TRANSBAY - BLOCK 3 PARK
The Webinar Presentation will start momentarily. Please wait!
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
TONIGHT'S PROGRAM TIME:INTRODUCTION: OCII - PROJECT & TEAM BACKGROUND 5 MINUTES
- POLL
PRESENTATION: DESIGN TEAM I - OVERVIEW OF COMMUNITY MEETING #1 FEEDBACK
II - PARK PROGRAM & ANALYSIS 25 MINUTES
III - PARK DESIGN ALTERNATIVES
FEEDBACK: COMMUNITY - PUBLIC COMMENT - Q&A 30 MINUTES
- ONLINE FEEDBACK SURVEY
NEXT STEPS - PROJECT SCHEDULE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
WELCOME & THANK YOU FOR ATTENDING! YOUR INPUT IS INVALUABLE
PROJECT TEAM:
• OFFICE OF COMMUNITY INVESTMENT & INFRASTRUCTURE (OCII) BENJAMIN BRANDIN - DEVELOPMENT SPECIALIST SALLY OERTH - DEPUTY DIRECTOR, PROJECTS & PROGRAMS
• SAN FRANCISCO RECREATION AND PARKS STACY BRADLEY - DEPUTY DIRECTOR OF PLANNING YAEL GOLAN - PLANNER ERIC ANDERSEN - SUPERINTENDENT OF PARKS AND OPEN SPACE
• SAN FRANCISCO PUBLIC WORKS KATHLEEN O’DAY - PROJECT MANAGER LIZZY HIRSCH - PROJECT LEAD FOR DESIGN TEAM BRETT DESMARAIS - DESIGN LAWRENCE CUEVAS - DESIGN VERONICA CHAN - DESIGN WINNIE CHANG - DESIGN
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
VIRTUAL MEETING FEEDBACK OVERVIEW
HOW TO PROVIDE FEEDBACK:
• PLEASE ENTER ALL QUESTIONS, COMMENTS, OR FEEDBACK INTO THE Q&A AT ANY POINT DURING THE PRESENTATION
• QUESTIONS WILL BE READ AND ANSWERED ALOUD DURING THE Q&A PERIOD FOLLOWING THE PRESENTATION
• A SUMMARY OF THE Q&A, INCLUDING ANY OUTSTANDING QUESTIONS THAT WERE NOT ANSWERED DURING THE MEETING, WILL BE POSTED TO THE PROJECT WEBSITE FOLLOWING THIS MEETING
• AGREE TO BE OPEN MINDED, LISTEN TO EACH OTHER’S IDEAS, COMMUNICATE WITH RESPECT
NOTE: THIS IS A WEBINAR FORMAT AND ONLY PANELISTS AND MODERATORS WILL BE SEEN OR HEARD. ADDITIONALLY, IT IS BEING RECORDED FOR PUBLIC DISTRIBUTION.
POST-MEETING SURVEY LINK:
https://www.surveymonkey.com/r/TransbayBlock3-CM2
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
POLL
• DID YOU ATTEND TRANSBAY BLOCK 3 PARK COMMUNITY MEETING #1 IN MARCH?
• DO YOU LIVE OR WORK IN EASY WALKING DISTANCE TO THE PROPOSED NEW TRANSBAY BLOCK 3 PARK (WITHIN 1 MILE APPROX)?
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
DESIGN DEVELOPMENT PROCESS
DESIGN PROCESS COMMUNITY INPUT SCHEDULE
PLACE-BASED DESIGN
CONCEPTS
CLIMATERESPONSIVE
DESIGN
MEETING 1: MARCH 2020
GOAL: ESTABLISH PREFERRED DESIGN DIRECTION
MEETING 2: SEPTEMBER 2020
MEETING 3: FALL 2020
COMPREHENSIVECOMMUNITYOUTREACH
RESEARCH + ANALYSIS
INITIAL DESIGN CONCEPTS
DESIGN REFINEMENT
DEVELOP SCHEMATICDESIGN PACKAGE:COMPLETED SUMMER, 2021
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PART I - OVERVIEW
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
SITE: CONTEXTUAL FRAMEWORK
0 0.5 1Miles
BEALE ST
MAIN ST
FOLSO
M ST
HOWARD ST
BLOCK 2
BLOCK 2
BLOCK 4
BLOCK 4
BLOCK 3
BLOCK 3
PARK
PARK
EXISTING SITE:
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
BEALE ST LOOKING NORTHEASTBEALE ST LOOKING NORTH
MAIN ST LOOKING NORTHWEST
what do you IMAGINE | community feedback
View From Beale & Clementina (future Block 3 development) looking north
N
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
WHO? PARK WISHLIST
East Cut CBD Online Community Survey results amended with responses from those who had not taken initial survey
Park activity:
48%
16%
relax
walk dog
eat or drink
exerciseplay
other
are from the area
live 2-5 min walk away
live in a 2 person home
have dogs
have children
85%
71%
65%
20%
24%Desired amenities:
grassy areas to sitfood & bev. vendorpublic artfarmer’s marketpublic restroomcommunity gardenother
74%
51%
47%
45%
32%
31%
28%
COMPOSITE SURVEY RESULTS POST COMMUNITY MEETING 1 - 03/04/2020
East Cut CBD Online Community Survey Results: 582 respondents
Community Meeting 1 Survey:18 additional responses
COMMUNITY MEETING 1 - DOT BOARD RESULTS
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
CULTURAL AMENITIESPARK SEATING PLAY IN THE PARKPARK CHARACTER
Yes Yes Yes YesMixed Mixed Mixed MixedNo Thanks No Thanks No Thanks
RESTROOM IN THE PARK?
LIKE
DISLIKE
DOT LEGEND:
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PART II - PARK PROGRAM & ANALYSIS
3 0 3 2 N D S T
H I L L S P L A Z A
S A L E S F O R C E TO W E R
F O U N D RY
S Q UA R E
B AY AR E A
M E T R O CE N T E R
O N E R I NCO N
H I L L
PA R K TO W E R
R I NCO N C
E N T E R
G A P HQ
G A P
U S F S C H O O L OF
MA N AG E M E N T
1 0 1
2 N D S T
CO U R T YA R D BY
MA R R I OT T
F D I C
S A I LO R S
U N I ON O
F
T H E
PAC I F I C
T H E
M E T R O P O L I TA N
J A S P E R
R I NCO N G
R E E N
A PA R T M E N TS
D I GI TA L R E A L I T
Y
DATA CE N T E R
P G & E
P O R TS I DE
3 3 3
F R E M O N T
3 4 0
F R E M O N T
3 9 9
F R E M O N T
P G & E
S U B S TAT I ON
S O L A I RE
T E R R A
G A L L E RY
G O L D E N
G AT E
U N I VE R S I T
Y
F E R RY
B U I L D I NG
I NF I N
I TY
LU M I NA
BLOCK 3
PARKBLOCK 4
BLOCK 2
MINNA STREET
NATOMA STREET
MISSION STREET
STEVENSON STREET
ANTHONY STREET
ECKER STREET
JESSIE STREET
ELIM ALLEY
POST STREET
SUTTER STREET
BUSH STREET
CALIFORNIA STREET
MON
TGOM
ERY S
TREE
T
SANS
OME S
TREE
T
BATT
ERY S
TREE
T
FRONT STREET
DAVIS STREET
DRUMM
STREET
RINCON STREET
FEDERAL STREET
STERLING STREET
MALDEN ALLEY
TEHAMA STREET
ECKER STREET
CLEMENTINA STREET
LANSING STREET
GUY PLACE
ZENO PLACE
BRYANT STREET
STEUART STREET
I-80
BAY BRIDGE
2ND STREET
1ST STREET
FREMONT STREET
BEALE STREET
MAIN STREET
SPEAR STREET
THE EMBARCADERO
MISSION STREET
HOWARD STREET
FOLSOM STREET
HARRISON STREET
Base map courtesy of The East Cut CBD
BLOCK 3 ADJACENT OPEN SPACE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
UNDER RAMP PARK
(FUTURE)
TRANSBAY PARK
FUTURE
AFFORDABLE
HOUSING
SALE
SFORCE PA
RK (ELE
VATED)
MARKET STREET
RINCONPARK
SF BAY
RINCON PARKUNDER RAMP
UNDER RAMP
PARK (F
UTURE)
PARK (F
UTURE)
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PARK - PROPOSED PROGRAMS
ADJACENT NEIGHBORHOOD PARK PROGRAMS:
- RINCON: OPEN GREEN, PUBLIC ART
- SALESFORCE: GARDENS, KIDS PROGRAM & PLAY, STROLLING, EVENT SPACE & FOOD
- UNDER RAMP (FUTURE): DOG PARK, FOOD & BEVERAGE, SPORTS COURT
BLOCK 3 PARK PROPOSED PROGRAMS:CRITERIA: PROVIDE PROGRAMS NOT AVAILABLE AT ADJACENT NEIGHBORING PARKS
& CREATE A COMMUNITY BASED HUB
- KIDS’ PLAY ELEMENT
- PASSIVE RECREATION/GATHERING
- FLEXIBLE PROGRAM SPACE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
DESIRED PROGRAM ELEMENTS
LARGE SCALE SPACES FOR:
FLEXIBLE PROGRAMMINGMOVIE NIGHT
FARMERS MARKETFOOD TRUCKS
MEDIUM SCALE SPACES FOR:
BIRTHDAY PARTIESPICNICKING
COMMUNAL SEATING ZONECOMMUNITY EVENTS
SMALL SCALE SPACES FOR:
PLACES TO SIT BY YOURSELF OR IN SMALL GROUPS SURROUNDED IN NATURE
SOUTH PARK, SFSQUARE JACQUES DE BOLLARDIERE,
NANTES, FR
PLAY SIZE SIMILAR TO:
THE COMMONS
OPEN FLEXIBLE SPACES SEATINGGATHERING SPACES PLAY
3,000 - 6,000 SF 4,000 SF50 SF500 - 2,000 SF
BLOCK 3 PARK: 40,000 SF
how BIG is block 3 park?Huntington Park - Nob Hill
1.3 Acres
Union Square - Downtown2.6 Acres
Block 3 Park<1.0 Acre
South Park - South Beach1.1 Acres
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
HISTORICAL PARK TYPOLOGIES
WASHINGTON SQUARE PARK: 2.4 ACRESBLOCK 3 PARK: <1 ACRE <1 ACRE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
FUTURE FOR BLOCK 3 PARK1870s - 1950s
FORMAL
1950s - CURRENT
INFORMAL DESIGN = SUSTAINABILITY GOAL + COMMUNITY NEEDS
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
TRANSBAY NEIGHBORHOOD HISTORY SUMMARY
5,000YEARS AGO
18TH
CENTURY
19TH
CENTURY
CURRENT
FUTURE?
+
+
+
+
+
+
+
+
+
+
TRANSPORTATION ENVIRONMENT SITE OCCUPANCY
BLOCK 3 ANALYSIS
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PEDESTRIAN CIRCULATION
MTA PLANNED BIKE PATHS
YEAR ROUND SUN ZONE
POTENTIAL GROUND FLOOR RETAIL
RESIDENTIAL CONNECTIONS TO PARK
VEHICULAR TRAFFIC DIRECTION
Main St
Beale St
Tehama St
Block 4
+ 5.12’SIGNALIZED CROSSING
~2% SLOPE
1.77’ +
+ 3.63’ 0.00’ +
Bock 2
Clementina St
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PART III - PARK DESIGN ALTNERATIVES
BLOCK 3 PARK CONCEPT DESIGN ALTERNATIVES
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
THE CLEARING THE COMMONS THE RIPPLE
+3 0 ”
+0 ”
+0 ” +0 ”
THE CLEARING
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
MAJOR CIRCULATIONMINOR CIRCULATIONOPEN FLEXIBLE SPACESGATHERING SPACESSEATINGPLAYMOST SUN YEAR ROUND
THE CLEARING INSPIRATION
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PICNIC TABLE
NATURAL MEADOW
WOODEN BENCH
WOODEN TERRACE
MULTI-TONED PAVING
CLEARING DESIGN CONCEPT
6
7
5 23
STONE WALL
1
54
2
6
3
4
4
7
THE COMMONS
MAJOR CIRCULATIONMINOR CIRCULATIONOPEN FLEXIBLE SPACESGATHERING SPACESSEATINGPLAYMOST SUN YEAR ROUNDFLEXIBLE TABLES/CHAIRS
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
THE COMMONS INSPIRATION
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
COLORFUL WINDY BENCHES
FLEXIBLE TABLES AND CH AIRS
RE-USE EXISTING PALMS
CURVED SEATWALL
WAVY PAVING
FOREST WALK
4
2
6
17
5
3
OVERHEAD STRUCTURE
1
54
2
6
3
7
THE RIPPLE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
MAJOR CIRCULATIONMINOR CIRCULATIONOPEN FLEXIBLE SPACESGATHERING SPACESSEATINGPLAYMOST SUN YEAR ROUND
L A W N
3 0 ” +
+0 ”
THE RIPPLE INSPIRATION
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
TREE GROVE
ISLAND INHABITATION
OVERHEAD W/ SWING BENCH
ELEVATED TURF
ISLAND SEATING
ISLAND DESIGN CONCEPT
3
7
6
4
1
54
2
6
3
7
5 2
PAVING RIPPLES
PLAY INSPIRATION
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PLAY
GRO
UN
D SP
ACES
IMAG
INAT
IVE
PLAY
INTE
RACT
IVE
PLAY
STRU
CTU
RE B
ASED
PLA
Y
SEATINGGATHERING SPACESOPEN FLEXIBLE SPACES PLAY
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
THE CLEARING THE COMMONS THE RIPPLE
COMPARATIVE DESIGN ALTERNATIVES
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
COMPARATIVE PROGRAM STRATEGIES
OPEN FLEXIBLE SPACES3,000 - 6,000 SF
SEATING50 SF
GATHERING SPACES500-2,000 SF
PLAY4,000 SF
L A W N
THE CLEARING THE COMMONS THE RIPPLE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
COMPARATIVE SUN/PROGRAM AREAS YEAR ROUNDAF
TERN
OO
N S
UN
MID
DAY
SUN
MO
RNIN
G SU
N
THE CLEARING THE COMMONS THE RIPPLE
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
COMPARATIVE DESIGN INSPIRATIONS
TREE GROVE
ISLAND SEATING
OVERHEAD W/ SWING BENCHELEVATED TURF
ISLAND INHABITATION
2
6
53
21
3
5 6
4
1
PAVING RIPPLES
FOREST WALK
COLORFUL WINDY BENCHES
OVERHEAD STRUCTURE
FLEXIBLE TABLES AND CHAIRS
WAVY PAVING
6
2
1
5
4
3
CURVED SEATWALL 43 4
1
5
2
6
WOODEN TERRACEPICNIC TABLE
WOODEN BENCH
STONE WALL MULTI-TONED PAVING
NATURAL MEADOW
1
6
42
5
5
4
1 2
3
3
6
THE
CLEA
RIN
G
THE
COM
MO
NS
THE
RIPP
LE
3
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
QUESTION & ANSWER SESSION WITH PANELISTSQUESTION & ANSWER SESSION WITH PANELISTS
PLEASE SHARE YOUR THOUGHTS, OBSERVATIONS, AND QUESTIONS
• IS THERE A DESIGN ALTERNATIVE YOU ARE MOST DRAWN TO AND WHY?• WHAT PARK ELEMENT IS MOST IMPORTANT TO YOU?• IS SOMETHING MISSING YOU WOULD LIKE TO SEE?
PLEASE FILL OUT THE SURVEY WITHIN THE NEXT TWO WEEKS:
https://www.surveymonkey.com/r/TransbayBlock3-CM2
FEEDBACK
SEATINGGATHERING SPACESOPEN FLEXIBLE SPACES PLAY
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
THE CLEARING THE COMMONS THE RIPPLE
COMPARATIVE DESIGN ALTERNATIVES
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
PROJECT SCHEDULE
PROJECT SCHEDULE: DEC 2019 - WINTER 2024 CONCEPT/PLANNING 11 MONTHS
SCHEMATIC DESIGN 8.5 MONTHS
DESIGN DEVELOPMENT 5 MONTHS
CONSTRUCTION DOCUMENTS 8 MONTHS
BID/AWARD 4.5 MONTHS
CONSTRUCTION 24 MONTHS
CONCEPT PHASE - OUTREACH SCHEDULE COMMUNITY MEETING 1: INFORMATION GATHERING
COMMUNITY MEETING 2: INITIAL DESIGN IDEAS
COMMUNITY MEETING 3: DESIGN REFINEMENT
PUBLIC SURVEYS
GOAL: ESTABLISH PREFERRED DESIGN DIRECTION
MEETING 1: MARCH 2020
MEETING 2: SEPTEMBER 2020
MEETING 3: FALL 2020
RESEARCH + ANALYSIS
INITIAL DESIGN CONCEPTS
DESIGN REFINEMENT
DEVELOP SCHEMATICDESIGN PACKAGE:COMPLETED SUMMER, 2021
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
FOR REGULAR UPDATES, VISIT THE PUBLIC WORKS WEBSITE: http://sfpublicworks.org/Block3Park
FOR QUESTIONS OR MORE INFORMATION, PLEASE CONTACT KATHLEEN O’DAY:
[email protected]; (415) 218-7515
CONTACT
BLOCK 3 PARK
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
APPENDIX
Community Meeting 2 | 9.9.2020Building Design & Construction
BLOCK 3 PARK
RESTROOM CONTEXT
JC DECAUX (CONCEPT IN DESIGN FOR INSTALLATION IN SF)
RESTROOM SCALE STUDY
6 MIN. WALK TO PUBLIC RESTROOMS
BLOCK 4
BLOCK 3
BLOCK 2