Training: MED-SOLAR
MODULE 6
Maintenance
of PV Power Plants
a) Surveillance level - basic up keeping duties to be performed by the
operator’s local service, e.g. technicians, keepers, etc.
verify that operational values are correct (fulfill the nominal specifications)
b) Preventive maintenance level – duties to be performed by the professional
maintenance contractor (Maintenance Contractor)
Verify that performance indicators, output, protection and durability are kept
within the correct operational ranges
c) Supervision – Evaluation level – duties to be performed by the premise
administrator or a subcontracted engineer evaluator (Engineering consultant)
data collection and analysis, write up of evaluation reports
The 3 levels of O&M intervention
Source: MDC Egypt
Level of preventive maintenance
The O&M Plan must always be:
• adapted to the plant implemented and to the site hosting it
• prepared by or with assistance of qualified professional (s)
Reference list of contents
1. Cover – with title, authors, date, and revision tracking registry
2. Identification of roles and staff for Basic Maintenance and Professional contractors – with copies of contracts in annex
3. PV plant description – project as-built
4. Task check-lists – specifying responsibility, frequency for each task
5. Protocol for Basic Maintenance (operating ranges, templates for O&M Book,
Troubleshooting)
6. Monitoring plan – specifying parameters, data logging, data downloading and
management
O&M plan – referencecontents
- Checklists by O&M level
- Tasks organised in categories - subsystems given in a PV installation:
- Also, frequency for each task must be specified:
FREQUENCY
(preventive
actions)
at all times
weekly
monthly
trimestral
semestral
yearly
every 3 - 4 years
SUBSYSTEM
0 - General
1 - PV Generator and roof
2 - Battery
3 - Charge Controller and data logger system
4 - Inverter
5 - DC distribution and protections
6 - Technical Cabinet
7 - AC connection to Grid
8 - AC feeder line and priority loads
Reference O&M taskchecklists
O&M CODE SUBSYSTEM NAME - DESCRIPTION Frequency
1 0 - General Existence and availability of O&M checklists at all times
2 0 - General Existence and availability of O&M plan at all times
3 0 - General Availability and updating of O&M book records (O&M book) at all times
9 0 - General
Access to Solar Panels (roofs), Tanks and control system
rooms is restricted only to maintenance and authorised
personnel
at all times
111 - PV Generator
and roof
Visual check for shading of the collectors during the day (mid-
morning, noon, and mid-afternoon)yearly
121 - PV Generator
and roofPrevent eventual vegetation growth that may produce shading. semestral
131 - PV Generator
and roofCleaning of eventual dusty or soiled panels trimestral
141 - PV Generator
and roofVisual Check for cracks, hot spots, colour defects in PV panels trimestral
151 - PV Generator
and roofSealant around roof penetrations should be in good condition. trimestral
161 - PV Generator
and roof
Visual Check all nuts and bolts fixing the panels to any support
structures for tightness, absence of corrosion in metallic partstrimestral
Task Checklist (18) for level 1 – Surveillance level
O&M CODE SUBSYSTEM NAME - DESCRIPTION Frequency
171 - PV Generator
and roof
Verify the reference photocell and the temperature sensor
condition (tight fixation, good contact, wire continuity)trimestral
181 - PV Generator
and roofVisual check the wiring good condition trimestral
20 2 - Battery Check the battery density and voltage (each cell) trimestral
21 2 - Battery Check the battery bank voltage monthly
22 2 - Battery
Visual check of cell condition - free of sediments and cristals,
electrolyte level, free of corrosion, connections tight and
protected)
monthly
23 2 - Battery Check availability of densimeter, gloves, goggles, distilled
water, thermometer, funnelmonthly
25
3 - Charge
Controller and
data logger
Check that basic performance parameters lie within design
specifications. Register basic parameters in M&E bookmonthly
336 - Technical
Cabinet
Check good ventilation , restricted acces and availability of
H&S equipment (fire extinguisher, hazard signaling
panels/plates, existing eye wash)
monthly
Task Checklist (18) for level1 – Surveillance level
Source: OPEXEnergy
Source: Solar Clean Hymach
Level 1 – Surveillance level
Source: Solar Clean Hymach
O&M templates (Surveillance level ) - Monthly-Trimestral
O&M
CODESUBSYSTEM NAME - DESCRIPTION Frequency
4 0 - General Existence and availability of as-built drawings at all times
5 0 - General Existence and availability of technical documentation at all times
6 0 - General Existence and availability of operations manuals at all times
7 0 - General Existence and availability of the monitoring and evaluation (M&E) plan at all times
8 0 - General Availability and updating of M&E reports (M&E book) at all times
10 0 - General General check-up of all elements and operating conditions semestral
191 - PV Generator
and roofCheck the panels and wiring condition, fulfilment of operating specifications semestral
24 2 - Battery Check good condition of wiring and terminals (including earthing), tight
connections, free of dust.semestral
30 4 - InverterCheck inverter state: operation, displays, alarms, verification of modes of
operation, etcsemestral
315 - DC distribution
and protections
Check good condition of wiring and terminals (including earthing), tight
connections, free of dust.semestral
325 - DC distribution
and protections
Check good condition of the ELV connection board - meter, switches, wiring and
terminals (including earthing), tight connections, free of dust.semestral
347 - AC connection
to Grid
Check good condition of the LV connection board - meter, switches, wiring and
terminals (including earthing), tight connections, free of dust.semestral
Task Checklist (12) for level2 – Maintenance Contractor
CODE SUBSYSTEM NAME - DESCRIPTION Frequency
263 - Charge Controller
and data loggerDownload monitoring data, check raw data for eventual errors or inconsistencies
trimestral
273 - Charge Controller
and data logger
Analyse monitoring data and prepare
evaluation reports (semestral, yearly and
aggregate). Draw conclusions and
recommendations on basic and operational parameters.
semestral
283 - Charge Controller
and data logger
If 3rd level monitoring is set, Analyse
Complete monitoring data, prepare evaluation
reports (semestral, yearly and aggregate) and draw conclusions / recommendations
semestral
293 - Charge Controller
and data logger
Check that Operational performance
parametres lie within design specifications. Register operational parameters in M&E book
monthly
Task Checklist (4) for level 3 – Engineering consultant
Revenues in large commercial and utility plants and microgrids = afford O&M contracted to professional staff.
Some contractors offer integrated services: monitoring, insurance and performance assurance.
The cost of O&M can widely vary not only as a function of technology, plant size and site conditions but also as a function of market development in the country.
Reference rule of thumb: 1.5 – 2.0% of the investment costs
Autonomous and back-up plants are more complex and expensive,maintenance-wise, than pure grid-dependent plants due to the additionalcomponents such as batteries and load control devices, and also due to theirrelative smaller size.
Technical O&M costs
RISK Insurance: protection from unexpected damage
COVERS: natural conditions (fire, lightning, storm, snow,…), water damage and flood, short-circuits, overcurrent and overvoltage, explosion, errors during construction or installation, material errors, subsidence, landslide, rockslide, thef and vandalism, operating error, negligence…
NOT COVER: earthquake, war, terrorism, nuclear accidents/ radiation or radioactive substances, internal unrest, normal operational or premature wear, corrosion, existing deficiencies…