training agenda planner module – september 20, 2005 afternoon session: i. planners training...
TRANSCRIPT
TRAINING AGENDA Planner Module – September 20, 2005
Afternoon Session:
I. Planners Training Exercise
Review Marie Headquarters Case Study
II. Complete 1391 for Integration of LID Approach into New
Construction of Stormwater System Projects:
– LID Project Objectives– Master Planning Process
• Integration into Site Analysis, Benefit Analysis, Site Design Selection, Plan Development
• Green Roof
– Discuss Traditional Site Plan vs. LID Approach
LID Project Objectives
LID Project Objectives
• LID approaches and techniques for the design of the MARFORLANT headquarters facility– Feasibility– Potential effectiveness
LID Project Objectives
• Utilizing LID techniques and practices to meet:– Regulatory requirements– Federal government program goals
• Water conservation• Energy conservation• Environmental stewardship
– Natural resource program management objectives
Norfolk Naval Support Activity Case Study: Master Planning Process
• Meet Virginia Department of Conservation and Recreation (VDCR) stormwater management regulations.
• rainfall used for non-potable uses (irrigation or toilet flushing)
• Ancillary benefits energy conservation – vegetated roof– strategic siting of vegetation.
Norfolk Naval Support Activity Case Study: Master Planning Process
• assist in meeting the Executive Council Storm Water Directive (EC Directive 01-1) “GOVERNMENT BY EXAMPLE”
• Eliminate pond option by replacing the hydrologic and hydraulic functions with LID practices such as bioretention. – eliminating pond maintenance – pond vector issues.
Master Planning Process
• Integration into:– Site Analysis–Benefit Analysis–Site Design Selection–Plan Development
Master Planning Process: Site description
• 7.1 acres in size.• The site slopes gently from the north and south
to a low point located approximately in the center of the property.
• mix of woods and grass The grass is in fair condition and some bare spots are present.
• The soils on site are compacted.• The drainage is conveyed by existing yard inlets
to a storm drain.
Master Planning Process: Proposal
• 55,000 sq. ft. building located on northern portion of site
• 280 employee parking spaces
• Future building is planned alone western side of proposed facility.
• Conventional stormwater facility shown along western edge of parking area
• Woods should remain undisturbed
Site Plan
Proposed building and parking
Master Planning Process: Hydrologic Analysis
• The Commonwealth of Virginia requires peak runoff post-development condition to equal or be below the discharge from the pre-development condition for the 2-year 24-hour storm
• the 10-year 24-hour storm event for urban areas for adequate conveyance.
• Pre-and Post-development conditions are compared to determine a storage volume
• Detention method was used because the presence of compacted soils
Master Planning Process: Hydrologic Analysis
• The site area required to maintain the pre-development runoff rate for:– 2-year 24-hour storm event using LID
practices with a six-inch depth is three (3) percent, or approximately 0.2 acres
– 10-year 24-hour storm event using six-inch depth LID practices with a six-inch depth is eight (8) percent, or approximately 0.6 acres
Master Planning Process: Non-potable water
• Secondary non-potable usage (i.e. toilet flushing, cooling)
• Daily water demand 4,500 gpd for 300 office workers (15 gal per person per day)
• Cistern size of 14 diameter and height of 37 ft to capture and reuse water.
LID Site Design
• Requirement of 8% of the site in LID features– Runoff will sheet flow to a centralized
bioretention facility with several perimeter bioretention facilities
– Permeable surfaces shown on walkways– Green roof
Master Planning Process
Green Roof
Green Roof
• Conditions that have spurred green roof development– Prevalence of combined sewer systems– Antiquated and over-taxed sewer and waste
treatment facilities– Widespread pollution of rivers and estuaries– Frequent nuisance flooding– Limited space for instituting large
management facilities
Green Roof (continued)
• Driving factors for Green roof at MARFORLANT facility– Mitigate water runoff impacts associated with new
development– Compensate for the loss of green space in the
memorial park– Limited treatment options for site are limited do the
location of low point and high water table– Increases service life of roofing system– Reducing energy cost
Layers of Green Roof
• Waterproofing membrane
• Root barrier (if the waterproofing is not certified as root resistant)
• Drainage layer
• Separation layer
• Growth media layer
• Plants
Green Roof Calculations
Dead Load (PSF) = 5.75 x depth of green roof
Green Roof: Planning Calculations
Conservative estimate of stormwater performance:
Reduction in Annual Runoff(%) = 45 x (MWC (in.))1/3
Storm Magnitude Controlled (in) = 2.5 x MWC (in.)
MWC = Maximum Water Capacity of green roof
Green Roof: Pollution Removal
• It is estimated 30% of all nitrogen and phosphorus in local streams is from roof runoff
• Green roof have demonstrated the removal of:– 68% of total phosphorus – 80% of total nitrogen
Green Roof Benefits: Energy
• Estimated 10% reduction in air-conditioning related energy costs
• Roofing system is expected to last 2-3 times longer than normal
Green Roof Costs
• Estimate 3 man-hr pre year per 1,000 sq ft
• $0.20 per square ft of impervious area annually
Green Roof: LEED Credits
• Stormwater management
• Water efficient landscape
• Improved energy performance
• Recycled material content
• Local and regional material
Totaling 16 credits
Traditional Site Plan vs. LID Approach
Traditional Site Plan vs. LID Approach
Conventional
• large capital investments in complex and costly engineering strategies
• pipes water to low spots as quickly as possible
LID Design
• Integrates, green space, native landscape, natural hydrology functions to generate less runoff.
• Uses micro-scale techniques to manage precipitation as close to where it hits the ground as possible
Traditional Site Plan vs. LID Approach
Conventional vs. LID: Military Housing Development
UFC
Conventional vs. LID:
Comparision of CN and Peak Discharge
0
10
20
30
40
50
60
70
80
90
CN Peak Discharge (CFS)2-year Storm 3” Depth
Peak Discharge (CFS)10-year Storm 5”
Depth
(CF
S)
Conventional CN
LID Design
Existing Condition
Conventional vs. LID
Volume Comparision
0
0.5
1
1.5
2
2.5
3
3.5
4
Volume (Depth in Inches) 2-YearStorm Event
Volume (Depth in Inches) 10-Year Storm Event
Vo
lum
e (d
epth
in) Conventional CN
LID Design
Existing Condition
1391 Process
1391PROJECT SUMMARY
PROJECT NAME MARFORLANT Facility
FACILITY Naval Support Activity Norfolk
PROJECT DESCRIPTION
Determine feasibility and effectiveness of LID site design and green roof study.
PROJECT OBJECTIVES
1) To improve water quality of site 2) To reduce runoff volume and peak flow rates for
compliance 3) Meet FEMP objectives for water conservation and
LID 4) Meet Greening Government, LEED, and other
program objectives
1391PROJECT BENEFITS
ENVIRONMENTAL
Reduces pollutant loads by volume reduction and filtering. Bioretention and green roof systems provide superior filtering of oil and grease, TPH, thermal pollutant reduction, atmospheric nitrogen deposition
WATER CONSERVATION
Reduces potable water consumption by minimizing irrigation requirements. Opportunities for cisterns for other non-potable uses.
ENERGY MANAGEMENT
Shading of parking areas. Vegetation orientation reduces energy consumption. Green roof provides energy benefits.
MAINTENANCE Minimizes maintenance requirements through the utilization of water-efficient, native, adaptable, climate-tolerant plant material.
AESTHETICS Integration of natural landscape design with native plants and additional vegetation in bioretention cells. Green roof may be viewed from building.
EDUCATION Promotes DoD awareness of environmental and water conservation activities
1391LEED ISSUES (US GREEN BUILDING COUNCIL)
Potential for LEED credits for using natural treatment systems that treat the site’s stormwater, increase on-site infiltration, and reduce potable water requirements
GREENING THE GOVERNMENT EXECUTIVE ORDERS
Consistent with:EO13101 – Greening the Government through Waste Prevention, Recycling, and Federal AcquisitionReuse of stormwaterEO13123 – Greening the Government through Efficient Energy ManagementReduction of potable water requirements; improvement of water quality; minimization of maintenance requirementsEO13134 – Developing and Promoting Biobased Products and BioenergyUse of recycled materials (mulch, composted leaves and organic materials) to amend and fertilize soilEO13148 – Greening the Government through Leadership in Environmental ManagementPromotion of sustainability through the use of native plants
1391DOE Consistent with DOE’s FEMP Sustainability
Initiative and Greening Program
EPA Regulatory Potential for NPDES Credits
Chesapeake Bay 2000 Agreement
Bioretention will reduce nutrient and sediment loadsCapture of atmospheric deposition by green roof and bioretentionGovernment by Example
Federal Agencies Chesapeake Ecosystem Unified Plan
Pollution Prevention State-of-the-Art TechniquesLow Impact Development
Chesapeake Bay Executive Council Directive 01-1 on Stormwater
Develop Innovative TechnologiesInstallation of Innovative BMP ProjectsEducation on Innovative BMPs
Funding Aspects
Funding
• Joint Effort – Department of Energy National Renewable
Energy Research Laboratory (NREL)– Federal Management Program (FEMP)– Atlantic Division of the Naval Facilities
Engineering Command (LANTDIV)
II. Complete 1391 for Integration of LID Approach into New Construction of Stormwater System Projects: 2:30 - 4:00pm
• Planners– Funding Aspects– Development of Planning Objectives, NEPA &
Performance Indicators– 1391 Process/Completion
• Engineers – Project Design– Construction Considerations & Proposal Development
• Facilities Maintenance– Site Monitoring, Inspection & Tracking
• Pre & Post Construction– Maintenance SOP & Implementation
• Operation• Landscape
Example: Bioretention
• Example site– 0.77 acre-site– Impervious area is 0.36 acres
• 0.16 impervious area in DA-1• 0.20 impervious area in DA-2
– Assume topography is suitable for the design– High water table is not a factor for this
exercise
Parameters
Parameter Description Value
P Design Rainfall Depth 1 in
P(avg) Average ponding depth 0.5 ft
k Minimum coefficient of permeability
0.5 ft/day
d Minimum filter thickness 2.5 ft
t Design drain time 2 days
Example Calculations
• Impervious Area (I) = 80%
• Volumetric runoff coefficient (Rv) = 0.77
• Water quality volume = 557.5 ft3
• Minimum surface area required for bioretention DA-1 using given parameters
= 465 ft2
LID vs. Conventional Installation costs
Cost per length of pipe per ft
C = 0.54D1.3024
for D = $14.40 (12in) D = $30.10 (24 in)
C ($/ft) = 14.45 (12 in) – 37.77 (24 in)
1999 dollars
Cost of grass swale per ft
C/L = K
K = 5-14
C ($/ft) = 5 - 14
No land cost where considered, but could be significant
EPA-600/R-02/021 (Cost of Urban Stormwater Control)
Cost of Different LID MethodsType of LID for half
Installation Costs
O&M Costs (annualized)
Bioretention Cell $10,000 $925
Bioswale $10,000 $600
Tree box $19,000 $950
Sand Filter $30,000 $2,800
Rain barrel $12,500 $900
Green Roof $250,000 $11,600 *
Infiltration Device $8,000 $1,125
Permeable Pavement $12,000 $950
Time of Concentration $8,000 $750
Landscaping $5,000 $575
Assumptions:
½ impervious acre.first 0.5” of rainfall is captured.
* Excluding replacement: $1,600 / year
All costs in 2005 dollars includes replacement in year 25
Planning Objectives
Development of Planning Objectives
• Meet specific regulatory • Water quality • To improve water quality of site • To reduce runoff volume and peak flow
rates for compliance
• Meet FEMP objectives for water conservation and LID
• Meet Greening Government, LEED, and other program objectives
NEPA
1391 Process/Completion
1391PROJECT SUMMARY
PROJECT NAME
FACILITY
PROJECT DESCRIPTION
PROJECT OBJECTIVES
1391PROJECT BENEFITS
ENVIRONMENTAL
WATER CONSERVATION
ENERGY MANAGEMENT
MAINTENANCE
AESTHETICS
EDUCATION
1391LEED ISSUES (US
GREEN BUILDING COUNCIL)
GREENING THE GOVERNMENT EXECUTIVE ORDERS
1391DOE
EPA Regulatory
Chesapeake Bay 2000 Agreement
Federal Agencies Chesapeake Ecosystem Unified Plan
Chesapeake Bay Executive Council Directive 01-1 on Stormwater