tunnel t80 across pir panjal mountain range: the longest transportation tunnel in india
DESCRIPTION
The Presentation Covers the General Technical Features of Tunnel T 80 across Pir Panjal Mountain Range, for Kashmir Rail Link. This presentation was made at Civil Engineering Society, IIT Kanpur on 30th September 2013.TRANSCRIPT
WELCOME YOU TO
PIRPANJAL RAILWAY TUNNEL
SITE THE LONGEST TRANSPORTATION
TUNNEL IN INDIA
2
• Location Overview
• Salient Features of The Tunnel
• Construction Approach
• Pre-construction Planning
• Usage Of NATM in T-80
• Construction Activities
• Quality Assurance
• Environment Issues
• Social Impact
PRESENTATION COVERS
LOCATION OVERVIEW
4
ALIGNMENT PLAN
JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL
LINK
QAZIGUN
D
SADUR
A
ANANTNAG
BIJBEHARA PUNZGA
M
AWANTIPORA
KAKPORA
PAMPOR
E
SRINAGA
R
BUDGA
M
RAJWANSHE
R
PATTAN
HAMRE
SOPORE BARAMULLA
BANIHA
L ARPINCHALA
BHATTA
LOALE
KOHLI SANGALDAN
BARALA BASAND
A--DHAR
REASI
KATRA
CHAKARWAH
UDHAMPUR
SALAL
RAMNAGAR
ROAD
MANWA
L
SANGAR
BAJALT
A JAMM
U
SURUKOT
PIR PANJAL RAIL TUNNEL
Length 11100 mts.
South portal photo
SOUTH PORTAL
5
6
SALIENT FEATURES OF T-80
• Total length – 11 Km
• Adit – 774 m (58 m2 exc. Area)
• Shaft : 55 m depth , 12 m dia
• Maximum overburden - 1.10 Km
• Tunnelling method :NATM (New Austrian Tunneling Method)
• Completed Cost – 1150 Crores
• Approx. 440 m below existing Jawahar Road Tunnel(2.75km)
• Underground excavation : 10 lac cubic meter
• Cross section Area : Excavation : 67 to 78 m2 ,
Finished Tunnel : 48 m2
• Investigation Bore Holes depth upto 640 m
7
SALIENT FEATURES OF T-80
(Contd.)
• 3 m wide road in tunnel for maintenance, emergency rescue & relief.
• High mid point & sloping in both directions for drainage.
• Provision of system for ventilation, fire fighting & safety monitoring.
• Adit & shaft for parallel working, to be used for ventilation, maintenance & emergency relief during service.
• Extensive instrumentation for monitoring during tunneling
• Consultants : M/s Geoconsult-RITES JV
8
MANY FIRSTS • The Longest Transport Tunnel In The Country
(11Km)
• Highest ‘Over- burden’ of 1100M
• Deepest ‘Drill holes’ for Geotechnical Investigations 640M
• First Large Scale Use of ‘New Austrian Tunneling Method (NATM)’ in India
• First Use of ‘Road header’ for ‘Tunnel Excavation’ in Railway Tunneling
CONSTRUCTION
APPROACH
10
APPROACH TO CONSTRUCTION
NO ADIT
11
Vertcal Shaft
55m deep,
12m dia
Cross Passage 55 m
Adit 788 m
APPROACH TO CONSTRUCTION
WITH SHAFT AND ADIT
12
Tunnel
Cross
Section:
STRUCTURAL GAUGE
13
TUNNELS SECTIONS USED ON KONKAN TRACK
14
TYPICAL RAILWAY TUNNEL SECTION USED ON JAMMU-
UDHAMPUR RAIL LINK
SHOTCRETE(25mm+WIRE MESH +50mm)
OR 50mm SFRS
300 TH. C.C. LINING
ISHB 150 @ 500 C/C
50mm TH. R.C.C. LAGGING
Min. EXCAVATION LINE
75Ø @ 2000 C/C
MS PLATE 12mm THICKISHB150-2NOS.
INVERT STRUT ISHB150 @ 500mm
ISHB200 @ 750 C/C
1676
R26
00
43
70
13
12
150
150
Max.
150(max)
50M20
1 in 40
RAIL LEVEL
FINISH LINE
PAY LINE 150 TH. FROM Min. EXCAVATION
25 mm Ø 3 to 5m ROCK BOLTS
AS PER SITE REQUIREMENT
ISHB 150 @ 750 c/c
PRESSURE RELIEF HOLES 5m DEEP @
3m c/c LONGITUDINALLY AS PER SITE
REQUIREMENT
150
PAY LINEMIN. EXCAV. LINE
BASE PLATE
12mm THICK
R3000
ISH
B 1
50
@ 5
00 c
/c
SH
OT
CR
ET
E25m
m +
WIR
EM
ES
H+
50m
m O
R 5
0m
m S
FR
S
50
TH
. R
.C.C
. LA
GG
ING
150
PR
ES
SU
RE
RE
LIE
F H
OLE
S 5
m
DE
EP
@ 3
m c
/c L
ON
GIT
UD
INA
LLY
AR
AS
PE
R S
ITE
RE
QU
IRE
ME
NT
BA
CK
FIL
LIN
G M
-10
50
FIN
ISH
LIN
E
30
0 T
H.
CO
NC
. LIN
ING
M-2
0
150
100
900
BLOWER
8Ø @ 150 C/C
50 675 150
100
65
675
25
mm
Ø 3
mto
5m
RO
CK
BO
LT
AS
PE
R S
ITE
RE
QU
IRE
ME
NT
SE
C. A
T A
-A
75
15
LOADING DIAGRAM FOR TUNNEL TOP PRESSURE-15000KG/M
AND SIDE PRESSURE-5000KG/M
16
BENDING MOMENTS DIAGRAM FOR
D-SHAPE TUNNEL TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M
MAX BENDING MOMENT = 137KN-M
17
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL
TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
MAX. BENDING MOMENT = 35.80KN-M
COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL
DESCRIPTION MAX.
AXIAL
FORCE
MAX.
BENDING
MOMENT
MAX.
SHEAR
FORCE
MAX.
DISPLACEMENT
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE
5000 KG/M
D-SHAPED
TUNNEL
412.5KN 137KN-M 15129 KG 0.083 M
ELLIPTICAL
TUNNEL
567 KN 35.80KN-M 9025 KG 0.024 M
WITH TOP PRESSURE 15000 KG/M
D-SHAPED
TUNNEL
412.5KN 48.10 KN-M 8565 KG 0.03 M
ELLIPTICAL
TUNNEL
639 KN 35.65 KN-M 9635 KG 0.028 M
19
CONSTRUCTION METHOD
SELECTION
• DRILL AND BLAST
• ROAD HEADER
• TUNNEL BORING MACHINE (TBM)
20
DRILL AND BLAST
• CONVENTIONAL, ART
WHICH COMES WITH
EXPERIENCE
• GOOD IN HARD ROCKY
STRATA
• WITH EXPERIENCE, CAN
DELIVER GOOD PROGRESS
• NON CONTINUOUS- CYCLE
INVOLVES VARIOUS
ACTIVITIES IN SEQUENCE
• MAY SPRING SUDDEN
SURPRISES
21
ROAD HEADER • CONTINUOUS ADVANCE-
LESS SURPRISES
• MORE CONTROLLED
EXCAVATION- LESS
OVERBREAK/CAVITY
FORMATION
• SUITABLE FOR MEDIUM
HARD ROCK
• CAN BE WITHDRAWN
MID WAY TO GIVE WAY
FOR OTHER METHODS
22
TUNNEL BORING MACHINE
• CONTINUOUS ADVANCE
• CIRCULAR SECTION
• NOT SUITABLE UNDER SQUEEZING CONDITIONS
• CANNOT BE WITHDRAWN MIDWAY TO GIVE WAY TO OTHER METHODS
23
WHY NO TBM
• Likelihood of Mixed Geology
• Heavily Faulted Areas and/or Wide Fault Zones
• High Squeezing Anticipated in middle with High Overburden (1100 mts.)
• Heavy Water Flow in Lime Stone Zone with High overburden
• TBM may be Trapped by Ground Movement Behind the Face
PRE-CONSTRUCTION
PLANNING
25
PRE-CONSTRUCTION
PLANNING • Engagement of Consultant
– QCB System Of tendering
• Survey and Investigation
• Head start by Taking up ADIT and shaft
works in advance
• Tender Planning
– Key dates
– Multi Method Approach
• Road Header/ D&B
27
USAGE OF NATM IN T-80 • Suitable for poor and Varying Geology of
Himalayan Region
• X-Section designed to develop Maximum Self Supporting Capacity
• Face Mapping, Probe Hole & Instrumentation data input for Initial Support Design – RESS – Primary Support System
• Resilient enough to Accept the deformations and readjustment of stresses and Strong enough to take the loads
• Deformation Monitoring to assess the stress redistribution, and stabilization before final lining
28
INSTRUMENTATION To provide early information about tunnel behaviour in order to optimize
excavation & support activities during construction and to recognize the requisite remedial measures.
Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring: With bi-reflex targets to monitor deformation in tunnel on daily basis
Extensometers: To measure stresses in surrounding rock mass
Radial Pressure Cells: To measure pressure of rockmass on shotcrete lining
Shotcrete Strain meter: To monitor stresses in shotcrete lining
Piezometer: To monitor hydrostatic pressure during tunneling
29
CONSTRUCTION ACTIVITES
• Open excavation & portal development
• Tunnel mining & primary lining
• Water-proof membrane installation +
drainage system.
• Secondary lining.
• Ventilation, system and safety
installations
• Track laying
30
QUALITY ASSURANCE
• Laid down responsibilities, procedures and checklists for various activities through:
–CPM, CQM, SH&EM
–PPM, PSM
–Organogram
–QAP
– ITP
31
QUALITY ASSURANCE (contd…)
• Availability of relevant documentation and defining the manner of execution of various activities
• Maintaining compliance through appropriate monitoring
• Ensuring adequate support facilities for successful & scheduled execution of work.
• Availability of competent/trained personnel to carry out various activities
• Compliance of statutory/regulatory requirements related to safety, environment etc.
32
Quality Assurance (contd…)
Check Lists and Forms for Process Control During Execution of Works:
• Required Excavation and Support Sheet (RESS)
• ATSS/ Shift Report/Blasting clearance report/ R/Bolt Installation report
• Shotcrete testing by Penetrometer test, Core crushing test, thickness verification etc.
• Geological mapping (Geological face mapping sheet)
• Lining Air Permeability Test
• All Material Testing at Site Lab
33
ENVIRONMENT ISSUES
• Identified Muck Dumping areas
• Recycling of Excavated Rocks
– aggregate for concrete constn.
• Effluent Settling Tank
– Fit for agriculture discharge
• Ventilation during Construction Stage
– Gas Analyser for air quality monitoring
• Controlled Blasting below Inhabited areas
• Lined Waterproof Tunnel
– No long term impact on water table/ Aquifers
34
SOCIAL IMPACT • All weather link, Alternate to Jawahar
Tunnel
• Even at Construction stage, given a
boost to
– local construction-industry
– Employment
– Transportation business
• A boost to Local economy of Banihal
35 Time Line
36
PIR PANJAL TUNNEL-
EXCAVATION PROGRESS Year Excavation
(mts.)
Remarks
2006 722 Two Faces
2007 1876 Start From 4 Faces
2008 2475
2009 2533
2010 1739 Two Faces after Jan’10
2011 947 High overburden,
Squeezing, Shale
2012 63
40
Miles to go……
“A thing should be made as simple as possible, but not simpler”. Einstein
41
THANKS !
42
ENGAGEMENT OF CONSULTANT
• Investigations for Tunneling Methodology Assessment
• Initial Design
– Usage of NATM
– Usage of Water proof Membrane for Semi Dry Tunnel
– Development of 4-Arc Tunnel X-Section
– Additional Access through ADIT and Shaft
– Portal Location Review
• Real Time Monitoring / Instrumentation and Design Support
43
INVESTIGATIONS & PLANNING 2003 Geological L-Section Profile Submitted by M/s
RITES based on GSI data.- Used to decide the Bore hole Location.
2003-04 Bore holes by RITES/ MECL- To Confirm Geological Mapping inference
2004 Consultants engaged in Feb. 2004 Geological Surface Mapping along the entire alignment by -
For Detailed Geological Section
2004 Data input for Tendering and a Decision Support System for
ADIT and Shaft decision
– Adit & Shaft Work Awarded in June 2004
2004 Detailed Topographical Survey for Portal
Location
2005 Main Tunnel Construction Work Awarded in
August 2005
44
45
46
BASIC PRINCIPLES OF NATM
• Rock Mass is the major load bearing member
• Primary Support shall
maintain the integrity & strength of Rock Mass
light, have good and area contact (shotcrete)
strengthen Rock Mass (bolt, grouting)
provide protection to workers (steel rib, mesh)
installed quickly
• Provide always an effective ring closure, if necessary by an invert if rock is not suitable
BASIC PRINCIPLES OF NATM (Contd.)
• Rounded shape of Cross-Section
• Continuous control of system behaviour
by monitoring
• Inner lining shall be installed only after
balance of stresses („zero“ deformation)
49
50 3D Monitoring Targets
51
52
53
EXTENSOMETER
54
FACE MAPPING
55
PROBING SHEET
56
57
58
59
Deformation
Monitoring in Primary
Lining Before start of
Secondary Lining
60
61
62 Charging of Face
63 Ventilation Duct
64 Mucking
65 Wire mesh & Lattice Girder Erection
66
Face sealing
Face sealing by Shotcrete
67 Drilling for Forepoling
68 Rock Bolting
69
TUNNEL MINING
Activity Cycle Time (hr.) 2 mt.
RC IV
Cycle time (hr.) 1.25
mt. RC V
Drilling & Excavation 1.7 0.9
Charging , Blasting
& Defuming 2.7 1.5
Mucking 1.1 0.8
Wire Mesh & Lattice
Girder 2.4 2.3
Shotcrete 0.9 0.8
Rock Bolting 1.8 1.0
Preparation of new
face 0.3 0.3
Maintenance 1.6 1.1
Forepoling 1.6 1.7
Total 14.1 10.4
70
71
Kicker Beam Casting
72 Geotextile Fixing
73 PVC Membrane Fixing
74 Membrane Stitching
75 Reinforcement for Overt Lining
76 Reinforcement Cage for Inner Lining
77 Concrete Lining Gantry
78
View of Finished Lining Concrete
79
Profile Checking with Total Station
80 Core Cutting
81 Testing of Joints (Membrane)
82
Sedimentation Tank
83
Effluent Quality
Test Report
84