SUPERIOR COURT OF NEW JERSEYLAW DIVISION, CIVIL PARTUNION COUNTY, NEW JERSEYDOCKET NUMBER: UNN-L-0140-08A.D. NO.:___________________
LEHIGH ACQUISITION, ET AL::
Plaintiff, :: TRANSCRIPT
vs. :: OF
TOWNSHIP OF CRANFORD, :: TRIAL
Defendant. :
Place: Union County CourthouseTwo Broad StreetElizabeth, New Jersey 07207
Date: September 28, 2010P.M. Session
BEFORE:
HONORABLE LISA F. CHRYSTAL, J.S.C.
TRANSCRIPT ORDERED BY:
CARL R. WOODWARD, III, ESQ. (Carella, Byrne,Cecchi, Olstein, Brody & Agnello)
APPEARANCES:
STEPHEN M. EISDORFER, ESQ. (Hill Wallack LLP)Attorney for the Plaintiff
CHARLES R. WOODWARD, ESQ. (Carella, Byrne, Cecchi,Olstein, Brody & Agnello)
Attorney for the Defendant
BRIAN FENLON, ESQ. (Carella, Byrne, Cecchi,Olstein, Brody & Agnello)
Attorney for the Defendant
DARCEL D. HARTUTOMATED TRANSCRIPTION SERVICES
P.O. Box 1582Laurel Springs, New Jersey
(856) 784-4276
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
2/79
2
APPEARANCES (Continued)
VINCENZO M. MOGAVERO, ESQ. (Carella, Byrne,Cecchi, Olstein, Brody & Agnello)
Attorney for the Defendant
DARCEL D. HARTUTOMATED TRANSCRIPTION SERVICES
P.O. Box 1582Laurel Springs, New Jersey
(856) 784-4276
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
3/79
3
I N D E X
September 28, 2010
WITNESSES Direct Cross Redirect Recross
Mr. Creelman 3
EXHIBITS Ident. Evid .
D-25c Photographs 30D-25d Photographs 30D-25m Photographs 30D-25n Photographs 30D-43 Site investigation report 21D-94 10/14/09 Creelman Report 9D-113 Report prepared in response to
L2A report 27D-138 Creelman Resume 6 8D-157 Alpha Survey prepared by Control
Point 10D-159 Letter from PS&S, Mr. Creelman dated
July 16, 2010 49D-162 August 3 plan 47D-178 Original development plans for the
site dated September 22, 2008 14D-179 Letter dated August 23, 2010 54D-181 Mr. Creelmans report 61D-182 The Urban Hydrology for Small
Watersheds 66D-184 Letter dated 9/2/10 with
supplemental information 60
P-37 Copy of the report from Mr. Dipple 27P-38 2/4/2010 letter from Mr. Dipple
to Mr. Eisdorfer 36
P-39 Concept Plan report dated 3/31/2010 37P_39a Board attached to the report 41P-80 Letter with flood storage volume
calculations 56P-82 Attachment to letter 57P-83 Attachment to letter 57P-87 August 19 report from Mr. Dipple 59
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
4/79
Creelman - Direct 4
(The afternoon session starts at 1:40 p.m.)1
MR. WOODWARD: Your Honor, Id like to call2
my next witness who Mr. Thomas Mr. Creelman.3
(Pause)4
T H O M A S C R E E L M A N, DEFENSE WITNESS, SWORN5
THE CLERK: State your name for the record.6
THE WITNESS: Tom Creelman.7
THE CLERK: Spell your last name.8
THE WITNESS: C-R-E-E-L-M-A-N.9
THE CLERK: Be seated.10
THE WITNESS: Okay. Thank you.11
DIRECT EXAMINATION (VOIR DIRE) BY MR. WOODWARD:12
Q Mr. Creelman, by whom are you employed?13
A Paulus, Sokolowski and Sartor, PS&S.14
Q And what is Paulus, Sokolowski and Sartor?15
A We are a consulting engineering firm.16
Q And could you give us the benefit of your17
background and qualifications?18
A Yes. I've been with the firm for approximately 2119
years. I'm a Senior Associate with the firm. My20
duties have included project management and design.21
During that course of time period, I received my22
license for, as a Professional Engineer in the State of23
New Jersey in 2002.24
My duties also include, as a Project Manager,25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
5/79
Creelman - Direct 5
we work in design teams in a Civil Group in our Civil1
Department. So I work with other peoples in my --2
other people in my team to design projects from3
conception to construction.4
Q And, where did you get your college degree?5
A I got my degree from the New Jersey Institute of6
Technology.7
Q And you're a licensed Professional Engineer?8
A Yes, I am.9
Q And, besides your current duties and10
responsibilities, what other prior employment have you11
had in the engineering field?12
A When I first graduated from college, I was13
employed by the engineering firm of Worchester14
(phonetic) Partnership.15
Q And what was your, what were your duties and16
responsibilities there?17
A I was a Staff Engineer, design of storm water18
systems, grading of sites, sanitary sewer system19
design, things of that nature.20
Q And is your area of practice Civil21
Engineering?22
A Yes.23
Q And Do you have any particular areas that you24
focus on?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
6/79
Creelman - Direct 6
A Probably in the past ten years, I have more1
focused on urban redevelopment, brownfield (phonetic)2
redevelopments in cities and so forth, where you take a3
what was formally a, industrial, more of an industrial4
site, and convert it into a residential and/or5
commercial use.6
Q And, as part of that, what sort of analysis7
do you--8
MR. WOODWARD: Strike that.9
BY MR. WOODWARD:10
Q Do you do analyses with respect to storm11
water management?12
A Yeah, we, we follow a, as of 2004, we now follow13
the new Storm Water Two regulations as adopted by the14
DEP.15
Q And, do you also practice in areas of16
determining flood hazards and flood hazard regulations?17
A Yes, we do.18
Q I'm going to show you what's been marked19
D-138 for identification, and ask you if you can20
identify this document. It's -- looks like it's a21
resume of sorts.22
A Yeah. This is my resume from my current firm,23
PS&S.24
Q And where is PS&S located?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
7/79
Creelman - Direct 7
A Our main office, our headquarters is in Warren1
Township, New Jersey in Somerset County.2
Q And is, is that the office that you work out3
of?4
A Yes, it is.5
Q Now, as part of your practice as a6
Professional Engineer, have you ever been qualified to7
testify, either before Planning Boards, Boards of8
Adjustment or in court?9
A Yes, I have, Planning Boards.10
Q And on how many occasions have you testified11
before Planning Boards?12
A Approximately 40.13
Q About 40 times?14
A Approximately 40 times, yes.15
Q And your testimony is in, is as a16
Professional Engineer. Is that correct?17
A Yes.18
MR. WOODWARD: Your Honor, Id like to offer19
Mr. Creelman as a engineering expert in the field of20
Civil Engineering at this time.21
MR. EISDORFER: No objection, Your Honor.22
THE COURT: He will be so qualified.23
MR. WOODWARD: Your Honor, Id also like to24
offer into evidence his resume which is D-138.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
8/79
Creelman - Direct 8
MR. EISDORFER: No objection.1
THE COURT: D-138 in evidence.2
(Pause)3
DIRECT EXAMINATION (CONTINUED) BY MR. WOODWARD:4
Q Now, in connection with this litigation5
before the Court, have you been retained by the6
Township of Cranford?7
A Yes, I have.8
Q And could you tell us what the nature and9
scope of your assignment for Cranford has been?10
A We were requested to review the site and documents11
provided to us for a site constraints analysis to12
determine what physical constraints on the site would13
inhibit development of the site?14
Q And you say physical constraints, does that15
include environmental constraints as well?16
A Environment -- wetlands, boundaries, flood hazard17
issues, riparian rights issues, endangered species18
issues; things of that nature.19
Q And during the course of your retention by20
the Township, have you prepared any reports?21
A Yes, I have.22
Q I'm going to show you what's first been23
marked as D-94. It's a document from you addressed to24
me dated October 14, 2009, and ask you if you can tell25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
9/79
Creelman - Direct 9
us what that is.1
A This is the first report that I prepared for the2
project after receiving documents. I received and3
reviewed several documents that I received from the4
Township through your office regarding elements of the5
site, a conceptual site plan prepared by the plaintiff6
dated September 22, 2008; a second conceptual site plan7
dated April 29, 2008; an aerial map of the site. Do8
you want me to list everything I went through that's in9
the report?10
Q Yeah, if you would go through it. I know11
it's fairly lengthy, but I think for the record, it's12
appropriate.13
A Okay. A water mane map, drawing number five, no14
date; center city sewer capacity study prepared in15
January 2009 by L2A; FEMA Study Map for the Township of16
Cranford dated September 20,2006; a letter of17
interpretation for a line verification for the property18
from the DEP dated August 20, 2009; the Township of19
Cranford applicable tax map last revised June 28, 1993;20
a copy of the Cranford Township Zoning Map; plaintiff's21
brief in support of the motion for the partial summary22
judgment dated January 30, 2009; the New Jersey State23
Development and Redevelopment Plan dated March 1, 2001;24
a Policy Map of the New Jersey Development and25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
10/79
Creelman - Direct 10
Redevelopment Plan dated March 1, 2001; a Site1
Assessment Report dated May 21, 2008 referred by L2A; a2
plan entitled Wetland Survey Plan prepared by Control3
Point, last revised in July 29, 2009; an Alpha Survey4
dated June 11, 2008, last revised September 11, 2008,5
as prepared by -- again prepared by Control Point. An6
existing Center City Sewer Map dated January 20097
prepared by L2A; a memorandum prepared by the Township8
of Cranford Engineer dated October 19, 2008; a Wetlands9
Delineation Report dated November 2008 and prepared by10
the Princeton Hydro (phonetic) for the Township of11
Cranford.12
Q Now with respect to your assignment preparing13
the analysis, what was your starting point?14
A We began looking at the, these documents to get an15
understanding of where the site was located in the16
Township, what zone it was located in, what some of the17
physical features of the site were, the size of the18
site, where the wetlands were located on the site, what19
structures were located on the site. The site20
contained approximately 15 acres of property, two21
buildings and two parking lots.22
Q I'm showing you whats been previously marked23
as D-157 in this case. Have you seen this before?24
A Is that the --25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
11/79
Creelman - Direct 11
Q If you want to get up and take --1
A Sure.2
Q -- a look at it, you can.3
A Yes, I've seen this document.4
Q And that is what?5
A It's the Alpha Survey prepared by Control Point.6
It's a boundary survey thats been certified to a7
certain individual. It shows existing structures,8
buildings, parking lots, and topography on the site and9
immediately surrounding the site.10
Q Does it also show a delineated wetlands line?11
A Yes, it does show a delineated wetlands line12
covering approximately six acres in the southwest13
portion of the site in this area here.14
THE COURT: What exhibit is that? What15
exhibit is that Mr. --16
MR. WOODWARD: D-157, Your Honor.17
THE COURT: Thank you.18
(Pause)19
BY MR. WOODWARD:20
Q Now, did you do an environmental evaluation21
of the site?22
A We reviewed the site from a standpoint of23
wetlands, wetlands buffers, riparian buffers,24
endangered species, plants, and animals. We concluded25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
12/79
Creelman - Direct 12
that there were no threatened or endangered species on1
the site based upon data sets that we reviewed from the2
DEP that are available through the DEP. We also3
indicated that based upon the delineation that was4
provided on the map and the letter of interpretation5
provided by the DEP, that the wetlands that had been6
delineated on the site were appropriate.7
Q With respect to the other portions of the8
site, did you, in terms of environmental, I think you9
said -- did you evaluate --10
MR. WOODWARD: Withdraw, withdrawing, Your11
Honor.12
BY MR. WOODWARD:13
Q Did you evaluate any storm water or flooding14
that occurred or may occur on the site?15
A We reviewed, we visited the site in early October.16
Q What year?17
A 2009.18
Q Okay.19
A And we reviewed some, the storm inlets, the20
overall topography of the site. The site is bounded to21
the west by a brook known as Casino Brook, otherwise22
identified as, I believe it's --23
Q You can refer to your report, by the way, if24
you wish.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
13/79
Creelman - Direct 13
A -- 10-24.1
Q And did you make any determinations as to2
whether there were, there was flooding on this3
property?4
A Based upon a review the FEMA maps and the5
delineation provided on the FEMA maps, it was our6
belief that there was a delineation of floodway and7
flood hazard lines to the site.8
Q You say there was from the FEMA maps?9
A Not on the FEMA maps, but the way they were10
configured, the adjacent towns, Kenilawn (sic)11
Kenilworth, sorry. Kenilworth showed a 100 year and12
500 year flood line ending at the municipal boundary13
line.14
We subsequently also called the DEP and asked15
for an interpretation of the map, and we were told that16
the, the, Kenilworth did request that FEMA map Casino17
Brook in their township, but Cranford did not. And,18
therefore, a delineation of the floodway on Casino19
Brook within the Township of Cranford did not exist.20
It was not mapped on the FEMA plans.21
Q So, did you form an opinion as to whether or22
not a flood hazard area study was required in23
connection with the proposed development on the site?24
A Based upon looking at the FEMA maps in25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
14/79
Creelman - Direct 14
Kenilworth -- I'm sorry, Kenilawn (sic) -- and for the1
mapping that was don for the Rahway River, we felt2
there was a necessity to have it done, that a floodway3
did exist, a flood hazard area would exist on the site.4
Q In connection with -- and I just referred to5
the proposed development on the site; I'm going to show6
you what's been marked as D-178 in evidence. And7
actually, I direct your attention to the exhibits.8
Take a moment to look at those. Have you ever seen9
those before? They're dated September 22, 2008.10
A Yes, I have.11
Q Okay. And was that the original development12
plan for this site proposed by the plaintiffs that you13
reviewed?14
A Yes, it is.15
Q Now, could you tell us exactly how the16
buildings were laid out on that particular site? As a17
matter of fact, I can also show you -- well, how were18
the parking lots laid out on that, on that map?19
A There were three, three buildings total. They20
were A, B, C. Building A is a residential building.21
Building B is a residential building. And Building C22
is a parking garage wrapped on three sides by Building23
B. A large portion of the, both buildings fronts on --24
to the north on Birchwood Avenue. And Building A takes25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
15/79
Creelman - Direct 15
up at least, I want to say, a third, if not more, of1
the frontage along Birchwood Avenue, as does Building2
B.3
Q And -- now, did you form a professional4
opinion as to whether a flood hazard area study in5
connection with a proposed development was required?6
A Yes, I did.7
Q And why was that?8
A Based upon the review of the documents from FEMA9
and our conversation and our call to FEMA, and the10
limits of what was provided upstream and downstream of11
the site, it was my professional opinion that a flood12
hazard area did exist for the site, even though one was13
not mapped at that point in time.14
Q Now, moving on in your report to the15
wetlands, did you -- you evaluated the wetlands survey,16
the wetlands delineation?17
A Yes, we did.18
Q And with respect to that, did you agree with19
all that was described in there?20
MR. WOODWARD: Strike that.21
BY MR. WOODWARD:22
Q Did you find any areas that may have required23
riparian buffer?24
A We felt that an area to the south of the parking25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
16/79
Creelman - Direct 16
lot on Lot 215 may be as it was an -- appeared to be a1
natural generalized water course may have a riparian2
buffer on it.3
Q And why did you feel that it needed a, may4
have needed a riparian buffer.5
A Under the regu, under the regulations, if the, if6
a natural channelized water course for the drainage7
area of 50 acres or more, it is required by regulation8
to have a buffer, a minimum buffer of 50 feet.9
Q Now, in reviewing the plan, did you review10
the parking analysis or the parking that was indicated11
on that plan, the September 22, 2008 plan?12
A Yes, we did.13
Q And what conclusions, if any, did you draw14
from that?15
A That the -- excuse me. That the general at grade16
parking, the size of the parking was adequate. Our17
main concern was the relationship of the parking, the18
encroachment of the parking into the wetlands buffer.19
Q And, what conclusion in terms of, what was20
the issue there that there if was a problem?21
A It's been our experience that the DEP normally22
doesnt like encroachments into the wetlands buffer23
parallel to it. They prefer you to go perpendicular to24
it if you're going to have encroachment into it at all.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
17/79
Creelman - Direct 17
Q Now, did you offer any comment on the storm1
water management in your report?2
A Yes, we did.3
Q And what observations -- first of all, what4
did you review, and what observations did you make, and5
what conclusions did you draw?6
A We reviewed the Alpha Survey. We met with the7
Township Engineer. We also visited the site. During8
my visit at the site, in reviewing the brook and the9
adjacent properties to the south side of 215 Birchwood,10
south of the parking lot, there is a channel. And11
adjacent to that channel where all the storm water for12
that parking lot drains to, there are existing13
structures that the parking lot pipes drain into.14
Leaving those structures, there is a different15
composition of pipe. And on top of those, above those16
grounds is indicated valves, some type of valve that17
can be closed.18
Q Could you go up to D-157 and point out to the19
Court -- first of all, 215 Birchwood versus 23520
Birchwood for the record?21
A Sure. I'm pointing at the Alpha Survey. And 21522
Birchwood is the site on the eastern half of the23
project. 235 Birchwood is the site located on the24
westerly half of the project. What I'm referring to is25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
18/79
Creelman - Direct 18
the area to the south of the parking lot at 2151
Birchwood.2
Q A parking lot sort of in the center of 215,3
correct?4
A Correct.5
Q All right.6
A In general, the drainage area for this parking lot7
drains to the south, southwest of the parking area into8
an area over here. The two pipes, the two main9
discharge pipes drain into two structures. Those two10
structures, the pipes enter on one side of the11
structure. On the opposite side of those structures,12
there is a ductile iron pipe that discharged. Those13
pipes eventually turn back from ductile iron pipe back,14
back into concrete pipes in the swale. But in the15
course of traveling underground, there are indications16
on the surface there are valves within, contained17
within those ductile iron pipes.18
Q Now what's a ductile iron pipe?19
A A ductile iron pipe is just a composition of pipe.20
It's made out of a type of steel thats used in21
development.22
Q And, --23
A Versus concrete pipe, plastic pipe, that sort of24
thing.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
19/79
Creelman - Direct 19
Q Okay, so what you found there on the south1
side of the parking lot was leading out of the chamber,2
a ductile iron pipe, and before it got to its full3
outlet, it was a concrete pipe?4
A Correct.5
Q And then you said there were valves?6
A In, in the line with, where the pipe left7
the -- leaves the chamber --8
Q Right.9
A -- and where the pipe discharges into the channel,10
surface indications there is a valve shown on the11
ground, there is a physical valve, or the remains of a12
valve if you will.13
Q And there was a valve in what each one of14
those --15
A Downstream of each chamber that was there, each16
concrete chamber, yes.17
Q And you said it was associated with a ductile18
iron pipe?19
A Yes.20
Q How do you know that?21
A Experience. You dont put a, a metal valve on a22
concrete pipe normally.23
Q Why not?24
A In trying to make it -- to seal it is more25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
20/79
Creelman - Direct 20
difficult. Would you, would you have a type of1
situation where you have ductile iron pipes connecting2
to a valve? There will be plates, and you can bolt3
them together very easily.4
Q Now, did you draw any conclusion from the5
storm water system or whatever you saw in that parking6
lot particularly into the whole site regarding storm7
water management?8
A Basically my -- I summarized that the -- in my9
report that the existing valving system was utilized to10
provide some level of reduction or retention of the11
storm water leaving the site to reduce the amount of12
water off the site during the peak storm event.13
Q Did you make any recommendations in your14
report about what should be done, if anything, to study15
further that area?16
A We recommended that during the post-development17
analysis and design of the storm water managing system18
that this existing detention be taken into account19
during the overall design of the proposed storm water20
management system.21
Q Now, at the end of your report on page nine22
in paragraph five addendum, you added something to that23
report. Could you tell us what that was?24
A Our initial, the initial package that we25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
21/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
22/79
Creelman - Direct 22
A That is a report entitled Site Investigation,1
Birchwood Avenue Cranford Township, Union County, New2
Jersey. It was prepared by L2A Design and dated3
May 21, 2008.4
Q And I'm going to show you at the end of the5
report an appendix. And the first item on the6
appendix, is that, is that the conceptual, first7
conceptual site plan you reviewed?8
A That is correct, yes.9
Q And, --10
MR. WOODWARD: I, I know the Court is looking11
for its documents right now.12
THE COURT: Yeah, let me look. It was D-43?13
MR. WOODWARD: Yes. Heres one for the14
Court.15
THE COURT: Thank you. It's already up here,16
but it --17
MR. WOODWARD: It will be easier.18
THE COURT: -- takes a while to read through19
them all to find it. Thank you.20
BY MR. WOODWARD:21
Q Take a look at D-43. Could you describe the22
Concept Plan that was presented first in April of 2008?23
A The original Concept Plan --24
MR. EISDORFER: Your Honor, object to the25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
23/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
24/79
Creelman - Direct 24
THE WITNESS: Yes.1
THE COURT: Okay. So you -- can you just2
point to what you're referring to?3
THE WITNESS: Sure. Absolutely. I'm4
referring to Building C. On the April 29, 2008 map,5
Im just saying that Building C as identified in6
September plan, is the parking garage, here.7
THE COURT: Okay.8
THE WITNESS: And then the other, the9
building that wraps around it to the south, west and10
north, --11
THE COURT: Thats B.12
THE WITNESS: -- is Building B. It takes up13
approximately a little more than 50 percent of the14
frontage along Birchwood Avenue for the width of the15
property, and a loop road wraps around it providing two16
access points from Birchwood Avenue into the site.17
Also the southern portion of Building B18
respects the, the natural channelized water portion to19
the south, and the wetlands immediately to the west of20
it.21
BY MR. WOODWARD:22
Q Okay. Now, thank you. With respect to the23
plan on -- now, there was one large building plus a24
parking garage, correct, on the April ---25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
25/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
26/79
Creelman - Direct 26
units in September?1
A Yes.2
Q In the September plan?3
A Correct, as well as the parking.4
Q What was the parking called out in, in the5
April plan?6
A Parking provided for, the 379 units was 6957
spaces. And in the September plan it was listed as 6738
spaces provided.9
Q So there are actually, actually fewer spaces.10
A Correct.11
Q Now, with the comparison of the April 29 th12
plan to the September plan, did you draw any13
conclusions as to the impact of the September 22 nd ,14
plan, whether that was an increase in impact, or15
decreased impact of -- over the building that was16
described in the April 29 plan?17
A The September 22, 2008 plan showed an increase in18
impervious coverage above what was provided or shown on19
the April 29, 2008 plan.20
Q And, did that have any impact in terms of21
what needed to be studied, analyzed, or provided for by22
way of storm water management at the site?23
A It would increase the amount of runoff. And that24
would have to be taken into account in the storm water25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
27/79
Creelman - Direct 27
management design.1
Q And so is that a recommendation of yours2
that it needed to be studied?3
A Yes.4
Q Now, you prepared a second report, a5
January 14, 2010, Exhibit D-113, 113. I'm going to6
show you a copy of that, and could you tell me if you7
can identify that?8
A Yes, I can.9
Q And, tell us what this is.10
A This report, excuse me. We prepared this report11
to review additional plans that were provided in, later12
in the year, and in response to plan, a letter prepared13
by Mr. Dipple of L2A Associates -- L2A Design.14
Q And, what was it that you, what was it that15
you did in terms of responding to Mr. Dipples report?16
A There was a indication that flood hazard issue17
still did not exist. We went and reviewed FEMAs flood18
study maps for the Township of Cranford again. Those19
plans -- that plan was dated September 2006 --20
September 20, 2006. And a flood study map, and a FEMA21
flood study map for the Borough of Kenilawn (sic)22
again dated September 20, 2006.23
Q Kenilworth?24
A I'm sorry, Kenilworth. Excuse me.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
28/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
29/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
30/79
Creelman - Direct 30
Town -- Cranford Taxpayers website, utilizing several1
of those photographs, we went and compared those2
specific photographs in, in that website to key points3
within the Alpha Survey which had elevations on it.4
And we were able to determine certain elevations, or5
approximate them, I should say.6
Q Now, the photographs are, are they exhibits7
C, D, E, and F, and G?8
A Yes.9
(Pause)10
Q I'm showing you what's -- and these are11
perhaps better copies. So, Id like to, to -- they're12
more presentable than, than the photocopies that you13
have. I'm showing exhibits D-25c, D-25d, D-25m, and14
D-25n. Are those the photographs that you used to15
assist you in trying to calculate the height of that16
particular flow?17
(Pause)18
A Some of them are, yes.19
Q Okay. Which ones did you use?20
A I used D-25n, D-25d, D-25c. And also, there's21
another photograph that doesnt appear to be in the22
pile here that I used.23
Q And that was --24
A It would be Exhibit C.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
31/79
Creelman - Direct 31
Q -- Exhibit C, if youd show the Court --1
A Certainly.2
Q -- is a photograph of Birchwood.3
THE COURT: Exhibit D-113, right?4
THE WITNESS: Yes, it is. Yes.5
BY MR. WOODWARD:6
Q Okay. Now, could you describe for us how you7
went about doing this evaluation based on the8
photographs and the, Alpha Survey, which is D-157.9
A Sure. I can go down to the map here real quick.10
Q Sure.11
A On the Alpha Survey, there are structures. In12
particular, I'm going to point to the west side of the13
entrance to the property at 235 Birchwood Avenue. If14
you look at Exhibit C, that picture was taken standing15
on the north side of Birchwood Avenue, excuse me; just16
west of the actual entrance to the property.17
If you look at the photograph, youll see two18
cars within the street that are, have water up to the19
rims. In the background of that, I don't think the20
photocopy is clear enough; youll see a structure that21
is a signage for the property. It identifies what this22
property is, the street number, the, the, who is there23
and all that kind of stuff. You can see that in the24
picture.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
32/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
33/79
Creelman - Direct 33
the elevation as well. That's it.1
Q And did that --2
A There was no hydraulic analysis involved in that3
study.4
Q Did that support in any way your5
recommendation that a flood hazard area study be6
performed?7
A It did because, the, the rainfall event that8
occurred I believe on that date which was9
April 15, 2007 was around, I think, eight, eight or10
nine inches.11
And, given that elevation and the -- what was12
shown in the photographs, and the information provided13
on the FEMA maps, upstream of the site, it was my14
opinion that clearly a flood study would be required.15
And if an analysis was done, a floodway and a flood16
hazard line would certainly be showing, could be17
generated for the site, would be generated for the18
site.19
Q Now, with respect to this, this site, was20
this a site that, in your opinion, flooded21
frequently -- or flooded?22
A Yes.23
Q And was that a severe flood that you saw?24
A I would say it was significant.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
34/79
Creelman - Direct 34
Q Now, with respect to storm water management,1
in your report, you also dealt with that particular2
issue. Could you tell us what your, whether there was3
any change in your position as earlier expressed or4
modification of your position? Please describe that.5
THE COURT: Which report are you referring6
to?7
MR. WOODWARD: I'm sorry, Your Honor, D-113.8
BY MR. WOODWARD:9
A I didn't change my opinion. I still felt that10
when a storm water management system was designed for11
the project, it would have to take into account the12
existing shower detention in the parking lot shown on13
215 Birchwood, and also that it needed to be taken into14
account once the flood hazard parameters were15
established. It would have to take that into account16
as well, that storm water analysis.17
Q And did you have any -- make any18
determination as to whether the conceptual site plan of19
September 22, 2008 provided sufficient detail to20
determine whether or not the fresh water wetlands21
regulations would be satisfied?22
A Could you ask that question again?23
Q Sure. Directing your attention to page four24
of your report, you have a comment about the detail for25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
35/79
Creelman - Direct 35
freshwater wetlands general permits and transition area1
waivers. Were you able to determine from the2
information provided whether or not there was adequate3
information to determine whether or not those permits4
would be granted?5
A No. No, there was not enough information.6
Q There was not enough information?7
A No, there was not.8
(Pause)9
Q Now, did there come a point in time when --10
let me just rephrase that. When Mr. Dipple in his11
October report -- take a look at this third paragraph12
down from the top of the page, and that first item,13
which is P-38. Your opinion was --14
MR. WOODWARD: Strike that.15
BY MR. WOODWARD:16
Q Mr. Dipple felt that method three could be17
used for determining the flood hazard area, correct?18
A Yes, in that paragraph of his October 29 th , report19
2000 --20
Q And what's, what's method three?21
A Method three allows you to look at flood insurance22
rate maps for areas that have been delineated by FEMA23
of flood waters for the -- within the 100 year and24
outside the 100 year, within the 500 year, and outside25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
36/79
Creelman - Direct 36
the 500 year flood plain. If the map is available and1
it's delineated, then method three permits you to use2
that as, to verify whether you do or do not have a3
flooding situation on your site.4
Q And did you differ from Mr. Dipple on that,5
whether method three could be used on this site?6
A I did.7
Q And what was your opinion?8
A I felt that based upon the information I had9
reviewed, both the FEMA maps, the site, the10
photographs, the -- and my conversation that we had11
with the DEP regarding the interpretation of the FEMA12
map that a flood study was warranted and that either13
method five or method six; method five being an14
estimation method, and method six being a complete15
backwater analysis, would be required to determine16
where the floodway line and the flood hazard line would17
be determined.18
Q Did Mr. Dipple ultimately agree with you?19
A Several months later, yes.20
Q I'm going to show you what's been marked as21
P-38. It's a letter dated February 4, 2010. Is that22
from Mr. Dipple --23
A Yes.24
Q -- to Mr. Eisdorfer?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
37/79
Creelman - Direct 37
A Yes, it is.1
Q And does that letter include his conclusions2
regarding whether or not method six should be used?3
A Yes, it does. He acknowledges that a, that a4
study would be required, and that method three was not5
appropriate, and that a, a flood hazard analysis, a6
hydraulic analysis would be required.7
Q Now, did there come a time when you became8
aware that a flood hazard study actually had been done?9
A Yes.10
(Pause - side discussion)11
BY MR. WOODWARD:12
Q I'm going to show you what's been marked as13
P-39. It's a report dated March 31, 2010. Have you14
ever seen that before?15
A Yes, I have.16
Q And, what is that?17
A This is a report by L2A by Mr. Dipple explaining18
that they went through and they prepared a backwater19
analysis -- I'm sorry, a flood plain analysis for the20
site using methodology number six, for -- to determine21
the flood hazard area, line as it wraps through the22
project.23
Q And does it -- is there anything else that's24
included with that report?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
38/79
Creelman - Direct 38
A It provides elevation upstream at the northern end1
of the site of 78.6 for the elevation of the flood2
hazard elevation as it traverses through the site, an3
elevation of 78.4 at the downstream end. It also4
provides for a -- can you give me one minute?5
Q Certainly. Take your time.6
(Pause)7
A It also provides a, a map entitled FEO-01 dated8
March 31, 2010. I believe the basis of the map was the9
Alpha Survey prepared by Control Point. And on that10
map has been plotted the, the floodway lines and the11
flood hazard -- limits of the flood hazard area limit12
lines as it traverses through the site.13
Q May I see that, please?14
A Sure. But I dont see the other one.15
MR. WOODWARD: Excuse me, Your Honor.16
(Pause)17
Q All right. Now when you looked at that, were18
you able to determine whether there was a flood hazard19
area on the site?20
A Based upon the analysis performed L2A, yes, I was21
able to determine there is a --22
Q And, and can you show the Court where the23
floodway line is and the flood hazard area line is?24
A On this one?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
39/79
Creelman - Direct 39
Q Hold it up, yeah. Show it to the Court.1
A Sure. The, the floodway line is a solid line2
traversing the site from north to south, about a third3
of the way in from the westerly property line. The4
other side of the floodway line is indicated on the5
west side of Casino Brook which is just on the property6
line adjacent to the adjacent property.7
The flood -- excuse me, the flood hazard area8
line, the easterly flood hazard area line is shown as a9
dash line approximately one-third off the east,10
easterly property line of the site.11
And the adjacent flood hazard area line to12
the westerly side of the stream is very close to the13
floodway line. Again, all, all of these refers to the14
north and south.15
THE COURT: Does it mean that everything in16
between is the floodway?17
THE WITNESS: Correct. The, the floodway18
goes to this, from this solid line here on the west19
side of the brook --20
THE COURT: To here.21
THE WITNESS: -- to this line here on the22
east side of the brook.23
THE COURT: (inaudible).24
THE WITNESS: Correct, that is the floodway25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
40/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
41/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
42/79
Creelman - Direct 42
the March 31, 2010 letter from Mr. Dipple. Was there a1
revised Concept Plan submitted?2
A Yes, there was.3
Q And, could you briefly tell us what the4
revisions were to the last plan which was September 22,5
2009 -- or 2008?6
A Youd like just a brief explanation of the7
comparison --8
Q Yes.9
A -- between the September 22 nd --10
Q Right.11
A -- and the -- okay.12
Q Right.13
A Do I still have a copy of the plan showing that?14
Q Here you go. It's D-178.15
A Okay.16
Q The exhibits D-178.17
A Thank you.18
THE COURT: Okay. So we're talking about19
D-43 and D-178, correct?20
MR. WOODWARD: P-39, Your Honor.21
THE COURT: P-39?22
MR. WOODWARD: P-39, Your Honor, yes.23
(Pause)24
THE COURT: Okay. P-39a, right?25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
43/79
Creelman - Direct 43
MR. WOODWARD: P-39. That's P-39a, Your1
Honor, on the board.2
THE COURT: I have it as P-39a. Is there a3
separate P-39?4
MR. WOODWARD: This is P-39a.5
THE COURT: Okay. The report is P-39.6
MR. WOODWARD: P-39. And there are actually7
two other pages that go with P-39 that are not there.8
MR. EISDORFER: They are, they are actually9
separate exhibits?10
MR. WOODWARD: Are they?11
MR. EISDORFER: Yes. So that's actually P-812
THE COURT: So what I'm looking at was in my13
binder.14
MR. EISDORFER: Right.15
THE COURT: So I just want to be clear that16
I'm looking at the same thing, --17
MR. EISDORFER: Yeah.18
THE COURT: -- that we're talking about in19
the testimony. So P-39a, --20
MR. WOODWARD: Is this board here, Your21
Honor.22
THE COURT: -- is the board that was23
attached? Okay. P-39 is the report, --24
MR. WOODWARD: Correct.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
44/79
Creelman - Direct 44
THE COURT: -- the Concept Plan.1
MR. WOODWARD: And then there are two other2
exhibits, --3
THE COURT: Which I don't have.4
MR. WOODWARD: -- that Mr. Eisdorfer says5
have separate exhibit numbers.6
MR. EISDORFER: Yeah. They have separate7
exhibit numbers. I believe hes referring to P-8,8
which is the March 31 st .9
THE COURT: Let me check. P-8?10
MR. EISDORFER: Yes. And that together with11
that is P-9, which is seven sections.12
THE COURT: Let me just get that.13
MR. WOODWARD: -- of P-8.14
MR. EISDORFER: And they may have D numbers15
too, but I'm not sure.16
THE COURT: Okay. So P-8 and P-9?17
MR. EISDORFER: Yes. And, actually, the18
defendant marked those as D-150 and D-151.19
THE COURT: So P-8 is D-150?20
MR. EISDORFER: Yes.21
THE COURT: And P-9 is D-151.22
MR. EISDORFER: That's correct.23
THE COURT: Thank you.24
(Pause)25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
45/79
Creelman - Direct 45
MR. WOODWARD: All right. Your Honor, just1
to clarify, what we're going to do here from the2
defense perspective, --3
THE COURT: Thank you.4
MR. WOODWARD: -- there are three documents5
which we have marked as D-149 which is the floodway6
exhibit, --7
THE COURT: Oh, wait a minute.8
MR. WOODWARD: -- which is also the colored9
version of P-39a. If you take -- yeah. That's that10
page.11
THE COURT: Okay. So D-149 equals P-39a?12
MR. WOODWARD: Correct.13
THE COURT: Okay.14
MR. WOODWARD: Then D-150 is the revised15
Concept Plan --16
THE COURT: That's here. Yes.17
MR. WOODWARD: -- dated March 31, 2010.18
THE COURT: P -- it's P-9, right?19
MR. WOODWARD: P -- ...20
(Tape #1 ends; Tape #2 begins)21
THE COURT: Well, it's a total of 705 -- from22
that, according to this witness' testimony. Let's put23
it that way. Okay. I'm sorry to interrupt.24
MR. WOODWARD: No. That's all right, Your25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
46/79
Creelman - Direct 46
Honor. Thank you.1
BY MR. WOODWARD:2
Q Now, you said Building A in the March 31 plan3
was revised. And what was the purpose of moving that4
and revising it?5
A Building A used to be a T with the top of the T6
parallel to Birchwood Avenue as a result of the7
delineation and plotting of the floodway line, as was8
done by L2A. The old configuration of Building A on9
the September 2008 plan would have been, I want to say10
more than, I'm estimating more than three quarters of11
the way within the floodway, which is not allowed under12
the DEP regulations. So Building A was reconfigured to13
a, a reversed L with its long side perpendicular to14
Birchwood Avenue to respect the floodway line.15
Q Now, did that plan that you're looking at16
right now from March 31, 2010 show the flood, the limit17
of the flood hazard area?18
A No, it does not.19
Q So, --20
A It only shows the floodway line.21
Q Is that a significant omission?22
A In, in my opinion, yes.23
Q Why?24
A You need to know, not only where the floodway line25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
47/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
48/79
Creelman - Direct 48
have a reasonable overlap, so we felt that they're1
relatively accurate to their comparison to one other.2
We utilize what's shown on both plans as this3
blue line right here as it wraps around, as shown on4
the exhibit, represents the location of the limit of5
the existing parking lot on the south side, east side6
and west side of 215 Birchwood that exists in both7
plans. We were able to use that as a key point, if you8
will, to approximate bringing this line easterly, flood9
hazard limit line from the other plan, this plan here,10
the flood area, and flood plain delineation plan,11
Exhibit P-39a, to be able to superimpose it on this12
plan to see where it, in fact, falls in relationship to13
Building B.14
Q And what, as a result of that overlay, what,15
what was its relationship, what was that flood hazards16
limitation or limit line in relation to building A?17
A It shows that all of Building A still remains18
within the, the area between the floodway line, and the19
flood hazard line, the flood area known as the flood20
fringe area here.21
Q Now, could you also determine whether or not22
any portion of proposed Building B was in the flood23
hazard area?24
A Yes. Based upon the plot, we were able to show25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
49/79
Creelman - Direct 49
that the northern, a northern portion of Building B was1
within the flood, flood fringe area, or within the,2
encroaches in the flood hazard area.3
Q Now, --4
THE COURT: What exhibit is this?5
MR. WOODWARD: That's P, I think it's 162.6
MR. EISDORFER: No, D.7
MR. WOODWARD: No, D, D-162.8
MR. EISDORFER: D-162.9
MR. WOODWARD: Dated August 3 rd .10
THE COURT: Thank you.11
BY MR. WOODWARD:12
Q Now, I'm going to show you what's been marked13
as D-159 for identification and ask you if you can14
identify that document? It's dated July 16, 2010.15
THE COURT: What is the number? I'm sorry,16
what number was that?17
THE WITNESS: D-159.18
BY MR. WOODWARD:19
A It's a letter from PS&S, myself, to Mr. Woodward20
dated July 16, 2010.21
Q And, what was this report?22
A This is a, a letter from us to, to respond to a23
request from you for us to review the information24
provided to us from the plaintiff on March 31, 2010.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
50/79
Creelman - Direct 50
Q And so the documents that we've gone through,1
the report from Mr. Dipple, the, the delineation of the2
floodway and the flood hazard line, and the revised3
Concept Plan were what you reviewed in that letter,4
correct?5
A Correct, yes.6
Q Okay. Could you go through your report and7
tell us what observations you made or -- from your8
analysis of the documents dated March 31, 20109
submitted by Mr. Dipple?10
A The, the new layout provided by Lessard increased11
the -- well actually more than doubled the amount of12
surface parking -- one minute; yes, more than doubled13
the amount of surface parking from 73 to 171 spaces,14
which would --15
THE COURT: 73 to what?16
THE WITNESS: From 73 to 171 spaces.17
BY MR. WOODWARD:18
A -- based upon the new alignment of the, the19
buildings and the reconfiguration of the buildings.,20
which resulted in the reconfiguration of,21
reconfiguration of the driveway. And I noted that the,22
I was concerned that the driveway where it's between23
Buildings A and B had a double, a left-hand turn and a24
quick right-hand. I was concerned with respect to the25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
51/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
52/79
Creelman - Direct 52
the, I was able to go back and show the impervious area1
did decrease slightly, but as the proposed roof area is2
significantly above the surface, any discharge from the3
roof area will not be detained in a parking lot at all,4
as it does on the existing addition. It will readily5
just discharge off site. It won't even backup, because6
it's certainly higher than the surrounding elevations.7
And that should all be taken into account in the8
significant, in the storm water management design.9
Q Did you have any comments on the wetlands10
buffer?11
A The wetlands buffer itself, I agreed, I believe12
the plaintiff had issued a letter indicating that the13
wetlands buffer south of the parking lot on 215 as that14
had a -- no resource value. A buffer of 50 feet was15
not required. And we agreed with that as far as the16
wetlands goes, we were still concerned about a riparian17
issue though, to determine if the, that natural18
channelized water course had a drainage area of 50 feet19
or -- 50 acres or more going to it.20
And also that we couldnt see any proof that21
the, that any displacement of storage within the flood22
fringe area, if it was compensated for, it had to be23
compensated for both below, above between a 10 year,24
and a 100 year, and above the 100 year storm itself.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
53/79
Creelman - Direct 53
You can't swap elevations for it.1
Q And was this as a result, these observations2
are from reviewing what was submitted on3
March 31, 2010, correct?4
A Correct.5
Q What conclusions did you draw from your6
analysis and the observations which youve just7
recounted to us?8
A Basically the entire project was squeezed closer9
together to the east property line, as a result of the10
delineation of the flood, floodway line, which you're11
not allowed to do any work within, beyond the floodway12
line. And that portion of -- all of Building A, and a13
portion of Building B would, would need to be14
compensated for, because that building footprints will15
lose storage volume below them within the floodway --16
or flood fringe area, excuse me.17
Q And, based on those documents,18
March 31, 2010, did you have an opinion as to whether a19
flood hazard area permit could have been granted, or20
would have been granted by the DEP based on the21
information and data contained in the Dipple report and22
the Concept Plan?23
A Of the March 31 st ?24
Q Yes.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
54/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
55/79
Creelman - Direct 55
yesterday?1
THE COURT: Did you?2
MR. WOODWARD: What was the number of that3
again?4
THE WITNESS: D-179?5
MR. EISDORFER: I don't have any record of6
having that handed out.7
(Pause)8
MR. WOODWARD: My apologies to all involved.9
I did not hand it out yet.10
THE COURT: I'm trying to stay organized,11
so --12
MR. WOODWARD: I know you are, yeah; and I'm13
not helping you. Thank you.14
THE COURT: D -- okay, D-179?15
MR. WOODWARD: Yeah.16
BY MR. WOODWARD: 17
Q I'm showing you what's been marked as D-17918
for identification. This is a letter dated19
August 23, 2010. Have you ever seen that before?20
A Yes, I have.21
Q And, what was the purpose of preparing this22
letter?23
A As a result of the information provided by the24
plaintiff regarding the plan listed on page one, we25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
56/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
57/79
Creelman - Direct 57
Q Also P-86.1
(Pause - side discussion)2
A Is that entitled Floodway and Existing Flood3
hazard Area Delineation?4
Q It says Floodway and Flood Claim5
Delineation.6
A Okay.7
(Pause)8
MR. EISDORFER: There was one that was that9
we did not mark. Was it an, they just had an10
additional one, I guess.11
MR. WOODWARD: It was what?12
MR. EISDORFER: Theres one that we did not13
mark, it was Plaintiffs P-39, except the numbers added14
to it.15
MR. WOODWARD: We have a representation from16
Counsel that the missing document is the same as P-39a.17
MR. EISDORFER: It's, it's this document18
here. We didn't use because it's the same except it19
gets the numbers.20
THE WITNESS: Okay. They both have the same21
date. I think it was --22
MR. EISDORFER: That's right.23
THE WITNESS: -- July 19 th ?24
MR. EISDORFER: Yes.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
58/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
59/79
Creelman - Direct 59
say a permit still would, would not be granted. This1
was submitted to the DEP.2
Q Now, with respect to -- there is one, I think3
P-86 document, which is the, which is that drainage4
map, there's a segment in the report, that area does5
not drain 50 acres, and, therefore, is -- does not6
require a riparian buffer. Have you reviewed that to7
see whether or not you agree with that conclusion?8
A I reviewed P-86. Based upon my review of that, I9
could not make a conclusive determination whether the10
area provided, in fact, was as stated on the drawing11
19.43 acres; mostly because the detail is insufficient.12
Q You couldnt make it out?13
A I couldnt, no.14
Q Now, did there come a point in time when you15
received another report dated August 19, 2010, which is16
P-87? Ill show you this. It's dated and it's from17
Mr. Dipple. Have you ever seen that?18
A Yes.19
Q And what is that letter about?20
A This letter talks about the conceptual design of a21
storm water management system that takes into account22
or tries -- it's an attempt to show that a storm water23
management system could be designed which will take24
into account the existing storm water detention that's25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
60/79
Creelman - Direct 60
provided on the easterly parking lot of 215, south of1
Building 215.2
Q And as I'm looking at P-39a, it's this, it's3
this area on the right-hand side that's outside, or4
generally outside the flood hazard area limit.5
A Correct. Correct.6
Q Did you perform an analysis of that report7
and all of the documents that were submitted with it?8
A We reviewed them and we, I believe we --9
Q You rendered a report?10
A We did, but I thought we had asked for some11
information first. I thought.12
Q Did you receive a letter dated13
September 2, 2010?14
A Yes, we did.15
Q D-184?16
A Yep.17
Q Is that the supplemental information?18
A Yes, it is.19
Q So, what was it that you reviewed, the letter20
dated August 19 th , correct?21
A Correct.22
Q And the letter with attachments dated23
September 2, 2010?24
A Correct.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
61/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
62/79
Creelman - Direct 62
ones and the appropriate mane (phonetic) coefficient1
could be applied to them.2
A time of concentration was assumed for3
drainage areas 3 and 2 of 25 minutes. A type two4
rainfall distribution instead of a type three rainfall5
distribution was used in existing drainage area number6
two.7
Also, we could not determine any backup8
information, or discern any backup information as to9
where the, some of the information came from for the10
broad-crested weirs, and the diameters of the pipes11
that were listed.12
And also that the, finally, that in looking13
at the routing of the existing drainage area for this14
parking lot south of Building 215, it appears that the15
analysis assume that there are 12 inch valves, that the16
storm piping sewer drained into were completely open.17
Q Now, let's talk about each one of these.18
With respect to the soil types, is there a document,19
and I think it's in the September 2 nd additional20
documents, that contain a depiction of what soil types21
were on this property?22
A Yes. It's -- looking at the September,23
September 2 nd L2A plan, or letter, D-1 -- entitled24
D-184, or identified as D-184, there's a plan entitled25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
63/79
Creelman - Direct 63
Web Soil Survey 2.0 National Cooperative Soil Survey.1
And what it does, it provides a, an aerial photograph2
of the site and some surrounding areas with the soil3
survey overlapped on top of it so you could discern4
approximately where the soil limits are.5
Q And which soil types, if you could hold it up6
to the Court so the Court can see; which soil types are7
you referring to and where are they located?8
A The soil types for the eastern, roughly the9
eastern half of the site are HA2b, which is designated10
as a Hydric Soil C. And the PS, PCSAT soil type which11
predominantly covers the western portion of the site.12
And that's known as a Hydric Soil Group D.13
Q And what's the difference between Group C and14
Group D?15
A The, the predominant difference is the ability for16
water to drain into the soil itself. A type C soil is17
more permeable, and a type D soil is less permeable.18
Q So is there a --19
A That, --20
Q Go ahead.21
A The, the result of that is as less water could22
permeate into the ground, you have a higher rate of23
runoff, and is -- not using, using all of C instead of24
C and D, you're artificially lowering the amount of25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
64/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
65/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
66/79
Creelman - Direct 66
the area that it covers, youll get less runoff from1
one acre of C soil than you would from one acre -- I'm2
sorry, let me rephrase that. Youll get one -- youll3
get less runoff from an acre of C soil than you would4
from an acre of D soil, because more water will be5
allowed to percolate into the ground depending on the6
ground cover.7
Q And if, if you're doing the calculations and8
youve got two types of soil and you only use one type9
of soil, will that effect the reliability of your10
calculations?11
A Yes, it will.12
Q How will it do that?13
A You will reduce, by only using the Type C soil14
which allows for a greater permeability into the15
ground, you will reduce the amount of runoff from the16
site, and, therefore, -- excuse me. You will, in your17
routing, you will be allowed to allow more water to go18
off the site.19
Q Now, with respect to -- I'm going to show you20
what's been marked as D-182 for identification. Could21
you tell us what this is?22
A This is entitled The Urban Hydrology for Small23
Watersheds, otherwise known as TR55. And it's24
produced by the NRCS, the Natural Resources25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
67/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
68/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
69/79
Creelman - Direct 69
to a quarter inch in depth, no more. Once you exceed1
that, you get into what they call shower concentrated2
flow. And the velocity of water within shower3
concentrated flow is higher than it is within sheet4
flow.5
Q Why is the, why is the, is the velocity of6
the flow higher in shower concentrated flow than in7
sheet flow?8
A The resistance of the water to go across the9
surface when it's very thin, is greater in sheet flow10
than it is in shower concentrated flow. And, again, if11
you think about these in three segments, as all three12
segments are added up and you end up with a time, the13
time concentration, the time it takes the water from14
its farthest reaches of the drainage area to the point15
of discharge, that relates to how much water would come16
off of that drainage area.17
There are additional calculations that have18
to be done, but that's that portion of it. And when19
you calculate that, that has an impact on the amount of20
water, the rate of water, the rate of discharge.21
Q So what's the difference between using a22
sheet flow of 100 -- of 200 feet versus 150 feet?23
A You are allowing a sheet flow, which means a24
longer time of concentration, a longer period of time.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
70/79
Creelman - Direct 70
And therefore, the rate of discharge, the peak rate of1
discharge will be lower, to some degree.2
Q And you mentioned that there are DEP3
regulations that require this?4
A Yes. There is a, in the DEP regulations, they5
require that you use 150 feet versus 200 feet. I6
believe I heard testimony earlier that they're allowed7
to do 200 feet for a parking area. I could not find8
that regulation. I found that the DEP, the TR55 says9
150 feet. Again, that goes to the amount of discharge10
within a given drainage area, both in the11
predevelopment and the post development condition.12
Q And that ultimately affects the size of any13
detention facilities that have to be constructed.14
A Right. What, what this all boils down to, is when15
you take all of these factors, the time of16
concentration, the coefficient of friction, when you17
calculate all these values, you end up with for any18
given storm in the predevelopment condition, a runoff19
rate, a flow -- discharge flow to a piping system in a20
drainage area.21
We are trying to show that, as it was said22
earlier by Mr. Morrisden (phonetic), that you're not23
going to exceed from the predevelopment in the post24
development. And the way to achieve that is to put25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
71/79
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
72/79
Creelman - Direct 72
guessed at it, but the odds are, we would probably come1
up with a different one. And that doesnt make sense.2
Q Now, going down your list, you indicate there3
is no backup data for the existing outlet structures4
for the watershed entitled, Existing Drainage Area5
One. Could you tell us what kind of backup data there6
should have been, and how that affects the ability to7
design this system, the storm water detention system?8
A Sure. The, the existing, when you're analyzing9
the existing discharge system from a site, be it a10
piping system, a surface flow; you need to know what11
the parameters are.12
In this case, the pipes were given as 1213
inch, and I believe it was, a four inch orifice and14
three broad-crested weirs. We could not confirm15
during -- at the time of this, reviewing of this letter16
if, where the four-inch pipe came out, and also where17
the broad-crested weirs were listed. They were listed18
at three different elevations. I think it was 80.1319
for 30 feet, 80.09 for 25 feet (God bless you.), and20
80.07 for 25 feet, for a total of, I believe, 80 feet21
in length.22
It wasnt clear as to where they were.23
Again, this all goes back to, you determine what your24
peak discharge under the existing condition is for a25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
73/79
Creelman - Direct 73
given storm, and then you compare that same storm event1
under the post development conditions. The delta, or2
the discharge, the difference in discharge between3
those two routings is what needs to be detained in4
storm water system.5
Q Now, with respect to the last point that you6
make there, the hydraulic calculations for the routing7
of the parking lot, the assumption was that the 12 inch8
valves were fully open.9
A Correct.10
Q Youve reviewed this parking lot, youve11
looked at the data, youve looked at the surveys; do12
you have a conclusion as to whether or not this parking13
lot was designed to retain or serve as a storm14
detention facility, storm water retention facility?15
A I believe it was designed to function as some type16
of detention facility, primarily based upon the17
observance of the valves that were at the downstream18
and -- or are at the downstream end of the existing19
pipes at the south end of the parking lot at 21520
Birchwood.21
Q And, what about those valves? What's the22
significance of them in terms of --23
A Well, --24
Q -- functioning as a storm water detention25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
74/79
Creelman - Direct 74
facility?1
A Well, let me, let me preface that by saying,2
working for developers, developers dont want to spend3
money. They do that barebones minimum. That applies4
now. It also applied back in 1973 when they built this5
facility or thereabouts.6
They would not have installed valves. They7
didn't have to. They didn't do it out of the8
generosity of their hearts. They didn't have to. They9
would have just put a 12 inch pipe in, and that could10
have acted, when they did the routing, as an orifice,11
or orifices.12
Therefore, having the valves installed, the13
purpose was to reduce the opening in the valves to some14
degree, I do not know what that degree is. I won't15
speculate on that; in order to provide or retain the16
existing water in the parking lot from discharging at a17
higher rate of, at a higher rate.18
Whether you close the valve from 12 inches,19
to nine inches to eight inches, to six inches; I --20
honestly I dont speculate. And I believe that's why21
Mr. Morrisden was saying the only way to determine or22
approximate how much those valves need to be, were23
closed, were to go back to compare what you have on the24
site today and then go back to the predevelopment25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
75/79
Creelman - Direct 75
condition and do a similar analysis, what I just1
described and say, okay, when it was a horse farm, it2
had 30 gallons, or 30 cubic feet per second, and now it3
has 40. Okay, well now we have to detain 10 cubic4
feet.5
So they close the valve down through modeling6
of the program -- through the TR55 modeling, and say,7
okay, well close the valve down from 12 inches to8
eight inches, and that will slow the discharge rate, so9
we detain an additional ten cubic feet per second10
within the parking area. And, therefore,11
predevelopment flows -- or post development flows will12
then equal predevelopment flows.13
Q Based on the foregoing and based on your14
analysis of the documentation submitted both in the15
August 19 th report and the September 2 nd16
supplementation, do you know, do you have an opinion as17
to whether or not the storm drainage facility proposed18
here by the plaintiffs would obtain a permit from the19
DEP?20
A Solely based upon the information provided to me,21
I would say that they would definitely not obtain a22
permit from the DEP --23
Q And why not?24
A -- for storm water management. One of the most25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
76/79
Creelman - Direct 76
significant ones is that, given the elevation of the1
swale that the proposed system would drain into, I2
believe the swale is somewhere around 75.1. The3
proposed discharge pipe from the underground storage4
system was at 75.4. They were providing a height of5
storage in a structure of 30 inches, 2 feet. We also6
know that the, the flood hazard elevation line is at7
78.6 uphill, on the up -- on the northern end of the8
site, and 78.4 on the downhill side.9
Somewhere below that is other storm events.10
The limits of where those flood waters would reach11
during those storm events, I'm going to pick on, I'm12
going to pick on, let's say the ten year storm event,13
which would probably occur somewhere, if we look at, I14
don't know what that, what's that exhibit again?15
Q P-39a.16
A If we look at P-39a. This is the --17
Q You're pointing -- you're using your --18
A I'm sorry. I'm pointing my laser pointer to point19
to P-39a. And showing the easterly floodway line20
traversing the site east of Casino Brook between the21
floodway line and the flood hazard line, we know that22
the 100 year flood line exists in there. It would not23
be unreasonable to say that somewhere in the limits of24
the 10 year storm event will also occur.25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
77/79
Creelman - Direct 77
If, when you're doing a storm water design1
and your discharging within the floodway, one of the2
requirements is that you design a storm water3
management system to be able to discharge against a4
head. A lot of times that head in this case may be the5
ten year design storm.6
Q When you say a head, is that like a7
tailwater?8
A A tailwater design, correct. So, instead of the9
pipe discharge freely at all times and not have any10
resistance, there would be water at the face of the11
pipe where your, where your proposed pipe is12
discharging to. So, instead of just flowing out into13
no mans land, it would be hitting water. That would14
re, that would result in an effect of the water, the15
proposed discharge of the water backing up in the16
piping system, and subsequently backing up in the17
proposed underground detention system.18
That could be equated to a loss in volume19
which would result in the underground detention system20
having to be increased in size to account for it's21
ability to need to store additional water until it,22
until this proposed discharge can hydraulically23
overcome the tailwater -- I'm looking for it; the24
tailwater effect, that's happening from a ten year25
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
78/79
Creelman - Direct 78
storm. And I didn't see that in anything that I saw1
here.2
Q There's no tailwater analysis?3
A No.4
Q And if there's no tailwater analysis, is that5
something DEP would require?6
A Absolutely.7
MR. WOODWARD: No further questions, Your8
Honor.9
THE COURT: Okay. I'm going to break now for10
the day, because I am actually teaching a, an11
(inaudible) course tonight which I have to get to.12
And, we're not going to finish with this witness today13
anyway, okay?14
MR. EISDORFER: Your Honor, I don't have a15
lot of cross-examination, but I'm happy to postpone it16
until first thing tomorrow.17
THE COURT: And we have to come back anyway,18
because Ms. McKenzie might have some questions. And19
then she has to give her total report. So, I'm going20
to break now for the day and well see you tomorrow21
morning.22
(Whereas proceedings of 9/28/10 were concluded)23
* * * * *24
-
7/31/2019 Transcript 9.28.10 Creelman Twp Outside Engineer
79/79
79
1
2
CERTIFICATION3
4
I, Darcel D. Hart, the assigned transcriber, do5
hereby certify that the foregoing transcript of6
proceedings in the matter of LEHIGH ACQUISITION, ET AL,7
VS. TOWNSHIP OF CRANFORD, heard in the Union County8
Superior Court, Law Division, Civil Part on9
September 28, 2010, Tape Number 237-10, Index #1430 to10
Index #7428, and Tape Number 238-10, Index #0001 to11
Index #3302, is prepared in full compliance with the12
current Transcript Format for Judicial Proceedings and13
is a true and accurate non-compressed transcript of the14
proceedings as recorded.15