Tullymurdoch Wind Farm Proposal

RDS Element Power

March 2012

Page 2: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Tullymurdoch Wind Farm Proposal

1

Introduction

Renewable Energy

Tullymurdoch Wind Farm

Project Programme

Community Council Liaison Group

Community Benefit

Questions

Page 3: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

2

Who are we?

Smithy House Associates Ltd is a public relations company based in the Scottish

Borders which provides community engagement services to the renewable energy

sector. We facilitate discussions between the developer and communities

neighbouring wind farm sites thereby increasing local participation in and awareness

of projects.

RDS Element Power is a joint venture between Element Power, a developer and

operator of renewable energy projects in the UK, and RDS, a small group of successful

Scottish developers with a portfolio of sites. We are based in Edinburgh with support

from the Element Power head office in London.

Tullymurdoch Wind Farm Proposal

Page 4: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

3

The Team

RDS Ltd: Three Scottish Directors, with agricultural backgrounds who have successfully consented 65MW of Wind Power.

Element Power UK Team: previously in key positions with companies such as RES, National Wind Power , nPower renewables , SSE renewables , Garrad Hassan and Novera Energy.

Achievements of the RDS Element Power team:

Consented the 50MW A’Chruach Wind Farm in five months.

Consented 52.5MW Baillie Wind Farm in Caithness (under construction).

30MW Lisset Airfield: From planning application to operation in two and a half years.

Consented 14 MW Pates Hill in West Lothian (now operational).

2009 Energy Institute awards for communications.

Tullymurdoch Wind Farm Proposal

Page 5: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Tullymurdoch Wind Farm Proposal

4

Climate Change : Reducing CO2 and greenhouse gas emissions;

UK Government Targets : 34% reduction in emissions by 2020 and 80% by 2050;

Scottish Targets : 100% of electricity by 2020; and

Security of supply : Finite supply - less reliance on imports.

The need for Renewables

Page 6: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Why wind?

5

Natural and free resource

Proven clean technology

Jobs and the economy

It is safe

Potential community benefit

Annual mean wind speed at 25m above ground level (m/s)

Page 7: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Site Boundary and Indicative Layout

6

Page 8: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Why Tullymurdoch?

7

What makes it a good site?

Area of low natural heritage sensitivity*

Good wind speeds

No National or European conservation designations*

Proven access routes

Alternative use for poor quality farmland

*taken from SNH Scoping Response

Page 9: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Tullymurdoch Wind Farm Proposal

8

The wind farm would consist of up to 7 wind turbines.

Each turbine would have a blade tip height of up to 120m (396 ft).

The site could have a capacity of up to 17.5MW which is approximately

enough electricity to power the annual needs of 9,300 homes.

The proposal will also include access tracks, an electrical sub station, crane

standings and a met mast.

120m

Page 10: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Tullymurdoch Wind Farm Proposal

9

Project Status

Previously identified as a site with potential for wind development

Survey work started in Summer 2009

Initial introduction to Community Councils in February 2012

Scoping with Perth & Kinross Council back in 2008

Further Consultation and discussions with local community

First Public Consultation Exhibitions anticipated April 2012

Next Steps......

Further surveys, modification and wind farm design

Full Environmental Impact Assessment carried out by a complete team of

specialist consultants and experts

Effects assessed for wind farm lifecycle:

Construction/Operation/Decommissioning

Planning Application submitted in Summer 2012

Page 11: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Community Council Liaison Group

10

Aims - to provide a forum for discussion and the exchange of information by:

• Receiving progress updates from RDS Element Power • Addressing questions and concerns arising from the surrounding communities • Establishing workshop discussions on key specific elements of the potential proposals, development and operation of the site.

Membership - Two representatives from each Community Council and one representative from the Alyth Business Association.

Minutes – Will be published on the Project Website and issued through the Community Councils. Copies will be sent for information purposes to:

•Member of Parliament •MSPs •Perth & Kinross Ward Councillors •Planning Department of Perth & Kinross Council

Page 12: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Community Benefit

11

If the Tullymurdoch Wind Farm were to be granted planning permission a dedicated community development trust fund would be established RDS Element Power would pay an agreed annual payment per MW, based on the installed capacity, into the fund. The fund would be indexed linked and provide financial support for projects and organisations in the vicinity of the wind farm.

Negotiations for voluntary community benefit would take place through the CCLG.

The Trust would be encouraged to seek matched funding for appropriate schemes.

RDS Element Power would encourage communities to use some of the money to assist projects that help reduce energy usage however local people will have the final decision on how the money is allocated.

Page 13: Tullymurdoch Wind Farm Proposal RDS Element Powerapi.ning.com/files/oS79sSzIqECmx3ktLkH0*1pp4oppfV1... · *taken from SNH Scoping ... Tullymurdoch Wind Farm Proposal 9 Project Status

Thank you

12

Project Enquiries

Douglas Hendry RDS Element Power

11 Brae Park Edinburgh EH4 6DJ

Mob: +44(0) 7552 129 077

E: [email protected]

Community Benefit Enquiries

Niall White Smithy House Associates Ltd

Ettrick Riverside Business Centre Dunsdale Road

Selkirk TD7 5EB

Phone: +44(0) 1750 505273

Mob: +44(0) 7834 352165

E: [email protected]