TVS RESi Dry & Concrete Floating Floor Systems University of Birmingham – Frankland Building, Edgbaston PROJECT INFORMATION One of the University of Birmingham’s most iconic buildings has now become a modern music hub thanks to extensive acoustic work by TVS Group. Client: Birmingham University Main Contractor: GTH Construction Acoustic Consultant: Hoare Lea Project Objective With its grade 11-listed Chamberlain Tower and red brick façade, the Frankland Building is one of the University of Birmingham’s most iconic buildings. But when it needed to be transformed into a new music hub it was time to call in the acoustic specialists, TVS Group. Approached by main contractor GTH Construction and working with acoustic consultants Hoare Lea, TVS was asked to help design and install over 1000m 2 of specialist acoustic flooring to meet the project’s specific requirements. TVS provided its well-proven TVS RESi Dry Floating Floor System throughout the ground and first floor areas covering multiple music rooms, workshops, rehearsal rooms and corridors. For the control room and recording studio it supplied and installed its TVS RESi Concrete Floating ©TVS Group

Upload: others

Post on 24-Aug-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TVS RESi Dry & Concrete Floating Floor Systems · 2020. 11. 2. · TVS RESi Dry & Concrete Floating Floor Systems University of Birmingham – Frankland Building, Edgbaston Construction

TVS RESi Dry & Concrete Floating Floor Systems University of Birmingham – Frankland Building, Edgbaston

PROJECT INFORMATION

One of the University of Birmingham’s most iconic buildings has now become a modern music hub thanks to extensive acoustic work by TVS Group.

Client: Birmingham University Main Contractor: GTH Construction Acoustic Consultant: Hoare Lea Project Objective With its grade 11-listed Chamberlain Tower and red brick façade, the Frankland Building is one of the University of Birmingham’s most iconic buildings. But when it needed to be transformed into a new music hub it was time to call in the acoustic specialists, TVS Group. Approached by main contractor GTH Construction and working with acoustic consultants Hoare Lea, TVS was asked to help design and install over 1000m2 of specialist acoustic flooring to meet the project’s specific requirements. TVS provided its well-proven TVS RESi Dry Floating Floor System throughout the ground and first floor areas covering multiple music rooms, workshops, rehearsal rooms and corridors. For the control room and recording studio it supplied and installed its TVS RESi Concrete Floating

©TVS Group

Page 2: TVS RESi Dry & Concrete Floating Floor Systems · 2020. 11. 2. · TVS RESi Dry & Concrete Floating Floor Systems University of Birmingham – Frankland Building, Edgbaston Construction

TVS RESi Dry & Concrete Floating Floor Systems University of Birmingham – Frankland Building, Edgbaston

PROJECT INFORMATION

Floor System. To prevent any noise transfer between rooms and corridors, an essential requirement of the project, it decoupled the walls. TVS also supplied the dry lining contractor with the company’s specialist sylomer wall insulation materials, including special acoustic washers for use beneath timber partitions to meet the natural frequency performance required. Product TVS RESi Dry Floating Floor System utilising: 20mm TVS Perimeter Isolation 25mm Sylomer SR450 Isolators 25mm Knauf Acoustic Roll 18mm Structural Plywood 20mm Cement Board

TVS RESi Concrete Floating Floor System utilising: 20mm TVS Perimeter Isolation 50mm Sylomer SR850 Isolators 50mm Knauf Acoustic Roll 18mm Structural Plywood DPM 100 Fibre Reinforced Concrete