traffic impact study - port of vancouver...memo conveyance for north shore wastewater treatment...
TRANSCRIPT
![Page 1: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/1.jpg)
Appendix E
Traffic Impact Study
![Page 2: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/2.jpg)
1/33
To: Joan Liu, P.Eng Metro Vancouver 4330 Kingsway Burnaby BC V5H 4G8
CC: Brent Start, P.Eng, P.E., Rick Bitcon, P.Eng (AECOM)
AECOM Canada Ltd. 3292 Production Way Suite 330 Burnaby BC V5A 4R4 Canada T: 604.444.6400 F: 604.294.8597 aecom.com
Project name: Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
Project ref: 60513172
From: Anthony Yu, EIT, Neil Snowball, P.Eng (AECOM)
Date: October 20, 2017
Memo – Traffic Plan
1. Site Location
As part of the proposed Conveyance System for the North Shore Wastewater Treatment Plant (NSWWTP), formerly known as
Lions Gate Secondary Wastewater Treatment Plant (LGSWWTP), will be located on the North Shore, will connect sewers in the
vicinity of the existing Lions Gate Waste Water Treatment Plant (LGWWTP) with the new NSWWTP on West 1st St.
This part of the Conveyance System is referred to as the North Shore Wastewater Treatment Conveyance System (Conveyance
System) is composed of the following key elements of infrastructure:
an extension to the existing Hollyburn Interceptor from the LGWWTP to the Bridge Road Pump Station (Hollyburn
Extension);
an extension to the existing Capilano trunk sewer extending from Capilano Road to the Hollyburn Interceptor near the
existing LGWWTP (Capilano Trunk);
a 900 mm forcemain extending from Bridge Road Pump Station to the eastern contract boundary near the NSWWTP
(Bridge Road Forcemain);
a 2100 mm secondary effluent pipe extending from a chamber upstream of the marine outfall at LGWWTP to the
eastern contract boundary near the NSWWTP (NSWWTP Outfall, Land Section);
a 250 mm gravity sewer serving an area west of the NSWWTP (within the District of North Vancouver) and extending
to the eastern contract boundary near the NSWWTP;
a pump station to collect sewage from the Hollyburn Extension and the Capilano Trunk and pump the combined flow to
a tie-in point at the eastern contract boundary near the NSWWTP (Bridge Road Pump Station); and
applicable utility re-locations and utility corridor crossings.
Refer to Figure 1 for the Conveyance System overview.
![Page 3: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/3.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
2/33
Figure 1 Conveyance System Overview
![Page 4: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/4.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
3/33
2. Existing Transportation Networks
This section provides an overview of the existing traffic network between the LGWWTP and the NSWWTP in the District of West
Vancouver (DWV), Squamish Nation IR#5 and the District of North Vancouver (DNV).
2.1 Roads
The alignment for the Conveyance System follows the CNR railway track between Bridge Road and Whonoak Road and will be
located within Right of Way (RoW) from Squamish Nation. To the east of Whonoak Road, the alignment follows
West 1st St. Refer to Figure 2 for the existing road network within the vicinity of the Conveyance System.
![Page 5: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/5.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
4/33
Figure 2 Alignment Impact on Existing Road Network
There is a short section of school zone 30km/h speed limit on Welch St between Mathias Rd and east of Lower Capilano Rd (shown in green dash). Bowser Ave is a
cul-de-sac accessed from Welch St (shown in yellow dash). The paved roadway along Bridge Rd ends south of the railway crossing (shown in light pink dash). Both
Lower Capilano Rd and Whonoak Rd south of Welch St are also dead end roads (shown in pink and blue dash).
![Page 6: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/6.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
5/33
2.1.1 West 1st Street
West 1st St is an east-west major arterial with one travel lane in each direction. The speed limit for major
arterials in the District of North Vancouver is 50 km/h. The roadway cross section is approximately 21.4 m wide,
and includes one traffic lane in each direction, curbside parking lanes, bike lanes and a median lane dedicated to
left turns along West 1st St to provide access to businesses. The curbside lanes are also used to form right turn
lanes at Philip Ave. West 1st St connects to Garden Ave and north to Welch St, West of Garden Ave, a section
of West 1st St provides access to businesses. This dead end section of West 1st St is shown in orange dash in
Figure 2. Within the District of North Vancouver Truck Routes Map, West 1st St is an assigned truck route.
Figure 3 shows the existing cross section layout on West 1st St. The eastbound left turn lane shows that there
are traffic demands for vehicles traveling eastbound on West 1st St turning northbound on to Pemberton Ave.
Figure 3 West 1st Street Cross-Section
2.1.2 Welch Street
Welch St parallels West 1st St, to the north, and is classified by District of North Vancouver as a minor arterial
road west of Pemberton Ave to Garden Ave. A short section of Welch St is classified as a major arterial between
Garden Ave. and Whonoak Rd. Welch St continues in the west direction till it intersects Bridge Rd to provide a
continuous east to west road access. A short section of Welch St between Mathias Rd and east of Lower
Capilano Rd is a school zone with 30km/h speed limit (shown in green dash in Figure 2). Squamish Nation's
Capilano residential community is located north of Welch St between Whonoak and Bridge Rd. The Norgate
residential community is also located north of Welch St. Several significant communities and activities are
located south of Welch St including chief Joe Mathias Centre, Youth Centre and Xwemeich'stn School (also
known as Capilano Little Ones School).
The Squamish Nation community has indicated that construction vehicles must avoid travelling along Welch St,
west of Whonoak Rd due to the proximity of an Elementary School and Community Centre. Therefore, the use
of Welch St as a construction route is not permitted.
2.1.3 Philip Avenue
Philip Ave is a north-south local road that connects Welch St. to McKeen Ave. A new road overpass has been
constructed on this road to replace the existing at-grade Pemberton Avenue rail crossing close to West 1st St. A
traffic study developed by MMM Group “Preliminary Traffic Overview – Philip Avenue Overpass Project” included
a future capacity analysis (2017) for the West 1st Street corridor. The report includes predicted traffic movements
following construction and indicates that the intersection operation at West 1st Street/Pemberton Ave will
improve significantly.
![Page 7: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/7.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
6/33
2.1.4 Bowser Avenue
Bowser Ave is a north-south cul-de-sac that is used for local business access from Welch St (refer to the yellow
dashed lines in Figure 2). It is an unmarked road for two-way traffic with parking on either side of the road.
There are multiple driveway and business entrances fronting Bowser Ave. There are no sidewalks on either side
of Bowser Ave. Pedestrians and cyclists have to share the roadway with vehicles in order to access businesses
along Bowser Ave.
2.1.5 Garden Avenue
Garden Ave is classified as a north-south major arterial road that connects Welch St. to West 1st St. Garden
Ave consists of two travel lanes, two bike lanes and a northbound parking lane (east side of Garden Ave.).
Vehicles traveling along Garden Ave. have the right of way as free flowing traffic. Two stop signs are located at
the intersection of Welch St for east and westbound traffic and another stop sign at West 1st St. for eastbound
traffic only.
2.1.6 Whonoak Road
Whonoak Rd provides access to residents north of Welch St. It is a paved road with speed humps from Lawa
Ave to Welch St. South of Welch St, Whonoak Rd is a narrow gravel road that provides access to the Norgate
Substation and the Pacific West Landscape Supply business property.
2.1.7 Lower Capilano Road
Technically the Lower Capilano Rd is not a road. It is a water easement that functions as a north to south paved
road that provides access to residents and businesses south of Marine Dr (Upper Capilano Rd connects to
Grouse Mountain north of Marine Dr). The Lower Capilano section between Marine Dr and Welch St is traffic
calmed with speed humps and has a posted speed limit of 30 km/h.
Lower Capilano Rd continues south of Welch St as a no-through road until it intersects with the CN Railway
property where it ends, providing access to the North Shore Paintball business, Chief Joe Mathias Centre and
Capilano Little Ones School. The Squamish Nation community has also indicated that the use of Capilano and
Lower Capilano Rd as construction routes and access for such activities is not permitted.
2.1.8 Bridge Road
Bridge Rd is a north to south that runs parallel and under the Lions Gate Bridge. It is a paved road that provides
access from Taylor Way to the LGWWTP. The paved section of roadway ends south of the railway crossing
then it becomes an unpaved area with no defining width. There is a locked swing gate that is located about 50m
south of the railway crossing. Access south of the locked swing gate will have restricted access (no public
access south of the locked gate).
Bridge Rd is used primarily for access to businesses (Capilano Highway Services, the LGWWTP, CN Railway,
etc.) and connects to the overpass on Taylor Way in which directs traffic into the Park Royal Shopping Center.
The Taylor Way overpass spans across the Capilano River and is not designed for heavy vehicles. Construction
vehicles are not permitted to use the overpass.
Most of the traffic that travels southbound on Bridge Rd is related to activity at the LGWWTP. The hours of
operation at the LGWWTP are between 6:30 am to 3:00 pm on Mondays to Fridays, as a result traffic is
expected to increase before and after the operating hours on weekdays.
![Page 8: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/8.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
7/33
2.2 Parking
On-street parking is permitted along the municipal streets in addition to the various private spaces for business
parking at each property lot:
West 1st St – on-street parking is permitted along the north and south side of the road;
Welch St – on-street parking is permitted on the south side only. There are two gravel lots permitted
for parking at the north side of the road;
Philip Ave – on-street parking is permitted along the east and west side of the road. There are several
driveway entrances along Philip Ave that reduces the number of available on-street parking stalls;
Garden Ave – on-street parking is permitted along the east side of Garden Ave only;
Bowser Ave – on-street parking is permitted along both sides along Bowser Ave. The road users have
established a trend to parallel park the vehicles on the west side and stall parking on the east side; and
Additionally, many of the commercial properties in the area have on-site parking lots.
2.3 Cycling
The Norgate area is crossed by multiple bicycle routes, both on and off the roadway. The Spirit Trail is a
dedicated cycle route (shared with pedestrians) spanning the North Shore. The Spirit Trail is located within
Welch Park, north of Welch St, connecting to West 1st Street east of Pemberton Ave. Further east, it crosses the
CN railway tracks using an overpass to connect to the Spirit Trail section bordering the North Shore Auto Mall. In
addition to the Spirit Trail, West 1st St and Garden Ave have cycle lanes within its cross section that can connect
to the Spirit Trail.
2.4 Pedestrians
There are sidewalks within the area between the LGWWTP and the NSWWTP, but pedestrian access is limited
due to the existing sidewalk connectivity. Welch St has continuous sidewalk on the south side for pedestrians to
travel in the east to west direction. West 1st St has a sidewalk on the north side and on the south side of West
1st St between Pemberton Ave and Philip Ave. There is significant pedestrian movement along Pemberton Ave
between Marine Dr and West 1st St, as a result of different businesses located along Pemberton Ave, the
industrial properties located at the southern end of Pemberton Ave, and transit networks located on Marine Dr.
Site observations indicate very few pedestrian movements along the north side of West 1st St. An alternative
pedestrian access would be the Spirit Trail which will provide an east to west connection, however the Spirit Trail
is also a cyclist route in which both pedestrians and cyclist will have to share the pathway. Refer to Figure 4 for
the location of sidewalks (shown in purple) and the pedestrian and cyclist share path (shown in yellow dash). A
higher volume of pedestrian movement will be expected on West 1st St between Pemberton Ave and Philip Ave
due to the Philip Ave overpass which replaces the current at-grade rail crossing at Pemberton Ave.
![Page 9: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/9.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
8/33
Figure 4 Existing Pedestrian Access
2.5 Transit
There are no transit services within the area between the LGWWTP and the NSWWTP. Figure 5 is an extract
from Translink's Bus Route Map for the District of North Vancouver and shows bus routes are mainly located on
Marine Dr. (http://www.translink.ca/en/Schedules-and-Maps/Transit-System-Maps.aspx)
Figure 5 TransLink Bus Route Map – District of North Vancouver
Blue Bus Transit has a depot located on Lloyd Street. This operator provides transit services for West
Vancouver, as well as Capilano University, Downtown Vancouver, Lions Bay, North Vancouver, and UBC. These
buses use West 1st St to access service routes.
![Page 10: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/10.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
9/33
2.6 Adjacent Land Use
The area to the north of West 1st St to Welch St is mainly mixed commercial. The Squamish Nation’s Capilano
residential community and the Norgate residential community are located north of Welch St. There are
businesses located north side of West 1st St between Whonoak Rd and Pemberton Ave. The Vancouver Fraser
Port Authority (VFPA) lands and heavy industrial lands are located to the south of West 1st Street. A large
portion of Squamish Nation land (Capilano Reserve #5) is bounded by Whonoak Rd, Burrard Inlet, Marine Dr,
and west of the Lions Gate Bridge. There are commercial businesses (Curtis Paving, Talaysay Tours, and
Northshore Paintball) that are located within the Squamish Nation Reserve Land (south of Welch St). Several
significant communities and activities are also located south of Welch St including chief Joe Mathias Centre,
Youth Centre and Capilano Little Ones School. Refer to Figure 6 for the approximate boundaries of each land
classification.
![Page 11: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/11.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
10/33
Figure 6 Adjacent Land Classification (approx. boundaries)
Figure 6 shows the land use classification within vicinity of the Conveyance System project. Some sections are classified as industrial and commercial within the
underlying classified as Squamish Nation land (Capilano 5).
![Page 12: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/12.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
11/33
2.7 Squamish Nation Land
A large portion of the Conveyance System project is located within Squamish Nation land in the District of West Vancouver. The
south eastern part of West Vancouver is classified as the Capilano 5 First Nations Reserve Land. West Vancouver’s municipal
land use bylaws do not apply, and Squamish Nation has land use and zoning jurisdiction over their lands. West Vancouver and
Metro Vancouver provide services within Capilano 5 through agreements with the Squamish Nation. Utilizing the existing east-
west arterial road to access Bridge Rd and the LGWWTP is a potential access route option, but the Squamish Nation will not
permit additional traffic traveling through their community. Therefore, the access option to use the existing east-west arterial
road to access Bridge Rd is not a viable option. Refer to Figure 7 for the Capilano 5 reserve land.
Figure 7 Capilano 5 First Nations Reserve Boundary
2.8 Canadian National Railway (CN) Right-of-Way
There are multiple CN railway tracks located south of Welch St. and run in parallel to Welch St. A single CN railway track runs
west of the Lions Gate Bridge and services West Vancouver. Immediately east of the Lions Gate Bridge the CN Railway track
splits into ten railway tracks south of the Squamish Nation Land (Capilano Reserve # 5) with three railway tracks, located further
south, which appears to be dead-end tracks. As the railway tracks travel east towards Whonoak Rd and south of West 1st St,
the tracks split up into more tracks as it connects into the Philip Ave rail yard and terminal facility. The Rocky Mountaineer train
operates from the North Vancouver rail station (corner of Philip Ave and West 1st St). The railway tracks will continue to run
parallel to West 1st St. and as it approaches Philips Ave, the tracks will converge into three rail tracks as it travels further east
into the North Vancouver.
![Page 13: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/13.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
12/33
2.9 Emergency Services
West 1st St is an emergency route and is considered one of the key east to west connection routes in North Vancouver. A Fire
Hall is located on West 15th St close to Pemberton Ave. Lions Gate Hospital is located within the City of North Vancouver on
East 15th St between St. Georges Ave and St. Andrews Ave. A City of North Vancouver Fire Hall and the RCMP are both
located close to Lions Gate Hospital on St. Georges Ave, at the corners of East 13th St and East 14th St, respectively.
2.10 Destinations
Destinations that generate vehicular movements along West 1st St include Park Royal shopping center, Capilano Mall, Walmart
and North Vancouver Auto Mall. Shift changes at the shipyards also generate considerable traffic volumes along the West 1st
St corridor during specific hours. Shift changes typically occur at 7:00 a.m. and at 3:00 p.m.
2.11 Business Access
The conveyance sewer alignments are located on the south side of Welch St within the Squamish Nation Reserve Land and a
mix of commercial/light industrial businesses. The Chief Joe Mathias Centre is a significant community facility for Squamish
Nation community and it will generate traffic to the area. Business accesses are located throughout West 1st St and Welch St.
These businesses mainly have designated parking spaces/lots on their properties which are primarily accessible from Welch St.
Currently there are no business accesses from West 1st St east of Garden Ave to Philip Ave. However, CN Railway and the
Pacific West Landscape Supply have business access at the western end of West 1st St. (where West 1st becomes a dead end
road).
![Page 14: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/14.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
13/33
3. Construction Impacts
There are five proposed pipe alignments (Hollyburn Interceptor Extension, Capilano Trunk, West 1st St Sewer,
NSWWTP Outfall, and Bridge Road Forcemain) that will be newly constructed as part of the conveyance for
NSWWTP. The Capilano Trunk will be slip-lined through the North Vancouver Interceptor and will not affect the
extent of construction. The Bridge Road Pump Station will be constructed south of the Bridge Rd alignment
(south of the locked swing gate on VFPA’s RoW) where the public will not be able to access the area, as a result
the construction impact will not have an effect on traffic or the public.
The Hollyburn Interceptor Extension will connect the existing Hollyburn Interceptor sanitary sewer at the north
side of the LGWWTP and connect to the new Bridge Road Pump Station. The 2100 mm diameter NSWWTP
Outfall alignment begins at the existing outfall located at the southern end of the LGWWTP where the Lions Gate
Bridge meets the north end of the Burrard inlet. From the connection point, the NSWWTP Outfall will run under
the Lions Gate Bridge and will turn north as it parallels the Bridge till it is north of CN Rail RoW. The Bridge
Road Forcemain start at the Bridge Road Pump Station and will span in the north direction (parallel the
NSWWTP Outfall alignment) until it is north of the railway tracks.
Once the alignments are on the north side of the railway tracks, they will span east and run parallel on the north
side of the CN railway tracks until they reach Lower Capilano Rd. The NSWWTP Outfall and Bridge Road
Forcemain will continue to run on the north side as they parallel the CN railway track until Whonoak Rd then both
alignments will run on the south side of West 1st St. The NSWWTP Outfall and Bridge Road Forcemain will
continue to run on the south side as they parallel West 1st Street till they tie into the NSWWTP at Philip Ave.
The West 1st St Sewer main (250 mm diameter) will be located on the north side of West 1st St between
Whonoak Rd and Philip Ave. Refer to
Figure 9 for the Conveyance layout and Table 1 for the potential traffic impact summary.
The Bridge Road Pump Station will be constructed as part of the Conveyance System. However, the pump
station is located at the south end of Bridge Road (south of the CN railway corridor) where public access is
limited. Traffic within the area is expected to be employees of the LGWWTP and CN Rail. All construction traffic
to the pump station would use the temporary construction easement for access via Whonoak St to the site.
The construction for the conveyance alignment is expected to be linear with each section approximately 30 m in
length. Therefore, driveway impacts (business access) would be expected to be closed up to two days.
3.1 Estimated Truck Volume
Truck hauling and other construction related traffic will be at the design builder’s discretion; however, the
following provides an estimate of construction traffic for the various routes based on how the construction might
occur. Squamish Nation has dictated that construction vehicles are not permitted to use Welch St between
Whonoak Rd and Bridge Rd. Therefore, construction vehicles (trucks, equipment, etc.) are only permitted to
travel on West 1st St, Garden Ave and along the temporary construction easement (north of the CN railway from
Whonoak Rd to Bridge Rd).
The peak of the construction traffic is predicted to occur at the latter end of the 2018 construction period or about
six months after the start of construction. The peak period is expected to last approximately six months. At this
time truck traffic is likely to be in the order of 20 trucks per working day on average, with possibility of 30 trucks
during peak day activities, to and from the Pump Station site and effecting Whonoak Rd, Welch St (between
Whonoak Rd and Garden Ave), Garden Ave, and West 1st St. Outside of this period construction traffic at the
site is expected to be somewhat less than in the peak construction period.
![Page 15: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/15.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
14/33
3.2 Traffic Impact
An east-west route is required for construction vehicles to access the Bridge Road Pump Station on Bridge Rd and the Conveyance System that connects the LGWWTP/pump station to the NSWWTP. There are two possible access options due to the location of the Bridge Road Pump Station and the alignment of the conveyance sewers (see Figure 8):
Option 1 - Use Welch St between Garden Ave and Bridge Rd to access the Bridge Road Pump Station and to
exit the area; and
Option 2 - Use the temporary construction easement off Whonoak to access the Bridge Road Pump Station
and the conveyance sewers.
Figure 8 Construction Access Route Options
Option 1 would use Welch St for construction traffic since Welch St is an existing pave roadway which would
provide a connection from West 1st St to Bridge Rd. However, as previously discussed, the Squamish Nation
will not permit construction vehicles entering their community. As a result, Welch St between Whonoak Rd and
Bridge Rd is not a viable option. Construction vehicles are not permitted to use Welch, however, construction
workers traveling in their private vehicle to access the construction site are not restricted to use Welch St as their
travel route.
Option 2 would use a minimum 10m wide temporary construction easement from Whonoak Rd at Welch St to the
north side of the CN RoW corridor and connects to Bridge Rd. The minimum 10m wide temporary construction
easement is required to permit two-way truck traffic and possibly located temporary piping during construction.
The primary object for the temporary construction easement is to provide access to construction vehicles such as
heavy trucks and construction equipment. Construction workers and similar traffic would not be required to use
the temporary construction easement. The use of the temporary construction easement for construction vehicles
will significantly reduce the potential impacts on Welch. The passage of construction employee vehicles on
Welch is considered to be minor, and well within the expected daily variation that Welch would experience.
Figure 9 and Table 1 describe the expected traffic related impacts during construction.
![Page 16: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/16.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
15/33
Figure 9 Proposed Conveyance Systems Layout
![Page 17: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/17.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
16/33
Table 1 Traffic Impact Summary
SEGMENTS
(refer to
Figure 9)
DESCRIPTION
TRAFFIC IMPACTS
ROAD PEDESTRIAN CYCLIST
A
NSWWTP Outfall point No impact (no public
access)
No impact (no
public access)
No impact (no
public access)
A to B
The NSWWTP Outfall will span
across the Bridge Rd alignment
(south of the locked swing gate).
The NSWWTP Outfall will span in
the north direction (point B) until it
is on the north side of the CN
Railway tracks (point F)
Minimal impact since the
area will not have public
access.
Traffic within the vicinity
of the area will be
employees accessing the
LGWWTP and CN
Railway access.
No impact (no
public access)
No impact (no
public access)
C
The Bridge Road Pump Station
will be constructed south of the
Bridge Rd alignment (no public
access)
The Hollyburn Interceptor
Extension will connect to the
Bridge Road Pump Station
The Bridge Road Forcemain
alignment construction will begin
at the Bridge Road Pump Station
and will span in the north direction
until it is north of the CN Railway
tracks (point F)
No impact (no public
access)
No impact (no
public access)
No impact (no
public access)
C to D
The Hollyburn Interceptor
Extension will connect the
existing Hollyburn Interceptor
(Point D) to the Bridge Road
Pump Station (point C)
Minor road impact along
west side of Bridge Rd
(south of the railway
tracks).
Traffic within the vicinity
of the area could be
employees accessing the
LGWWTP and CN
Railway
Pedestrian traffic
within the vicinity
of the area could
be employees
accessing the
LGWWTP, CN
Railway, and
nearby
businesses.
Cyclist Traffic
within the vicinity
of the area could
be employees
accessing the
LGWWTP, CN
Railway, and
nearby
businesses.
D
Capilano Trunk and Hollyburn
Interceptor Extension connects to
the north side of the LGWWTP
No Impact No impact No impact
![Page 18: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/18.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
17/33
SEGMENTS
(refer to
Figure 9)
DESCRIPTION
TRAFFIC IMPACTS
ROAD PEDESTRIAN CYCLIST
D to E
The Capilano Trunk (from the
LGWWTP) will span under the
railway tracks to the north side
then it will span in the east
direction across Bridge Rd (slip
lined through the existing NVI).
Construction of the
Hollyburn Extension will
be adjacent to the Dalton
Trucking Ltd property.
Driveway access to the
business will be
maintained.
Construction will cross
Bridge Road, north of the
CN Rail tracks.
May cause impact to the
permit area of Squamish
Nation, east of Bridge Rd.
No impact No impact
F
Construction vehicles are only
permitted to use the temporary
construction easement between
Bridge Rd and Whonoak Rd.
Construction vehicles can enter
and exit at point F (on Bridge Rd)
to access the temporary
construction easement.
Increase in construction
vehicle traffic at point F
Construction vehicles can
enter and exit at point F
to travel along the
temporary construction
easement.
Construction vehicles can
only exit from point F to
access the Bridge Road
Pump Station.
Construction vehicles are
not permitted to use
Bridge Rd.
May cause impact to
property or access of
Squamish Nation permit
holder(s), east of Bridge
Rd.
No impact No impact
E to F
The Capilano Trunk will span
under Bridge Rd (slip lined
through the existing NVI).
Construction vehicles can
only enter and exit the
temporary construction
easement at point F.
Pedestrians could be within the vicinity due to the businesses nearby.
Cyclist could be
within the vicinity
due to the
businesses
nearby.
![Page 19: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/19.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
18/33
SEGMENTS
(refer to
Figure 9)
DESCRIPTION
TRAFFIC IMPACTS
ROAD PEDESTRIAN CYCLIST
F to G
All three alignments (Capilano
Trunk, NSWWTP Outfall, and
Bridge Road Forcemain) will be in
one construction trench.
The three alignments (Capilano
Trunk, NSWWTP Outfall, and
Bridge Road Forcemain) will run
parallel on the north side of CN
Railway’s RoW.
Construction vehicles can
access the Bridge Road
Pump Station at point F
and the conveyance
sewers adjacent to the
temporary construction
easement.
No impact No impact
G
The Capilano Trunk will tie into
the existing District of North
Vancouver Gravity Connection at
the end of the Lower Capilano Rd.
There will be no impact to
Lower Capilano Rd since
Construction vehicles are
not permitted to use
Capilano Rd.
Construction vehicles are
not permitted to use the
southern end of Lower
Capilano Rd for staging
or turn around point.
The public is
likely to be within
the area due to
the North Shore
Paintball
business, and to
access the
Recreation
Center
There are no
sidewalk
accesses but
there may be
people within the
area that could
be exposed to
construction.
There are
potential for
cyclist to travel to
the southern end
of Lower
Capilano Rd to
have access to
the Paintball
business.
G to H
The NSWWTP Outfall and Bridge
Road Forcemain will continue to
span to the east as they parallel
the CN Railway’s RoW.
Construction vehicles will
travel along the temporary
construction easement to
access the conveyance
sewers
Pedestrians
could be within
the vicinity due
to the
businesses
nearby.
No impact
H
There are existing power poles
that connects to the Norgate
substation. The power poles are
located south of Whonoak Rd.
Construction vehicles
cannot travel through
point H (CN Rail
Intermodal Yard).
Construction vehicles are
only permitted to exit the
construction site via
Whonoak Rd.
Pedestrians
could be within
the vicinity due
to the
businesses
nearby.
No impact
![Page 20: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/20.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
19/33
SEGMENTS
(refer to
Figure 9)
DESCRIPTION
TRAFFIC IMPACTS
ROAD PEDESTRIAN CYCLIST
H to I
Both the NSWWTP Outfall and
the Bridge Road Forcemain will
be constructed in the north
direction towards West 1st St.
The West 1st St Sewer will begin
construction at the north side of
West 1st St (point I)
Potential increase in
construction vehicles at
the west end of West 1st
Street.
Pedestrians
could be within
the vicinity due
to the
businesses
nearby.
Cyclist could be
within the vicinity
to access the
businesses
nearby.
I to J
Construction of the NSWWTP
Outfall and the Bridge Road
Forcemain will be on the south
side of West 1st St.
Construction of the West 1st
Street Sewer will be on the north
side of West 1st St.
There are no sidewalks
or driveway access on
the south side of West
1st St.
The construction will be
within the road way and
the construction limit
could encroach onto the
parking and bike lane.
The eastbound travel
lane should not be
affected.
Fences are
recommended to
separate the construction
area from the travel lane.
The intersection at Garden Ave and West 1st St. cannot be closed during construction. Maintain at least 3 m travel lane for Single Lane Alternating Traffic (SLAT) as a minimum for traffic to travel through the intersection.
Pedestrians will
not have access
along the north
side of West 1st
St. (between
Garden Ave and
Philip Ave)
during
construction.
Pedestrians will
be detoured to
use Welch or the
Spirit Trail.
Advanced
warning signs
must be placed
at West 1st St
and Philips Ave
for pedestrians
traveling
westbound and
at Welch St and
Garden Ave for
pedestrians
traveling
eastbound.
Eastbound
cyclist must be
detoured to use
Welch St. during
construction.
Advanced
warning signs
should be place
at Welch St and
Garden Ave to
detour cyclist to
use Welch St or
the Spirit Trail
Westbound
cyclist can still
use West 1st St,
but fences are
recommended to
separate the
construction
zone from the
westbound bike
lane.
![Page 21: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/21.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
20/33
SEGMENTS
(refer to
Figure 9)
DESCRIPTION
TRAFFIC IMPACTS
ROAD PEDESTRIAN CYCLIST
J
All three alignments will be tied
into the NSWWTP at Philip.
The intersection at Philip
Ave and West 1st St.
cannot be closed during
construction. Maintain at
least 3 m travel lane for
Single Lane Alternating
Traffic (SLAT) as a
minimum for traffic to
travel through the
intersection.
Pedestrians
traveling east
and westbound
must be
detoured to use
Welch St. or the
Spirit Trail.
Advanced
warning signs
must be in place
(at least a block
in advanced) to
provide sufficient
warning and
detours.
Cyclist traveling
east and
westbound must
be detoured to
use Welch St. or
the Spirit Trail.
Advanced
warning signs
must be in place
(at least a block
in advanced) to
provide sufficient
warning and
detours.
3.3 Construction Easement
There are several active railway tracks within the vicinity of the proposed construction envelope located north of the Burrard Inlet
between Lions Gate Bridge and Whonoak Rd. According to the CN Customer Safety Handbook, a clearance distance of 25 feet
(minimum) is required from the nearest rail unless a CN representative has placed a block for train movements. The CN RoW
was approximately mapped out with the proposed alignment.
The construction of the alignments at the north side of the railway corridor will required to utilize a combination of existing and
potential new RoW to permit a construction trench for the alignments. On the north side of the rail tracks between Bridge Rd
and Lower Capilano Rd, the construction limit will required to use the existing MV RoW and a section of the potential RoW within
the Squamish Nation Land (see Figure 10 for the approximate RoW layout). Between Lower Capilano Rd and Whonoak Rd, the
construction limit will required use of the existing NVI RoW, and possibly a new section of RoW within DNV land and a section of
potential RoW within the Squamish Nation Land. The temporary construction easement will be constructed south of Welch St,
adjacent to Whonoak Rd for heavy trucks and construction equipment access only. It is recommended to use a minimum 10 m
wide RoW in order to construct a 7 m wide temporary construction easement (two 3.5 m lanes) with a minimal V-ditch on each
side of the temporary construction easement for drainage. A flag person may be required at the intersection of Welch St and
Whonoak St to manage the interaction of trucks with the other road users. Construction workers can use Welch St to arrive and
leave the construction site (see Figure 11 for the proposed RoW layout). Fencing is recommended along the construction
easement for security and to separate the construction area from the public.
![Page 22: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/22.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
21/33
Figure 10 Construction RoW Between Bridge Road and Lower Capilano Road
![Page 23: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/23.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
22/33
Figure 11 Proposed Construction RoW Between Lower Capilano Road and Whonoak Road
![Page 24: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/24.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
23/33
3.4 Property Impacts
The construction envelope may have some minor impact to the businesses within the Squamish Nation Land. Three areas have
been identified that could potentially have impact to the business property: east of the Lions Gate Bridge, east of Capilano Rd
(North Shore Paintball), and west of Whonoak Rd (Pacific West Landscape Supply).
The area east of Lions Gate Bridge just north of the CN Railway Tracks is anticipated to have minor impacts to the businesses.
The parking area of the business might need to be adjusted due to the construction limit and the entrance/exit into the business
might need widening to the north. See Figure 12 for details.
Figure 12 Business Impact East of Lions Gate Bridge
The area east of the lower Capilano Rd (North shore Paintball) could potentially have some minor adjustments during
construction of the sewer alignments. The storage area at the end of the Lower Capilano Rd might need to be moved and north
of the railway tracks might need adjustments due to the possible construction extent. Since North Shore Paintball attracts public
users to the area, it is recommended to install a fence between the construction extent and the business property to prevent the
public from going into the construction site. If the existing CN gates are opened or removed, due diligence is required to prevent
the public from trespassing on CN property. Refer to Figure 13 for details.
![Page 25: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/25.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
24/33
Figure 13 Business Impact East of Capilano Road
The area west of Whonoak Rd could have a more significant impact. The storage area within CN Rail Intermodal Yard might
need to relocate the storage containers that are within the easement/construction extent. The entire west end of the Intermodal
Yard might need adjustment to allow for construction equipment and the construction boundary. On the opposite property,
Pacific West Landscape Supply might need to adjust their parking/storage area to accommodate for the close proximity of the
construction extent. See
Figure 14 for details.
![Page 26: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/26.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
25/33
Figure 14 Business Impact East of Whonoak Road
3.5 City Street Impacts
The proposed sewer alignments will be constructed on West 1st St between Whonoak Rd and Philip Ave. The NSWWTP
Outfall and the Bridge Road Forcemain will be on the south side of West 1st St and the smaller influent gravity main will be on
the north side of West 1st St. Construction of the alignments will not have major impacts/disruptions to the businesses along
West 1st St, however the eastbound parking and possibly the eastbound bike lane along West 1st St between Garden Ave and
Philip Ave could be removed during construction. There could be some minor adjustments for business properties along West
1st St, west of Garden Ave due to the construction extent for the north side construction. The intersection at Garden Ave and
West 1st St. will need to be staged to allow single lane alternating traffic (SLAT) at the intersection to permit vehicles to travel
north and southbound along Garden Ave.
3.5.1 Pedestrian Impacts
Pedestrians will not have access along the north side of West 1st St during to construction. There are no sidewalks along the
south side of West 1st St. so pedestrians can be detoured to use the south side of Welch St. or use the shared path along the
Spirit Trail. Construction warning signs are highly recommended to be installed in advance along West 1st St to detour
pedestrians off West 1st St. and to give advanced warning to other road users for the increase in truck traffic within the area. It
is recommended to install detour and warning signs at Garden Ave and Welch St and at Philip Ave and West 1st St to give
pedestrians advanced warning. The solid red lines shown in Figure 15 represent the sidewalks that are still available for
pedestrian use during construction and the red dotted lines represent closed sidewalks.
![Page 27: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/27.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
26/33
Figure 15 Pedestrian Detour Routes
3.5.2 Cyclists Impacts
The westbound bike lanes along West 1st St should be maintained during construction. If the eastbound bike lane on West 1st
St needs to be removed due to the extent of the construction footprint, cyclist access would be directed to use Welch St or to the
Spirit Trail. However, efforts should be made to keep both bike lanes along West 1st St open. It is recommended to install a
fence between the eastbound bike lane and the construction area to protect cyclists from the adjacent construction activities.
3.6 NSWWTP Site Construction
The proposed NSWWTP is being developed by Metro Vancouver to meet its wastewater secondary treatment obligations which
comes into effect at the end of 2020. It will be located on an existing brownfield site in the District of North Vancouver (on West
1st St. between Philip Ave and Pemberton Ave) approximately 1.7km east of the LGWWTP. Refer to Figure 16 for the
NSWWTP site location.
![Page 28: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/28.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
27/33
Figure 16 NSWWTP Site Location
![Page 29: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/29.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
28/33
4. Construction Access
Construction vehicles should be restricted to major routes and designated truck routes to access the construction site, to avoid
travelling through residential areas. Construction vehicles will use the Second Narrows Bridge to access the north shore and to
exit back to the city. It is expected that construction vehicles travel from the east to access the construction site. West 1st Street
and Marine Dr are two truck routes that can be used for construction vehicles. The section of Bridge Rd, north of Welch St,
Welch St between Whonoak Rd and Bridge Rd and Capilano Rd (Upper and Lower) are not permitted to be used by
construction vehicles. Permits are required by the governing municipality and may be required by Squamish Nation before
construction vehicles can use the non-designated truck routes for access. Refer to Figure 17 for area indicating the possible
arterial routes.
![Page 30: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/30.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
29/33
Figure 17 Arterial Routes Map (approximate locations)
![Page 31: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/31.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
30/33
An access road is required within the temporary construction access easement to provide construction vehicles to
access the sewer alignments. The existing CN access road is not permitted for access, therefore the proposed
access road will be located north of the existing CN access road and it will be within the temporary easement to avoid
infringement onto adjacent lands. The temporary construction easement will be used as an east to west access from
Whonoak Rd to Bridge Rd during construction. The temporary construction easement will be used by construction
trucks and equipment only (public access is not permitted). The access road will be removed and the land will be
rehabilitated after construction is complete.
4.1 Proposed Construction Access
The proposed Bridge Road Pump Station is located under the Lions Gate Bridge adjacent to Bridge Rd. Construction
vehicles will travel westbound on West 1st St, southbound on Whonoak Rd to the access the temporary construction
easement then westbound towards Bridge Rd to access the Bridge Road Pump Station. Bridge Rd is not a heavily
used road for access and would be used by vehicles exiting the Park Royal Shopping Center and employees from the
local businesses that are located on Bridge Rd just south of Welch St. Construction vehicles exiting from the Bridge
Road Pump Station location will have to travel eastbound onto the temporary construction easement then northbound
(adjacent to Whonoak Rd) towards Welch St. Construction vehicles are not permitted to use the Bridge Rd, Welch
St, and Capilano Rd (Upper and Lower). Construction workers can still use Bridge Rd and Welch St. Refer to Figure
18 for the route layout.
![Page 32: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/32.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
31/33
Figure 18 Proposed Bridge Road Pump Station Access
![Page 33: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/33.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
32/33
5. Mitigations and Recommendations
5.1 General Requirements
Construction activities for the sewer alignment is expected to be within the preliminary Metro Vancouver surveyed
RoW, however a temporary construction easement will be required to be built on a strip of easement north of CN
Railway’s RoW. There might be minor encroachment onto private RoW and minor disruptions to the District’s street
network. The following mitigation measures and recommendations should be applied:
Taylor Way overpass, and Bridge Rd, are not permitted to be used for construction vehicles;
Coordinate with CN Rail for ensure that the clearance distance to work near tracks is acceptable and a rail
flagger is not required since work is within the easement;
Coordinate with CN Rail regarding construction of the Conveyance System across the CN railway tracks
near the LGWWTP. Avoid construction work in the area during CN Rail’s peak operation hours;
Notify nearby businesses to inform them about the possible minor impacts to their business;
Install fences between the construction extent and the North Shore Paintball property to ensure the public
will not enter the construction site when a paintball event is active. Fencing is also recommended to be
installed along the temporary construction easement;
The south end of Lower Capilano Rd is not permitted to be used as for staging or as a turnaround area for
construction vehicles traveling along the temporary construction easement.
Notify BC Hydro that construction will be adjacent to Whonoak Rd and that construction vehicles and
equipment will be working near and under the power lines. Coordination with BC Hydro is recommended to
ensure construction activity is permitted;
Due to the restrictions to access the work site, construction vehicles (heavy trucks and equipment) must
use the temporary construction easement from Bridge Rd to Whonoak Rd (north of the CN railway tracks);
The temporary access RoW to build the temporary construction easement must be a minimum of 10m wide
to safely accommodate for two-way traffic and possibly temporary piping;
The temporary construction easement is not permitted for public use. Construction workers/laborers may
use Welch Street to access the construction site;
A flag person will be needed at the intersection of Whonoak St and Welch St to manage truck access.
During construction on West 1st St, ensure that the intersection at West 1st St and Garden Ave remains
open. Stage construction to provide SLAT, if necessary, to permit traffic flow. Only partial closure at the
intersection is permitted;
If there is sufficient space on the south side of West 1st St during construction to maintain the eastbound
bike lane, install a fence to protect cyclists from the construction activities or detour cyclists to the Spirit
Trail;
Provide advance warning signs to detour pedestrians on to Welch St or the Spirit Trail; and
Advance warning signs must be placed in advance (at least one city block) of construction areas to provide
ample notice to drivers.
![Page 34: Traffic Impact Study - Port of Vancouver...Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan AECOM 4 /33 Figure 2 Alignment Impact on Existing Road Network](https://reader030.vdocuments.us/reader030/viewer/2022040515/5e7265480ea5fd5c2f7a8440/html5/thumbnails/34.jpg)
Memo Conveyance For North Shore Wastewater Treatment Plant – Traffic Plan
AECOM
33/33
5.2 Mitigations and Recommendations on Squamish Nations Reserve Land
The following mitigation measures and recommendations must be applied within the Squamish Nations Reserve
Land (approximately west of Whonoak Rd):
Welch St (between Whonoak Rd and Bridge Rd) and Capilano Rd (Upper and Lower) are not permitted to
be used for construction vehicles;
Notify the Squamish Nation about construction activities that will take place within Squamish Nation lands.
Advanced notice must be given to the Squamish Nation representative for any changes to construction
activities that could impact the Squamish Nation land;
Squamish Nation will require weekly or bi weekly updates on construction as well as attendance at weekly
construction meetings;
All applicable activities and recommendations described in section 5.1 and elsewhere in the Traffic Plan.