tutorial b1.31 tb 538 - eprimydocs.epri.com/...schmidt-cigre_b1.31_tutorial.pdf · prior cigre tb...
TRANSCRIPT
Page 1 Cigré SCB1
RECOMMENDATIONS FOR TESTING OF SUPERCONDUCTING CABLES
Convener: D Lindsay (US)
Secretary: T Masuda (JP)
TUTORIAL B1.31 – TB 538
Page 2 Cigré SCB1
Technical Brochure Outline
EXECUTIVE SUMMARY 5
1.0 Introduction 6
1.1 Background 6
1.2 Experience with Superconducting Cables 7
1.3 Cryogenic System Issues 8
1.4 Future Work 9
1.5 Definitions 9
2.0 Tests for Engineering Information 12
2.1 AC loss 12
2.2 Heat invasion of cryostat 12
2.3 Electrical parameters 13
2.4 Short circuit tests (Fault current) 13
•
Page 3 Cigré SCB1
Technical Brochure Outline
3.0 Type Tests on Cable Systems 14
3.1 Range of Approval 14
3.2 Summary of Type Tests 14
3.3 Type tests on complete cable systems 15
3.4 Type Tests on Cable 19
3.5 Type Tests on Accessories 19
4.0 Factory / Routine Tests 20
4.1 AC Voltage test for cable 20
4.2 AC Voltage test for accessory 21
4.3 Ic measurement test 21
4.4 Vacuum leak test 22
4.5 Pressure test 22
Page 4 Cigré SCB1
Technical Brochure Outline
5.0 After Laying Tests 23
5.1 General 23
5.2 Tests in warm conditions 23
5.3 Tests in cold conditions 24
5.4 Additional tests after commissioning 28
6.0 Bibliography / References 30
Annex A Abbreviations 31
Annex B Critical Current (Ic) Measurement 32
B.1 Critical Current Measurement Test 32
Page 5 Cigré SCB1
Technical Brochure Outline
Annex C Cryogenic System Considerations 34
C.1 Introduction 34
C.2 Refrigeration 34
C.3 Functional Requirements 36
C.4 Specification Guide for End User 42
C.5 Safety 43
Page 6 Cigré SCB1
Prior Cigre TB on Superconducting Cables
1. TB 199, “Superconducting Cables. Impact on Network Structure and Control” (2002)
2. TB 229, “High Temperature Superconducting (HTS) Cable Systems” (2003)
3. TB 418, “Status of Development and Field Test Experience with High-Temperature Superconducting Power Equipment” (2010)
Page 7 Cigré SCB1
Scope of this Brochure
• Provides recommendations for Type Testing and After Laying tests for AC superconducting cables
• “High Temperature” superconductors only. Excluded are “low temperature” materials.
• Voltages up to 150 (170) kV
• Included as an Annex is information and guidelines related to cryogenic system performance, specifications and safety.
Page 8 Cigré SCB1
Key Definitions (1/2)
AC Loss For HTS cables, this term is used to describe the heat load generated by hysteretic losses associated with alternating current cycles in the superconducting materials. This heat must be accounted for in the thermal budget of the overall system design. HTS cables operating in direct current (DC) circuits do not generate AC losses.
Cold Dielectric (CD) A type of superconducting cable in which the dielectric material operates within the cryogenic environment.
Critical Current (Ic) The current in a superconducting material that results in an electric field of 1 µV/cm. For I>Ic the superconductor operates in a resistive (normal) state.
Page 9 Cigré SCB1
Key Definitions (2/2)
Cryostat An apparatus designed to contain and thermally insulate a cryogenic environment.
High Temperature Superconductor (HTS) Superconducting materials that achieve the superconducting state at temperatures greater than 20 K (-253ºC). Typically, HTS materials are used in superconducting power applications that can be cooled with liquid cryogens. Most common is liquid nitrogen at 77 K (-196 ºC) due to its availability, cost and dielectric properties.
Low Temperature Superconductors (LTS) Superconducting materials that achieve the superconducting state at temperatures below 20 K (-253ºC). Examples of common LTS materials are Niobium-Titanium and Niobium-Tin alloys.
Page 10 Cigré SCB1
Types of HTS Cables – Single Core Cable
• One electrical phase per cryostat
• HTS wires for phase conductor and concentric neutral of the cable
• May or may not include copper wires to shunt short-circuit currents to protect HTS wires
Page 11 Cigré SCB1
Types of HTS Cables – Three Core Cable
• Three single-phase cable cores inside a common cryostat.
• HTS wires for phase conductor and concentric neutral of the core
• May or may not include copper wires to shunt short-circuit currents to protect HTS wires
Page 12 Cigré SCB1
Types of HTS Cables – Triaxial Cable
• Three electrical phases are concentric on a common core inside a common cryostat
• Dielectric layers are phase-to-phase voltage rather than common phase-to-ground
• Cable screen/neutral may be copper or HTS wires
Page 13 Cigré SCB1
Global Experience – HTS Installed in Power Grids
Country &
Utility
In-service
Date Voltage
Designed
Power
Level
Length Design
DK 2001 24 kV 30 m
Warm
Dielectric,
Single Core*
CN, China
Southern
Power Grid
2004 35 kV 120 MVA 33.5 m
Warm
Dielectric,
Single Core*
USA,
National
Grid
2006 34.5 kV 48 MVA 350 m Three Core
USA, AEP 2006 13.2 kV 69 MVA 200 m Triaxial
USA, LIPA 2008 138 kV 574 MVA 600 m Single Core
KR, KEPCO 2011 22.9 kV 50 MVA 500 m Three Core
JP TEPCO 2012 66 kV 200 MVA 250 m Three Core
Page 14 Cigré SCB1
Pictures from Cigre TB418
Page 15 Cigré SCB1
Global Experience – HTS Tested in Laboratories and Industrial Applications
Country Dates Voltage Designed
Power Level Length Design
JP Super-
GM 2005 77 kV 133MVA 500 m Single Core
US -
Carrollton 2000 - 2006 12.4 kV 27 MVA 30 m Single Core
KR - KEPRI 2007 22 kV 48 MVA 100 m Three Core
MX 2007 23 kV 80 MVA 100 m Three Core
DE / ES 2008 10 kV 17 MVA 30 m Single Core
DE / ES 2010 24 kV 133 MVA 30 m Single Core
Russia 2010 20 kV 104 MVA 200 m Single Core
KR 2011 154 kV 1000 MVA 100 m Single Core
Page 16 Cigré SCB1
Section 2: Tests for Engineering Information
2.0 Tests for Engineering Information 12
2.1 AC loss 12
2.2 Heat invasion of cryostat 12
2.3 Electrical parameters 13
2.4 Short circuit tests (Fault current) 13
Page 17 Cigré SCB1
2.1 AC Loss
• Resistive losses in HTS wires due to hysteretic losses of AC cycles
• Information needed to properly size cryo system
• Measured from 0 to 1.2x rated current
• Methods:
o Electrical
o Calorimetric – Vaporization of Liquid Cryogen
o Calorimetric – Liquid Cryogen Mass Flow
• AC losses in each phase of a Triaxial design may be different. Therefore each phase should be measured. Ideally they should be measured simultaneously
Page 18 Cigré SCB1
2.2 Heat Invasion of Cryostat
• Heat leak into the cryostat is always present and represents significant load on cryogenic system
• Information used to properly size cryogenic system
• Methods:
o Calorimetric – Vaporization of Liquid Cryogen
o Calorimetric – Liquid Cryogen Mass Flow
Page 19 Cigré SCB1
2.3 Electrical Parameters
• The inductance, capacitance and tan delta will be tested on a cable sample of a 1 m sample (or longer). The tests will be performed at rated cryogenic temperature.
• Cables with a Triaxial design will have different electrical parameters in each phase. The electrical parameters will be measured for each phase.
• Tan delta and capacitance will be determined at Uo to determine the dielectric losses.
Page 20 Cigré SCB1
2.4 Short Circuit Tests
• Thermal management and mitigation during short circuit events is critical to system performance
• Fault Current Limiting Cables are in development
• Parameters to test:
o temperature and pressure reaction to limiting event (implying pressurized liquid nitrogen system)
o level and wave form of the limited current
o recovery time
Page 21 Cigré SCB1
Section 3: Type Tests on Cable Systems
3.0 Type Tests on Cable Systems 14
3.1 Range of Approval 14
3.2 Summary of Type Tests 14
3.3 Type tests on complete cable systems 15
3.4 Type Tests on Cable 19
3.5 Type Tests on Accessories 19
Page 22 Cigré SCB1
3.1 Range of Approval
• U, Uo and Um follow IEC 60183
• Type Tests are valid under the following conditions:
o The voltage group is not higher than that of the tested cable system (common Um)
o The nominal current is not larger than that of the tested cable
o The cable and the accessories have the same or similar constructions as that of the tested cable system(s)
Page 23 Cigré SCB1
3.2 Summary of Type Tests
• Min cable length = 10m
• Min cable length between accessories = 5m
• Accessories shall be installed after the bending test on the cable
• Cable and accessories shall be assembled in the manner specified by the manufacturer's instructions
Page 24 Cigré SCB1
3.3 Type Tests on Complete Cable Systems
Tests and Sequence of Tests
a) Bending test (See 3.3.3) on the cable and Ic measurement tests
b) Pressure test on the assembly (See 3.3.4)
c) Load cycle voltage test on the assembly (See 3.3.5)
d) AC voltage test on the assembly (See 3.3.6)
e) Lightning impulse voltage test followed by AC voltage test on the assembly (See 3.3.7)
f) Partial discharge tests on the assembly (See 3.3.8)
Page 25 Cigré SCB1
Bending Test
• Bending performed at ambient temperature
• 3 times reverse bend without axial rotation
• Cable core(s) shall be inside cryostat or similar corrugated tube
Page 26 Cigré SCB1
Load Cycle Voltage Test
• 20x load cycles
• 8 Hrs ON + 16 Hrs OFF
• Voltage == 2 Uo during whole test period
Page 27 Cigré SCB1
Voltage Tests
Note factor for
Triaxial Cables
Page 28 Cigré SCB1
Partial Discharge Test
NOTE: At the time of this writing, not all manufacturers have access to screened HV test rooms that also support the required cryogenic systems needed for HTS cables. Achieving 5 pC partial discharge sensitivity is difficult in these situations.
The test shall be performed in accordance with IEC 60840, the sensitivity being 5 pC or better. A test may be acceptable up to 10 pC, but samples of cable and accessory dielectric components must be tested to 5 pC sensitivity per section 3.4.2 and 3.5.1.
Page 29 Cigré SCB1
3.4 Type Tests on Cables
• Bending Test
o Bending per test required prior to system assembly
o Min 95% retention of critical current of cable
• Partial Discharge on Cable (if 10 pC on System Level PD)
o Cable sample tested to max 5 pC
o Same voltage, temperature & pressure as system level test
Page 30 Cigré SCB1
3.5 Type Tests on Accessories
• Partial Discharge on Accessory Components (if 10 pC on System Level PD)
o Cable sample tested to max 5 pC
o Same voltage, temperature & pressure as system level test
Page 31 Cigré SCB1
Section 4: Factory / Routine Tests
4.0 Factory / Routine Tests 20
4.1 AC Voltage test for cable 20
4.2 AC Voltage test for accessory 21
4.3 Ic measurement test 21
4.4 Vacuum leak test 22
4.5 Pressure test 22
Page 32 Cigré SCB1
4.1 AC Voltage Test for Cable
• One sample from each shipping reel shall be taken and subjected to the voltage test. In case several shipping reels are created by cutting cable length that was produced in the same manufacturing batch, the number of samples to be tested shall be such that one sample in each 500 meter section will be tested
• Min 1 meter sample
• 30 min at 2.5 Uo
• PD Test after withstand
o 1.75 Uo for MV
o 1.5 Uo for HV
Page 33 Cigré SCB1
4.2 AC Voltage Test for Accessories
The main insulation parts of each prefabricated accessory shall undergo voltage and partial discharge test at ambient temperature according to either 1) or 2) below :
1) by using a host accessory into which a component of an accessory is substituted for test;
2) by using a simulated accessory rig in which the electrical stress environment of a main insulation component is reproduced. The test voltage shall be selected to obtain electrical stresses at least the same as those on the components in a complete accessory when subjected to the test voltages specified in 4.1.
• 30 min at 2.5 Uo
• PD Test after withstand
o 1.75 Uo for MV
o 1.5 Uo for HV
Page 34 Cigré SCB1
4.3 Ic Measurement Test
• Critical current (Ic) of the cable cores in the test cable shall be measured for superconducting properties to check the damage of the superconducting wires due to bending. The measured Ic shall be more than 95 % of the designed Ic in consideration of LN2 temperature, magnetic field and so on. The measured Ic is defined as the current which generates 1 µV /cm voltage rise across the sample (See Annex B).
Page 35 Cigré SCB1
4.4 Vacuum Leak Test
• The vacuum leak test at ambient temperature shall be carried out in accordance with local specification for all finished cables and components where the vacuum seal is made at the factory
• The test cable or components shall be evacuated by a vacuum pump system. The leak rate of tracer gas to the vacuum area through the outer and inner wall shall be detected by a helium leak detector (mass spectrometer). The final leak rate for a given test cable or components should be recognized as the sum of all individual leaks measured
Page 36 Cigré SCB1
4.5 Pressure Test
• Pressure test shall be performed as a routine factory testing on specific components at request of customer or option of manufacturer. The test shall be carried out in accordance with local regulations for pressure equipment or engineering best practice
• Pressure test shall be carried out on components where pressurized gas or liquid must be contained. The components shall be made as a pressure vessel following local standards. The cable shall be pressurized with gas until the test pressure higher than predetermined value. The holding time shall follow to the local regulations
Page 37 Cigré SCB1
Section 5: After Laying Tests
5.0 After Laying Tests 23
5.1 General 23
5.2 Tests in warm conditions 23
5.3 Tests in cold conditions 24
5.4 Additional tests after commissioning 28
Page 38 Cigré SCB1
5.2 Tests in Warm Conditions
1. Vacuum Test
2. Pressure Test (According to Local Pressure Regulation Standards)
Page 39 Cigré SCB1
5.3 Tests in Cold Conditions
1. DC Cricital Current (Ic) Test
Page 40 Cigré SCB1
5.3 Tests in Cold Conditions
2. Voltage Test; options
a) AC Voltage (20-300 Hz)
b) DC Voltage
c) VLF
Page 41 Cigré SCB1
5.3 Tests in Cold Conditions
3. Verify System Operational Control Parameters
o The cable system shall be in stabilized conditions and the cooling system shall be operating with the nominal mass flow and nominal supply temperature.
o The integration of control signals with the utility Supervisory Control and Data Acquisition (SCADA) system shall be verified. The selection of signals to be verified shall be at the discretion of the customer. As a minimum requirement those signals relevant for the cable system trip logic must be verified.
o The total temperature increase and the pressure drop of the cooling medium shall be measured. The measured values shall be in good agreement with the design values.
4. Dielectric Soak Test (optional if voltage test performed)
Page 42 Cigré SCB1
5.4 Additional Tests after Commissioning
• Shielding Test
o applicable for single core cables only
o Measure of induced current from phase layer into neutral layer HTS wires
• A symmetrical current system shall be applied to the cable system by means of connecting the system to the grid. The current system shall be considered symmetric if the amplitude of each current of the three phases does not deviate by more than 5% from any of the other two phases current amplitudes and if the phase angle between the three currents is equal to 120°.
Page 43 Cigré SCB1
Annex B – Critical Current Measurements
V
I 0
V
I 0
V-I Curve, HTS Only V-I Curve, HTS + Cu Component
Page 44 Cigré SCB1
Annex C: Cryogenic System Considerations
Annex C Cryogenic System Considerations 34
C.1 Introduction 34
C.2 Refrigeration 34
C.3 Functional Requirements 36
C.4 Specification Guide for End User 42
C.5 Safety 43
Page 50 Cigré SCB1