tusla programme management (pmo) design and establishment · 2018-09-21 · 4 executive summary...
TRANSCRIPT
![Page 1: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/1.jpg)
1
Tusla Programme Management (PMO) Design and EstablishmentFergal Collins – 20th September 2018
![Page 2: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/2.jpg)
2
Contents
• Tusla Overview
• Executive Summary.
Choosing an operating model for the PMO.
− 3 PMO Models to choose from.
− PMO Model chosen.
− Key PMO Processes.
− PMO Responsibilities.
Positioning the PMO into the overall governance structure of Tusla.
How the PMO supports a governance structure for the Transformation Programme (TP).
Governance Framework for TP Delivery.
Timeline for implementation.
Effective governance needs the right PMO support.
Challenges.
![Page 3: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/3.jpg)
3
Tusla
• Established on 1st January 2014 – The Child and Family Agency – Tusla
• 4,200 staff and an annual budget of €750m
• Range of universal and targeted services
Child Protection and Welfare
Educational Welfare
Psychological Services
Alternative Care
Family and Locally-base community supports
Early years services
Domestic, sexual and gender-based violence services.
• Over 380 Offices nationwide
![Page 4: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/4.jpg)
4
Executive Summary
• The purpose of this presentation is to outline the main steps I took in the design and establishment of a Programme Management Office (PMO) for Tusla and the challenges I face in the context of the scale and size of the transformation plan underway in Tusla – the Child and Family Agency.
• This presentation outlines five key phases that needed to be gone through to establish, position and resource the PMO so that the PMO adds real value to Tusla.
Choosing an Operating Model for the PMO
Demonstrating how the PMO can support a governance structure for the Transformation Programme
Resourcing the PMO
Positioning the PMO into the overall governance structure of Tusla
1
2
3
4
Bringing in the correct IT solution for the PMO and Tusla5
![Page 5: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/5.jpg)
5
• A number of standardised PMO service models are available that organisations can adopt and customise to meet their own particular need. Each Model will generate value, depending on the scope of it’s authority and the type of interactions it has with projects.
• The models are1. A supportive PMO;
2. A Directive PMO; and
3. A Controlling PMO.
• Real world PMO models are generally not a pure adoption of the specific typical PMO models. Most organisations will develop a customised model by first selecting a core model and then tailoring that model to their particular circumstance by integrating a mix of other models determined by considerations such as the types and numbers of projects involved, the strategic importance of the project portfolio, the requirements of the organisation, and even resource availability.
• The most appropriate PMO model option can also change over time and with gains in PMO capability maturity.
Choosing an Operating Model for the PMO1
![Page 6: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/6.jpg)
6
Three PMO Models to choose from;
Level 1: Supportive PMO
- Support role for projects and programmes.
- Equips Tusla with methodologies, standards and tools to enable project managers to better deliver projects.
- A central information point of contact for project managers.
Level 2: Directive PMO
- Support and compliance role for projects and programmes.
- Ensures mandated methodology is used consistently.
- Projects and programmes are required to pass regular reviews by the controlling PMO
Level 3: Controlling PMO
- Managing role for projects and programmes.
- Responsible for alignment of project and programme work to corporate strategy.
- Establishes and ensures appropriate enterprise governance.
- Responsible for the resourcing for projects, including project manager assignments.
- Has direct responsibility for or influence over other lower-level PO’s.
1: Supportive
2: Controlling
3: Controlling
![Page 7: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/7.jpg)
7
PMO Model: Supportive PMO
I chose a Supportive PMO Model for Tusla for the following reasons;
1. The PMO was implementing a number of small / medium sized projects
2. Tusla did not have an established or standardised project management discipline.
3. Tusla had no PMO or only a recently established PMO and so had a low maturity level as a result.
4. The PMO initially had limited staffing capacity available and had limited resources with specialised project management skills and experience
5. The PMO had limited funding available to ensure effective project and programme management.
6. The PMO had an agreed methodology and a process agreed by work done by PWC and Prospectus
• Once this model is stable and mature then Tusla can consider further development of the PMO in future years.
![Page 8: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/8.jpg)
8
Initial Key PMO Processes: Scope of Initial PMO Support;
Process Scope of Initial PMO Support
Project Selection Record details of projects selected by the TP governance board including project scope, plan and deliverables.
Project Initiation Assist project managers with controlled project initiation
Project planning Assist project managers with project planning.
Risk Management Support project managers with risk identification and mitigation planning
Issue Management Support project managers with issue resolution planning
Status Reporting Facilitate regular project status reporting.
Quality Assurance Ensure appropriate quality assurance is in place.
Change Control Co-ordinate change control management process across the Department’s portfolio of projects.
![Page 9: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/9.jpg)
9
PMO Responsibilities: Scope of PMO Support;
Service Offering PMO Responsibilities
Coordinate and support the delivery of the Transformation Programme
Daily Operations• Responsible for the day-to-day running of the TP governance
framework.• Single point of contact for all TP related queries.• Organise the inputs to meetings.• Support the meeting chair during update meetings; and • Distribute the outputs of all TP meetings to appropriate stakeholders.Reporting• Responsible for collecting MI / status reports from programme leads
in each of the three clusters.• Provide MI / status reports to Senior Management Team (SMT).• Implement and maintain a central repository for all reports and other
essential project information to enable effective knowledge sharing.Shareholder Management• Support the SMT in the management of key stakeholder
management.
Manage reporting to external stakeholders as required
• Support the Management Team with the preparation of materials required for any ministerial reports.
• Manage the circulation of reports to external stakeholders.
Coordinate and support the delivery of Business Plans
• Prepare and support business planning process, guidelines and templates.
• Arrange meetings between the 3 clusters and the SMT to discuss.• Coordinate all collate the production of business plans.• Facilitate monthly business planning meetings.
![Page 10: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/10.jpg)
10
• The diagram below illustrates the organisation structure for the PMO
• Structurally the PMO reports to the Chief Executive (Appendix 1)
• The double blue reporting line from the Tusla project managers to the PMO indicates a peer relationship rather than the projects reporting to the PMO.
• Project managers remain responsible to the project sponsor, although this could potentially change as the PMO Project Management Maturity Levels improve.
Management Team
Project Steering Committee
Transformation Programme (TP) PMO
Tusla ProjectsProject 1
Chief Executive Officer
Establish strategy
objectives and priorities
Define and implement structures,
policies, standards and
procedures
Execute and manage projects
following governance framework
Project 2 Project 3
Programme Management Office
Joint Working
Provide guidance,
mitigate risk and resolve
issues
Monitor and report
performance progress,
costs, risks and issues
Tusla Business Planning
TP Support
Cluster 1 Cluster 2 Cluster 3
Project Status Reporting Line Mgt Reporting Peer Reporting Relationship
Positioning the PMO into the overall governance structure of Tusla2
![Page 11: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/11.jpg)
11
Clarifying the definition of Transformation:• I assessed the existing programmes across Tusla, and developed potential definitions for
Transformation to ensure the correct programmes and projects were included in the Transformation Programme.
• Confirmed definition and related principles on Transformation with senior stakeholders
Defining the governance framework enabled the MT accountabilities for the Transformation Programme to be fulfilled based on the principles from 1, ensuring: Formal, consistent roles and accountabilities definition via clear terms of reference
for each governance body. Benefits realisation ownership reflected in accountabilities and assurance roles Definition of the assurance and decisions owned by each governance body Efficient, productive processes and meetings that balance pace with rigour Control over the wider impact via communications and change management Measurement and continuous improvement of governance performance
1
2
How the PMO supports a governance structure for the Transformation Programme3
![Page 12: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/12.jpg)
12
• To address the responsibilities and activities outlined above, I believed that the PMO staff compliment needed to consist of 6 Programme Managers, a Business Process Improvement Manager, LEAN Specialist, Business Analyst, and admin staff
• The workload evolved quickly as project activity and oversight increased and as formal project management came into broader use across Tusla.
• One large ICT Programme – National Childcare Care Information System took on board a team of 28 staff including 3 Programme Managers, myself, and a number of PMO admin staff.
Resourcing the PMO4
![Page 13: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/13.jpg)
13
SMT Review/Approval
PMO Design and Establishment TimelineFeb 17 Mar 17 Apr 17 May 17 Jun 17 July 17 Aug 17 Sept 17 Oct 17 Nov 17 Dec 17 Jan 18
Management Team Meetings & Reporting Calendar
MT Mtg
Governance & Engagement for PMO Design and Establishment
Carry out PM Survey and P3MS and produce final report
TP Governance Framework Agreed
PMO Staffing in place
ICT Solution put in place
SMT Update/Approval
PMO Model Agreed
MT Mtg MT MtgMT MtgMT MtgMT MtgMT Mtg
SMT Review/Approval
Timeline for implementation
![Page 14: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/14.jpg)
14
Effective governance needs the right PMO support
• Effective governance depends on the right information being available at the right time to the right people The right PMO provides this support.
• Effective governance at the scale of the Transformation Programme required an integrated assessment of cumulative risk, organisational impact and delivery capacity across all programmes The right PMO provides this cumulative assessment
across the portfolio.
Governance
PMO
• Rigorous programme delivery at this scale generates significant amounts of information on scope, dependencies, risks, resources and milestones The right PMO provides integrated structures that give easy access to up-to-date
information to decision-makers.
Designing governance and PMO models together ensures there are no gaps and inconsistencies in how these principles are applied at each level.
Therefore, governance and PMO models are most effectively designed together
![Page 15: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/15.jpg)
15
Challenges starting off and now..
• The size of Tusla with over 4,088 employees (2016 Business Plan Table 4.2) spread over 380 offices. The PMO’s staff are based in Galway, Cork, Limerick, Navan and Dublin
• Priorities in the Transformation Programme needed to be altered following publication of Minister Zappone’s Statement of Strategy in 2017’s Business Plan.
• Resource constraints – it may not be possible to full resource all Programmes under the Transformation Programme – despite a €37m increase on 2016’s budget.
• An PMO ICT solution to support reporting and governance on the TP and all other PMO functions will be required and this will need financial support and will require a tendering process.
• Training on the new processes, governance structures and ICT solution were required and are ongoing.
![Page 16: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/16.jpg)
16
• An PMO ICT solution was required to support reporting and governance on the TP and all other PMO functions.
• A Business Case was produced and detailed specification document and required to be put through a Request For Quotation tendering process.
• Cora won this competition and we engaged Cora to build the system System was configured to match the PMO Methodology and Process User training and system administration training
• All Projects added to PV• System now used for Reporting into Senior Management Team Large Scale complex Change Management Systems
https://tusla.corasystems.com/Tusla_Live/manuallogon.aspx?Action=logout
Getting the right ICT solution to support the PMO5
![Page 17: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/17.jpg)
17
• Choose the correct type of PMO to fit the organisation
• Resource your PMO
• Carry out P3M3 and start Project Management Training
• Choose the Correct IT Project Management Solution
• Expansion of Project Vision Additional functionality Additional Licences New Platform
Summary
![Page 18: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/18.jpg)
18
Thank you – Any Questions??
![Page 19: Tusla Programme Management (PMO) Design and Establishment · 2018-09-21 · 4 Executive Summary •The purpose of this presentation is to outline the main steps I took in the design](https://reader030.vdocuments.us/reader030/viewer/2022040509/5e536b77f6fc066b0e676e87/html5/thumbnails/19.jpg)
19
Appendix 1: List of Abbreviations
• TP – Transformation Programme
• SMT – Senior Management Team
• PMO – Programme Management Office
• P3M3 - is a management maturity model looking across an organization at how it delivers its projects, programmes and portfolio(s).