turmeric processing

Upload: baldev-singh

Post on 14-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 TURMERIC Processing

    1/13

    295. PROFILE ON PROCESSING OF TURMERIC

  • 7/30/2019 TURMERIC Processing

    2/13

    2

    TABLE OF CONTENTS

    PAGE

    I. SUMMARY 295 - 3

    II. PRODUCT DESCRIPTION & APPLICATION 295 - 3

    III. MARKET STUDY AND PLANT CAPACITY 295 - 3

    A. MARKET STUDY 295 - 3

    B. PLANT CAPACITY & PRODUCTION PROGRAMME 295 - 6

    IV. RAW MATERIALS AND INPUTS 295 - 7

    A. RAW & AUXILIARY MATERIALS 295 - 7

    B. UTILITIES 295 - 7

    V. TECHNOLOGY & ENGINEERING 295 - 8

    A. TECHNOLOGY 295 - 8

    B. ENGINEERING 295 - 8

    VI. MANPOWER & TRAINING REQUIREMENT 295 - 9

    A. MANPOWER REQUIREMENT 295 - 9

    B. TRAINING REQUIREMENT 295 - 9

    VII. FINANCIAL ANLYSIS 295 - 10

    A. TOTAL INITIAL INVESTMENT COST 295 - 11

    B. PRODUCTION COST 295 - 12

    C. FINANCIAL EVALUATION 295 - 13

    D. ECONOMIC BENEFITS 295 - 13

  • 7/30/2019 TURMERIC Processing

    3/13

    3

    I. SUMMARY

    This profile envisages the establishment of a plant for the processing of turmeric

    with a capacity of 150 tonnes per annum.

    The present demand for the proposed product is estimated at 460 tonnes per annum. The

    demand is expected to reach at 828 tonnes by the year 2022.

    The plant will create employment opportunities for 19 persons.

    The total investment requirement is estimated at about Birr 2.86 million, out of which Birr1.1 million is required for plant and machinery.

    The project is financially viable with an internal rate of return (IRR) of 21 % and a net

    present value (NPV) of Birr 1.41 million discounted at 8.5%.

    II. PRODUCT DESCRIPTION AND APPLICATION

    Turmeric is an East Indian perennial herb "Curcuma longa" with a large aromatic deep

    yellow rhizome. Processed turmeric is the cleaned, boiled, sun-dried, and usually pulveized

    rhizome of the turmeric plant used as a colouring agent, a condiment (as in pickling and in

    curry powder), or a stimulant.

    III. MARKET STUDY AND PLANT CAPACITY

    A. MARKET STUDY

    1. Past Supply and Present Demand

    The country's requirement for turmeric is essentially met through domestic production.

    However, data on domestic production of the product is not readily available. Therefore, the

  • 7/30/2019 TURMERIC Processing

    4/13

    4

    Revised Report on the 1995/96 Household Income, Consumption and Expenditure Survey is

    analyzed in estimating the demand for turmeric. Table 3.1 depicts the average amount of

    turmeric consumed by different expenditure groups in urban and rural areas according to the

    survey finding.

    Table 3.1

    DOMESTIC CONSUMPTION OF TURMERIC

    Number of Average Total

    Income Individuals Annual Annual

    Group in the Consumption Consumption

    Group (gram) (kg)

    < 600 17,253 - -

    600 - 999 125,904 10 1,259

    1000-1399 432,547 7 3,028

    1400-1999 580,104 18 10,442

    2000-2599 4,217,465 21 88,567

    2600-3399 649,8555 17 110,475

    3400-4199 784,4772 25 196,1194200-5399 1,088 ,5614 26 283,026

    5400-6599 800,7978 32 256,255

    6600-8999 881,7091 41 361,501

    9000-12599 511,4961 44 225,058

    12600-16199 1,765,555 47 82,981

    16200-19999 673,706 68 45,812

    > 20000 972,722 57 55,445

    Total 55,954,227 1719,969

    Source: CSA, Revised Report on the 1995/96 Household Income Consumption and

    Expenditure Survey, 2001.

  • 7/30/2019 TURMERIC Processing

    5/13

    5

    As can be seen from Table 3.1, the total consumption requirement of households for turmeric

    is 1,719,969 kg per annum. Given a total population of 55,954,227 at the time the survey was

    conducted, the per capita consumption of turmeric is computed to be 0.03 kg. Assuming the

    regional market constitutes the viable market for the product, the present demand of

    households for turmeric is estimated at 460 tons using the total population of the region for

    2007.

    2. Projected Demand

    The consumption of processed turmeric is mainly associated with the urban population.

    Accordingly, a growth rate of 4% that corresponds to the rate of urbanization in the country

    is considered in projecting the demand for turmeric. The projected demand for the product isshown in Table 3.2.

    Table 3.2

    PROJECTED DEMAND FOR TURMERIC (TONNES)

    Year Projected

    Demand

    2007 460.00

    2008 478.402009 497.54

    2010 517.44

    2011 538.13

    2012 559.66

    2013 582.05

    2014 605.33

    2015 629.54

    2016 654.72

    2017 680.91

    2018 708.152019 736.47

    2020 765.93

    2021 796.57

    2022 828.43

  • 7/30/2019 TURMERIC Processing

    6/13

    6

    3. Pricing and Distribution

    The retail price of turmeric is Birr 25 per kg. Allowing margin for wholesale and retail a

    price of Birr 20 per kg is recommended for the product of the envisaged plant.

    The product can get its market outlet through the existing wholesale and retail network,

    which includes department stores, merchandise shops and supermarkets.

    B. PLANT CAPACITY AND PRODUCTION PROGRAM

    1. Plant Capacity

    The annual production capacity of the project is 150 tonnes of processed turmeric based on

    300 working days and single shift ( 8 hours) per day.

    2. Production Program

    The production program is indicated in Table 3.2. At the initial stages of production, the

    project may require some years to penetrate the market. Therefore, in the first and second

    year of production, the capacity utilization rate will be 70 and 90%, respectively. In the third

    year and thereafter, full capacity production shall be attained.

    Table 1

    PRODUCTION PROGRAM

    Description Production Year

    1 2 3-10

    1 Clove powder (ton) 105 135 150

    2 Capacity utilization rate (%) 70 90 100

  • 7/30/2019 TURMERIC Processing

    7/13

    7

    IV. RAW MATERIAL AND INPUTS

    A. RAW AND AUXILIARY MATERIALS

    The annual raw and auxiliary materials requirement and cost are indicated in Table 4.1.

    Table 4.1

    RAW AND AUXILIARY MATERIAL REQUIREMENT & COST

    S.No Material Unit Qty Cost (000 Birr)

    1 Turmeric Ton 165 3,300

    2 Packing material kg 4500 112.5Total 3,412.5

    B. UTILITY

    Water and electricity are the utilities of the project. The annual utility requirement and its

    cost are shown in Table 3.

    Table 3

    ANNUAL UTILITY REQUIREMENT & COST

    S.No Utility Unit Qty Cost (000 Birr)

    1 Electricity kWh 120,000 56.88

    2 Water M3

    1,000 10

    Total 66.88

  • 7/30/2019 TURMERIC Processing

    8/13

    8

    V. TECHNOLOGY AND ENGINEERING

    A. TECHNOLOGY

    1. Process Description

    Turmeric seeds will first be cleaned and washed manually and then sun dried. Solar drying

    is the cheapest and popular mode of drying agricultural products.

    The dry turmeric seeds enters to the milling unit in which milling and pulverization

    operations are carried out.

    The power is then sifted and tested according to standard procedures depending on the target

    market. It is then packed for sales.

    2. Source of Technology

    Turmeric processing plant can be acquired from different suppliers. The following company

    could be requested for the offer.

    Food and Biotech Engineers

    Khwaja, Faridabad, Haryana-121003, India

    Phone +91-129-2510924

    B. ENGINEERING

    1. Machinery & Equipment

    The list of machinery and equipment required for the project is indicated in Table 5.1. The

    total cost of machinery and equipment is estimated at Birr 1,100,000 of which Birr 916,700 is

    in foreign currency.

  • 7/30/2019 TURMERIC Processing

    9/13

    9

    Table 5.1

    LIST OF MACHINERY & EQUIPMENT

    S.No Description Qty

    1 Chamber solar drier 1

    2 Vibratory screen 1

    3 Disintegrator 1

    4 Micropulverizer 1

    5 Sifting machine 1

    6 Weighing and packing unit 1 unit

    7 Miscellaneous equipments like

    handling bins, storage vessels, Etc.

    Lump

    sum

    2. Land, Building and Civil work

    The total land requirement of the project is estimated at 1000 m2

    of which the built-up area is

    300 m2. Therefore, the cost of building is Birr 450,000. The lease value of land is about Birr

    80,000 at a rate of 1 Birr per m2

    per annum for 80 years.

    3. Location and Site

    Yadeta town is the best location for the proposed project for its proximity to major raw

    material sources.

    VI. MANPOWER AND TRAINING REQUIREMENT

    A. MANPOWER

    Table 6.1 shows the list and cost of manpower. The total annual labour cost is estimated at

    Birr 201,000.

  • 7/30/2019 TURMERIC Processing

    10/13

    10

    Table 6.1

    MANPOWER REQUIREMENT & COST

    S.No Manpower No. Monthly

    Salary (Birr)

    Annual Salary

    (Birr)

    1 General manager 1 3,000 36,000

    2 Secretary 1 700 8,400

    3 Production head 1 2,000 24,000

    4 Accountant 1 2,000 24,000

    5 Operator 3 2,100 25,200

    6 Labourers 10 3,000 36,000

    7 Guards 2 600 7,200

    Sub total 19 13,400 160,800

    Benefit

    (25% Basic salary)

    3,350 40,200

    Total 16,750 201,000

    B. TRAINING

    On-the-job training shall be carried out by the experts of machinery suppliers and its cost is

    estimated at Birr 15,000.

    VII. FINANCIAL ANALYSIS

    The financial analysis of the turmeric processing project is based on the data presented in

    the previous chapters and the following assumptions:-

    Construction period 1 year

    Source of finance 30 % equity

    70 % loan

    Tax holidays 3 years

    Bank interest 8%

  • 7/30/2019 TURMERIC Processing

    11/13

    11

    Discount cash flow 8.5%

    Accounts receivable 30 days

    Raw material local 30days

    Work in progress 2 days

    Finished products 30 days

    Cash in hand 5 days

    Accounts payable 30 days

    A. TOTAL INITIAL INVESTMENT COST

    The total investment cost of the project including working capital is estimated at Birr 2.86

    million, of which 53 per cent will be required in foreign currency.

    The major breakdown of the total initial investment cost is shown in Table 7.1.

    Table 7.1

    INITIAL INVESTMENT COST

    Sr. Total Cost

    No. Cost Items (000 Birr)

    1 Land lease value 80.0

    2 Building and Civil Work 450.0

    3 Plant Machinery and Equipment 1,100.0

    4 Office Furniture and Equipment 100.0

    5 Vehicle 200.0

    6 Pre-production Expenditure* 290.4

    7 Working Capital 644.9

    Total Investment cost 2,865.3Foreign Share 53

    * N.B Pre-production expenditure includes interest during construction ( Birr 140.37 thousand )

    training (Birr 15 thousand ) and Birr 135 thousand costs of registration, licensing and formation

    of the company including legal fees, commissioning expenses, etc.

  • 7/30/2019 TURMERIC Processing

    12/13

    12

    B. PRODUCTION COST

    The annual production cost at full operation capacity is estimated at Birr 4.07 million (see

    Table 7.2). The material and utility cost accounts for 85.45 per cent, while repair and

    maintenance take 1.84 per cent of the production cost.

    Table 7.2

    ANNUAL PRODUCTION COST AT FULL CAPACITY ('000 BIRR)

    Items Cost %

    Raw Material and Inputs 3,412.50 83.81

    Utilities 66.8 1.64

    Maintenance and repair 75 1.84

    Labour direct 96.48 2.37

    Factory overheads 32.16 0.79

    Administration Costs 64.32 1.58

    Total Operating Costs 3,747.26 92.03

    Depreciation 212.5 5.22

    Cost of Finance 111.98 2.75Total Production Cost 4,071.74 100

    C. FINANCIAL EVALUATION

    1. Profitability

    According to the projected income statement, the project will start generating profit in the

    first year of operation. Important ratios such as profit to total sales, net profit to equity

    (Return on equity) and net profit plus interest on total investment (return on total

    investment) show an increasing trend during the life-time of the project.

    The income statement and the other indicators of profitability show that the project is viable.

  • 7/30/2019 TURMERIC Processing

    13/13

    13

    2. Break-even Analysis

    The break-even point of the project including cost of finance when it starts to operate at full

    capacity ( year 3) is estimated by using income statement projection.

    BE = Fixed Cost = 36 %

    Sales Variable Cost

    3. Pay Back Period

    The investment cost and income statement projection are used to project the pay-back period.The projects initial investment will be fully recovered within 5 years.

    4. Internal Rate of Return and Net Present Value

    Based on the cash flow statement, the calculated IRR of the project is 21 % and the net

    present value at 8.5% discount rate is Birr 1.41 million.

    D. ECONOMIC BENEFITS

    The project can create employment for 19 persons. In addition to supply of the domestic

    needs, the project will generate Birr 1.12 million in terms of tax revenue. The establishment

    of such factory will have a foreign exchange saving effect to the country by substituting the

    current imports.