tunnels and a ten years

Upload: acu-messina

Post on 14-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 tunnels and a ten years

    1/6

    4

    MINING &CONSTRUCTION

    TUNNELSAND A TEN-YEAR

    The Atlas Copco Rocket Boomer WL3 C drill

    rig (above and top right) at work on the Torres

    Finale road scheme in Sicily.

    SPO

    TLIGHT

    ON ITALY

    M&C

  • 7/29/2019 tunnels and a ten years

    2/6

    MINING &CONSTRUCTION

    , TALCWAITAs Italy goes ahead with nationwide construction and

    mining projects, a number of worksites have one

    important similarity the same project partner.

    M&C reports fromthree of the most interesting loca-

    tions. First, a series of tunnels to complete a major

    motorway scheme in Sicily. Second, an unusual exam-

    ple of small-scale mining in the Alps. And last, a long-

    awaited road bypass to skirt the countrys largest lake.

    5

    All systems go in Italy: Excellent results are being achieved at these

    three worksites just a few examples of many around the country.

    PalermoPalermo

    Brusada-Ponticelli mineBrusada-Ponticelli mine

    MessinaMessina

    Mori bypassMori bypass

    Lake GardaLake Garda

  • 7/29/2019 tunnels and a ten years

    3/6

    6

    TThe words Torre Finale, Piano Par-

    adiso and Cozzo Mineria have an

    exotic ring. Something to do with

    Italian opera, perhaps? Not quite. They

    are the elegant names of tunnels being

    constructed along the Sicilian coastline.

    The 250 km coastline motorway

    between Palermo and the city of Messina

    has been under construction from bothends for the past 10 years.

    For most of the way, the sea is in sight

    and the views are stunning. And where

    the motorway is forced inland to avoid

    coastal towns, the elevation increases dra-

    matically and the highway becomes a

    series of tunnels and spectacular viaducts.

    Italian tunnelling contractors excel in

    this kind of situation and those working

    for Consorzio per le Autostrade Siciliane

    (CAS), the consortium of contractors at

    work here, are no exception. Some 26

    km of twin tunnels are complete, exceptthe last missing link a 10.7 km tunnel

    which is now being constructed.

    Access to the two Torre Finale tun-

    nels (1.02 km and1.07 km long) is via a

    steep, unpaved construction road. The

    portals have been established with a 12

    m width and 40 m separation, and the

    hillside around them is secured using

    grouted cable bolts at 2 m intervals.

    The first 54 m in each drive required

    umbrella drilling, where inserted steel

    pipes were pressure-grouted in position.

    The fullface section is 98 sqm and this

    achieved by driving a top heading in

    advance and following on with bench or

    trench, according to rock conditions. The

    geology consists mainly of flysch.

    Advanced drill rig

    An advanced drill rig, an Atlas Copco

    Rocket Boomer WL3 C three-boom unit,

    is being used by contractor C.E.C Gitto,

    to handle all the drilling. During M&Cs

    visit, the rig was drilling 4.5 m-long

    blast holes, but is equipped for up to

    5.9m. The face is lightly shotcreted

    before drilling, and only gelatine explo-

    sives are used. The advance rate is some

    50-60m per week.

    In addition to Atlas Copcos Rig Con-

    trol System (RCS), the rig features inter-

    MINING &CONSTRUCTION

    Torre Finale

    Building t he missinglink on Sicily s

    beaut if ul coast l ine

    Site Manager Monaco Sebastiano (right) with

    Atlas Copco Italias Ivan Sinibaldi: We

    dont expect problems and we dont get them.

    Francesco Ranazzo, Site Man-

    ager: The WL3 C rig has ex-

    ceeded our expectations.

    Operator Filippo Parisi: The WL3 C seemed

    an amazing machine, but after only a week, I

    found it pretty simple to drive.

    Making headway:

    The Rocket Boomer

    WL3 C drills 50, 70

    or 90 holes in the top

    heading depending

    on the friability of

    the rock.

    SPO

    TLIGHT

    ON ITALY

    M&C

  • 7/29/2019 tunnels and a ten years

    4/6

    7

    OOne of the worlds most interesting

    small mines lies at an altitude of

    between 1,165 and 1,500 m in the

    Italian Alps, north of Sondrio and just

    five km from the Swiss border.

    The Brusada-Ponticelli mine is

    owned by IMI-Fabi, which owns the

    rights to a 2,400 hectare sub-vertical de-posit of industrial talc. With a mining

    width of 1565 m and an average of 25

    m, the mineralised section at the mine is

    1.2 km long over a vertical distance of

    335 m and with an 800-metre cover.

    IMI-Fabi, which recently achieved an

    ISO 14000 rating, produces 150,000

    tonnes per year of which some 40,000 is

    waste and reserves are plentiful.

    Extension drilling

    The mine operates a room and pillar sys-

    tem with 12 m-wide pillars and 6 m widerooms. After driving two 30 sqm access

    drifts at top and bottom of the future

    room, excavation starts with 25 m-high x

    2 m-wide slots from the far end of the

    top heading down to the lower level. Talc

    is blasted in 22.8 m retreats.

    An Atlas Copco Diamec 252 drill rig

    is used for exploration drilling while an

    Atlas Copco Boomer H 251 mounted

    with a single COP 1238 drifter has been

    working on development. These have

    been joined by a Rocket Boomer M2 Ctwin-boom drill rig equipped with the

    COP 1838 rock drill. The rig uses

    MINING &CONSTRUCTION

    Ioris Manfroi, MD of IMI-Fabi:Every

    aspect of our operation will improve.

    Brusada-Ponticelli

    Winning

    t alc f romt he A lps

    w

    active operator control panels, full

    colour display of the computer-based

    drilling system, auto-collaring and anti-

    jamming protection.

    The rock drills, COP 1838ME, have

    an impact power of 20 kW and an impact

    rate of 60 Hz with double reflex dampen-

    ing. The advanced boom control system

    (ABC Total) supports and guides the

    operator in drill hole positioning and

    alignment to reduce costly overbreak.The rig uses Secoroc Speedrods, T38-

    R32, Hex35, length 5530mm.

    Before the rig was started up, there

    was some concern about it being located

    far from the Atlas Copco Service Centre.

    But a combination of the well-trained rig

    operators, the customers efficient ser-

    vice team and the rigs reliability re-

    duced problems to a minimum most of

    which were easily solved over the phone.

    Poor rock

    At the Piano Paradiso tunnels (2 x 2.88

    km) the twin tubes are being umbrella

    drilled throughout their entire length.

    This is due to extremely poor ground

    conditions in the area. Each 12 m-deep x

    34-hole umbrella is reinforced with ce-

    ment pressure-grouted steel tubes and,

    due to the plasticity of the strata, it is

    necessary to arch the invert and install a

    reinforced concrete lining.

    Access at the Messina end of the tun-

    nels is so difficult that the portals have to

    be established at different elevations. A

    large flood culvert is being installed

    across the front of the portals to provideadequate access for tunnelling.

    The mudstone and soil strata has poor

    strength characteristics and tunnelling

    will most likely be as difficult as it is

    proving to be from the Palermo end.

    The two top headings at the Cozzo

    Mineria tunnel site (2 x 2.48 km) are being

    developed with steel arch and concrete

    support throughout. The softer rock in one

    heading is being broken using a hydraulic

    hammer while a Boomer H174 drill rig is

    at work in the other heading drilling blast

    holes and bolting holes when needed.

    There are multiple faults and disloca-

    tions in the strata at the face, and

    advance is proving a difficult task.

    Dramatic and

    difficult ter-

    rain:The tow-

    ering road

    bridge and

    Castelbuono

    tunnels.

  • 7/29/2019 tunnels and a ten years

    5/6

    8

    The Mori Bypass

    All syst emsgo af t er adecade ofdelay

    AAslowdown in the Italian construc-

    tion industry in the early 1990s

    was followed by a lack of funding

    and resulted in long delays for the

    Brenner Autostrada project.

    So long in fact that the planned MoriBypass at the northern end of Garda,

    Italys largest lake, has had to wait 10

    years before a start could be made on re-

    placing a part of the SS 240 motorway.

    The project involves an intersection

    with the motorway, a bridge which cross-

    es it, a river and a railway, and twin tun-

    nels 2.2 km-long with 90 m2 tubes to be

    equipped with two lanes each.

    Eighty per cent of the tunnels is being

    driven in sedimentary rock and 20% in

    volcanic rock. The contractor, Cari-

    boniStrade e Gallerie, started construc-

    tion work in October, 1999 and is using

    two Atlas Copco drill rigs a Robot

    Boomer 353E unit and a recently deliv-

    MINING &CONSTRUCTION

    Spreading its wings: The new Rocket Boomer WL3 C drilling rig at the mouth of the

    twin-tunnel Mori bypass project, fully-computerised for contractor Cariboni.

    ered Rocket Boomer WL3 C, fully com-

    puterised and equipped with advanced

    boom control (ABC Total). Secoroc

    Speedrods T38-R32, Hex 35, length

    6,100mm are also used.

    High pressure

    Before the portals could be established,

    vertical micropiles were constructed

    across the entrances and tied back with

    25 metre, 60 tonnes ground anchors and

    beams. The anchors were grouted under

    high pressure with a cement mix, which

    hardened for 10 days before being

    attached to steel cross beams and pre-

    stressed in sections.

    ate support and safety and some 25,000

    bolts have been installed so far.

    A mixed fleet of loaders, including an

    Atlas Copco Wagner ST 3.5 Scooptram,

    has been strengthened by a new ST 1010with a 10-ton bucket. A Wagner MT 413

    14-ton dump truck complements the

    Penetration rate has been increased

    from 1.20 m/min to 1.70m /min and pro-

    duction increased from 80 dm/hour to 175

    dm/hour. Standard Swellex 2.7 and 3.2 m

    rockbolts are in widespread use and themine was one of the first in Italy to adopt

    Swellex for its quick installation, immedi-

    Secoroc Speedrods, T38-R32, Hex 35,

    length 4,300 mm. Scaling is carried out

    by an excavator equipped with an Atlas

    Copco SBC 255 hydraulic hammer.

    Ioris Manfroi, Managing Director of

    the mine says: We decided to go for this

    new type of rig and it has been a great

    success. I am more than satisfied. In the

    M2 C we have purchased capability thatwe now have to adapt to. Every aspect of

    our operation will improve.

    w

    Caribonis Renato Lusi, Tunnel Manager

    (left) and Luigi Cimenti, Drillmaster:

    We are very satisfied with the new rig.

    SPO

    TLIGHT

    ON ITALY

    M&C

  • 7/29/2019 tunnels and a ten years

    6/6

    M & C 3 q0 1

    Horizontal holes were then drilled

    around the arches, into which steel tubes

    were placed and pressure-grouted into

    position to form micropile umbrellas.

    Four umbrellas were needed in each tube

    to reach stable ground. When the groundbecame rock, blastholes and minimum

    explosive shook it up enough for hy-

    draulic breaker excavation. The WL3 C is

    equipped with the Atlas Copco rig con-trol system (RCS) and features operator

    control panels with full colour display of

    the computer-based drilling system.

    Automatic functions provide highspeed drilling and outstanding drill steel

    economy with the COP 1838 rock drill,

    which achieves the maximum penetration

    possible in any rock and maintains a high

    hole quality with negligible deviation,

    allowing easy insertion of explosives.

    There is immediate identification of

    faulty components and transfer of data

    between office and drill rig by PC card.

    Control system

    ABC, the advanced boom control sys-

    tem, guides the operator in drill holepositioning and alignment, helping to

    reduce overbreak to a minimum.

    The rig has also been used in semi-

    automatic mode for face drilling while

    its centre boom has been involved in

    rockbolt drilling. Radial boltholes are

    drilled at 1.5 m separation for 4 m-long

    anchored and grouted bolts, followed by

    steel arches at 1 m intervals with mesh

    steel-fibre reinforced shotcrete.

    loader fleet on long hauls. Virtually all the

    mines loading machines are remote con-

    trolled and can work in open stopes with-

    out risk to drivers.

    A tight team consisting of a director,

    shift boss, maintenance fitter and 15miners work in shifts from 6am-10pm.

    And a planned maintenance contract will

    cover both the Rocket Boomer M2 C rig

    and the Wagner ST1010 loader the firstcontract of its kind in an Italian mine.

    Scooptram in thesnow: The ST 1010

    comes to the surface

    of the talc mine for a

    change of shift. In the

    foreground, visiting

    the site is Antonio

    Belcastro, General

    Manager, Atlas

    Copco Italy.