transcript 9.28.10 creelman twp outside engineer

Upload: mariner12

Post on 05-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    1/79

    SUPERIOR COURT OF NEW JERSEYLAW DIVISION, CIVIL PARTUNION COUNTY, NEW JERSEYDOCKET NUMBER: UNN-L-0140-08A.D. NO.:___________________

    LEHIGH ACQUISITION, ET AL::

    Plaintiff, :: TRANSCRIPT

    vs. :: OF

    TOWNSHIP OF CRANFORD, :: TRIAL

    Defendant. :

    Place: Union County CourthouseTwo Broad StreetElizabeth, New Jersey 07207

    Date: September 28, 2010P.M. Session

    BEFORE:

    HONORABLE LISA F. CHRYSTAL, J.S.C.

    TRANSCRIPT ORDERED BY:

    CARL R. WOODWARD, III, ESQ. (Carella, Byrne,Cecchi, Olstein, Brody & Agnello)

    APPEARANCES:

    STEPHEN M. EISDORFER, ESQ. (Hill Wallack LLP)Attorney for the Plaintiff

    CHARLES R. WOODWARD, ESQ. (Carella, Byrne, Cecchi,Olstein, Brody & Agnello)

    Attorney for the Defendant

    BRIAN FENLON, ESQ. (Carella, Byrne, Cecchi,Olstein, Brody & Agnello)

    Attorney for the Defendant

    DARCEL D. HARTUTOMATED TRANSCRIPTION SERVICES

    P.O. Box 1582Laurel Springs, New Jersey

    (856) 784-4276

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    2/79

    2

    APPEARANCES (Continued)

    VINCENZO M. MOGAVERO, ESQ. (Carella, Byrne,Cecchi, Olstein, Brody & Agnello)

    Attorney for the Defendant

    DARCEL D. HARTUTOMATED TRANSCRIPTION SERVICES

    P.O. Box 1582Laurel Springs, New Jersey

    (856) 784-4276

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    3/79

    3

    I N D E X

    September 28, 2010

    WITNESSES Direct Cross Redirect Recross

    Mr. Creelman 3

    EXHIBITS Ident. Evid .

    D-25c Photographs 30D-25d Photographs 30D-25m Photographs 30D-25n Photographs 30D-43 Site investigation report 21D-94 10/14/09 Creelman Report 9D-113 Report prepared in response to

    L2A report 27D-138 Creelman Resume 6 8D-157 Alpha Survey prepared by Control

    Point 10D-159 Letter from PS&S, Mr. Creelman dated

    July 16, 2010 49D-162 August 3 plan 47D-178 Original development plans for the

    site dated September 22, 2008 14D-179 Letter dated August 23, 2010 54D-181 Mr. Creelmans report 61D-182 The Urban Hydrology for Small

    Watersheds 66D-184 Letter dated 9/2/10 with

    supplemental information 60

    P-37 Copy of the report from Mr. Dipple 27P-38 2/4/2010 letter from Mr. Dipple

    to Mr. Eisdorfer 36

    P-39 Concept Plan report dated 3/31/2010 37P_39a Board attached to the report 41P-80 Letter with flood storage volume

    calculations 56P-82 Attachment to letter 57P-83 Attachment to letter 57P-87 August 19 report from Mr. Dipple 59

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    4/79

    Creelman - Direct 4

    (The afternoon session starts at 1:40 p.m.)1

    MR. WOODWARD: Your Honor, Id like to call2

    my next witness who Mr. Thomas Mr. Creelman.3

    (Pause)4

    T H O M A S C R E E L M A N, DEFENSE WITNESS, SWORN5

    THE CLERK: State your name for the record.6

    THE WITNESS: Tom Creelman.7

    THE CLERK: Spell your last name.8

    THE WITNESS: C-R-E-E-L-M-A-N.9

    THE CLERK: Be seated.10

    THE WITNESS: Okay. Thank you.11

    DIRECT EXAMINATION (VOIR DIRE) BY MR. WOODWARD:12

    Q Mr. Creelman, by whom are you employed?13

    A Paulus, Sokolowski and Sartor, PS&S.14

    Q And what is Paulus, Sokolowski and Sartor?15

    A We are a consulting engineering firm.16

    Q And could you give us the benefit of your17

    background and qualifications?18

    A Yes. I've been with the firm for approximately 2119

    years. I'm a Senior Associate with the firm. My20

    duties have included project management and design.21

    During that course of time period, I received my22

    license for, as a Professional Engineer in the State of23

    New Jersey in 2002.24

    My duties also include, as a Project Manager,25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    5/79

    Creelman - Direct 5

    we work in design teams in a Civil Group in our Civil1

    Department. So I work with other peoples in my --2

    other people in my team to design projects from3

    conception to construction.4

    Q And, where did you get your college degree?5

    A I got my degree from the New Jersey Institute of6

    Technology.7

    Q And you're a licensed Professional Engineer?8

    A Yes, I am.9

    Q And, besides your current duties and10

    responsibilities, what other prior employment have you11

    had in the engineering field?12

    A When I first graduated from college, I was13

    employed by the engineering firm of Worchester14

    (phonetic) Partnership.15

    Q And what was your, what were your duties and16

    responsibilities there?17

    A I was a Staff Engineer, design of storm water18

    systems, grading of sites, sanitary sewer system19

    design, things of that nature.20

    Q And is your area of practice Civil21

    Engineering?22

    A Yes.23

    Q And Do you have any particular areas that you24

    focus on?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    6/79

    Creelman - Direct 6

    A Probably in the past ten years, I have more1

    focused on urban redevelopment, brownfield (phonetic)2

    redevelopments in cities and so forth, where you take a3

    what was formally a, industrial, more of an industrial4

    site, and convert it into a residential and/or5

    commercial use.6

    Q And, as part of that, what sort of analysis7

    do you--8

    MR. WOODWARD: Strike that.9

    BY MR. WOODWARD:10

    Q Do you do analyses with respect to storm11

    water management?12

    A Yeah, we, we follow a, as of 2004, we now follow13

    the new Storm Water Two regulations as adopted by the14

    DEP.15

    Q And, do you also practice in areas of16

    determining flood hazards and flood hazard regulations?17

    A Yes, we do.18

    Q I'm going to show you what's been marked19

    D-138 for identification, and ask you if you can20

    identify this document. It's -- looks like it's a21

    resume of sorts.22

    A Yeah. This is my resume from my current firm,23

    PS&S.24

    Q And where is PS&S located?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    7/79

    Creelman - Direct 7

    A Our main office, our headquarters is in Warren1

    Township, New Jersey in Somerset County.2

    Q And is, is that the office that you work out3

    of?4

    A Yes, it is.5

    Q Now, as part of your practice as a6

    Professional Engineer, have you ever been qualified to7

    testify, either before Planning Boards, Boards of8

    Adjustment or in court?9

    A Yes, I have, Planning Boards.10

    Q And on how many occasions have you testified11

    before Planning Boards?12

    A Approximately 40.13

    Q About 40 times?14

    A Approximately 40 times, yes.15

    Q And your testimony is in, is as a16

    Professional Engineer. Is that correct?17

    A Yes.18

    MR. WOODWARD: Your Honor, Id like to offer19

    Mr. Creelman as a engineering expert in the field of20

    Civil Engineering at this time.21

    MR. EISDORFER: No objection, Your Honor.22

    THE COURT: He will be so qualified.23

    MR. WOODWARD: Your Honor, Id also like to24

    offer into evidence his resume which is D-138.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    8/79

    Creelman - Direct 8

    MR. EISDORFER: No objection.1

    THE COURT: D-138 in evidence.2

    (Pause)3

    DIRECT EXAMINATION (CONTINUED) BY MR. WOODWARD:4

    Q Now, in connection with this litigation5

    before the Court, have you been retained by the6

    Township of Cranford?7

    A Yes, I have.8

    Q And could you tell us what the nature and9

    scope of your assignment for Cranford has been?10

    A We were requested to review the site and documents11

    provided to us for a site constraints analysis to12

    determine what physical constraints on the site would13

    inhibit development of the site?14

    Q And you say physical constraints, does that15

    include environmental constraints as well?16

    A Environment -- wetlands, boundaries, flood hazard17

    issues, riparian rights issues, endangered species18

    issues; things of that nature.19

    Q And during the course of your retention by20

    the Township, have you prepared any reports?21

    A Yes, I have.22

    Q I'm going to show you what's first been23

    marked as D-94. It's a document from you addressed to24

    me dated October 14, 2009, and ask you if you can tell25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    9/79

    Creelman - Direct 9

    us what that is.1

    A This is the first report that I prepared for the2

    project after receiving documents. I received and3

    reviewed several documents that I received from the4

    Township through your office regarding elements of the5

    site, a conceptual site plan prepared by the plaintiff6

    dated September 22, 2008; a second conceptual site plan7

    dated April 29, 2008; an aerial map of the site. Do8

    you want me to list everything I went through that's in9

    the report?10

    Q Yeah, if you would go through it. I know11

    it's fairly lengthy, but I think for the record, it's12

    appropriate.13

    A Okay. A water mane map, drawing number five, no14

    date; center city sewer capacity study prepared in15

    January 2009 by L2A; FEMA Study Map for the Township of16

    Cranford dated September 20,2006; a letter of17

    interpretation for a line verification for the property18

    from the DEP dated August 20, 2009; the Township of19

    Cranford applicable tax map last revised June 28, 1993;20

    a copy of the Cranford Township Zoning Map; plaintiff's21

    brief in support of the motion for the partial summary22

    judgment dated January 30, 2009; the New Jersey State23

    Development and Redevelopment Plan dated March 1, 2001;24

    a Policy Map of the New Jersey Development and25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    10/79

    Creelman - Direct 10

    Redevelopment Plan dated March 1, 2001; a Site1

    Assessment Report dated May 21, 2008 referred by L2A; a2

    plan entitled Wetland Survey Plan prepared by Control3

    Point, last revised in July 29, 2009; an Alpha Survey4

    dated June 11, 2008, last revised September 11, 2008,5

    as prepared by -- again prepared by Control Point. An6

    existing Center City Sewer Map dated January 20097

    prepared by L2A; a memorandum prepared by the Township8

    of Cranford Engineer dated October 19, 2008; a Wetlands9

    Delineation Report dated November 2008 and prepared by10

    the Princeton Hydro (phonetic) for the Township of11

    Cranford.12

    Q Now with respect to your assignment preparing13

    the analysis, what was your starting point?14

    A We began looking at the, these documents to get an15

    understanding of where the site was located in the16

    Township, what zone it was located in, what some of the17

    physical features of the site were, the size of the18

    site, where the wetlands were located on the site, what19

    structures were located on the site. The site20

    contained approximately 15 acres of property, two21

    buildings and two parking lots.22

    Q I'm showing you whats been previously marked23

    as D-157 in this case. Have you seen this before?24

    A Is that the --25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    11/79

    Creelman - Direct 11

    Q If you want to get up and take --1

    A Sure.2

    Q -- a look at it, you can.3

    A Yes, I've seen this document.4

    Q And that is what?5

    A It's the Alpha Survey prepared by Control Point.6

    It's a boundary survey thats been certified to a7

    certain individual. It shows existing structures,8

    buildings, parking lots, and topography on the site and9

    immediately surrounding the site.10

    Q Does it also show a delineated wetlands line?11

    A Yes, it does show a delineated wetlands line12

    covering approximately six acres in the southwest13

    portion of the site in this area here.14

    THE COURT: What exhibit is that? What15

    exhibit is that Mr. --16

    MR. WOODWARD: D-157, Your Honor.17

    THE COURT: Thank you.18

    (Pause)19

    BY MR. WOODWARD:20

    Q Now, did you do an environmental evaluation21

    of the site?22

    A We reviewed the site from a standpoint of23

    wetlands, wetlands buffers, riparian buffers,24

    endangered species, plants, and animals. We concluded25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    12/79

    Creelman - Direct 12

    that there were no threatened or endangered species on1

    the site based upon data sets that we reviewed from the2

    DEP that are available through the DEP. We also3

    indicated that based upon the delineation that was4

    provided on the map and the letter of interpretation5

    provided by the DEP, that the wetlands that had been6

    delineated on the site were appropriate.7

    Q With respect to the other portions of the8

    site, did you, in terms of environmental, I think you9

    said -- did you evaluate --10

    MR. WOODWARD: Withdraw, withdrawing, Your11

    Honor.12

    BY MR. WOODWARD:13

    Q Did you evaluate any storm water or flooding14

    that occurred or may occur on the site?15

    A We reviewed, we visited the site in early October.16

    Q What year?17

    A 2009.18

    Q Okay.19

    A And we reviewed some, the storm inlets, the20

    overall topography of the site. The site is bounded to21

    the west by a brook known as Casino Brook, otherwise22

    identified as, I believe it's --23

    Q You can refer to your report, by the way, if24

    you wish.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    13/79

    Creelman - Direct 13

    A -- 10-24.1

    Q And did you make any determinations as to2

    whether there were, there was flooding on this3

    property?4

    A Based upon a review the FEMA maps and the5

    delineation provided on the FEMA maps, it was our6

    belief that there was a delineation of floodway and7

    flood hazard lines to the site.8

    Q You say there was from the FEMA maps?9

    A Not on the FEMA maps, but the way they were10

    configured, the adjacent towns, Kenilawn (sic)11

    Kenilworth, sorry. Kenilworth showed a 100 year and12

    500 year flood line ending at the municipal boundary13

    line.14

    We subsequently also called the DEP and asked15

    for an interpretation of the map, and we were told that16

    the, the, Kenilworth did request that FEMA map Casino17

    Brook in their township, but Cranford did not. And,18

    therefore, a delineation of the floodway on Casino19

    Brook within the Township of Cranford did not exist.20

    It was not mapped on the FEMA plans.21

    Q So, did you form an opinion as to whether or22

    not a flood hazard area study was required in23

    connection with the proposed development on the site?24

    A Based upon looking at the FEMA maps in25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    14/79

    Creelman - Direct 14

    Kenilworth -- I'm sorry, Kenilawn (sic) -- and for the1

    mapping that was don for the Rahway River, we felt2

    there was a necessity to have it done, that a floodway3

    did exist, a flood hazard area would exist on the site.4

    Q In connection with -- and I just referred to5

    the proposed development on the site; I'm going to show6

    you what's been marked as D-178 in evidence. And7

    actually, I direct your attention to the exhibits.8

    Take a moment to look at those. Have you ever seen9

    those before? They're dated September 22, 2008.10

    A Yes, I have.11

    Q Okay. And was that the original development12

    plan for this site proposed by the plaintiffs that you13

    reviewed?14

    A Yes, it is.15

    Q Now, could you tell us exactly how the16

    buildings were laid out on that particular site? As a17

    matter of fact, I can also show you -- well, how were18

    the parking lots laid out on that, on that map?19

    A There were three, three buildings total. They20

    were A, B, C. Building A is a residential building.21

    Building B is a residential building. And Building C22

    is a parking garage wrapped on three sides by Building23

    B. A large portion of the, both buildings fronts on --24

    to the north on Birchwood Avenue. And Building A takes25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    15/79

    Creelman - Direct 15

    up at least, I want to say, a third, if not more, of1

    the frontage along Birchwood Avenue, as does Building2

    B.3

    Q And -- now, did you form a professional4

    opinion as to whether a flood hazard area study in5

    connection with a proposed development was required?6

    A Yes, I did.7

    Q And why was that?8

    A Based upon the review of the documents from FEMA9

    and our conversation and our call to FEMA, and the10

    limits of what was provided upstream and downstream of11

    the site, it was my professional opinion that a flood12

    hazard area did exist for the site, even though one was13

    not mapped at that point in time.14

    Q Now, moving on in your report to the15

    wetlands, did you -- you evaluated the wetlands survey,16

    the wetlands delineation?17

    A Yes, we did.18

    Q And with respect to that, did you agree with19

    all that was described in there?20

    MR. WOODWARD: Strike that.21

    BY MR. WOODWARD:22

    Q Did you find any areas that may have required23

    riparian buffer?24

    A We felt that an area to the south of the parking25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    16/79

    Creelman - Direct 16

    lot on Lot 215 may be as it was an -- appeared to be a1

    natural generalized water course may have a riparian2

    buffer on it.3

    Q And why did you feel that it needed a, may4

    have needed a riparian buffer.5

    A Under the regu, under the regulations, if the, if6

    a natural channelized water course for the drainage7

    area of 50 acres or more, it is required by regulation8

    to have a buffer, a minimum buffer of 50 feet.9

    Q Now, in reviewing the plan, did you review10

    the parking analysis or the parking that was indicated11

    on that plan, the September 22, 2008 plan?12

    A Yes, we did.13

    Q And what conclusions, if any, did you draw14

    from that?15

    A That the -- excuse me. That the general at grade16

    parking, the size of the parking was adequate. Our17

    main concern was the relationship of the parking, the18

    encroachment of the parking into the wetlands buffer.19

    Q And, what conclusion in terms of, what was20

    the issue there that there if was a problem?21

    A It's been our experience that the DEP normally22

    doesnt like encroachments into the wetlands buffer23

    parallel to it. They prefer you to go perpendicular to24

    it if you're going to have encroachment into it at all.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    17/79

    Creelman - Direct 17

    Q Now, did you offer any comment on the storm1

    water management in your report?2

    A Yes, we did.3

    Q And what observations -- first of all, what4

    did you review, and what observations did you make, and5

    what conclusions did you draw?6

    A We reviewed the Alpha Survey. We met with the7

    Township Engineer. We also visited the site. During8

    my visit at the site, in reviewing the brook and the9

    adjacent properties to the south side of 215 Birchwood,10

    south of the parking lot, there is a channel. And11

    adjacent to that channel where all the storm water for12

    that parking lot drains to, there are existing13

    structures that the parking lot pipes drain into.14

    Leaving those structures, there is a different15

    composition of pipe. And on top of those, above those16

    grounds is indicated valves, some type of valve that17

    can be closed.18

    Q Could you go up to D-157 and point out to the19

    Court -- first of all, 215 Birchwood versus 23520

    Birchwood for the record?21

    A Sure. I'm pointing at the Alpha Survey. And 21522

    Birchwood is the site on the eastern half of the23

    project. 235 Birchwood is the site located on the24

    westerly half of the project. What I'm referring to is25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    18/79

    Creelman - Direct 18

    the area to the south of the parking lot at 2151

    Birchwood.2

    Q A parking lot sort of in the center of 215,3

    correct?4

    A Correct.5

    Q All right.6

    A In general, the drainage area for this parking lot7

    drains to the south, southwest of the parking area into8

    an area over here. The two pipes, the two main9

    discharge pipes drain into two structures. Those two10

    structures, the pipes enter on one side of the11

    structure. On the opposite side of those structures,12

    there is a ductile iron pipe that discharged. Those13

    pipes eventually turn back from ductile iron pipe back,14

    back into concrete pipes in the swale. But in the15

    course of traveling underground, there are indications16

    on the surface there are valves within, contained17

    within those ductile iron pipes.18

    Q Now what's a ductile iron pipe?19

    A A ductile iron pipe is just a composition of pipe.20

    It's made out of a type of steel thats used in21

    development.22

    Q And, --23

    A Versus concrete pipe, plastic pipe, that sort of24

    thing.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    19/79

    Creelman - Direct 19

    Q Okay, so what you found there on the south1

    side of the parking lot was leading out of the chamber,2

    a ductile iron pipe, and before it got to its full3

    outlet, it was a concrete pipe?4

    A Correct.5

    Q And then you said there were valves?6

    A In, in the line with, where the pipe left7

    the -- leaves the chamber --8

    Q Right.9

    A -- and where the pipe discharges into the channel,10

    surface indications there is a valve shown on the11

    ground, there is a physical valve, or the remains of a12

    valve if you will.13

    Q And there was a valve in what each one of14

    those --15

    A Downstream of each chamber that was there, each16

    concrete chamber, yes.17

    Q And you said it was associated with a ductile18

    iron pipe?19

    A Yes.20

    Q How do you know that?21

    A Experience. You dont put a, a metal valve on a22

    concrete pipe normally.23

    Q Why not?24

    A In trying to make it -- to seal it is more25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    20/79

    Creelman - Direct 20

    difficult. Would you, would you have a type of1

    situation where you have ductile iron pipes connecting2

    to a valve? There will be plates, and you can bolt3

    them together very easily.4

    Q Now, did you draw any conclusion from the5

    storm water system or whatever you saw in that parking6

    lot particularly into the whole site regarding storm7

    water management?8

    A Basically my -- I summarized that the -- in my9

    report that the existing valving system was utilized to10

    provide some level of reduction or retention of the11

    storm water leaving the site to reduce the amount of12

    water off the site during the peak storm event.13

    Q Did you make any recommendations in your14

    report about what should be done, if anything, to study15

    further that area?16

    A We recommended that during the post-development17

    analysis and design of the storm water managing system18

    that this existing detention be taken into account19

    during the overall design of the proposed storm water20

    management system.21

    Q Now, at the end of your report on page nine22

    in paragraph five addendum, you added something to that23

    report. Could you tell us what that was?24

    A Our initial, the initial package that we25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    21/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    22/79

    Creelman - Direct 22

    A That is a report entitled Site Investigation,1

    Birchwood Avenue Cranford Township, Union County, New2

    Jersey. It was prepared by L2A Design and dated3

    May 21, 2008.4

    Q And I'm going to show you at the end of the5

    report an appendix. And the first item on the6

    appendix, is that, is that the conceptual, first7

    conceptual site plan you reviewed?8

    A That is correct, yes.9

    Q And, --10

    MR. WOODWARD: I, I know the Court is looking11

    for its documents right now.12

    THE COURT: Yeah, let me look. It was D-43?13

    MR. WOODWARD: Yes. Heres one for the14

    Court.15

    THE COURT: Thank you. It's already up here,16

    but it --17

    MR. WOODWARD: It will be easier.18

    THE COURT: -- takes a while to read through19

    them all to find it. Thank you.20

    BY MR. WOODWARD:21

    Q Take a look at D-43. Could you describe the22

    Concept Plan that was presented first in April of 2008?23

    A The original Concept Plan --24

    MR. EISDORFER: Your Honor, object to the25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    23/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    24/79

    Creelman - Direct 24

    THE WITNESS: Yes.1

    THE COURT: Okay. So you -- can you just2

    point to what you're referring to?3

    THE WITNESS: Sure. Absolutely. I'm4

    referring to Building C. On the April 29, 2008 map,5

    Im just saying that Building C as identified in6

    September plan, is the parking garage, here.7

    THE COURT: Okay.8

    THE WITNESS: And then the other, the9

    building that wraps around it to the south, west and10

    north, --11

    THE COURT: Thats B.12

    THE WITNESS: -- is Building B. It takes up13

    approximately a little more than 50 percent of the14

    frontage along Birchwood Avenue for the width of the15

    property, and a loop road wraps around it providing two16

    access points from Birchwood Avenue into the site.17

    Also the southern portion of Building B18

    respects the, the natural channelized water portion to19

    the south, and the wetlands immediately to the west of20

    it.21

    BY MR. WOODWARD:22

    Q Okay. Now, thank you. With respect to the23

    plan on -- now, there was one large building plus a24

    parking garage, correct, on the April ---25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    25/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    26/79

    Creelman - Direct 26

    units in September?1

    A Yes.2

    Q In the September plan?3

    A Correct, as well as the parking.4

    Q What was the parking called out in, in the5

    April plan?6

    A Parking provided for, the 379 units was 6957

    spaces. And in the September plan it was listed as 6738

    spaces provided.9

    Q So there are actually, actually fewer spaces.10

    A Correct.11

    Q Now, with the comparison of the April 29 th12

    plan to the September plan, did you draw any13

    conclusions as to the impact of the September 22 nd ,14

    plan, whether that was an increase in impact, or15

    decreased impact of -- over the building that was16

    described in the April 29 plan?17

    A The September 22, 2008 plan showed an increase in18

    impervious coverage above what was provided or shown on19

    the April 29, 2008 plan.20

    Q And, did that have any impact in terms of21

    what needed to be studied, analyzed, or provided for by22

    way of storm water management at the site?23

    A It would increase the amount of runoff. And that24

    would have to be taken into account in the storm water25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    27/79

    Creelman - Direct 27

    management design.1

    Q And so is that a recommendation of yours2

    that it needed to be studied?3

    A Yes.4

    Q Now, you prepared a second report, a5

    January 14, 2010, Exhibit D-113, 113. I'm going to6

    show you a copy of that, and could you tell me if you7

    can identify that?8

    A Yes, I can.9

    Q And, tell us what this is.10

    A This report, excuse me. We prepared this report11

    to review additional plans that were provided in, later12

    in the year, and in response to plan, a letter prepared13

    by Mr. Dipple of L2A Associates -- L2A Design.14

    Q And, what was it that you, what was it that15

    you did in terms of responding to Mr. Dipples report?16

    A There was a indication that flood hazard issue17

    still did not exist. We went and reviewed FEMAs flood18

    study maps for the Township of Cranford again. Those19

    plans -- that plan was dated September 2006 --20

    September 20, 2006. And a flood study map, and a FEMA21

    flood study map for the Borough of Kenilawn (sic)22

    again dated September 20, 2006.23

    Q Kenilworth?24

    A I'm sorry, Kenilworth. Excuse me.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    28/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    29/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    30/79

    Creelman - Direct 30

    Town -- Cranford Taxpayers website, utilizing several1

    of those photographs, we went and compared those2

    specific photographs in, in that website to key points3

    within the Alpha Survey which had elevations on it.4

    And we were able to determine certain elevations, or5

    approximate them, I should say.6

    Q Now, the photographs are, are they exhibits7

    C, D, E, and F, and G?8

    A Yes.9

    (Pause)10

    Q I'm showing you what's -- and these are11

    perhaps better copies. So, Id like to, to -- they're12

    more presentable than, than the photocopies that you13

    have. I'm showing exhibits D-25c, D-25d, D-25m, and14

    D-25n. Are those the photographs that you used to15

    assist you in trying to calculate the height of that16

    particular flow?17

    (Pause)18

    A Some of them are, yes.19

    Q Okay. Which ones did you use?20

    A I used D-25n, D-25d, D-25c. And also, there's21

    another photograph that doesnt appear to be in the22

    pile here that I used.23

    Q And that was --24

    A It would be Exhibit C.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    31/79

    Creelman - Direct 31

    Q -- Exhibit C, if youd show the Court --1

    A Certainly.2

    Q -- is a photograph of Birchwood.3

    THE COURT: Exhibit D-113, right?4

    THE WITNESS: Yes, it is. Yes.5

    BY MR. WOODWARD:6

    Q Okay. Now, could you describe for us how you7

    went about doing this evaluation based on the8

    photographs and the, Alpha Survey, which is D-157.9

    A Sure. I can go down to the map here real quick.10

    Q Sure.11

    A On the Alpha Survey, there are structures. In12

    particular, I'm going to point to the west side of the13

    entrance to the property at 235 Birchwood Avenue. If14

    you look at Exhibit C, that picture was taken standing15

    on the north side of Birchwood Avenue, excuse me; just16

    west of the actual entrance to the property.17

    If you look at the photograph, youll see two18

    cars within the street that are, have water up to the19

    rims. In the background of that, I don't think the20

    photocopy is clear enough; youll see a structure that21

    is a signage for the property. It identifies what this22

    property is, the street number, the, the, who is there23

    and all that kind of stuff. You can see that in the24

    picture.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    32/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    33/79

    Creelman - Direct 33

    the elevation as well. That's it.1

    Q And did that --2

    A There was no hydraulic analysis involved in that3

    study.4

    Q Did that support in any way your5

    recommendation that a flood hazard area study be6

    performed?7

    A It did because, the, the rainfall event that8

    occurred I believe on that date which was9

    April 15, 2007 was around, I think, eight, eight or10

    nine inches.11

    And, given that elevation and the -- what was12

    shown in the photographs, and the information provided13

    on the FEMA maps, upstream of the site, it was my14

    opinion that clearly a flood study would be required.15

    And if an analysis was done, a floodway and a flood16

    hazard line would certainly be showing, could be17

    generated for the site, would be generated for the18

    site.19

    Q Now, with respect to this, this site, was20

    this a site that, in your opinion, flooded21

    frequently -- or flooded?22

    A Yes.23

    Q And was that a severe flood that you saw?24

    A I would say it was significant.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    34/79

    Creelman - Direct 34

    Q Now, with respect to storm water management,1

    in your report, you also dealt with that particular2

    issue. Could you tell us what your, whether there was3

    any change in your position as earlier expressed or4

    modification of your position? Please describe that.5

    THE COURT: Which report are you referring6

    to?7

    MR. WOODWARD: I'm sorry, Your Honor, D-113.8

    BY MR. WOODWARD:9

    A I didn't change my opinion. I still felt that10

    when a storm water management system was designed for11

    the project, it would have to take into account the12

    existing shower detention in the parking lot shown on13

    215 Birchwood, and also that it needed to be taken into14

    account once the flood hazard parameters were15

    established. It would have to take that into account16

    as well, that storm water analysis.17

    Q And did you have any -- make any18

    determination as to whether the conceptual site plan of19

    September 22, 2008 provided sufficient detail to20

    determine whether or not the fresh water wetlands21

    regulations would be satisfied?22

    A Could you ask that question again?23

    Q Sure. Directing your attention to page four24

    of your report, you have a comment about the detail for25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    35/79

    Creelman - Direct 35

    freshwater wetlands general permits and transition area1

    waivers. Were you able to determine from the2

    information provided whether or not there was adequate3

    information to determine whether or not those permits4

    would be granted?5

    A No. No, there was not enough information.6

    Q There was not enough information?7

    A No, there was not.8

    (Pause)9

    Q Now, did there come a point in time when --10

    let me just rephrase that. When Mr. Dipple in his11

    October report -- take a look at this third paragraph12

    down from the top of the page, and that first item,13

    which is P-38. Your opinion was --14

    MR. WOODWARD: Strike that.15

    BY MR. WOODWARD:16

    Q Mr. Dipple felt that method three could be17

    used for determining the flood hazard area, correct?18

    A Yes, in that paragraph of his October 29 th , report19

    2000 --20

    Q And what's, what's method three?21

    A Method three allows you to look at flood insurance22

    rate maps for areas that have been delineated by FEMA23

    of flood waters for the -- within the 100 year and24

    outside the 100 year, within the 500 year, and outside25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    36/79

    Creelman - Direct 36

    the 500 year flood plain. If the map is available and1

    it's delineated, then method three permits you to use2

    that as, to verify whether you do or do not have a3

    flooding situation on your site.4

    Q And did you differ from Mr. Dipple on that,5

    whether method three could be used on this site?6

    A I did.7

    Q And what was your opinion?8

    A I felt that based upon the information I had9

    reviewed, both the FEMA maps, the site, the10

    photographs, the -- and my conversation that we had11

    with the DEP regarding the interpretation of the FEMA12

    map that a flood study was warranted and that either13

    method five or method six; method five being an14

    estimation method, and method six being a complete15

    backwater analysis, would be required to determine16

    where the floodway line and the flood hazard line would17

    be determined.18

    Q Did Mr. Dipple ultimately agree with you?19

    A Several months later, yes.20

    Q I'm going to show you what's been marked as21

    P-38. It's a letter dated February 4, 2010. Is that22

    from Mr. Dipple --23

    A Yes.24

    Q -- to Mr. Eisdorfer?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    37/79

    Creelman - Direct 37

    A Yes, it is.1

    Q And does that letter include his conclusions2

    regarding whether or not method six should be used?3

    A Yes, it does. He acknowledges that a, that a4

    study would be required, and that method three was not5

    appropriate, and that a, a flood hazard analysis, a6

    hydraulic analysis would be required.7

    Q Now, did there come a time when you became8

    aware that a flood hazard study actually had been done?9

    A Yes.10

    (Pause - side discussion)11

    BY MR. WOODWARD:12

    Q I'm going to show you what's been marked as13

    P-39. It's a report dated March 31, 2010. Have you14

    ever seen that before?15

    A Yes, I have.16

    Q And, what is that?17

    A This is a report by L2A by Mr. Dipple explaining18

    that they went through and they prepared a backwater19

    analysis -- I'm sorry, a flood plain analysis for the20

    site using methodology number six, for -- to determine21

    the flood hazard area, line as it wraps through the22

    project.23

    Q And does it -- is there anything else that's24

    included with that report?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    38/79

    Creelman - Direct 38

    A It provides elevation upstream at the northern end1

    of the site of 78.6 for the elevation of the flood2

    hazard elevation as it traverses through the site, an3

    elevation of 78.4 at the downstream end. It also4

    provides for a -- can you give me one minute?5

    Q Certainly. Take your time.6

    (Pause)7

    A It also provides a, a map entitled FEO-01 dated8

    March 31, 2010. I believe the basis of the map was the9

    Alpha Survey prepared by Control Point. And on that10

    map has been plotted the, the floodway lines and the11

    flood hazard -- limits of the flood hazard area limit12

    lines as it traverses through the site.13

    Q May I see that, please?14

    A Sure. But I dont see the other one.15

    MR. WOODWARD: Excuse me, Your Honor.16

    (Pause)17

    Q All right. Now when you looked at that, were18

    you able to determine whether there was a flood hazard19

    area on the site?20

    A Based upon the analysis performed L2A, yes, I was21

    able to determine there is a --22

    Q And, and can you show the Court where the23

    floodway line is and the flood hazard area line is?24

    A On this one?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    39/79

    Creelman - Direct 39

    Q Hold it up, yeah. Show it to the Court.1

    A Sure. The, the floodway line is a solid line2

    traversing the site from north to south, about a third3

    of the way in from the westerly property line. The4

    other side of the floodway line is indicated on the5

    west side of Casino Brook which is just on the property6

    line adjacent to the adjacent property.7

    The flood -- excuse me, the flood hazard area8

    line, the easterly flood hazard area line is shown as a9

    dash line approximately one-third off the east,10

    easterly property line of the site.11

    And the adjacent flood hazard area line to12

    the westerly side of the stream is very close to the13

    floodway line. Again, all, all of these refers to the14

    north and south.15

    THE COURT: Does it mean that everything in16

    between is the floodway?17

    THE WITNESS: Correct. The, the floodway18

    goes to this, from this solid line here on the west19

    side of the brook --20

    THE COURT: To here.21

    THE WITNESS: -- to this line here on the22

    east side of the brook.23

    THE COURT: (inaudible).24

    THE WITNESS: Correct, that is the floodway25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    40/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    41/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    42/79

    Creelman - Direct 42

    the March 31, 2010 letter from Mr. Dipple. Was there a1

    revised Concept Plan submitted?2

    A Yes, there was.3

    Q And, could you briefly tell us what the4

    revisions were to the last plan which was September 22,5

    2009 -- or 2008?6

    A Youd like just a brief explanation of the7

    comparison --8

    Q Yes.9

    A -- between the September 22 nd --10

    Q Right.11

    A -- and the -- okay.12

    Q Right.13

    A Do I still have a copy of the plan showing that?14

    Q Here you go. It's D-178.15

    A Okay.16

    Q The exhibits D-178.17

    A Thank you.18

    THE COURT: Okay. So we're talking about19

    D-43 and D-178, correct?20

    MR. WOODWARD: P-39, Your Honor.21

    THE COURT: P-39?22

    MR. WOODWARD: P-39, Your Honor, yes.23

    (Pause)24

    THE COURT: Okay. P-39a, right?25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    43/79

    Creelman - Direct 43

    MR. WOODWARD: P-39. That's P-39a, Your1

    Honor, on the board.2

    THE COURT: I have it as P-39a. Is there a3

    separate P-39?4

    MR. WOODWARD: This is P-39a.5

    THE COURT: Okay. The report is P-39.6

    MR. WOODWARD: P-39. And there are actually7

    two other pages that go with P-39 that are not there.8

    MR. EISDORFER: They are, they are actually9

    separate exhibits?10

    MR. WOODWARD: Are they?11

    MR. EISDORFER: Yes. So that's actually P-812

    THE COURT: So what I'm looking at was in my13

    binder.14

    MR. EISDORFER: Right.15

    THE COURT: So I just want to be clear that16

    I'm looking at the same thing, --17

    MR. EISDORFER: Yeah.18

    THE COURT: -- that we're talking about in19

    the testimony. So P-39a, --20

    MR. WOODWARD: Is this board here, Your21

    Honor.22

    THE COURT: -- is the board that was23

    attached? Okay. P-39 is the report, --24

    MR. WOODWARD: Correct.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    44/79

    Creelman - Direct 44

    THE COURT: -- the Concept Plan.1

    MR. WOODWARD: And then there are two other2

    exhibits, --3

    THE COURT: Which I don't have.4

    MR. WOODWARD: -- that Mr. Eisdorfer says5

    have separate exhibit numbers.6

    MR. EISDORFER: Yeah. They have separate7

    exhibit numbers. I believe hes referring to P-8,8

    which is the March 31 st .9

    THE COURT: Let me check. P-8?10

    MR. EISDORFER: Yes. And that together with11

    that is P-9, which is seven sections.12

    THE COURT: Let me just get that.13

    MR. WOODWARD: -- of P-8.14

    MR. EISDORFER: And they may have D numbers15

    too, but I'm not sure.16

    THE COURT: Okay. So P-8 and P-9?17

    MR. EISDORFER: Yes. And, actually, the18

    defendant marked those as D-150 and D-151.19

    THE COURT: So P-8 is D-150?20

    MR. EISDORFER: Yes.21

    THE COURT: And P-9 is D-151.22

    MR. EISDORFER: That's correct.23

    THE COURT: Thank you.24

    (Pause)25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    45/79

    Creelman - Direct 45

    MR. WOODWARD: All right. Your Honor, just1

    to clarify, what we're going to do here from the2

    defense perspective, --3

    THE COURT: Thank you.4

    MR. WOODWARD: -- there are three documents5

    which we have marked as D-149 which is the floodway6

    exhibit, --7

    THE COURT: Oh, wait a minute.8

    MR. WOODWARD: -- which is also the colored9

    version of P-39a. If you take -- yeah. That's that10

    page.11

    THE COURT: Okay. So D-149 equals P-39a?12

    MR. WOODWARD: Correct.13

    THE COURT: Okay.14

    MR. WOODWARD: Then D-150 is the revised15

    Concept Plan --16

    THE COURT: That's here. Yes.17

    MR. WOODWARD: -- dated March 31, 2010.18

    THE COURT: P -- it's P-9, right?19

    MR. WOODWARD: P -- ...20

    (Tape #1 ends; Tape #2 begins)21

    THE COURT: Well, it's a total of 705 -- from22

    that, according to this witness' testimony. Let's put23

    it that way. Okay. I'm sorry to interrupt.24

    MR. WOODWARD: No. That's all right, Your25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    46/79

    Creelman - Direct 46

    Honor. Thank you.1

    BY MR. WOODWARD:2

    Q Now, you said Building A in the March 31 plan3

    was revised. And what was the purpose of moving that4

    and revising it?5

    A Building A used to be a T with the top of the T6

    parallel to Birchwood Avenue as a result of the7

    delineation and plotting of the floodway line, as was8

    done by L2A. The old configuration of Building A on9

    the September 2008 plan would have been, I want to say10

    more than, I'm estimating more than three quarters of11

    the way within the floodway, which is not allowed under12

    the DEP regulations. So Building A was reconfigured to13

    a, a reversed L with its long side perpendicular to14

    Birchwood Avenue to respect the floodway line.15

    Q Now, did that plan that you're looking at16

    right now from March 31, 2010 show the flood, the limit17

    of the flood hazard area?18

    A No, it does not.19

    Q So, --20

    A It only shows the floodway line.21

    Q Is that a significant omission?22

    A In, in my opinion, yes.23

    Q Why?24

    A You need to know, not only where the floodway line25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    47/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    48/79

    Creelman - Direct 48

    have a reasonable overlap, so we felt that they're1

    relatively accurate to their comparison to one other.2

    We utilize what's shown on both plans as this3

    blue line right here as it wraps around, as shown on4

    the exhibit, represents the location of the limit of5

    the existing parking lot on the south side, east side6

    and west side of 215 Birchwood that exists in both7

    plans. We were able to use that as a key point, if you8

    will, to approximate bringing this line easterly, flood9

    hazard limit line from the other plan, this plan here,10

    the flood area, and flood plain delineation plan,11

    Exhibit P-39a, to be able to superimpose it on this12

    plan to see where it, in fact, falls in relationship to13

    Building B.14

    Q And what, as a result of that overlay, what,15

    what was its relationship, what was that flood hazards16

    limitation or limit line in relation to building A?17

    A It shows that all of Building A still remains18

    within the, the area between the floodway line, and the19

    flood hazard line, the flood area known as the flood20

    fringe area here.21

    Q Now, could you also determine whether or not22

    any portion of proposed Building B was in the flood23

    hazard area?24

    A Yes. Based upon the plot, we were able to show25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    49/79

    Creelman - Direct 49

    that the northern, a northern portion of Building B was1

    within the flood, flood fringe area, or within the,2

    encroaches in the flood hazard area.3

    Q Now, --4

    THE COURT: What exhibit is this?5

    MR. WOODWARD: That's P, I think it's 162.6

    MR. EISDORFER: No, D.7

    MR. WOODWARD: No, D, D-162.8

    MR. EISDORFER: D-162.9

    MR. WOODWARD: Dated August 3 rd .10

    THE COURT: Thank you.11

    BY MR. WOODWARD:12

    Q Now, I'm going to show you what's been marked13

    as D-159 for identification and ask you if you can14

    identify that document? It's dated July 16, 2010.15

    THE COURT: What is the number? I'm sorry,16

    what number was that?17

    THE WITNESS: D-159.18

    BY MR. WOODWARD:19

    A It's a letter from PS&S, myself, to Mr. Woodward20

    dated July 16, 2010.21

    Q And, what was this report?22

    A This is a, a letter from us to, to respond to a23

    request from you for us to review the information24

    provided to us from the plaintiff on March 31, 2010.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    50/79

    Creelman - Direct 50

    Q And so the documents that we've gone through,1

    the report from Mr. Dipple, the, the delineation of the2

    floodway and the flood hazard line, and the revised3

    Concept Plan were what you reviewed in that letter,4

    correct?5

    A Correct, yes.6

    Q Okay. Could you go through your report and7

    tell us what observations you made or -- from your8

    analysis of the documents dated March 31, 20109

    submitted by Mr. Dipple?10

    A The, the new layout provided by Lessard increased11

    the -- well actually more than doubled the amount of12

    surface parking -- one minute; yes, more than doubled13

    the amount of surface parking from 73 to 171 spaces,14

    which would --15

    THE COURT: 73 to what?16

    THE WITNESS: From 73 to 171 spaces.17

    BY MR. WOODWARD:18

    A -- based upon the new alignment of the, the19

    buildings and the reconfiguration of the buildings.,20

    which resulted in the reconfiguration of,21

    reconfiguration of the driveway. And I noted that the,22

    I was concerned that the driveway where it's between23

    Buildings A and B had a double, a left-hand turn and a24

    quick right-hand. I was concerned with respect to the25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    51/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    52/79

    Creelman - Direct 52

    the, I was able to go back and show the impervious area1

    did decrease slightly, but as the proposed roof area is2

    significantly above the surface, any discharge from the3

    roof area will not be detained in a parking lot at all,4

    as it does on the existing addition. It will readily5

    just discharge off site. It won't even backup, because6

    it's certainly higher than the surrounding elevations.7

    And that should all be taken into account in the8

    significant, in the storm water management design.9

    Q Did you have any comments on the wetlands10

    buffer?11

    A The wetlands buffer itself, I agreed, I believe12

    the plaintiff had issued a letter indicating that the13

    wetlands buffer south of the parking lot on 215 as that14

    had a -- no resource value. A buffer of 50 feet was15

    not required. And we agreed with that as far as the16

    wetlands goes, we were still concerned about a riparian17

    issue though, to determine if the, that natural18

    channelized water course had a drainage area of 50 feet19

    or -- 50 acres or more going to it.20

    And also that we couldnt see any proof that21

    the, that any displacement of storage within the flood22

    fringe area, if it was compensated for, it had to be23

    compensated for both below, above between a 10 year,24

    and a 100 year, and above the 100 year storm itself.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    53/79

    Creelman - Direct 53

    You can't swap elevations for it.1

    Q And was this as a result, these observations2

    are from reviewing what was submitted on3

    March 31, 2010, correct?4

    A Correct.5

    Q What conclusions did you draw from your6

    analysis and the observations which youve just7

    recounted to us?8

    A Basically the entire project was squeezed closer9

    together to the east property line, as a result of the10

    delineation of the flood, floodway line, which you're11

    not allowed to do any work within, beyond the floodway12

    line. And that portion of -- all of Building A, and a13

    portion of Building B would, would need to be14

    compensated for, because that building footprints will15

    lose storage volume below them within the floodway --16

    or flood fringe area, excuse me.17

    Q And, based on those documents,18

    March 31, 2010, did you have an opinion as to whether a19

    flood hazard area permit could have been granted, or20

    would have been granted by the DEP based on the21

    information and data contained in the Dipple report and22

    the Concept Plan?23

    A Of the March 31 st ?24

    Q Yes.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    54/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    55/79

    Creelman - Direct 55

    yesterday?1

    THE COURT: Did you?2

    MR. WOODWARD: What was the number of that3

    again?4

    THE WITNESS: D-179?5

    MR. EISDORFER: I don't have any record of6

    having that handed out.7

    (Pause)8

    MR. WOODWARD: My apologies to all involved.9

    I did not hand it out yet.10

    THE COURT: I'm trying to stay organized,11

    so --12

    MR. WOODWARD: I know you are, yeah; and I'm13

    not helping you. Thank you.14

    THE COURT: D -- okay, D-179?15

    MR. WOODWARD: Yeah.16

    BY MR. WOODWARD: 17

    Q I'm showing you what's been marked as D-17918

    for identification. This is a letter dated19

    August 23, 2010. Have you ever seen that before?20

    A Yes, I have.21

    Q And, what was the purpose of preparing this22

    letter?23

    A As a result of the information provided by the24

    plaintiff regarding the plan listed on page one, we25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    56/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    57/79

    Creelman - Direct 57

    Q Also P-86.1

    (Pause - side discussion)2

    A Is that entitled Floodway and Existing Flood3

    hazard Area Delineation?4

    Q It says Floodway and Flood Claim5

    Delineation.6

    A Okay.7

    (Pause)8

    MR. EISDORFER: There was one that was that9

    we did not mark. Was it an, they just had an10

    additional one, I guess.11

    MR. WOODWARD: It was what?12

    MR. EISDORFER: Theres one that we did not13

    mark, it was Plaintiffs P-39, except the numbers added14

    to it.15

    MR. WOODWARD: We have a representation from16

    Counsel that the missing document is the same as P-39a.17

    MR. EISDORFER: It's, it's this document18

    here. We didn't use because it's the same except it19

    gets the numbers.20

    THE WITNESS: Okay. They both have the same21

    date. I think it was --22

    MR. EISDORFER: That's right.23

    THE WITNESS: -- July 19 th ?24

    MR. EISDORFER: Yes.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    58/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    59/79

    Creelman - Direct 59

    say a permit still would, would not be granted. This1

    was submitted to the DEP.2

    Q Now, with respect to -- there is one, I think3

    P-86 document, which is the, which is that drainage4

    map, there's a segment in the report, that area does5

    not drain 50 acres, and, therefore, is -- does not6

    require a riparian buffer. Have you reviewed that to7

    see whether or not you agree with that conclusion?8

    A I reviewed P-86. Based upon my review of that, I9

    could not make a conclusive determination whether the10

    area provided, in fact, was as stated on the drawing11

    19.43 acres; mostly because the detail is insufficient.12

    Q You couldnt make it out?13

    A I couldnt, no.14

    Q Now, did there come a point in time when you15

    received another report dated August 19, 2010, which is16

    P-87? Ill show you this. It's dated and it's from17

    Mr. Dipple. Have you ever seen that?18

    A Yes.19

    Q And what is that letter about?20

    A This letter talks about the conceptual design of a21

    storm water management system that takes into account22

    or tries -- it's an attempt to show that a storm water23

    management system could be designed which will take24

    into account the existing storm water detention that's25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    60/79

    Creelman - Direct 60

    provided on the easterly parking lot of 215, south of1

    Building 215.2

    Q And as I'm looking at P-39a, it's this, it's3

    this area on the right-hand side that's outside, or4

    generally outside the flood hazard area limit.5

    A Correct. Correct.6

    Q Did you perform an analysis of that report7

    and all of the documents that were submitted with it?8

    A We reviewed them and we, I believe we --9

    Q You rendered a report?10

    A We did, but I thought we had asked for some11

    information first. I thought.12

    Q Did you receive a letter dated13

    September 2, 2010?14

    A Yes, we did.15

    Q D-184?16

    A Yep.17

    Q Is that the supplemental information?18

    A Yes, it is.19

    Q So, what was it that you reviewed, the letter20

    dated August 19 th , correct?21

    A Correct.22

    Q And the letter with attachments dated23

    September 2, 2010?24

    A Correct.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    61/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    62/79

    Creelman - Direct 62

    ones and the appropriate mane (phonetic) coefficient1

    could be applied to them.2

    A time of concentration was assumed for3

    drainage areas 3 and 2 of 25 minutes. A type two4

    rainfall distribution instead of a type three rainfall5

    distribution was used in existing drainage area number6

    two.7

    Also, we could not determine any backup8

    information, or discern any backup information as to9

    where the, some of the information came from for the10

    broad-crested weirs, and the diameters of the pipes11

    that were listed.12

    And also that the, finally, that in looking13

    at the routing of the existing drainage area for this14

    parking lot south of Building 215, it appears that the15

    analysis assume that there are 12 inch valves, that the16

    storm piping sewer drained into were completely open.17

    Q Now, let's talk about each one of these.18

    With respect to the soil types, is there a document,19

    and I think it's in the September 2 nd additional20

    documents, that contain a depiction of what soil types21

    were on this property?22

    A Yes. It's -- looking at the September,23

    September 2 nd L2A plan, or letter, D-1 -- entitled24

    D-184, or identified as D-184, there's a plan entitled25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    63/79

    Creelman - Direct 63

    Web Soil Survey 2.0 National Cooperative Soil Survey.1

    And what it does, it provides a, an aerial photograph2

    of the site and some surrounding areas with the soil3

    survey overlapped on top of it so you could discern4

    approximately where the soil limits are.5

    Q And which soil types, if you could hold it up6

    to the Court so the Court can see; which soil types are7

    you referring to and where are they located?8

    A The soil types for the eastern, roughly the9

    eastern half of the site are HA2b, which is designated10

    as a Hydric Soil C. And the PS, PCSAT soil type which11

    predominantly covers the western portion of the site.12

    And that's known as a Hydric Soil Group D.13

    Q And what's the difference between Group C and14

    Group D?15

    A The, the predominant difference is the ability for16

    water to drain into the soil itself. A type C soil is17

    more permeable, and a type D soil is less permeable.18

    Q So is there a --19

    A That, --20

    Q Go ahead.21

    A The, the result of that is as less water could22

    permeate into the ground, you have a higher rate of23

    runoff, and is -- not using, using all of C instead of24

    C and D, you're artificially lowering the amount of25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    64/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    65/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    66/79

    Creelman - Direct 66

    the area that it covers, youll get less runoff from1

    one acre of C soil than you would from one acre -- I'm2

    sorry, let me rephrase that. Youll get one -- youll3

    get less runoff from an acre of C soil than you would4

    from an acre of D soil, because more water will be5

    allowed to percolate into the ground depending on the6

    ground cover.7

    Q And if, if you're doing the calculations and8

    youve got two types of soil and you only use one type9

    of soil, will that effect the reliability of your10

    calculations?11

    A Yes, it will.12

    Q How will it do that?13

    A You will reduce, by only using the Type C soil14

    which allows for a greater permeability into the15

    ground, you will reduce the amount of runoff from the16

    site, and, therefore, -- excuse me. You will, in your17

    routing, you will be allowed to allow more water to go18

    off the site.19

    Q Now, with respect to -- I'm going to show you20

    what's been marked as D-182 for identification. Could21

    you tell us what this is?22

    A This is entitled The Urban Hydrology for Small23

    Watersheds, otherwise known as TR55. And it's24

    produced by the NRCS, the Natural Resources25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    67/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    68/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    69/79

    Creelman - Direct 69

    to a quarter inch in depth, no more. Once you exceed1

    that, you get into what they call shower concentrated2

    flow. And the velocity of water within shower3

    concentrated flow is higher than it is within sheet4

    flow.5

    Q Why is the, why is the, is the velocity of6

    the flow higher in shower concentrated flow than in7

    sheet flow?8

    A The resistance of the water to go across the9

    surface when it's very thin, is greater in sheet flow10

    than it is in shower concentrated flow. And, again, if11

    you think about these in three segments, as all three12

    segments are added up and you end up with a time, the13

    time concentration, the time it takes the water from14

    its farthest reaches of the drainage area to the point15

    of discharge, that relates to how much water would come16

    off of that drainage area.17

    There are additional calculations that have18

    to be done, but that's that portion of it. And when19

    you calculate that, that has an impact on the amount of20

    water, the rate of water, the rate of discharge.21

    Q So what's the difference between using a22

    sheet flow of 100 -- of 200 feet versus 150 feet?23

    A You are allowing a sheet flow, which means a24

    longer time of concentration, a longer period of time.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    70/79

    Creelman - Direct 70

    And therefore, the rate of discharge, the peak rate of1

    discharge will be lower, to some degree.2

    Q And you mentioned that there are DEP3

    regulations that require this?4

    A Yes. There is a, in the DEP regulations, they5

    require that you use 150 feet versus 200 feet. I6

    believe I heard testimony earlier that they're allowed7

    to do 200 feet for a parking area. I could not find8

    that regulation. I found that the DEP, the TR55 says9

    150 feet. Again, that goes to the amount of discharge10

    within a given drainage area, both in the11

    predevelopment and the post development condition.12

    Q And that ultimately affects the size of any13

    detention facilities that have to be constructed.14

    A Right. What, what this all boils down to, is when15

    you take all of these factors, the time of16

    concentration, the coefficient of friction, when you17

    calculate all these values, you end up with for any18

    given storm in the predevelopment condition, a runoff19

    rate, a flow -- discharge flow to a piping system in a20

    drainage area.21

    We are trying to show that, as it was said22

    earlier by Mr. Morrisden (phonetic), that you're not23

    going to exceed from the predevelopment in the post24

    development. And the way to achieve that is to put25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    71/79

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    72/79

    Creelman - Direct 72

    guessed at it, but the odds are, we would probably come1

    up with a different one. And that doesnt make sense.2

    Q Now, going down your list, you indicate there3

    is no backup data for the existing outlet structures4

    for the watershed entitled, Existing Drainage Area5

    One. Could you tell us what kind of backup data there6

    should have been, and how that affects the ability to7

    design this system, the storm water detention system?8

    A Sure. The, the existing, when you're analyzing9

    the existing discharge system from a site, be it a10

    piping system, a surface flow; you need to know what11

    the parameters are.12

    In this case, the pipes were given as 1213

    inch, and I believe it was, a four inch orifice and14

    three broad-crested weirs. We could not confirm15

    during -- at the time of this, reviewing of this letter16

    if, where the four-inch pipe came out, and also where17

    the broad-crested weirs were listed. They were listed18

    at three different elevations. I think it was 80.1319

    for 30 feet, 80.09 for 25 feet (God bless you.), and20

    80.07 for 25 feet, for a total of, I believe, 80 feet21

    in length.22

    It wasnt clear as to where they were.23

    Again, this all goes back to, you determine what your24

    peak discharge under the existing condition is for a25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    73/79

    Creelman - Direct 73

    given storm, and then you compare that same storm event1

    under the post development conditions. The delta, or2

    the discharge, the difference in discharge between3

    those two routings is what needs to be detained in4

    storm water system.5

    Q Now, with respect to the last point that you6

    make there, the hydraulic calculations for the routing7

    of the parking lot, the assumption was that the 12 inch8

    valves were fully open.9

    A Correct.10

    Q Youve reviewed this parking lot, youve11

    looked at the data, youve looked at the surveys; do12

    you have a conclusion as to whether or not this parking13

    lot was designed to retain or serve as a storm14

    detention facility, storm water retention facility?15

    A I believe it was designed to function as some type16

    of detention facility, primarily based upon the17

    observance of the valves that were at the downstream18

    and -- or are at the downstream end of the existing19

    pipes at the south end of the parking lot at 21520

    Birchwood.21

    Q And, what about those valves? What's the22

    significance of them in terms of --23

    A Well, --24

    Q -- functioning as a storm water detention25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    74/79

    Creelman - Direct 74

    facility?1

    A Well, let me, let me preface that by saying,2

    working for developers, developers dont want to spend3

    money. They do that barebones minimum. That applies4

    now. It also applied back in 1973 when they built this5

    facility or thereabouts.6

    They would not have installed valves. They7

    didn't have to. They didn't do it out of the8

    generosity of their hearts. They didn't have to. They9

    would have just put a 12 inch pipe in, and that could10

    have acted, when they did the routing, as an orifice,11

    or orifices.12

    Therefore, having the valves installed, the13

    purpose was to reduce the opening in the valves to some14

    degree, I do not know what that degree is. I won't15

    speculate on that; in order to provide or retain the16

    existing water in the parking lot from discharging at a17

    higher rate of, at a higher rate.18

    Whether you close the valve from 12 inches,19

    to nine inches to eight inches, to six inches; I --20

    honestly I dont speculate. And I believe that's why21

    Mr. Morrisden was saying the only way to determine or22

    approximate how much those valves need to be, were23

    closed, were to go back to compare what you have on the24

    site today and then go back to the predevelopment25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    75/79

    Creelman - Direct 75

    condition and do a similar analysis, what I just1

    described and say, okay, when it was a horse farm, it2

    had 30 gallons, or 30 cubic feet per second, and now it3

    has 40. Okay, well now we have to detain 10 cubic4

    feet.5

    So they close the valve down through modeling6

    of the program -- through the TR55 modeling, and say,7

    okay, well close the valve down from 12 inches to8

    eight inches, and that will slow the discharge rate, so9

    we detain an additional ten cubic feet per second10

    within the parking area. And, therefore,11

    predevelopment flows -- or post development flows will12

    then equal predevelopment flows.13

    Q Based on the foregoing and based on your14

    analysis of the documentation submitted both in the15

    August 19 th report and the September 2 nd16

    supplementation, do you know, do you have an opinion as17

    to whether or not the storm drainage facility proposed18

    here by the plaintiffs would obtain a permit from the19

    DEP?20

    A Solely based upon the information provided to me,21

    I would say that they would definitely not obtain a22

    permit from the DEP --23

    Q And why not?24

    A -- for storm water management. One of the most25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    76/79

    Creelman - Direct 76

    significant ones is that, given the elevation of the1

    swale that the proposed system would drain into, I2

    believe the swale is somewhere around 75.1. The3

    proposed discharge pipe from the underground storage4

    system was at 75.4. They were providing a height of5

    storage in a structure of 30 inches, 2 feet. We also6

    know that the, the flood hazard elevation line is at7

    78.6 uphill, on the up -- on the northern end of the8

    site, and 78.4 on the downhill side.9

    Somewhere below that is other storm events.10

    The limits of where those flood waters would reach11

    during those storm events, I'm going to pick on, I'm12

    going to pick on, let's say the ten year storm event,13

    which would probably occur somewhere, if we look at, I14

    don't know what that, what's that exhibit again?15

    Q P-39a.16

    A If we look at P-39a. This is the --17

    Q You're pointing -- you're using your --18

    A I'm sorry. I'm pointing my laser pointer to point19

    to P-39a. And showing the easterly floodway line20

    traversing the site east of Casino Brook between the21

    floodway line and the flood hazard line, we know that22

    the 100 year flood line exists in there. It would not23

    be unreasonable to say that somewhere in the limits of24

    the 10 year storm event will also occur.25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    77/79

    Creelman - Direct 77

    If, when you're doing a storm water design1

    and your discharging within the floodway, one of the2

    requirements is that you design a storm water3

    management system to be able to discharge against a4

    head. A lot of times that head in this case may be the5

    ten year design storm.6

    Q When you say a head, is that like a7

    tailwater?8

    A A tailwater design, correct. So, instead of the9

    pipe discharge freely at all times and not have any10

    resistance, there would be water at the face of the11

    pipe where your, where your proposed pipe is12

    discharging to. So, instead of just flowing out into13

    no mans land, it would be hitting water. That would14

    re, that would result in an effect of the water, the15

    proposed discharge of the water backing up in the16

    piping system, and subsequently backing up in the17

    proposed underground detention system.18

    That could be equated to a loss in volume19

    which would result in the underground detention system20

    having to be increased in size to account for it's21

    ability to need to store additional water until it,22

    until this proposed discharge can hydraulically23

    overcome the tailwater -- I'm looking for it; the24

    tailwater effect, that's happening from a ten year25

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    78/79

    Creelman - Direct 78

    storm. And I didn't see that in anything that I saw1

    here.2

    Q There's no tailwater analysis?3

    A No.4

    Q And if there's no tailwater analysis, is that5

    something DEP would require?6

    A Absolutely.7

    MR. WOODWARD: No further questions, Your8

    Honor.9

    THE COURT: Okay. I'm going to break now for10

    the day, because I am actually teaching a, an11

    (inaudible) course tonight which I have to get to.12

    And, we're not going to finish with this witness today13

    anyway, okay?14

    MR. EISDORFER: Your Honor, I don't have a15

    lot of cross-examination, but I'm happy to postpone it16

    until first thing tomorrow.17

    THE COURT: And we have to come back anyway,18

    because Ms. McKenzie might have some questions. And19

    then she has to give her total report. So, I'm going20

    to break now for the day and well see you tomorrow21

    morning.22

    (Whereas proceedings of 9/28/10 were concluded)23

    * * * * *24

  • 7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer

    79/79

    79

    1

    2

    CERTIFICATION3

    4

    I, Darcel D. Hart, the assigned transcriber, do5

    hereby certify that the foregoing transcript of6

    proceedings in the matter of LEHIGH ACQUISITION, ET AL,7

    VS. TOWNSHIP OF CRANFORD, heard in the Union County8

    Superior Court, Law Division, Civil Part on9

    September 28, 2010, Tape Number 237-10, Index #1430 to10

    Index #7428, and Tape Number 238-10, Index #0001 to11

    Index #3302, is prepared in full compliance with the12

    current Transcript Format for Judicial Proceedings and13

    is a true and accurate non-compressed transcript of the14

    proceedings as recorded.15

    AUTOMATED TRANSCRIPTION SERVICES16

    17

    BY: Darcel D. Hart A.O.C. #53818

    Darcel D. Hart19

    20