24 TUNNELLING JOURNAL State of the art segments: SINCE BAZALGETTE’S revolutionary sewer network was built in the 1800s London’s population has quadrupled. The system now operates at double its designed capacity and struggles to cope if as little as 2mm of rainfall occurs. This means that every year around 39 million tonnes of untreated sewage is discharged, via 57 combined sewer overflows (CSOs), into the Lee and Thames rivers. These overflows have a substantial impact on river ecology and pose a significant health risk to those living and working on the rivers. Tideway and the Lee Tunnel In order to combat the problem, the US$1bn (£635M) Lee Tunnel is the first of two major tunnel projects being undertaken by client Thames Water as part of the Thames Tideway scheme, which also includes the US$5.9bn (£3.6bn) Thames Tunnel. Once completed, in 2014, the Lee Tunnel will divert CSOs away from London’s largest outfall at Abbey Mills, in Stratford, and convey them to the upgraded Beckton Sewage Works for treatment. This will eliminate 40% of the current overflows into the Thames via its tributary the River Lee. Morgan Sindall/VINCI Construction Grands Projets/Bachy Soletanche (MVB) Joint Venture was awarded the US$652M (£400M) design- build contract for the tunnel and its four associated large diameter shafts in January 2010. Come early next year, the JV will launch an 8.8m diameter Herrenknecht Mixshield from the 82m deep Beckton Drive Shaft on a 6.8km westward drive to a reception shaft located at the Abbey Mills pumping station. Design-build proposals for the project were based on a preliminary design completed by Aecom and specifications drawn up on behalf of Thames Water by Tideway’s Programme Manager, the CH2M Hill-Halcrow partnership. Running at depths of up to 75m, within the Upper Chalk aquifer, the Lee Tunnel will be London’s deepest to date and a principle challenge on the project will be dealing with anticipated water pressures of up to 8 bar. Taking into account the loadings, pressure and long-term durability requirements that will be placed on the tunnel during its life, one of the UK’s most state-of-the-art precast segmental linings has been specified for the project. Designed by MVB’s engineer, Morgan Sindall Underground Professional Services (UnPS), the 1.7m wide, 350mm thick, seven segment + key universal tapered ring is currently under production at Morgan Sindall’s permanent precast factory, at Ridham Dock, in Kent. A number of emerging technologies – such as steel fibre reinforcement, cast-in EPDM gaskets, 3D laser checking of cast segments Precast segment manufacture for London’s deepest ever tunnel, Thames Water’s 6.8km long, 7.8m diameter, Lee Tunnel sewer project, is now up to full speed. Amanda Foley recently visited Morgan Sindall’s production facility, at Ridham Dock, in Kent, to find out more about this state-of-the-art tunnel lining VMT’s 3-D laser tracker system is used to check segments are within tolerance Lining the Lee Tunnel

Upload: thomas1959

Post on 11-Mar-2015

188 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Tunnelling Journal - Lee Tunnel - State of the Art Segments

24 TUNNELLING JOURNAL

State of the art segments:

SINCE BAZALGETTE’S revolutionary sewernetwork was built in the 1800s London’spopulation has quadrupled. The system nowoperates at double its designed capacity andstruggles to cope if as little as 2mm of rainfalloccurs. This means that every year around 39million tonnes of untreated sewage isdischarged, via 57 combined sewer overflows(CSOs), into the Lee and Thames rivers. Theseoverflows have a substantial impact on riverecology and pose a significant health risk tothose living and working on the rivers.

Tideway and the Lee TunnelIn order to combat the problem, the US$1bn(£635M) Lee Tunnel is the first of two majortunnel projects being undertaken by clientThames Water as part of the Thames Tidewayscheme, which also includes the US$5.9bn(£3.6bn) Thames Tunnel. Once completed, in2014, the Lee Tunnel will divert CSOs awayfrom London’s largest outfall at Abbey Mills, inStratford, and convey them to the upgradedBeckton Sewage Works for treatment. This willeliminate 40% of the current overflows intothe Thames via its tributary the River Lee.

Morgan Sindall/VINCI Construction GrandsProjets/Bachy Soletanche (MVB) Joint Venturewas awarded the US$652M (£400M) design-build contract for the tunnel and its four

associated large diameter shafts in January2010. Come early next year, the JV will launchan 8.8m diameter Herrenknecht Mixshieldfrom the 82m deep Beckton Drive Shaft on a6.8km westward drive to a reception shaftlocated at the Abbey Mills pumping station.

Design-build proposals for the project werebased on a preliminary design completed byAecom and specifications drawn up on behalfof Thames Water by Tideway’s ProgrammeManager, the CH2M Hill-Halcrow partnership.

Running at depths of up to 75m, within theUpper Chalk aquifer, the Lee Tunnel will beLondon’s deepest to date and a principlechallenge on the project will be dealing withanticipated water pressures of up to 8 bar.Taking into account the loadings, pressure andlong-term durability requirements that will beplaced on the tunnel during its life, one of theUK’s most state-of-the-art precast segmentallinings has been specified for the project.

Designed by MVB’s engineer, MorganSindall Underground Professional Services(UnPS), the 1.7m wide, 350mm thick, sevensegment + key universal tapered ring iscurrently under production at Morgan Sindall’spermanent precast factory, at Ridham Dock, inKent. A number of emerging technologies –such as steel fibre reinforcement, cast-in EPDMgaskets, 3D laser checking of cast segments

Precast segmentmanufacture forLondon’s deepest evertunnel, ThamesWater’s 6.8km long,7.8m diameter, LeeTunnel sewer project,is now up to fullspeed. Amanda Foleyrecently visitedMorgan Sindall’sproduction facility, atRidham Dock, in Kent,to find out more aboutthis state-of-the-arttunnel lining

VMT’s 3-D lasertracker system isused to check segments arewithin tolerance

Lining the Lee Tunnel

TJ_0411_Lee_024_030.qxd:Feature 21/4/11 23:28 Page 24

Page 2: Tunnelling Journal - Lee Tunnel - State of the Art Segments

TUNNELLING JOURNAL 25

for quality control and a unique maturitymonitoring system – have all been broughttogether for the first time during segmentfabrication for this project. Although thefactory’s two year long, 32,500 segment,manufacturing run has only just got up to fullspeed, the results are promising and set totake the production of precast tunnel liningsanother step forward in the UK.

Casting excellenceFor the well-established Ridham Precast factory– which has been has been turning out high-

quality tunnel lining segments since it opened10-years ago – one of the most unique thingsabout the Lee segment design is the adoptionof cast-in gaskets. “It’s a big step in the rightdirection as far as we’re concerned,” says MickTown, Manager of Ridham Precast. “It gives usa far better quality fit of gasket.”

Having gone from a bit of glue and a bit ofhope, to securely anchored gaskets that sitperfectly square at the corners, the superiorquality of the overall unit is visually apparent.The elimination of gluing also reduces labourand removes solvents from the factory, whichimproves the working environment. “The glueisn’t a major health hazard, but there’s alwaysthat lingering smell in the factory, which isn’tgood, and it’s a dirty job as well,” says Town.

“There’s also the fact you don’t have to re-work the gaskets,” says Ridham’s EngineeringManager, Dave Hicks. “With glued gasketsyou always run the risk that the glue willdelaminate if they’re stored for a long time.Then you have to re-work them before theycan go out. With cast-in gaskets that issue iseliminated completely, which is a big plus.”

The idea of cast-in tunnel gaskets has beenaround for some time, but was brought on byseal specialist Phoenix Dichtungstechnik (nowknown as PDT). “We saw what they had donewith Ceresola moulds in Moscow,” says Town.

“It was only a very short tunnel, but it lookedlike a great idea. So we got PDT talking to CBEour regular mould supplier and between themthey devised the system here, which is great.”

“The interesting thing is, when I was inSwitzerland running the CUC training school,we did a course in segment production andwe demonstrated with a Ceresola mould, aPhoenix cast-in gasket and steel fibre self-compacting concrete,” says Charles Allen, aconsultant working alongside ProgrammeManagement partner CH2MHill. “That was 10years ago and it’s taken that long for cast-ingaskets to take off. This will be the longesttunnel in the world to use the system.”

There isn’t a great deal in cost differencebetween the two systems, as cast-in gasketsare slightly more expensive than traditional

gaskets, but this is offset against reducedlabour costs. “It’s the quality of the unit whichis the major difference though,” says Town.“So far it’s looking very, very, promising.”

Ridham is using 40 CBE moulds, on one ofits two fully PLC-automated carousels, toproduce an average of 60 segments (or 7.5rings) per day for the Lee Tunnel, which is themaximum physically possible on a single shift.Following mould cleaning and placement ofinserts, the custom PDT gaskets are push fittedinto the mould’s gasket slots and given a finalquality check prior to concrete pouring. Grade

PRECAST LININGS

The START (STrength Assessment in RealTime) maturity monitoring system

Lee’s segments employ 30kg/m3 of Dramixsteel fibre reinforcement

A quality control check to ensure a proper fit of the PDTgasket in the CBE mould priorto concrete pouring

TJ_0411_Lee_024_030.qxd:Feature 21/4/11 23:28 Page 25

Page 3: Tunnelling Journal - Lee Tunnel - State of the Art Segments

26 TUNNELLING JOURNAL

www.coray.co

m

> More than 60 co

untr

ies

bein

g se

rved

PRO

CESS O

FFERING

FO

R T

UN

NELING AND MINING

Tell us your needs!

www.normet.fi · www.taminternational.com

GROUND CONTROL SOLUTIONS

North AmericaUSA

South AmericaChile

EMEA Austria

APAC (ASEAN)Australia

THREADBAR® Anchors Rebar Rock Bolts and SpilesIBO, IBI & DYWI® DrillSelf-Drilling Bolts and Spiles

OMEGA-BOLT® AT – Power Set Self-Drilling BoltsDYWIDAG Rock Bolts and Soil NailsMortar-Mixing PumpsSteel Arches and TH-BeamsLiner PlatesPantex® Lattice GirdersLSC- (Lining Stress Controllers)AT – Pipe Umbrella Support SystemAT – Drainage SystemAT – GRP Injection System

Each tunnel has a different geology and requires specific customized products and systems. DSI Tunneling Products and Systems match these requirements perfectly.

DSI is a leading provider in the development, production and application of ground control solutions to the tunneling market. In line with our strong service approach, we are always committed to

satisfying our customers’ demands.

DSI is global market leader in the development, production and application of Post-Tensioning and Geotechnical Systems as well as Concrete Accessories for the Construction industry. DSI is also the

leading supplier of Ground Control Solutions for the Mining and Tunneling industry worldwide.

www.dsi-tunneling.com

TJ_0411_Lee_024_030.qxd:Feature 21/4/11 23:28 Page 26

Page 4: Tunnelling Journal - Lee Tunnel - State of the Art Segments

PRECAST LININGS

TUNNELLING JOURNAL 27

C50/60 concrete, with granite aggregates and30kg/m3 of Dramix steel fibre, is volumetricallypoured into the moulds and hand finishedprior to being placed in the curing tunnel.

The segments are de-moulded after aboutfive hours curing, at a minimum strength of11MPa, therefore an early concern was thatthe gaskets would get pulled out of the youngconcrete whilst opening the moulds.

However, PDT and CBE got together andexamined the retention force required for thegasket. “It’s a bit of a trade off,” explainsHicks, “the gasket has to fit in easily, as we’reworking so quickly, but it also has to withstandpouring, vibration and stripping from themould.” Trials paid off however and this hasn’tbeen an issue at all. “It is a little more difficultto clean the mould than it would be if you hada normal gasket groove, because it’s more of acompact shape,” says Town. “But the benefitsfar outweigh that as far as we’re concerned.”

Superior durabilityLee will be the largest diameter tunnel in theUK to use steel fibre reinforcement to date,but this is nothing new for Ridham Precast.They have been working with fibres for over10 years, since the factory was first set up toproduce segments for Heathrow’s Terminal 5tunnels. The benefits of using steel fibres aresignificant, resulting in reduced manufacturingcosts, improved durability and crack resistance,and less damage during handling. “When itcomes to cost, durability and handling, fibreswin hands-down,” says Town. Fibres alsorepresent a significant reduction in the overallamount of steel used on the project.Traditional rebar reinforced segments willtypically incorporate anywhere between 80kgto 120kg of steel rebar, whereas an equivalentsteel fibre segment is likely to contain 30kg to35kg of steel. There is also labour to consider.“We need at least two or three men on the

production line if we’re fitting cages and thenthere’s an additional QC process,” says Hicks.“With steel fibres you just fill the hopper andyou’re done for the day.”

The Lee Tunnel’s segments were designedutilising UnPS's extensive experience in steelfibre reinforced concrete linings (reaching backto the Heathrow Baggage Tunnel in 1994),however due to the lack of design codes forsteel fibre reinforcement, the design wasvalidated by full scale physical modelling at theBuilding Research Establishment, in Watford.

Although not a major risk, fires have beenknown to occur in tunnels under construction.Therefore, in addition to 30kg/m3 of Dramixsteel fibres, Lee’s segments also incorporate1kg/m3 of Adfil polypropylene fibres tomitigate against spalling in case of fire.

Systematic checkingAnother first for the UK is the requirementthat Lee’s segments be checked daily using a3D laser tracker system. “The VMT systemwas a major investment for us,” says Hicks.“But we can see the benefits.” Up until now,Ridham has always manually checked itsmoulds by micrometer, now instead they arechecking segments using the laser tracker.“Because you’re checking the end product,rather than what’s producing the end product,it’s a much better QC approach in my view,”says Hicks.

With a trapezoidal tapered segment, forexample, it is virtually impossible to manuallycheck the tolerance of a segment, as there areno straight reference faces to work from.“You’re starting with nothing. But a 3Dsystem doesn’t care, it’s got a 3D model, itknows what the shape the segment should beand it compares what it sees against themodel and tells you whether its good or not,”says Hicks.

Checking segments also means productionisn’t affected as it was before. “If a segment isbeginning to go out of tolerance, there aretrigger levels built into the laser trackersystem’s software,” says Allen. “As soon asthose trigger levels are reached, you pull themould off the line and reset it – or re-engineerit if necessary – then check it again and put itback on the line. So it’s far less disruptive.“

“With everything being done off-line, wecan also check a lot more regularly, so the riskto us as a manufacturer is lot less,” explainsHicks. “If one segment is out of tolerance,everything has to be quarantined and re-checked back to the last known in-tolerancesegment. Previously we were checking mouldsevery 100 uses, which meant 100 segmentswould have to be quarantined. Now we arechecking daily, our quarantine exposure riskhas almost been halved, to 60 segments.”

The learning curve for the laser trackersystem has been relatively short and Ridhampartly puts this down to the training receivedfrom VMT. “The laser tracker checking is a lotquicker to use than we thought it was goingto be, significantly quicker than manualchecking,” says Hicks. The level of precisionskill required is also less. “I don’t want todumb down what the guys are doing now,because there’s a lot of computermanipulation required to operate the lasertracker system, but the skill needed formanual measuring is gone,” explains Hicks.“We’ve produced 50 rings now and, althoughwe certainly haven’t laser checked everysegment, the guys are very capable now.”

Prior to shipping, the Lee moulds were laser

The Lee Tunnel’s segment moulds are opened followingfive hours in the curing tunnel. Early concerns that thesegment’s cast-in gaskets would be pulled from the youngconcrete, rather than mould, have proved unfounded

TJ_0411_Lee_024_030.qxd:Feature 21/4/11 23:28 Page 27