transportation & capital improvements...
TRANSCRIPT
TRANSPORTATION &
CAPITAL IMPROVEMENTS
(TCI)2012 – 2017 Bond Projects
–1
2012 – 2017 Bond Projects
MAIN/SOLEDAD: COMMERCE TO
PECAN STREET
MAIN/SAN PEDRO/NAVARRO
ROUNDABOUT UPDATE
September 27, 2016
Presenter: Peter Rodriguez
Capital Project Officer
Location: Central Library
600 Soledad
Agenda
• TCI Introductions
• Main/Soledad: Commerce to Pecan Street Project
– Project Map
– Existing Conditions
– Planned improvements
– Sequence of Work
– Schedule
–2
– Schedule
• Main/San Pedro/Navarro Roundabout Project Update
– Project map
– Project scope
– Planned improvements
– Schedule
• TCI Commitments
• Public Comments and Questions
22
• City Council District 1
• Office of Councilman Roberto C. Treviño
• TCI Design/Construction Team
David Mc Beth P.E. – Project Manager
Florencio Rodriguez P.E. – Project Engineer
Peter Rodriguez – Capital Projects Officer
• Steven Cordell - TCI Inspector
TCI Introductions
–3
• Steven Cordell - TCI Inspector
• Main Ave. & Soledad
Design Consultant – Poznecki Camarillo – Fernando Camarillo P.E. – Project Manager
• Contractor
E-Z Bel Construction – Randy Hood
• Main/San Pedro/Navarro Roundabout
Design Consultant – CDM Smith – Matt Hunter P.E. – Project Manager
3
Main/Soledad: Commerce to Pecan St.
Main Street Soledad Street
–4
Project Construction Cost: $9.5 million allocated in the 2012 – 2017 Bond
Project Location Map
WESTON CENTRE
ROBERT E. LEE
HOTEL
–5 5
EMBASSY SUITES
FROST BANK
RIVERVIEW
TOWERS
HOTEL
Existing Conditions Main Ave. & Soledad
–6 66
Main Ave. & Soledad Streets:
• One-way streets
• Outdated drive approaches
• Cracks on street pavement
• Broken and cracked sidewalks
• Outdated sidewalk ADA wheel ramps
• Lack of pedestrian and bicycle connectivity
• Outdated storm drainage system
• Curbside Parallel Parking
•Main Ave.• Total roadway reconstruction (Commerce St. to Pecan St.)
• Conversion from one-way to two-way traffic operations.
• 10’ foot wide traffic lanes in each direction
• Variable width sidewalks and paver bands
• 5’ foot wide bike lanes in each direction
Planned Improvements
–7
• 5’ foot wide bike lanes in each direction
• Bulb-outs for street side parallel parking
• Install new storm drain inlets to reduce localized flooding
• Curb and gutter, sidewalks and incidental driveway construction
• Landscaping plan
• Street and pedestrian lighting and amenities (bike-racks, benches)
• ADA compliant wheelchair ramps
• Main: Pecan to Navarro (fog seal /restriping)
7
• Soledad Street• Total roadway reconstruction (Commerce St. to Pecan St.)
• Conversion from one-way to two-way traffic operations
• 10’ foot wide traffic lanes in each direction
• Continues left turn lane
• Variable width sidewalks and paver bands
Planned Improvements
–8
• Variable width sidewalks and paver bands
• Bulb-outs for street side parallel parking
• Install new storm drain inlets to reduce localized flooding
• Curb and gutter, sidewalks and incidental driveway construction
• Landscaping plan
• Pedestrian lighting and amenities (bike racks, benches)
• ADA compliant wheelchair ramps
• Soledad: Pecan to San Pedro (fog seal/restriping)
8
Planned Improvements
–9 9
Planned Improvements
–10 10
Planned Improvements
–11 11
Planned Improvements
–12 12
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 1– Soledad: Commerce to Pecan Street – duration approx. 3 months (mid Oct 2016- mid Jan 2017)Construct CPS gas and SAWS sewer mains and laterals
Phase 2 – Soledad: Commerce to Pecan Street (West Side) – duration approx. 5-1/2 months (mid Nov 2016-end of Mar 2017)*
–13 13
5-1/2 months (mid Nov 2016-end of Mar 2017)*Construct storm sewer inlets, roadway, curb and gutter, sidewalks and drive approachesConstruct Travis Street
Phase 3 – Soledad: Commerce to Pecan Street (East Side) – duration approx. 2-1/2 months (end of Mar – mid-June 2017)*Construct SAWS water main and laterals storm sewer inletsConstruct roadway, curb and gutter, sidewalks and drive approaches
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 4 – Main Ave.: Commerce to Houston St. – duration approx. 1 month ( Jan – Feb 2017)*o Construct CPS gas and SAWS water mains and sewer laterals.
Phase 5 – Step 1 Main Ave.: Commerce to Pecan (West Side) – duration approx. 4-1/2 months (mid May-Oct 2017)*o SAWS water work construction
–14 14
o SAWS water work constructiono Construct storm sewer inlets, roadway, curb and gutter, sidewalks and
drive approacheso Construct Travis Street and Salinas Street intersections
Phase 6 – Step 1 Main Ave.: Commerce to Pecan (East Side) – duration approx. 2-1/2 months (end of Aug-mid Nov 2017)*o Storm drain inlet worko Construct storm drain inlets, roadway, curb and gutter, sidewalks and
drive approaches
Traffic Control Plan/Sequence of Work
Sequence of Work (*all durations are weather permitting)
Phase 7 – Soledad: Commerce to Pecan Street – duration approx. 6-1/2 months (May - mid Nov 2017)*o Install Traffic signals on Soledad from Commerce to Martino Install traffic signals on Main Ave for Commerce to Martin
Install small signs
–15 15
o Install small signso Install final riding surface of asphalto Install final stripingo Final Clean up
Main Ave. & Soledad
• Contractor shall provide access at all times to include pedestrian
access, drop off and deliveries
• TCI has notified all affected services (EMS, USPS, etc.), Council
Office
TCI Project Commitments
–16
Office
• Any property owners or stakeholders with special needs will be
identified
• Contractor to notify property owners 48 hour in advance of
driveway construction
• Message boards will be installed to notify public of upcoming
construction
• TCI has coordinated with other TCI divisions and B-Cycle
16
Historic Tiled Entryways
Robert E. Lee Hotel
Alpha Hotel
–17 17
Project Schedule
Main Ave. & Soledad ScheduleMain Ave. & Soledad Schedule
Construction start October 17th 2016
Estimated construction
completion*
November 2017
* Weather permitting
–18 18
For information in regards to the project during the Construction Phase: Please contact: Pete Rodriguez – TCI Capital Projects Officer at 210-207-8154
If you would like to be added to an e-mail list for project updates or future meeting
announcements, please ensure you fill out the sign-in sheet and check the permission
block.
Main/Navarro/San Pedro Roundabout Update
–19
Project Location Map
BAPTIST
CENTRAL CHRISTIAN
CHURCH
–20 20
CENTRAL LIBRARY
FOX TECH H. S.
BAPTIST
HOSPITAL
A.P.I.
Project Scope:
Main/San Pedro/Navarro Roundabout
This project includes full reconstruction of the intersection of San Pedro Ave and N. Main
Ave. This is a 5-leg intersection, two of the legs being N. Main, the other three being San
Pedro Ave., Camden, and Navarro. The reconstruction will include raised medians to better
Project Scope
–21 21
facilitate traffic and pedestrians. Included in this project will be a 10’ share use path to
improve bicycle and pedestrian connectivity, curb and gutter, incidental driveway
construction, landscaping, pedestrian lighting and amenities, and this project will include a
public art component.
SAWS sewer and water work
CPS Gas and over head adjustments
Project Budget:
$6,000,000 allocated in the 2012 – 2017 General Obligation Bond
Planned Improvements
–22 22
Roundabout (Rendering – Plan View)
Project Schedule
Main/San Pedro/Navarro Design ScheduleMain/San Pedro/Navarro Design Schedule
Project Bidding November 2016
Construction start January 2017
–23 23
Construction start January 2017
Estimated construction
completion*
October 2017
* Weather permitting
Questions or Comments
–24
TCI Thanks You for Your Attendance
24