tunnel t80 across pir panjal mountain range: the longest transportation tunnel in india

84
WELCOME YOU TO PIRPANJAL RAILWAY TUNNEL SITE THE LONGEST TRANSPORTATION TUNNEL IN INDIA

Upload: hitesh-khanna

Post on 07-May-2015

2.311 views

Category:

Education


10 download

DESCRIPTION

The Presentation Covers the General Technical Features of Tunnel T 80 across Pir Panjal Mountain Range, for Kashmir Rail Link. This presentation was made at Civil Engineering Society, IIT Kanpur on 30th September 2013.

TRANSCRIPT

Page 1: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

WELCOME YOU TO

PIRPANJAL RAILWAY TUNNEL

SITE THE LONGEST TRANSPORTATION

TUNNEL IN INDIA

Page 2: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

2

• Location Overview

• Salient Features of The Tunnel

• Construction Approach

• Pre-construction Planning

• Usage Of NATM in T-80

• Construction Activities

• Quality Assurance

• Environment Issues

• Social Impact

PRESENTATION COVERS

Page 3: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

LOCATION OVERVIEW

Page 4: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

4

ALIGNMENT PLAN

JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL

LINK

QAZIGUN

D

SADUR

A

ANANTNAG

BIJBEHARA PUNZGA

M

AWANTIPORA

KAKPORA

PAMPOR

E

SRINAGA

R

BUDGA

M

RAJWANSHE

R

PATTAN

HAMRE

SOPORE BARAMULLA

BANIHA

L ARPINCHALA

BHATTA

LOALE

KOHLI SANGALDAN

BARALA BASAND

A--DHAR

REASI

KATRA

CHAKARWAH

UDHAMPUR

SALAL

RAMNAGAR

ROAD

MANWA

L

SANGAR

BAJALT

A JAMM

U

SURUKOT

PIR PANJAL RAIL TUNNEL

Length 11100 mts.

South portal photo

SOUTH PORTAL

Page 5: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

5

Page 6: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

6

SALIENT FEATURES OF T-80

• Total length – 11 Km

• Adit – 774 m (58 m2 exc. Area)

• Shaft : 55 m depth , 12 m dia

• Maximum overburden - 1.10 Km

• Tunnelling method :NATM (New Austrian Tunneling Method)

• Completed Cost – 1150 Crores

• Approx. 440 m below existing Jawahar Road Tunnel(2.75km)

• Underground excavation : 10 lac cubic meter

• Cross section Area : Excavation : 67 to 78 m2 ,

Finished Tunnel : 48 m2

• Investigation Bore Holes depth upto 640 m

Page 7: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

7

SALIENT FEATURES OF T-80

(Contd.)

• 3 m wide road in tunnel for maintenance, emergency rescue & relief.

• High mid point & sloping in both directions for drainage.

• Provision of system for ventilation, fire fighting & safety monitoring.

• Adit & shaft for parallel working, to be used for ventilation, maintenance & emergency relief during service.

• Extensive instrumentation for monitoring during tunneling

• Consultants : M/s Geoconsult-RITES JV

Page 8: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

8

MANY FIRSTS • The Longest Transport Tunnel In The Country

(11Km)

• Highest ‘Over- burden’ of 1100M

• Deepest ‘Drill holes’ for Geotechnical Investigations 640M

• First Large Scale Use of ‘New Austrian Tunneling Method (NATM)’ in India

• First Use of ‘Road header’ for ‘Tunnel Excavation’ in Railway Tunneling

Page 9: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

CONSTRUCTION

APPROACH

Page 10: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

10

APPROACH TO CONSTRUCTION

NO ADIT

Page 11: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

11

Vertcal Shaft

55m deep,

12m dia

Cross Passage 55 m

Adit 788 m

APPROACH TO CONSTRUCTION

WITH SHAFT AND ADIT

Page 12: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

12

Tunnel

Cross

Section:

STRUCTURAL GAUGE

Page 13: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

13

TUNNELS SECTIONS USED ON KONKAN TRACK

Page 14: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

14

TYPICAL RAILWAY TUNNEL SECTION USED ON JAMMU-

UDHAMPUR RAIL LINK

SHOTCRETE(25mm+WIRE MESH +50mm)

OR 50mm SFRS

300 TH. C.C. LINING

ISHB 150 @ 500 C/C

50mm TH. R.C.C. LAGGING

Min. EXCAVATION LINE

75Ø @ 2000 C/C

MS PLATE 12mm THICKISHB150-2NOS.

INVERT STRUT ISHB150 @ 500mm

ISHB200 @ 750 C/C

1676

R26

00

43

70

13

12

150

150

Max.

150(max)

50M20

1 in 40

RAIL LEVEL

FINISH LINE

PAY LINE 150 TH. FROM Min. EXCAVATION

25 mm Ø 3 to 5m ROCK BOLTS

AS PER SITE REQUIREMENT

ISHB 150 @ 750 c/c

PRESSURE RELIEF HOLES 5m DEEP @

3m c/c LONGITUDINALLY AS PER SITE

REQUIREMENT

150

PAY LINEMIN. EXCAV. LINE

BASE PLATE

12mm THICK

R3000

ISH

B 1

50

@ 5

00 c

/c

SH

OT

CR

ET

E25m

m +

WIR

EM

ES

H+

50m

m O

R 5

0m

m S

FR

S

50

TH

. R

.C.C

. LA

GG

ING

150

PR

ES

SU

RE

RE

LIE

F H

OLE

S 5

m

DE

EP

@ 3

m c

/c L

ON

GIT

UD

INA

LLY

AR

AS

PE

R S

ITE

RE

QU

IRE

ME

NT

BA

CK

FIL

LIN

G M

-10

50

FIN

ISH

LIN

E

30

0 T

H.

CO

NC

. LIN

ING

M-2

0

150

100

900

BLOWER

8Ø @ 150 C/C

50 675 150

100

65

675

25

mm

Ø 3

mto

5m

RO

CK

BO

LT

AS

PE

R S

ITE

RE

QU

IRE

ME

NT

SE

C. A

T A

-A

75

Page 15: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

15

LOADING DIAGRAM FOR TUNNEL TOP PRESSURE-15000KG/M

AND SIDE PRESSURE-5000KG/M

Page 16: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

16

BENDING MOMENTS DIAGRAM FOR

D-SHAPE TUNNEL TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M

MAX BENDING MOMENT = 137KN-M

Page 17: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

17

BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL

TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M

MAX. BENDING MOMENT = 35.80KN-M

Page 18: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL

DESCRIPTION MAX.

AXIAL

FORCE

MAX.

BENDING

MOMENT

MAX.

SHEAR

FORCE

MAX.

DISPLACEMENT

WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE

5000 KG/M

D-SHAPED

TUNNEL

412.5KN 137KN-M 15129 KG 0.083 M

ELLIPTICAL

TUNNEL

567 KN 35.80KN-M 9025 KG 0.024 M

WITH TOP PRESSURE 15000 KG/M

D-SHAPED

TUNNEL

412.5KN 48.10 KN-M 8565 KG 0.03 M

ELLIPTICAL

TUNNEL

639 KN 35.65 KN-M 9635 KG 0.028 M

Page 19: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

19

CONSTRUCTION METHOD

SELECTION

• DRILL AND BLAST

• ROAD HEADER

• TUNNEL BORING MACHINE (TBM)

Page 20: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

20

DRILL AND BLAST

• CONVENTIONAL, ART

WHICH COMES WITH

EXPERIENCE

• GOOD IN HARD ROCKY

STRATA

• WITH EXPERIENCE, CAN

DELIVER GOOD PROGRESS

• NON CONTINUOUS- CYCLE

INVOLVES VARIOUS

ACTIVITIES IN SEQUENCE

• MAY SPRING SUDDEN

SURPRISES

Page 21: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

21

ROAD HEADER • CONTINUOUS ADVANCE-

LESS SURPRISES

• MORE CONTROLLED

EXCAVATION- LESS

OVERBREAK/CAVITY

FORMATION

• SUITABLE FOR MEDIUM

HARD ROCK

• CAN BE WITHDRAWN

MID WAY TO GIVE WAY

FOR OTHER METHODS

Page 22: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

22

TUNNEL BORING MACHINE

• CONTINUOUS ADVANCE

• CIRCULAR SECTION

• NOT SUITABLE UNDER SQUEEZING CONDITIONS

• CANNOT BE WITHDRAWN MIDWAY TO GIVE WAY TO OTHER METHODS

Page 23: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

23

WHY NO TBM

• Likelihood of Mixed Geology

• Heavily Faulted Areas and/or Wide Fault Zones

• High Squeezing Anticipated in middle with High Overburden (1100 mts.)

• Heavy Water Flow in Lime Stone Zone with High overburden

• TBM may be Trapped by Ground Movement Behind the Face

Page 24: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

PRE-CONSTRUCTION

PLANNING

Page 25: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

25

PRE-CONSTRUCTION

PLANNING • Engagement of Consultant

– QCB System Of tendering

• Survey and Investigation

• Head start by Taking up ADIT and shaft

works in advance

• Tender Planning

– Key dates

– Multi Method Approach

• Road Header/ D&B

Page 26: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India
Page 27: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

27

USAGE OF NATM IN T-80 • Suitable for poor and Varying Geology of

Himalayan Region

• X-Section designed to develop Maximum Self Supporting Capacity

• Face Mapping, Probe Hole & Instrumentation data input for Initial Support Design – RESS – Primary Support System

• Resilient enough to Accept the deformations and readjustment of stresses and Strong enough to take the loads

• Deformation Monitoring to assess the stress redistribution, and stabilization before final lining

Page 28: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

28

INSTRUMENTATION To provide early information about tunnel behaviour in order to optimize

excavation & support activities during construction and to recognize the requisite remedial measures.

Instrumentation data is basic input of the NATM, the observational approach.

Instrumentation in Pir Panjal Tunnel:

Optical 3 D monitoring: With bi-reflex targets to monitor deformation in tunnel on daily basis

Extensometers: To measure stresses in surrounding rock mass

Radial Pressure Cells: To measure pressure of rockmass on shotcrete lining

Shotcrete Strain meter: To monitor stresses in shotcrete lining

Piezometer: To monitor hydrostatic pressure during tunneling

Page 29: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

29

CONSTRUCTION ACTIVITES

• Open excavation & portal development

• Tunnel mining & primary lining

• Water-proof membrane installation +

drainage system.

• Secondary lining.

• Ventilation, system and safety

installations

• Track laying

Page 30: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

30

QUALITY ASSURANCE

• Laid down responsibilities, procedures and checklists for various activities through:

–CPM, CQM, SH&EM

–PPM, PSM

–Organogram

–QAP

– ITP

Page 31: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

31

QUALITY ASSURANCE (contd…)

• Availability of relevant documentation and defining the manner of execution of various activities

• Maintaining compliance through appropriate monitoring

• Ensuring adequate support facilities for successful & scheduled execution of work.

• Availability of competent/trained personnel to carry out various activities

• Compliance of statutory/regulatory requirements related to safety, environment etc.

Page 32: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

32

Quality Assurance (contd…)

Check Lists and Forms for Process Control During Execution of Works:

• Required Excavation and Support Sheet (RESS)

• ATSS/ Shift Report/Blasting clearance report/ R/Bolt Installation report

• Shotcrete testing by Penetrometer test, Core crushing test, thickness verification etc.

• Geological mapping (Geological face mapping sheet)

• Lining Air Permeability Test

• All Material Testing at Site Lab

Page 33: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

33

ENVIRONMENT ISSUES

• Identified Muck Dumping areas

• Recycling of Excavated Rocks

– aggregate for concrete constn.

• Effluent Settling Tank

– Fit for agriculture discharge

• Ventilation during Construction Stage

– Gas Analyser for air quality monitoring

• Controlled Blasting below Inhabited areas

• Lined Waterproof Tunnel

– No long term impact on water table/ Aquifers

Page 34: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

34

SOCIAL IMPACT • All weather link, Alternate to Jawahar

Tunnel

• Even at Construction stage, given a

boost to

– local construction-industry

– Employment

– Transportation business

• A boost to Local economy of Banihal

Page 35: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

35 Time Line

Page 36: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

36

PIR PANJAL TUNNEL-

EXCAVATION PROGRESS Year Excavation

(mts.)

Remarks

2006 722 Two Faces

2007 1876 Start From 4 Faces

2008 2475

2009 2533

2010 1739 Two Faces after Jan’10

2011 947 High overburden,

Squeezing, Shale

2012 63

Page 37: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India
Page 38: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India
Page 39: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India
Page 40: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

40

Miles to go……

“A thing should be made as simple as possible, but not simpler”. Einstein

Page 41: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

41

THANKS !

Page 42: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

42

ENGAGEMENT OF CONSULTANT

• Investigations for Tunneling Methodology Assessment

• Initial Design

– Usage of NATM

– Usage of Water proof Membrane for Semi Dry Tunnel

– Development of 4-Arc Tunnel X-Section

– Additional Access through ADIT and Shaft

– Portal Location Review

• Real Time Monitoring / Instrumentation and Design Support

Page 43: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

43

INVESTIGATIONS & PLANNING 2003 Geological L-Section Profile Submitted by M/s

RITES based on GSI data.- Used to decide the Bore hole Location.

2003-04 Bore holes by RITES/ MECL- To Confirm Geological Mapping inference

2004 Consultants engaged in Feb. 2004 Geological Surface Mapping along the entire alignment by -

For Detailed Geological Section

2004 Data input for Tendering and a Decision Support System for

ADIT and Shaft decision

– Adit & Shaft Work Awarded in June 2004

2004 Detailed Topographical Survey for Portal

Location

2005 Main Tunnel Construction Work Awarded in

August 2005

Page 44: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

44

Page 45: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

45

Page 46: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

46

Page 47: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

BASIC PRINCIPLES OF NATM

• Rock Mass is the major load bearing member

• Primary Support shall

maintain the integrity & strength of Rock Mass

light, have good and area contact (shotcrete)

strengthen Rock Mass (bolt, grouting)

provide protection to workers (steel rib, mesh)

installed quickly

• Provide always an effective ring closure, if necessary by an invert if rock is not suitable

Page 48: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

BASIC PRINCIPLES OF NATM (Contd.)

• Rounded shape of Cross-Section

• Continuous control of system behaviour

by monitoring

• Inner lining shall be installed only after

balance of stresses („zero“ deformation)

Page 49: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

49

Page 50: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

50 3D Monitoring Targets

Page 51: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

51

Page 52: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

52

Page 53: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

53

EXTENSOMETER

Page 54: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

54

FACE MAPPING

Page 55: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

55

PROBING SHEET

Page 56: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

56

Page 57: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

57

Page 58: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

58

Page 59: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

59

Deformation

Monitoring in Primary

Lining Before start of

Secondary Lining

Page 60: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

60

Page 61: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

61

Page 62: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

62 Charging of Face

Page 63: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

63 Ventilation Duct

Page 64: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

64 Mucking

Page 65: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

65 Wire mesh & Lattice Girder Erection

Page 66: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

66

Face sealing

Face sealing by Shotcrete

Page 67: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

67 Drilling for Forepoling

Page 68: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

68 Rock Bolting

Page 69: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

69

TUNNEL MINING

Activity Cycle Time (hr.) 2 mt.

RC IV

Cycle time (hr.) 1.25

mt. RC V

Drilling & Excavation 1.7 0.9

Charging , Blasting

& Defuming 2.7 1.5

Mucking 1.1 0.8

Wire Mesh & Lattice

Girder 2.4 2.3

Shotcrete 0.9 0.8

Rock Bolting 1.8 1.0

Preparation of new

face 0.3 0.3

Maintenance 1.6 1.1

Forepoling 1.6 1.7

Total 14.1 10.4

Page 70: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

70

Page 71: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

71

Kicker Beam Casting

Page 72: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

72 Geotextile Fixing

Page 73: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

73 PVC Membrane Fixing

Page 74: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

74 Membrane Stitching

Page 75: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

75 Reinforcement for Overt Lining

Page 76: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

76 Reinforcement Cage for Inner Lining

Page 77: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

77 Concrete Lining Gantry

Page 78: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

78

View of Finished Lining Concrete

Page 79: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

79

Profile Checking with Total Station

Page 80: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

80 Core Cutting

Page 81: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

81 Testing of Joints (Membrane)

Page 82: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

82

Sedimentation Tank

Page 83: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

83

Effluent Quality

Test Report

Page 84: Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

84