Warwick University MSc. Course 2015 Project Controls Types of Risks Project Development Procurement Project Delivery Insured Risks Political risks Contractors risks (C & P) Health and safety Employers Liability Insurance(EL I) Cost escalation/s cope creep Client risks (C & P) Cost and programme Contractors all risks/Projec t Insurance(CA R) Environmenta l Impacts Procedural risks(proces s challenges) Public Safety Public Liability(PL ) Reputational Tendering Environmenta Professional

Upload: emmeline-malone

Post on 17-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Types of Risks Project Development ProcurementProject DeliveryInsured Risks Political risksContractors risks (C & P) Health and safetyEmployers Liability

Warwick University MSc. Course 2015Project Controls

Types of Risks Project Development

Procurement Project Delivery Insured Risks

Political risks Contractors risks (C & P)

Health and safety Employers Liability Insurance(ELI)

Cost escalation/scope creep

Client risks (C & P) Cost and programme

Contractors all risks/Project Insurance(CAR)

Environmental Impacts

Procedural risks(process challenges)

Public Safety Public Liability(PL)

Reputational Risks Tendering costs Environmental Impacts

Professional Indemnity

Page 2: Types of Risks Project Development ProcurementProject DeliveryInsured Risks Political risksContractors risks (C & P) Health and safetyEmployers Liability

Warwick University MSc. Course 2015Project Controls

Contractors risk monitoring—Risk Premium

Risk identified Likelihood Impact Risk Premium

Subsidence event 20% £200,000 £40,000

Adverse ground conditions

10% £550,000 £55,000

TBM major breakdown

10% £1,000,000 £100,000

Environmental Pollution incident

5% £400,000 £20,000

Page 3: Types of Risks Project Development ProcurementProject DeliveryInsured Risks Political risksContractors risks (C & P) Health and safetyEmployers Liability

Warwick University MSc. Course 2015Project Controls

Risk Premium Monitoring

5-Nov-01 24-May-02 10-Dec-02 28-Jun-03 14-Jan-04 1-Aug-04 17-Feb-050

5,000,000

10,000,000

15,000,000

20,000,000

25,000,000 Risk Profile to 12/12/03Residual Risk

Risk Budget

Risk Monies Spent

Risk Remaining

Total No of Risks 358No. Closed out 239 No.