1 INCH OR 2 INCHES UNDER LOAD
8. ALL CABLE MANAGEMENT STRAPS INSTALLED
SHALL BE THE HOOK AND LOOP TYPE.
PLASTIC CABLE TIES SHALL NOT BE USED AT
ANY TIME DURING THE INSTALLATION.
9. WITHIN RACKS, CABINETS AND WIRE
MANAGEMENT, MANAGE AND DRESS CABLES
NEATLY USING CABLE MANAGEMENT
STRAPS WHERE REQUIRED AT A MAXIMUM
OF 2-3 FT. INTERVALS. CABLES SHALL BE
BUNDLED IN GROUPS OF NOT MORE THAN 12
CABLES.
10. AVOID CABLE STRESS DURING INSTALLATION
AS A RESULT OF THE FOLLOWING:
a CABLE TWIST DURING PULLING OR
INSTALLATION
b TENSION IN SUSPENDED CABLE RUNS
c TIGHTLY PINCHED CABLE MANAGEMENT
STRAPS
d TIGHT BEND RADIUS
e OTHER CAUSES OF CABLE STRESS
11.CABLES BUNDLED AND ROUTED IN OPEN
HORIZONTAL PATHWAYS SHALL BE:
a SUPPORTED BY APPROVED CABLE
HANGERS AT INTERVALS NOT
EXCEEDING 5 FEET
b BUNDLES SHALL NOT EXCEED 50 CABLES
12. ALL INSTALLED CABLING SHALL BE ROUTED
PARALLEL OR PERPENDICULAR TO BUILDING
LINES. THE CONTRACTOR SHALL FOLLOW
MANUFACTURER'S GUIDELINES FOR
BENDING RADIUS AND PULLING TENSION OF
ALL TELECOMMUNICATIONS CABLES.
3.3. CABLE TERMINATION
A. ALL INSTALLED CABLES SHALL BE CLEARLY
LABELED, TERMINATED AND CERTIFICATION.
B. FOR OPEN CABLE INSTALLATIONS THE
CONTRACTOR SHALL LEAVE APPROPRIATE
SERVICES LOOPS IN THE PREMISES:
1. WALL OUTLETS: 3FT SERVICE LOOP COILED AT
THE CONDUIT STUB UP LOCATION.
2. ACCESS POINTS: 25FT SERVICE LOOP COILED
AT THE ACCESS POINT LOCATION.
C. FOR INSTALLATIONS IN COMPLETE CONDUIT
SYSTEMS SERVICE LOOPS SHALL ONLY BE
REQUIRED FOR ACCESS POINTS.
1. ACCESS POINTS: 25FT SERVICE LOOP COILED
AT THE ACCESS POINT LOCATION.
3.4. CABLE PATHWAYS
A. DISTANCE REQUIREMENTS:
1. THE MAXIMUM ALLOWABLE HORIZONTAL
PATHWAY DISTANCE SHALL NOT EXCEED
265FT.
2. THE CONTRACTOR SHALL REVIEW AND VERIFY
ALL HORIZONTAL LENGTHS PRIOR TO CABLE
INSTALLATION.
B. CONDUIT SYSTEMS
1. CONDUITS ROUTES WHEN DENOTED ON
DRAWINGS ARE DIAGRAMMATIC,
CONTRACTOR SHALL COORDINATE THE
ENTIRE CONDUIT INSTALLATION WITH ALL
TRADES, ENGINEER OF RECORD (EOR), AND
WITH FIELD CONDITIONS PRIOR TO
INSTALLATION.
2. EXACT CONDUIT LENGTHS AND ROUTING SHALL
BE COORDINATED BY THE CONTRACTOR SO
AS TO NOT EXCEED CABLE LENGTH
LIMITATIONS AS DIRECTED BY
TELECOMMUNICATIONS SPECIFICATIONS.
3. CONTRACTOR SHALL SUBMIT SHOP DRAWINGS
INDICATING EXACT CONDUIT AND PULL BOX
LAYOUTS. CONTRACTOR SHALL
COORDINATE WITH APPROPRIATE TRADE
CONTRACTORS AND EOR.
4. CONTRACTOR SHALL PROVIDE A PULL STRING
FOR EACH TELECOMMUNICATIONS CONDUIT
RUN INSTALLED AS PART OF THIS PROJECT.
ANY PULL STRING USED FOR INSTALLATION
OF CABLE AS PART OF THIS PROJECT SHALL
BE REPLACED WITH A NEW PULL STRING.
5. CONTRACTOR SHALL STUB ALL CONDUITS INTO
TELECOMMUNICATIONS ROOM(S) AS
REQUIRED BY TELECOMMUNICATIONS
DRAWING AND SPECIFICATIONS AND
PROVIDE AN INSULATED GROUNDING
BUSHING FOR EACH CONDUIT END.
6. ALL CONDUIT BENDS SHALL BE WIDE RADIUS
TYPE. CONTRACTOR SHALL PROVIDE PULL
BOXES (PLENUM RATED WHERE REQUIRED)
FOR ALL RUNS WHERE MORE THAN 180
DEGREES OF CONDUIT BENDS OCCUR OR
WHERE A CONDUIT RUN EXCEEDS 100
LINEAR FEET, SIZE AND LOCATE PULL BOXES
AS REQUIRED DUE TO EXISTING FIELD
CONDITIONS, AND TO COMPLY WITH CODES
AND REGULATIONS. PULL BOXES SHALL NOT
BE USED FOR A DIRECTIONAL CHANGE
WITHIN A PATHWAY.
7. CONTRACTOR SHALL TERMINATE CONDUITS
AND INSTALL CONDUIT SLEEVES INTO THE
TELECOMMUNICATIONS ROOM(S).
8. ALL CORE SIZES AND LOCATIONS SHALL BE
SUBMITTED TO THE BUILDING OWNER'S
REPRESENTATIVE AND ARCHITECT FOR
REVIEW AND APPROVAL BY THE BUILDING
OWNER'S STRUCTURAL ENGINEER PRIOR TO
CORING.
9. ALL CONDUIT RACEWAY CAPACITIES ARE
BASED ON UNSHIELDED 24 GAUGE 4-PAIR
TWISTED PAIR CABLING. THE EXACT
QUANTITY OF CABLES PER OUTLET
LOCATION SHALL BE CONFIRMED WITH THE
CONTRACTOR AND/OR EOR, AND
COMMUNICATIONS DRAWINGS SO AS TO NOT
EXCEED 38% FILL OF RACEWAY. THE EXACT
QUANTITY AND TYPE OF CABLE(S) PER WALL,
FLOOR OR FURNITURE COMMUNICATIONS
OUTLETS SHALL BE DETERMINED BY THE
COMMUNICATIONS DRAWINGS.
10.MINIMUM CONDUIT SIZING FOR ALL
COMMUNICATIONS OUTLETS SUPPORTING
CATEGORY 5E OR CATEGORY 6 CABLES
SHALL BE (3/4) INCH UNO.
NUMBER OF
CABLES
CONDUIT
SYSTEMS
WIRE WAYS
AND
SURFACE
METAL
SYSTEMS
OPEN
CABLE
TRAYS
1 53% N/A N/A
2 31% 20% N/A
>2 38% 20% 25%
11.CONDUIT HOMERUN SIZING SHALL BE BASED
ON THE FOLLOWING MAXIMUM FILLS:
a FOR 0.25” O.D. CABLE (MAX. SIZE FOR =
CATEGORY 6):
CONDUIT SIZE 4-PAIR CABLES
3/4” 4
1” 6
1-1/4” 11
1-1/2” 15
2” 25
2-1/2” 45
3” 68
3-1/2” 89
4” 114
12.CONDUIT FILL CAPACITY MAY BE ADJUSTED
BASED ON ACTUAL CABLE DIAMETERS WITH
PRIOR APPROVAL FROM EOR.
C. FIRESTOPPING
1. ALL FIRESTOP SYSTEMS SHALL BE LISTED BY
AN NTRL FOR THE INTENDED APPLICATION.
2. CONTRACTOR SHALL PROVIDE LISTED FIRE
SEAL SYSTEM FOR ALL CONDUITS OR
SLEEVES THAT PENETRATE A FIRE RATED
FLOOR OR WALL. THE SYSTEM SHALL BE
RATED TO MATCH THE RATING OF THE
FLOOR OR WALL BEING PENETRATED.
D. TELECOMMUNICATION BOXES
1. WALL BOXES SHALL BE 4-11/16” X 4-11/16” X 2
1/2” DOUBLE GANG BOXES (11B TYPE) DEEP
JUNCTION BOX WITH A SINGLE GANG
PLASTER RING OPENING UNO.
CONTRACTOR SHALL COORDINATE WITH
THE ARCHITECTURE AND ELECTRICAL PLANS
TO COORDINATE WITH CABLE QUANTITY AND
TYPE.
E. CABLE TRAY SYSTEMS
1. GROUND CABLE TRAY AGAINST FAULT
CURRENT, NOISE, LIGHTNING AND
ELECTROMAGNETIC INTERFERENCE BY
BONDING A CONTINUOUS GROUND
CONDUCTOR TO EACH 10' CABLE TRAY
SECTION WITH A GROUNDING CLAMP.
2. FOR CEILING MOUNTED INSTALLATION, CABLE
TRAYS SHALL BE SUPPORTED WITH THREADED
ROD IN A TRAPEZE SUPPORT AT INTERVALS OF
NOT MORE THAN 5' OR INTERVALS BASED ON
THE SUPPORTED LOAD, WHICHEVER IS LESS.
3. A MINIMUM 12” CLEARANCE BETWEEN THE TOP
OF THE TRAY AND THE BOTTOM OF THE TRUSS
STRUCTURE SHALL BE MAINTAINED.
4. CONTRACTOR SHALL INSTALL BENDS IN CABLE
TRAY TO SUPPORT ANSI/TIA BEND RADIUS
REQUIREMENTS FOR THE INSTALLED CABLES.
ADHERE TO MANUFACTURER INSTALLATION
REQUIREMENTS.
3.5. HARDWARE COMPONENTS:
A. GROUNDING (EARTHING)
1. ALL TELECOMMUNICATIONS GROUNDING
EQUIPMENT SHALL CONFORM TO
ANSI/TIA-607 STANDARD.
2. CONTRACTOR SHALL PROVIDE A COPPER
GROUNDING BAR WITHIN ALL
TELECOMMUNICATIONS ROOMS AND
EQUIPMENT ROOMS AND GROUND ALL
RACEWAY, RACKS AND, CABINETS IN
ACCORDANCE WITH MANUFACTURER
RECOMMENDATIONS AND ANSI/TIA-607
STANDARD, NFPA 70 AND ALL APPLICABLE
BUILDING CODES. SEE DESIGN DOCUMENTS
FOR PROJECT SPECIFICATIONS.
3. ALL GROUNDING CONNECTIONS SHALL BE
IRREVERSIBLE; COMPRESSION OR THERMAL
WELD. MECHANICAL SCREW-ON LUGS ARE
NOT ALLOWED.
4. EACH GROUNDING BUSBAR (TMGB & TGB) AND
GROUNDING CONDUCTORS MUST BE
LABELED PER THE REQUIREMENTS OF
ANSI/TIA-607 STANDARD, INCLUSIVE OF ALL
ADDENDA. LABELS SHALL BE NON-METALLIC.
5. CONTRACTOR SHALL PROVIDE A COPPER
GROUNDING BAR WITHIN ALL
TELECOMMUNICATIONS ROOMS AND
PROVIDE A GROUND CONDUCTOR IN
CONDUIT TO BUILDING GROUND RISER
UNLESS NOTED OTHERWISE ON DRAWINGS.
GROUND BAR(S) SHALL HAVE SUFFICIENT
LUG POSITIONS FOR GROUNDING OF ALL
RACKS, CONDUITS, EQUIPMENT AND SIX
FUTURE GROUNDING CONNECTIONS.
CONTRACTOR SHALL COORDINATE EXACT
GROUNDING REQUIREMENTS WITH THE EOR
PRIOR TO INSTALLATION.
6. ALL METALLIC TELECOMMUNICATION RACEWAY
AND EQUIPMENT LOCATED IN A
TELECOMMUNICATION ROOM MUST BE
BONDED TO THE TMGB OR TGB WITHIN THAT
ROOM.
7. ALL LADDER RACKS, CABLE TRAYS OR OTHER
OPEN RACEWAY SYSTEMS WITHIN A TR OR
ER SHALL HAVE A SINGLE, CONTINUOUS
GROUNDING CONDUCTOR ROUTED
THROUGH THE RACEWAY SYSTEM AND
BONDED TO EACH SECTION OF RACEWAY.
8. CONTRACTOR SHALL PROVIDE A #6 AWG
GROUNDING CONDUCTOR FROM EACH
COMMUNICATIONS CONDUIT GROUNDING
BUSHING TO THE COPPER GROUND BAR
LOCATED WITHIN THE TR OR ER.
3.6. LABELING
A. ALL LABELING OF SCS COMPONENTS (CABLE,
PATCH PANELS, ETC.), PATHWAY ELEMENTS,
GROUNDING, RACKS, CABINETS, SPACES, ETC.
SHALL BE IN ACCORDANCE WITH ANSI/TIA-606
AND ASSOCIATED ADDENDA AND ANSI/TIA-942 AS
APPLICABLE.
B. CONTRACTOR SHALL LABEL ALL
TELECOMMUNICATIONS CABLES, FACEPLATES,
PATCH PANELS AND TERMINATION HARDWARE
WITH PERMANENT MACHINE TYPED LABELS IN
ACCORDANCE WITH TELECOMMUNICATION
DRAWINGS.
C. CABLE LABELS SHALL BE PLACED 12 TO 18
INCHES FROM THE POINT OF TERMINATION.
D. FACEPLATE LABELS SHALL BE ¼ INCH TEXT SIZE
PLACED UNDER THE TRANSPARENT FACEPLATE
LABEL PROTECTOR.
E. RACK/CABINET LABELS SHALL BE ¾” TEXT ON 1”
TAPE OR LAMINATE.
F. ELECTRICAL PANELS AND OUTLETS:
1. “A” AND “B” ELECTRICAL PANELS SHALL BE
COLOR CODED BLUE AND RED.
2. PANELS AND OUTLETS SHALL HAVE MATCHING
COLOR MACHINE PRINTED LABELS.
3.7. CABLE CERTIFICATION:
A. TWISTED PAIR CABLE CERTIFICATION.
1. CERTIFICATION OF ALL COPPER WIRING SHALL
BE PERFORMED PRIOR TO SYSTEM
CUTOVER. 100 PERCENT OF THE
HORIZONTAL, RISER AND INTER-CABINET
WIRING PAIRS SHALL BE TESTED FOR
OPENS, SHORTS, POLARITY REVERSALS,
TRANSPOSITION AND PRESENCE OF AC
VOLTAGE.
2. VOICE AND DATA HORIZONTAL WIRING PAIRS
SHALL BE CERTIFIED FROM EQUIPMENT
OUTLET TO EQUIPMENT OUTLET. THE
CATEGORY CABLE RUNS SHALL BE TESTED
FOR CONFORMANCE TO THE
SPECIFICATIONS AS DEFINED IN
ANSI/TIA-568. FIELD TEST INSTRUMENTS
USED TO VERIFY CATEGORY 5E OR
CATEGORY 6 CABLE PERFORMANCE SHOULD
BE COMPLIANT TO THE LEVEL III, LEVEL IIIE
OR LEVEL IV REQUIREMENTS AS DEFINED IN
ANSI/TIA-1152. ANY CABLES OR PAIRS NOT
MEETING THE REQUIREMENTS OF THE
STANDARD SHALL BE BROUGHT INTO
COMPLIANCE BY THE CONTRACTOR, OR
REPLACED AT NO COST TO THE CLIENT.
3. ALL TWISTED PAIR CABLING SHALL INCLUDE
THE FOLLOWING PERMANENT LINK TESTS:
WIRE MAP (INCLUDING THE SHIELD
CONNECTION IF PRESENT), DC LOOP
RESISTANCE, LENGTH, INSERTION LOSS,
NEXT LOSS (PAIR-TO-PAIR, MEASURED FROM
BOTH THE LOCAL END AND THE FAR END),
PROPAGATION DELAY AND DELAY SKEW.
4. IN ADDITION TO THE PARAMETERS LISTED
ABOVE, ALL CATEGORY 5E AND CATEGORY 6
TWISTED-PAIR CABLING SHALL ALSO
INCLUDE THE FOLLOWING PERMANENT LINK
TESTS: RETURN LOSS, PSNEXT LOSS
(MEASURED FROM BOTH THE LOCAL END
AND THE FAR END), ACRF (MEASURED FROM
BOTH THE LOCAL END AND THE FAR END)
AND PSACRF (MEASURED FROM BOTH THE
LOCAL END AND THE FAR END).
5. THE CONTRACTOR SHALL NOTIFY THE CLIENT
AND EOR IN WRITING A MINIMUM OF 72
HOURS PRIOR TO THE START OF
CERTIFICATION AND PROVIDE A COMPLETE
CERTIFICATION SCHEDULE TO ALLOW FOR
WITNESSING OF TESTING.
6. CONTRACTOR SHALL PROVIDE CURRENT
CERTIFICATE(S) OF CALIBRATION FOR ALL
TEST EQUIPMENT TO BE USED FOR THIS
PROJECT. CERTIFICATES MUST INDICATE
SERIAL NUMBERS AND CERTIFICATION
DATES AND THAT THE TEST SET(S) HAS
BEEN CALIBRATED BY THE MANUFACTURER.
NO CERTIFICATION TESTS SHALL BE
PERFORMED WITH TEST EQUIPMENT THAT
HAS NOT BEEN CALIBRATED WITHIN 6
MONTHS PRIOR TO FIELD CERTIFICATION.
7. COMPLETE END TO END CERTIFICATION
RESULTS SHALL BE SUBMITTED TO THE
CLIENT AND EOR IN ELECTRONIC FORMAT.
NO HAND WRITTEN TEST RESULTS WILL BE
ACCEPTED. IF SPECIAL SOFTWARE OR
LICENSE IS REQUIRED TO REVIEW
CERTIFICATION DATA ELECTRONICALLY,
CONTRACTOR SHALL PROVIDE ONE COPY OF
SOFTWARE AND APPROPRIATE LICENSE
WITH EACH SET OF CERTIFICATION DATA.
8. ACCEPTABLE COPPER TEST SETS:
AGILENT
FLUKE
ENGINEER APPROVED EQUAL
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.05 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC0-01
STRUCTURED CABLINGSPECIFICATIONS
NONE
1 ISSUED FOR BID 02/13/2018
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.05 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652
TELECOMMUNICATIONS SYMBOLS
ENLARGED PLAN REFERENCE. 'X'
REPRESENTS THE DETAIL NUMBER,
'Y' REPRESENTS THE DRAWING
NUMBER.
Y
X
ABBREVIATIONS
AHJ - AUTHORITY HAVING JURISDICTION
ANSI - AMERICAN NATIONAL STANDARDS INSTITUTE
AWG - AMERICAN WIRE GAUGE
AVC - AUDIO VISUAL CONTRACTOR
DC - DATA CENTER
EC - ELECTRICAL CONTRACTOR
ER - EQUIPMENT ROOM
EOR - ENGINEER OF RECORD
F/UTP - FOILED/UNSHIELDED TWISTED PAIR CABLE
GC - GENERAL CONTRACTOR
IDC - INSULATION DISPLACEMENT CONNECTION
IDF - INTERMEDIATE DISTRIBUTION ROOM (SEE ALSO ER OR TR)
MDF - MAIN DISTRIBUTION ROOM (SEE ALSO MER, TR OR
SERVER ROOM)
MM - MULTI MODE FIBER
NEC - NATIONAL ELECTRICAL CODE
NFPA - NATIONAL FIRE PROTECTION AGENCY
NRTL - NATIONALLY RECOGNIZED TESTING LABORATORY
PDU - POWER DISTRIBUTION UNIT
RMU - RACK MOUNT UNIT (SEE ALSO RU)
RU - RACK UNIT
SC - SECURITY CONTRACTOR
SCS - STRUCTURED CABLING SYSTEM
SM - SINGLE MODE FIBER
STP - SHIELDED TWISTED PAIR CABLE
TC - TELECOMMUNICATIONS CONTRACTOR
TIA - TELECOMMUNICATION INDUSTRY ASSOCIATION
TGB - TELECOMMUNICATIONS GROUNDING BUS BAR
TMGB - TELECOMMUNICATIONS MAIN GROUNDING BUS BAR
TR - TELECOMMUNICATIONS ROOM
UNO - UNLESS NOTED OTHERWISE
UPS - UNINTERRUPTABLE POWER SUPPLY
UTP - UNSHIELDED TWISTED PAIR CABLE
2 PORT FACEPLATE WITH (2)
CAT6 CABLE
COPPER CONNECTIVITY
KEY DESCRIPTION COMMENTS
C1 CAT 5E OR CAT 6 CABLE, CMR, BLUE
C2 CAT 5E OR CAT 6 JACK, BLUE
C3 BLANK INSERT, BLACK
C4 2 PORT FACEPLATE
C5 CAT 5E OR CAT 6 PATCH PANEL, 48 PORT, BLACK
C6 2-RMU HORIZONTAL WIRE MANAGER, BLACK
RACKS & ACCESSORIES
KEY DESCRIPTION
R1 VERTICAL WIRE MANAGER, 84"H x 6"W, DOUBLE-SIDED FINGER STYLE WITH COVER
COPPER PATCH CORDS
LOCATION PURPOSE CATEGORY QUANTITY PERLOCATION
PERCENT OFTOTAL
LENGTH (FT) COLOR FURNISHED BY INSTALLED BY COMMENTS
PREMISES WIRELESS ACCESS POINT 5e OR 6 1 PER PORT 100% 1 BLUE CONTRACTOR CONTRACTOR WAP FURNISHED BY CONTRACTOR, INSTALLED BY CONTRACTORPREMISES WIRELESS ACCESS POINT 5e OR 6 1 PER PORT 100% 7 BLUE CONTRACTOR CONTRACTOR WAP FURNISHED BY CONTRACTOR, INSTALLED BY CONTRACTORTELECOM
ROOM SWITCHES - POE 5e OR 6 1 PER PORT 100% 7 BLUE CONTRACTOR CONTRACTOR WAP FURNISHED BY CONTRACTOR, INSTALLED BY CONTRACTOR
NEW EQUIPMENT
KEY DESCRIPTION
N1 48-PORT POE SWITCH
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.06 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC0-02
STRUCTURED CABLINGSPECIFICATIONS
NONE
1 ISSUED FOR BID 02/13/2018
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.06 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652
SYMBOL:
SCALE: NTS
3 2 PORT FACEPLATE
C2
C4
C1
JACK POSITIONS
PAIR 2
PAIR 3
PAIR 1 PAIR 4
PAIR 3
8
W-BR
7
W-BL
5
G
6
BL
43
O
21
W-O W-G BR
RJ-45
(1) 4 PAIR UTP CABLE
SCALE: NTS
2 JACK PAIR ASSIGNMENTS (T568B)8-WIRE/8-POSITION MODULAR
MATCH EXISTING LABELING SCHEME
MATCH EXISTING LABELING SCHEME
12" TO 18"
UTP CABLE
WHITE LABEL AND BLACK LETTERS W/
CLEAR TAPE COVERING. LABEL SHALL
BE PLACED NOT CLOSER THAN 12" AND
NOT FURTHER THAN 18" FROM ENDS OF
CABLE (BOTH ENDS OF CABLE)
SCALE: NTS
4 COPPER CABLE LABELING DETAILTYPICAL HORIZONTAL
MATCH EXISTING LABELING SCHEME
XXX-XX XXX-XX
NOTE:
CONTRACTOR SHALL PROVIDE AND
INSTALL MACHINE PRINTED BLACK
LETTERS ON WHITE LABELS AND
ADHERE TO PANEL
SCALE: NTS
5 PATCH PANEL LABELING DETAIL
XXX-XX XXX-XX
18"
FLOOR
CEILING
SCALE: NTS
1 NEW WAP DATA OUTLET
WAP DEVICE
EXISTING/NEW
DATA OUTLET
1' PATCH CORD
.
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.07 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC0-03
STRUCTURED CABLINGSPECIFICATIONS
NONE
1 ISSUED FOR BID 12/13/2018
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cg_01.dw
g 02/13/2018 15:32.07 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
1
KEY NOTES:
1. EXISTING DATA OUTLET LOCATED HIGH ON WALL (+7'-+10') TO BE REUSED FORNEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
2. NEW DATA OUTLET LOCATED HIGH ON WALL (18" BELOW CEILING) TO USEDFOR NEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
#
2
2
2
2
2
1
1
1
GENERAL NOTES:
1. ALL NEW DATA LOCATIONS ARE TO BE FED FROM THE MDF ROOM2. REFER TO KEY NOTES FOR IDENTIFICATION OF DATA OUTLETS THAT ARE
EXISTING TO REMAIN AND NEW.3. SCHEDULE AND COORDINATE ALL NOISE MAKING CONSTRUCTION ACTIVITIES
WITH OWNER PRIOR TO BEGINNING WORK.4. ALL WORK SHALL COMPLY WITH DISTINCTIVE FACILITY STANDARDS,
MEANSAND METHODS, AND SAFETY POLICY.5. CONTRACTOR SHALL COORDINATE THE CONDUIT ROUTES TO MDF ROOM IN
MOST EFFICIENT MANNER POSSIBLE AND SHALL TAKE CARE NOT TO EXCEED40% OF CONDUIT CAPACITY, IF APPLICABLE.
6. COORDINATE ANY REQUIRED WALL PENETRATIONS, FLOOR CUTTING OR DUCTCORING WITH DISTINCTIVE FACILITIES. PERFORM FLOOR SCANNING PRIOR TOCORING. INSTALL FIRESTOPPING FOR ALL PENETRATIONS THROUGH RATEDWALLS AND FLOORS. FIRESTOPPING SHALL MATCH THE RATING OF THEWALLS/FLOORS. FLOOR CUTTING AND PATCHING SHALL BE BY CONTRACTOR.
BASEMENT
MDF
SC3-00
2
6" W
ID
E V
ER
TIC
AL W
IR
E M
AN
AG
ER
KEY Rack 01
6" W
ID
E V
ER
TIC
AL W
IR
E M
AN
AG
ER
45
EXISTING PANEL
45
44 44
43 43
42 42
41 41
40 40
39 39
38 38
37 EXISTING PANEL 37
36 EXISTING PANEL 36
35 EXISTING PANEL 35
34
C6 HWM
34
33 33
32
C5 D2 - PATCH PANEL
32
31 31
30
C6 HWM
30
29 29
28 N1 SWITCH 28
27 N1 SWITCH 27
26
C6 HWM
26
25 25
24 N1 SWITCH 24
23 N1 SWITCH 23
22
C6 HWM
22
21 21
20 N1 SWITCH 20
19 N1 SWITCH 19
18
C6 HWM
18
17 17
16 N1 SWITCH 16
15 15
14 14
13 13
12 12
11 11
10 10
9 9
8 8
7 7
6 6
5 5
4 4
3 3
2 2
1 1
R1
Existing Rack
R1
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cp_00.dw
g 02/13/2018 15:32.08 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC3-00
BASEMENTTECHNOLOGY
PLAN
1/8"=1'-0"
1 ISSUED FOR BID 02/13/2018
BASEMENT NEW TECHNOLOGY PLAN
1/8"=1'-0"1
1/8" = 1'-0"
0 4 8 16
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652
BASEMENT MDF RACK ELEVATION (FRONT)
NTS2
1
KEY NOTES:
1. EXISTING DATA OUTLET LOCATED HIGH ON WALL (+7'-+10') TO BE REUSED FORNEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
2. NEW DATA OUTLET LOCATED HIGH ON WALL (18" BELOW CEILING) TO USEDFOR NEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
#
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
1
1
1
GENERAL NOTES:
1. ALL NEW DATA LOCATIONS ARE TO BE FED FROM THE MDF ROOM2. REFER TO KEY NOTES FOR IDENTIFICATION OF DATA OUTLETS THAT ARE
EXISTING TO REMAIN AND NEW.3. SCHEDULE AND COORDINATE ALL NOISE MAKING CONSTRUCTION ACTIVITIES
WITH OWNER PRIOR TO BEGINNING WORK.4. ALL WORK SHALL COMPLY WITH DISTINCTIVE FACILITY STANDARDS,
MEANSAND METHODS, AND SAFETY POLICY.5. CONTRACTOR SHALL COORDINATE THE CONDUIT ROUTES TO MDF ROOM IN
MOST EFFICIENT MANNER POSSIBLE AND SHALL TAKE CARE NOT TO EXCEED40% OF CONDUIT CAPACITY, IF APPLICABLE.
6. COORDINATE ANY REQUIRED WALL PENETRATIONS, FLOOR CUTTING OR DUCTCORING WITH DISTINCTIVE FACILITIES. PERFORM FLOOR SCANNING PRIOR TOCORING. INSTALL FIRESTOPPING FOR ALL PENETRATIONS THROUGH RATEDWALLS AND FLOORS. FIRESTOPPING SHALL MATCH THE RATING OF THEWALLS/FLOORS. FLOOR CUTTING AND PATCHING SHALL BE BY CONTRACTOR.
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cp_00.dw
g 02/13/2018 15:32.1 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC3-01
1ST FLOORTECHNOLOGY
PLAN
1/8"=1'-0"
1 ISSUED FOR BID 02/13/2018
1ST FLOOR NEW TECHNOLOGY PLAN
1/8"=1'-0"1
1/8" = 1'-0"
0 4 8 16
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652
1
GENERAL NOTES:
1. ALL NEW DATA LOCATIONS ARE TO BE FED FROM THE MDF ROOM2. REFER TO KEY NOTES FOR IDENTIFICATION OF DATA OUTLETS THAT ARE
EXISTING TO REMAIN AND NEW.3. SCHEDULE AND COORDINATE ALL NOISE MAKING CONSTRUCTION ACTIVITIES
WITH OWNER PRIOR TO BEGINNING WORK.4. ALL WORK SHALL COMPLY WITH DISTINCTIVE FACILITY STANDARDS,
MEANSAND METHODS, AND SAFETY POLICY.5. CONTRACTOR SHALL COORDINATE THE CONDUIT ROUTES TO MDF ROOM IN
MOST EFFICIENT MANNER POSSIBLE AND SHALL TAKE CARE NOT TO EXCEED40% OF CONDUIT CAPACITY, IF APPLICABLE.
6. COORDINATE ANY REQUIRED WALL PENETRATIONS, FLOOR CUTTING OR DUCTCORING WITH DISTINCTIVE FACILITIES. PERFORM FLOOR SCANNING PRIOR TOCORING. INSTALL FIRESTOPPING FOR ALL PENETRATIONS THROUGH RATEDWALLS AND FLOORS. FIRESTOPPING SHALL MATCH THE RATING OF THEWALLS/FLOORS. FLOOR CUTTING AND PATCHING SHALL BE BY CONTRACTOR.
KEY NOTES:
1. EXISTING DATA OUTLET LOCATED HIGH ON WALL (+7'-+10') TO BE REUSED FORNEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
2. NEW DATA OUTLET LOCATED HIGH ON WALL (18" BELOW CEILING) TO USEDFOR NEW WAP. REFER TO SHEET SC0-03, DETAIL #1.
#
2
2
2
2
2
2
2
2
1
1
1
1
1
1
1
1
1
DATENO.
SCALE
PRINCIPAL IN CHARGE
PROJECT MANAGER
PROJECT ENGINEER
PROJECT NUMBER
SHEET NUMBER
RECORD
DATE
T:\8130 S
C
alifornia\C
IC
S – W
rightw
ood C
am
pus\D
WG
S\C
AD
\S
CS
\cp_00.dw
g 02/13/2018 15:32.11 by: jw
eyrauch
Copyright © by Environmental Systems Design, Inc.2015
RR 53152
CRD
Environmental Systems Design, Inc.
175 West Jackson Blvd. Suite 1400
Chicago, Illinois 60604
312 372 1200 fax 312 372 1222
www.esdglobal.com
CHICAGO CHARTER
SCHOOL FOUNDATION
TECHNOLOGY UPGRADES
02/13/2018
SC3-02
2ND FLOORTECHNOLOGY
PLAN
1/8"=1'-0"
1 ISSUED FOR BID 02/13/2018
1/8" = 1'-0"
0 4 8 16
2ND FLOOR NEW TECHNOLOGY PLAN
1/8"=1'-0"1
C.I.C.S. WRIGHTWOOD SCHOOL
8130 SOUTH CALIFORNIA AVENUE
CHICAGO, ILLINOIS 60652