transmission network congestion

37
TRANSMISSION NETWORK CONGESTION Paul L. Joskow December 6, 2007

Upload: others

Post on 12-Sep-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRANSMISSION NETWORK CONGESTION

TRANSMISSION NETWORK CONGESTION

Paul L. Joskow

December 6, 2007

Page 2: TRANSMISSION NETWORK CONGESTION

TRANSMISSION NETWORK CONGESTION• Why do we care?

– Higher generating costs as low-cost generation is “constrained off”– Stressed networks are less reliable

• Why does congestion emerge?– Thermal/physical limits on lines and transformers– Engineering reliability and contingency criteria (N-1, N-2, etc.)

• How are these engineering criteria defined?• How do they relate to economic valuations of lost load (VOLL), priced-based

demand response, rolling blackouts, and network collapse?• How to allocate “scarce” transmission capacity with competitive G sector?

– Alternatives to central dispatch by vertically integrated utilities– Non-price rationing hierarchies (intra- and inter-control area TLR protocols) with

tariff-based transmission service contracts– Security constrained bid-based dispatch (nodal pricing) plus financial transmission

rights (FTR)– Tradeable cost-based physical transmission rights between defined zones or “flow

gates” • How do we stimulate investment in new transmission capacity?

– Reliability rules– Congestion cost reduction– Market power mitigation– Regulated transmission investment– Merchant transmission investment– Hybrid models

Page 3: TRANSMISSION NETWORK CONGESTION

TRANSMISSION CONGESTION

G2

K

C1 = C1(q1)

C2 = C2(q2)

Q = q1 + q2 = D(p2)

C1’ < C2’

q1 = K

p1* = C1’(K)p2* = C2’(D(p2* - K)) > p1*q1 = KD(p2*) = q1 + q2 = K + q2η∗ = p2* - p1*

G1Cheapgen

DeargenLoad

Joskow-Tirole

Page 4: TRANSMISSION NETWORK CONGESTION

TRANSMISSION CONGESTION WITH LOOP FLOW

Node 1: Cheapgen

Cost: C1(q1)

Node 2: DeargenCost: C2(q2)

Node 3: Consumptionq3 = D(p3)

KC1’ < C2’

q1 + q2 = q31/3(q1 - q2) < Κp1 = p3 - η/3p2 = p3 + η/3p3 = (p1+p2)/2p1 = C1’(q1) = C1’(q2 + 3K) p2 = 2P(2q2 + 3K) - p1

p3 = P(q3)

G1

G2

D

Joskow-Tirole

Page 5: TRANSMISSION NETWORK CONGESTION

400 MwMC = 10

400 MwMC = 12

400 MwMC = 20

Page 6: TRANSMISSION NETWORK CONGESTION

400 MwMC = 12

400 MwMC = 20

Page 7: TRANSMISSION NETWORK CONGESTION

400 MwMC = 12

400 MwMC = 20

Page 8: TRANSMISSION NETWORK CONGESTION

RELIABILITY AND CONTINGENCY CRITERIA

• Transmission capacity is rarely limited by thermal constraints on facilities

• Limits are typically a consequence of applying engineering reliability and contingency criteria– These criteria are not simple– They are based on a large number of assumptions about system

conditions on many transmission links, generating stations and interconnected control areas

– They can vary widely with system conditions and weather conditions– They can be affected by the installation of enhanced real time

monitoring equipment– They are affected by the status of remedial action plans, information

transfer and communication speeds– They give the system operator a lot of discretion

• These reliability and contingency criteria have been carried over from the old world of (many) regulated vertically integrated monopoly control area operators– There has been little evaluation of the economic rational or economic

effects of these criteria– They affect wholesale market prices for energy

Page 9: TRANSMISSION NETWORK CONGESTION
Page 10: TRANSMISSION NETWORK CONGESTION

NERC

Page 11: TRANSMISSION NETWORK CONGESTION

NERC

Page 12: TRANSMISSION NETWORK CONGESTION

Source: Platts

MAJOR U.S. CONGESTED INTERFACES

Page 13: TRANSMISSION NETWORK CONGESTION

Security Coordinators

NERC

Page 14: TRANSMISSION NETWORK CONGESTION

DAY-AHEAD PEAK WHOLESALE ENERGY PRICES (2004) $/MWH

0

20

40

60

80

100

120

140

160

180

1/14

/200

4

1/21

/200

4

1/28

/200

4

2/4/

2004

2/11

/200

4

2/18

/200

4

2/25

/200

4

3/3/

2004

3/10

/200

4

3/17

/200

4

3/24

/200

4

3/31

/200

4

4/7/

2004

4/14

/200

4

4/21

/200

4

4/28

/200

4

5/5/

2004

5/12

/200

4

5/19

/200

4

5/26

/200

4

6/2/

2004

MASS HUB NY-G NY-J PJM-W CINERGY

Page 15: TRANSMISSION NETWORK CONGESTION

CONGESTION MANAGEMENT IN THE U.S.

• Nodal Pricing Areas– New England– New York– PJM– MISO– California (next year)– Texas (Zonal/flowgates nodal)

• Rest of U.S.– Tariff-based transmission service with limited trading– No congestion pricing– Administrative rationing of scarce capacity

Page 16: TRANSMISSION NETWORK CONGESTION

Source: State of the Markets Report 2004, FERC Office of Market Oversight andInvestigations (2005, page 53).

ISO/RTOs in the United States 2006

ISO NENYISO

PJM

MISO

ERCOT

SPPCAISO

Page 17: TRANSMISSION NETWORK CONGESTION

Source: FERC 2006 State of the Markets Report

Page 18: TRANSMISSION NETWORK CONGESTION

ISO-NE (2006)

Page 19: TRANSMISSION NETWORK CONGESTION

NODAL PRICING MODEL• The nodal pricing models now work reasonably well in

the Eastern ISOs from both economic dispatch and reliability perspectives

• NE, NY and PJM now include marginal losses in prices• Congestion is managed economically and least bid-cost

dispatch is achieved• Nodal prices provide a good indication of congestion

costs (except during scarcity conditions)• Day-ahead and real-time prices are well arbitraged in an

expected value sense• Market power and gaming are more transparent than

with other systems• Coordination between ISOs is improving

– PJM internalized through expansion and joint operating agreements with MISO

• California and Texas are moving to nodal pricing due to problems with zonal models

Page 20: TRANSMISSION NETWORK CONGESTION

NON-PRICE RATIONALING

NERC

Page 21: TRANSMISSION NETWORK CONGESTION

NERC

Page 22: TRANSMISSION NETWORK CONGESTION

NERC

Page 23: TRANSMISSION NETWORK CONGESTION

NERC

Page 24: TRANSMISSION NETWORK CONGESTION

NERC

Page 25: TRANSMISSION NETWORK CONGESTION

NON-PRICE RATIONING

• Works reasonably well from a reliability perspective as long as there is good communication between SOs, between SOs and generators and generators follow instructions

• Redispatch is not necessarily efficient because it is not based on hour-ahead costs of redispatch

• TLRs continue to increase• Continuing arguments about whether redispatch

was “fair” and consistent with contracts– This problem is exacerbated when SO also owns

generating capacity on the network• Cost and price of congestion is not transparent

Page 26: TRANSMISSION NETWORK CONGESTION

WECC

●●

●● ●

● ●

●●

Adapted from NERC

Page 27: TRANSMISSION NETWORK CONGESTION
Page 28: TRANSMISSION NETWORK CONGESTION

DOE

Page 29: TRANSMISSION NETWORK CONGESTION

DOE

Page 30: TRANSMISSION NETWORK CONGESTION

DOE

Page 31: TRANSMISSION NETWORK CONGESTION

CAISO

Page 32: TRANSMISSION NETWORK CONGESTION

CAISO

Page 33: TRANSMISSION NETWORK CONGESTION

CAISO

Page 34: TRANSMISSION NETWORK CONGESTION
Page 35: TRANSMISSION NETWORK CONGESTION

CAISO

Page 36: TRANSMISSION NETWORK CONGESTION

CAISO

Page 37: TRANSMISSION NETWORK CONGESTION

TRANSMISSION INVESTMENT• Driven by reliability criteria and economic opportunities

to reduce congestion– These are not independent– Implementation of reliability criteria affect market prices

• Origins of engineering reliability criteria are opaque– Solutions to restore reliability criteria are complex and do not

have unique solutions– Require interaction over entire synchronized network involving

multiple SOs• Not conducive to link-by-link merchant investments• Regional planning and integrated assessment of

reliability and economic criteria are essential• Economic implications and justifications for reliability

criteria need a fresh assessment