traffic impact assessment (roadnet 2016)...roadnet pty ltd has been engaged by scolexia pty ltd...
TRANSCRIPT
Appendix D
Traffic ImpactAssessment (RoadNet 2016)
Traffic Impact Assessment
The Ranch
Poultry Production Complex – Farm 5
at
Tysons Road (nr Kidman Way),
Tabbita, NSW
for
Scolexia Pty Ltd
19 February 2016
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 2 of 66 pages Date 19/02/2016
FINAL
Document Control Sheet
Document Status DRAFT FINAL
Version 1 2
Date 15 February 2016 19 February 2016
Issued to Adam Williams,
SLR Consulting
Adam Williams,
SLR Consulting
Prepared By Steve Manton Steve Manton
Reviewed By John Weatherall John Weatherall
Prepared by: RoadNet Pty Limited
8 Sixth Avenue
PALM BEACH QLD 4221
07 5525 7377
L12, 1 Pacific Highway
NORTH SYDNEY NSW 2060
02 9959 1080
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 3 of 66 pages Date 19/02/2016
FINAL
CONTENTS
1. INTRODUCTION .................................................................................................................................................. 5
1.1 Background to Development Proposal ......................................................................................................... 6
1.2 Scope of Traffic Impact Assessment for The Ranch Farm 5 ...................................................................... 13
2. EXISTING CONDITIONS ................................................................................................................................... 14
2.1 The Site ...................................................................................................................................................... 14
2.2 Existing Road Network ............................................................................................................................... 17
2.3 Existing Land Use ....................................................................................................................................... 23
2.4 Existing Traffic Volumes ............................................................................................................................. 23
2.5 Background Traffic Growth ......................................................................................................................... 26
2.6 Existing Pedestrian and Cyclist Facilities ................................................................................................... 26
3. PROPOSED DEVELOPMENT ........................................................................................................................... 27
3.1 Development Description ........................................................................................................................... 27
3.2 Vehicular Access and Internal Road Layout ............................................................................................... 28
3.3 Pedestrians, Cyclists and Public Transport ................................................................................................ 28
3.4 Development Traffic Generation ................................................................................................................. 28
3.5 Future Design Year Volumes...................................................................................................................... 32
3.6 Heavy Vehicle Routes Servicing Development .......................................................................................... 34
3.7 Peak Activity Traffic Generation ................................................................................................................. 35
4. OTHER DEVELOPMENTS IN THE STUDY AREA ............................................................................................ 38
4.1 The Ranch Poultry Production Complex ..................................................................................................... 38
4.2 Other Developments ................................................................................................................................... 40
5. ACCESS REQUIREMENTS FOR THE PROPOSED DEVELOPMENT ............................................................. 44
5.1 Kidman Way / Tysons Road Intersection .................................................................................................... 44
5.2 Access Road and Driveway to Development .............................................................................................. 46
5.3 Internal Access Requirements .................................................................................................................... 47
6. CONSTRUCTION STAGING AND TRAFFIC ..................................................................................................... 48
7. IMPACTS ON ADJOINING ROAD NETWORK .................................................................................................. 50
7.1 Kidman Way ............................................................................................................................................... 50
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 4 of 66 pages Date 19/02/2016
FINAL
7.2 Heavy Vehicle Routes used by Development ............................................................................................. 51
7.3 Intersections ............................................................................................................................................... 52
7.4 Pedestrians and Cyclists ............................................................................................................................ 53
7.5 Impacts during Construction ....................................................................................................................... 53
7.6 Cumulative Impacts of Developments ........................................................................................................ 54
8. CONCLUSIONS ................................................................................................................................................. 57
9. RECOMMENDATIONS ...................................................................................................................................... 61
APPENDICES
APPENDIX A ............................................................................................................................................................... 62
PROPOSED DEVELOPMENT LOCATION AND LAYOUT ..................................................................................... 62
APPENDIX B ............................................................................................................................................................... 65
REVISED TRIP GENERATION FOR THE RANCH FARMS 1, 2 AND 3 (8-SHED ONLY) .................................... 65
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 5 of 66 pages Date 19/02/2016
FINAL
1. INTRODUCTION
RoadNet Pty Ltd has been engaged by Scolexia Pty Ltd (Scolexia), on behalf of VOAG 5 Pty Ltd (VOAG 5),
to prepare a Traffic Impact Assessment (TIA) for a proposed poultry development, referred to as The Ranch
Farm 5, located within a rural property in the area known as Tabbita in south-western New South Wales
(NSW). The site is located within the Carrathool Local Government Area (LGA) approximately 5.5 kilometres
(km) north-east of Tabbita, 19km south-east of Goolgowi and 26km north-west of Griffith. Access to the site
is proposed via the adjoining Tysons Road and Kidman Way (B87).
The location of the site is shown in Figure 1.1.
Figure 1.1: Locality Plan (Source: Google Maps)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 6 of 66 pages Date 19/02/2016
FINAL
1.1 Background to Development Proposal
On 15 December 2015 Carrathool Shire Council (Council) granted Development Consents DA 2016/017, DA
2016/022 and DA 2016/023 to develop three poultry farms at Tabbita known as The Ranch Farm 1, The
Ranch Farm 2 and The Ranch Farm 3. Development consent is now being sought for two more poultry
farms, being The Ranch Farm 4 (the subject of a separate development consent) and The Ranch Farm 5
(the subject of this TIA). Collectively, The Ranch Farms 1 to 5 are being referred to as “The Ranch Poultry
Production Complex”.
Each of The Ranch Farms 4 and 5 will be the subject of a separate development application (DA) and a
separate Environmental Impact Statement (EIS) to be lodged with Council. The applications for The Ranch
Farm 4 and The Ranch Farm 5 are expected to be lodged concurrently in February 2016.
The locations of the five farms that make up The Ranch Poultry Production Complex are shown in Figure 1.2
on the next page.
Indicative timeframes for the proposed commencement of construction and operational activities at the five
farms (subject to obtaining the relevant approvals) are as follows:
The Ranch Farm 1 – 8 sheds (approved) – commence construction: January 2016
– commence operation: July 2016
The Ranch Farm 2 – 8 sheds (approved) – commence construction: July 2016
– commence operation: January 2017
The Ranch Farm 3 – 8 sheds (approved) – commence construction: January 2017
– commence operation: July 2017
The Ranch Farm 4 – 16 sheds (proposed) – commence construction: July 2017
– commence operation: July 2018
The Ranch Farm 5 – 16 sheds (proposed) – commence construction: July 2018
– commence operation: July 2019
Access to the five farms comprising The Ranch Poultry Production Complex during their construction and
operation will be achieved via a new internal farm access road connecting to Tysons Road approximately
1km to the east of its intersection with Kidman Way. All movements to and from each of the farms will occur
via this new site access onto Tysons Road and the existing Kidman Way / Tysons Road intersection.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 7 of 66 pages Date 19/02/2016
FINAL
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 8 of 66 pages Date 19/02/2016
FINAL
1.1.1 Previous Development Applications and Associated Consent Conditions
Separate TIA’s were prepared as part of the previous development applications and EIS’s for The Ranch
Farm 1 (DA 2016/017), The Ranch Farm 2 (DA 2016/022) and The Ranch Farm 3 (DA 2016/023) which
examined the potential traffic impacts of each of these developments in isolation as well as the cumulative
impacts of The Ranch Farms 1 to 3 combined when operating concurrently in the future. The relevant
documents prepared are summarised below:
Traffic Impact Assessment – The Ranch Poultry Production Complex – Farm 1 at Tysons Road (nr Kidman Way), Tabbita, NSW (RoadNet, 18 September 2015)
Traffic Impact Assessment – The Ranch Poultry Production Complex – Farm 2 at Tysons Road (nr Kidman Way), Tabbita, NSW (RoadNet, 16 October 2015)
Traffic Impact Assessment – The Ranch Poultry Production Complex – Farm 3 at Tysons Road (nr Kidman Way), Tabbita, NSW (RoadNet, 19 October 2015)
Since The Ranch Farm 1 is intended to be developed first, the TIA for that development made a number of
recommendations in relation to the external road network, in particular the proposed site access onto Tysons
Road and the Kidman Way / Tysons Road intersection, to address the potential cumulative impacts of the
developments. It also made recommendations in relation to the internal road network required to connect
The Ranch Farm 1 development to Tysons Road.
The TIAs prepared for The Ranch Farm 2 and The Ranch Farm 3 were predicated on approval being
granted for The Ranch Farm 1 development, since they each share the same external access requirements
as The Ranch Farm 1 and also require use of the section of internal access road between the Ranch Farm 1
and the site entrance. Hence the applications for The Ranch Farm 2 and The Ranch Farm 3 sought
approval only for the additional sections of internal access road required between The Ranch Farm 1 and
The Ranch Farm 2, and between The Ranch Farm 2 and The Ranch Farm 3, respectively (once again the
application for The Ranch Farm 3 was predicated on The Ranch Farm 2 being approved and then developed
first). The recommendations made in the respective TIAs were tailored accordingly.
The Conditions of Consent issued for each of the approved developments are structured in the same way,
with the following requirements specified by Council and Roads and Maritime Services (RMS) in relation to
Roadworks for each of the development applications:
The Ranch Farm 1 (DA 2016/017)
34. ROADWORKS
The follow requirements have been prepared by Council and RMS and must be completed prior to the issue of a Final Occupation Certificate. CARRATHOOL SHIRE COUNCIL
a) Tyson Road is to be upgraded from the end of the sealed section to the access gate of The Ranch development (approximately 0.75km) with a finished 150mm gravel road-base at 6m wide and with a cross fall of 3%. All table drains are to be formed and cleared prior to the completion of the works.
b) B-double access will only be allowed on this road, after written application is received by Council and approval is given by National Heavy Vehicle Regulator (NHVR).
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 9 of 66 pages Date 19/02/2016
FINAL
Note: B-Double access would be granted at this stage only for their vehicles at the number that has been identified, any increase in traffic numbers may require the road to be sealed. c) The intersection of the access driveway with Tysons Road is to be located and the roadside maintained so as to provide the required Safe Intersection Sight Distance (SISD) in either direction in accordance with the Austroads Publications for the prevailing speed limit. d) As a minimum the driveway to Tysons Road shall be constructed as a "Rural Property Access" type treatment in accordance with the Austroads Guide to Road Design. The driveway is to be constructed to provide for two way movement for at least 100 metres from its intersection with Tysons Road and with a minimum width to accommodate the largest size of vehicle likely to access the subject site. e) As a minimum a sealed Basic Left Turn (BAL) treatment is to be constructed at the intersection of the access driveway with Tysons Road in accordance with the Austroads Guide to Road Design for the prevailing speed limit and shall be designed to accommodate road train vehicles. f) Any entry gate to the site shall be located at least 40m from the edge of seal of the carriageway of Tysons Road or at the property boundary whichever is the greater. This is to allow for the standing of large vehicles when gates are to be opened.
g) Where a proposed driveway intersects with a sealed road, the driveway shall be sealed from the edge of seal of the carriageway to the entry gate or the property boundary whichever is the greater.
h) The driveway access within the subject property shall be constructed using an all weather surface, with a management plan to provide measures to suppress dust generation from the development site and Tyson Road shall be prepared and implemented to the satisfaction of Council.
i) The access driveway is to be designed and constructed so as not to interfere with the capacity of the current roadside drainage network and to prevent water from proceeding onto, or ponding within, the carriageway of Tysons Road. Any culvert proposed to be located within the clear zone of the carriageway for the prevailing speed zone is to be constructed with a traversable type headwall.
REASON: to ensure safe road network and access to the site and suitable protection to Council asset.
ROADS AND MARITIME SERVICES
j) As a minimum the intersection of the Kidman Way (MR321) and Tysons Road is to be constructed and the roadside maintained so as to provide the required Safe Intersection Sight Distance (SISD) in either direction in accordance with the Austroads Publications as amended by the supplements adopted by Roads and Maritime Services for the prevailing speed limit. Compliance with this requirement is to be certified by an appropriately qualified person prior to construction of the vehicular access.
k) As a minimum the intersection of the Kidman Way (MR321) and Tysons Road is to be constructed and line marked as a public road intersection with a sealed Basic Right Turn (BAR) and Basic Left Turn (BAL) intersection treatment in accordance with the Austroads Guide to Road Design as amended by the supplements adopted by Roads and Maritime Services for the prevailing speed zone on the Kidman Way. The intersection is to be constructed to the standard required for an approved road train route.
I) The intersection of Tysons Road with the Kidman Way shall be designed and constructed so that vehicles turning between the Kidman Way and Tysons Road are not required to cross to the opposing travel lane in order to perform a turn manoeuvre. The intersection shall be line marked in accordance with Australian standards.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 10 of 66 pages Date 19/02/2016
FINAL
m) A management plan to provide measures to suppress dust generation from the development site and Tysons Road shall be prepared and implemented to the satisfaction of Council and Roads and Maritime Services. n) Any damage or disturbance to the road reserve of the Kidman Way is to be restored to match surrounding landform in accordance with Council requirements.
o) The Kidman Way (MR321) is part of the State Road network. For works on the State Road network the developer is required to enter into a Works Authorisation Deed (WAD) with Roads and Maritime Services before finalising the design or undertaking any construction work within or connecting to the road reserve. The applicant is to contact the Land Use Manager for the South West Region on Ph. 02 69371611 for further detail.
p) The developer will be required to submit detailed design plans and all relevant additional information including cost estimates and pavement design details for the works, as may be required in the Works Authorisation Deed documentation, for each specific change to the state road network for assessment and approval by Roads and Maritime Services. However, the developer is encouraged to submit concept plans of the layout of the proposed works for checking by Roads and Maritime Services prior to undertaking the detailed design phase.
q) Any works within the road reserve of the Kidman Way (MR321) requires approval under Section 138 of the Roads Act, 1993 from the road authority (Council) and concurrence from Roads and Maritime Services prior to commencement of any such works. The developer is responsible for all public utility adjustment/relocation works, necessitated by the development and as required by the various public utility authorities and/or their agents. r) All works associated with the development shall be at no cost to Roads and Maritime Services.
REASON: To comply with section 138(2) of the Roads Act 1993.
The Ranch Farm 2 (DA 2016/022)
34. ROADWORKS
The follow requirements have been prepared by Council and RMS and must be completed prior to the issue of a Final Occupation Certificate. CARRATHOOL SHIRE COUNCIL a) B-double access will only be allowed on this road, after written application is received by Council and approval is given by National Heavy Vehicle Regulator (NHVR). Note: B-Double access would be granted at this stage only for their vehicles at the number that has been identified, any increase in traffic numbers may require the road to be sealed.
b) The driveway access within the subject property shall be constructed using an all weather surface, with a management plan to provide measures to suppress dust generation from the development site and Tyson Road shall be prepared and implemented to the satisfaction of Council.
REASON: to ensure safe road network and access to the site and suitable protection to Council asset.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 11 of 66 pages Date 19/02/2016
FINAL
ROADS AND MARITIME SERVICES c) Prior to issue of a Construction Certificate, all works for the construction of Tyson Road, its intersection
with the Kidman Way (MR321) and the internal access road as per the Development Consent for DA2016/017 shall be completed and to the satisfaction of the relevant road authority.
d) Operational measures to minimise the cumulative peak traffic generation resultant from the combined
operation of Farms 1 and 2 shall be submitted to, and approved by Council and Roads and Maritime Services prior to occupation of Farm 2. The measures shall address the operational activities for Farm I and 2 combined, including bird placement, bird removal, litter placement and removal, etc. which shall be detailed in the Operational Environmental Management Plan.
e) As a minimum the roadside at the intersection of the Kidman Way (MR321) and Tyson Road is to be maintained so as to provide the required Safe Intersection Sight Distance (SISD) in either direction in accordance with the Austroads Publications as amended by the supplements adopted by Roads and Maritime Services for the prevailing speed limit. f) Measures for the control of dust generation from the development site, particularly internal roadways, and Tyson Road must be addressed within the Operational EMP to the satisfaction of the consent authority. g) Any damage or disturbance to the road reserve of the Kidman Way is to be restored to match surrounding landform in accordance with Council requirements. h) Any works within the road reserve of the Kidman Way (MR321) requires concurrence from Roads and Maritime Services under section 138 of the Roads Act 1993 prior to commencement of any such works. The developer is responsible for all public utility adjustment/relocation works, necessitated by the development and as required by the various public utility authorities and/or their agents. i) All works associated with the development shall be at no cost to Roads and Maritime Services.
REASON: To comply with section 138(2) of the Roads Act 1993.
The Ranch Farm 3 (DA 2016/023)
34. ROADWORKS The follow requirements have been prepared by Council and RMS and must be completed prior to the issue
of a Final Occupation Certificate.
CARRATHOOL SHIRE COUNCIL a) B-double access will only be allowed on this road, after written application is received by Council and
approval is given by National Heavy Vehicle Regulator (NHVR). Note: B-Double access would be granted at this stage only for their vehicles at the number that has been identified, any increase in traffic numbers may require the road to be sealed.
b) The driveway access within the subject property shall be constructed using an all weather surface, with a management plan to provide measures to suppress dust generation from the development site and Tyson Road shall be prepared and implemented to the satisfaction of Council.
c) Requests for additional maintenance outside the scheduled Maintenance Hierarchy will need to be in writing and additional costs could be incurred for these works.
REASON: to ensure safe road network and access to the site and suitable protection to Council asset.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 12 of 66 pages Date 19/02/2016
FINAL
ROADS AND MARITIME SERVICES d) Prior to issue of the Construction Certificate all works for the construction of Tyson Road, its intersection with the Kidman Way (MR321) and the internal access road as per the Development Consent for DA2016/017 shall be completed and to the satisfaction of the relevant road authority. e) Operational measures to minimise the cumulative peak traffic generation resultant from the combined operation of Farms 1, 2 and 3 shall be submitted to, and approved by Council and Roads and Maritime Services prior to occupation of Farm 3. The measures shall address the operational activities for Farms 1, 2 and 3 combined, including bird placement, bird removal, litter placement and removal, etc. which shall be detailed in the Operational Environmental Management Plan. f) As a minimum the roadside at the intersection of the Kidman Way (MR321) and Tyson Road is to be maintained so as to provide the required Safe Intersection Sight Distance (SISD) in either direction in accordance with the Austroads Publications as amended by the supplements adopted by Roads and Maritime Services for the prevailing speed limit. g) Measures for the control of dust generation from the development site, particularly internal roadways, and Tyson Road must be addressed within the Operational EMP to the satisfaction of the consent authority. h) Any damage or disturbance to the road reserve of the Kidman Way is to be restored to match surrounding landform in accordance with Council requirements. i) Any works within the road reserve of the Kidman Way (MR321) requires concurrence from Roads and Maritime Services under section 138 of the Roads Act 1993 prior to commencement of any such works. The developer is responsible for all public utility adjustment/relocation works, necessitated by the development and as required by the various public utility authorities and/or their agents. j) All works associated with the development shall be at no cost to Roads and Maritime Services.
REASON: To comply with section 138(2) of the Roads Act 1993.
1.1.2 Development Application for The Ranch Farm 5
As noted in the previous section, the upgrades required to be made at the Kidman Way / Tysons Road
intersection, as well as the construction of the new site entrance onto Tysons Road and the internal access
road to The Ranch Farm 1, will be undertaken as part of the consent requirements for The Ranch Farm 1.
Similarly, the section of internal access road between The Ranch Farm 1 and The Ranch Farm 2 will be
constructed as part of the consent requirements for The Ranch Farm 2, and the section of internal access
road between The Ranch Farm 2 and The Ranch Farm 3 will be constructed as part of the consent
requirements for The Ranch Farm 3.
The DA and EIS for The Ranch Farm 5 assume that the development approvals and associated consent
conditions for each of The Ranch Farms 1 to 3 will have been implemented prior to construction
commencing on The Ranch Farm 5. The application for The Ranch Farm 5 is also predicated on The Ranch
Farm 4 being approved and developed first, since that development will provide the section of internal
access road between The Ranch Farm 3 and The Ranch Farm 4. Accordingly, the application for The
Ranch Farm 5 seeks approval for the construction and use of the additional section of internal access road
between The Ranch Farm 4 and The Ranch Farm 5 only. The additional section of internal access road for
The Ranch Farm 5 will connect directly to the internal access road constructed as part of The Ranch Farm 4
development.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 13 of 66 pages Date 19/02/2016
FINAL
1.2 Scope of Traffic Impact Assessment for The Ranch Farm 5
This TIA report examines the potential impacts of traffic generated by The Ranch Farm 5 proposed
development on the existing traffic movements on Tysons Road, Kidman Way and adjacent areas. It also
considers the cumulative impacts of all five farms which collectively comprise The Ranch Poultry Production
Complex, when operating concurrently.
This assessment is prepared in accordance with relevant Council and RMS standards. The following tasks
have been undertaken in the preparation of this report:
Site inspection, review of existing traffic information and collection of additional traffic data through traffic surveys to establish existing operating conditions along Tysons Road, Kidman Way and other relevant roads in the vicinity of the proposed development;
Assessment of traffic generation to and from the proposed development during its construction and operation;
Assessment of background traffic growth;
Determination of future traffic volumes with and without the proposed development;
Examination of the potential impacts of the additional traffic generated by The Ranch Farm 5 on the operation of the external road network, including Tysons Road and Kidman Way;
Identification of access requirements for The Ranch Farm 5 proposed development; and
Consideration of the cumulative impacts of The Ranch Poultry Production Complex when all five farms are operating concurrently, in conjunction with other known developments in the study area.
As discussed previously, an EIS is being prepared (by SLR Consulting Australia Pty Ltd (SLR)) to
accompany the development application for The Ranch Farm 5 proposed development, which in turn will be
informed by this TIA. As part of this process a Briefing Paper was prepared by SLR to inform relevant
government agencies of the proposed development, and in response to this the Secretary’s Environmental
Assessment Requirements (SEARs) for the Development have been received. The key issues in relation to
transport and road traffic that were identified in the SEARs are summarised in Table 1.1 below, which also
shows the location in this report where each of the issues is addressed.
Aspect – Transport and Road Traffic Where addressed in this report
details of road transport routes and access to the site Sections 2, 3.2, 3.6 and 5
road traffic predictions for the development during construction and operation; and
Sections 3.4, 3.5, 3.7, 4 and 6
an assessment of impacts to the safety and function of the road network; and the details of any road upgrades required for the development
Sections 7, 8 and 9
Table 1.1 – SEARs relating to Transport and Road Traffic for The Ranch Farm 5
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 14 of 66 pages Date 19/02/2016
FINAL
2. EXISTING CONDITIONS
2.1 The Site
The proposed development site referred to as The Ranch Farm 5 is located between Goolgowi and Griffith in
south-western NSW, approximately 5.5km north-east of Tabbita. Access to the site during both its
construction and operation is proposed via a new internal access road that connects to Tysons Road.
Tysons Road is an existing local rural road that connects to Kidman Way (B87) at its western end and Back
Hillston Road, another local rural road which runs along the site’s eastern boundary, at its eastern end.
Plans showing the proposed access arrangements and supporting infrastructure for The Ranch Farms 1 to 5
collectively are provided in Figures 2.1(a) and 2.1(b) on the following pages. Additional plans showing the
proposed location and development layout for The Ranch Farm 5 are provided in Appendix A.
The proposed farm will comprise of 16 tunnel-ventilated, fully-enclosed, climate-controlled poultry sheds with
associated support infrastructure and staff amenities. The proposed Development Site is to be located
within Lot 77 in Deposited Plan (DP) 720257, in an area that comprises of approximately 42.3 hectares (ha)
of vacant rural land. Access to the development during its construction and operation will be achieved via a
new internal farm access road connecting to Tysons Road approximately 1km to the east of Kidman Way,
near the boundaries with the adjacent Lot 47 in DP756045, Lot 2 in DP1157807 and Lot 14 in DP756061.
All movements to and from the site will occur via this new site access onto Tysons Road and the existing
Kidman Way / Tysons Road intersection.
As previously noted in Section 1.1, development approval for the proposed upgrades at the Kidman Way /
Tysons Road intersection, the new site entrance onto Tysons Road and the internal access road to The
Ranch Farm 1 were previously sought and granted as part of the DA (DA 2016/017) and associated EIS
prepared and lodged for that development. Similarly, development approval for the construction and
operation of the additional section of internal access road between The Ranch Farm 1 and The Ranch Farm
2, and between The Ranch Farm 2 and The Ranch Farm 3, were sought and granted as part of DA
2016/022 and DA 2016/023 respectively.
The application for The Ranch Farm 5 is predicated on The Ranch Farm 4 being approved and developed
first, since that development will provide the section of internal access road between The Ranch Farm 3 and
The Ranch Farm 4. The DA and EIS for The Ranch Farm 5 seek approval for the construction and use of the
additional section of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 15 of 66 pages Date 19/02/2016
FINAL
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 16 of 66 pages Date 19/02/2016
FINAL
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 17 of 66 pages Date 19/02/2016
FINAL
2.2 Existing Road Network
2.2.1 Kidman Way (B87)
Kidman Way is a state-controlled rural highway running north-south through southern NSW, extending from
Bourke at its northern end all the way to its connection to the Newell Highway at the southern end near
Jerilderie, a total distance of approximately 640km. It is a designated B-Double route and also an approved
Road Train route. Within the study area it intersects with the Mid-Western Highway (B64) at Goolgowi via a
large rural roundabout, as well as with Burley Griffin Way (B94) at Griffith and the Sturt Highway (A20) near
Darlington Point.
Of particular relevance to this study, Kidman Way provides access to Griffith, being the area’s major centre,
as well as to the poultry industry operations located near Hanwood approximately 6km south of Griffith.
Kidman Way between Goolgowi and Griffith is a 2-lane, 2-way rural highway with 3.5m sealed lanes, sealed
shoulders typically varying in width between approximately 0.5m and 1.0m and grassed verges. To the south
of Griffith the lane widths are similar but the shoulders are narrower and generally less than 0.5m wide
(except where the road has more recently been upgraded). The speed limit varies along the route, with a
maximum posted speed limit of 80 or 100km/h occurring outside of the urban areas and 50km/h (or 40km/h
at school zones on school days) within the urban areas of Griffith, Hanwood and Darlington Point. The
speed limit near Tysons Road is 100km/h.
Photos of Kidman Way taken near its intersection with Tysons Road at Tabbita (between Goolgowi and
Griffith) are provided in Figures 2.2 and 2.3.
Figure 2.2: Looking north along Kidman Way at Tabbita (Tysons Road on RHS)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 18 of 66 pages Date 19/02/2016
FINAL
Figure 2.3: Looking south along Kidman Way at Tabbita (Tysons Road on LHS)
2.2.2 Tysons Road
Tysons Road is a local rural road extending in an east-west direction from Kidman Way at its western end to
Back Hillston Road at its eastern end, a total distance of approximately 2.6km. It crosses the Temoro – Roto
Railway Line approximately 150m to the east of Kidman Way. This railway line, which is a branch line from
the Main South Railway (which runs between Sydney and the NSW state border with Victoria at Albury),
once accommodated passenger services but is now only used infrequently for freight haulage (mainly wheat)
and is closed beyond Hillston (to the north of Goolgowi).
Tysons Road is sealed and unlinemarked from its intersection with Kidman Way up to the railway crossing
and then beyond for a further 135m up to the existing access driveway to the adjacent ROTY Grain Store
depot (i.e. a total length of approximately 285m). Beyond this point it is an unsealed (dirt) road up to its
intersection with Back Hillston Road.
There is an access road / turnaround area located approximately 50m east of the Kidman Way /Tysons
Road intersection on the northern side of Tysons Road, which appears to have previously been used to
service GrainCorp’s Tabbita Silo located near the northeast quadrant of the intersection (see Figure 2.2)
which is currently closed. Tysons Road has no intermediate connections with other local roads and, apart
from a small number of rural farm accesses, it was observed to provide access to only one other
development approximately 750m east of the railway line, namely Northern Riverina Grains P/L. The
proposed access to The Ranch Poultry Production Complex, which includes The Ranch Farm 5
development site, would be located approximately 150m to the east of this access.
Between Kidman Way and the proposed site access Tyson Road has a width of approximately 7m (sufficient
to accommodate 2-way traffic) except near the intersection with Kidman Way where it widens out to 11m or
more to accommodate the turn paths of larger vehicles. There is no posted speed limit on Tysons Road and
the open road speed limit of 100km/h therefore applies.
Figures 2.4 to 2.9 show the general layout of Tysons Road at various locations.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 19 of 66 pages Date 19/02/2016
FINAL
Figure 2.4: Tysons Road looking north-east from Kidman Way (nr access to GrainCorp’s Tabbita Silo)
Figure 2.5: Tysons Road looking east at railway level crossing
Figure 2.6: Tysons Road looking west at railway level crossing
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 20 of 66 pages Date 19/02/2016
FINAL
Figure 2.7: Tysons Road looking east near end of seal (access to ROTY Grain Store on LHS)
Figure 2.8: Tysons Road looking east from access to Northern Riverina Grains P/L (proposed site
access to be approx. 150m further to the east on LHS)
Figure 2.9: Tysons Road looking west near proposed site access (RHS)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 21 of 66 pages Date 19/02/2016
FINAL
2.2.3 Back Hillston Road
Back Hillston Road is another local rural road extending in a north-south direction from Kidman Way near
Tabbita (approximately 3.9km south) at its southern end, to Bunda N Road and thence Rankins Springs
Road near Hillston at its northern end, a total distance of approximately 67km. It crosses the state-controlled
Mid-Western Highway (B64) at a point approximately 15km northeast of Goolgowi, but otherwise intersects
with only a few local rural roads including Tysons Road at its southern end. It appears to have a similar
formation width to Tysons Road and is an unsealed (dirt) road. There is no posted speed limit on Back
Hillston Road and the open road speed limit of 100km/h therefore applies.
Figures 2.10 to 2.11 show the general layout of Back Hillston Road in the vicinity of Tysons Road.
Figure 2.10: Back Hillston Road looking north in vicinity of Tysons Road
Figure 2.11: Back Hillston Road looking south in vicinity of Tysons Road
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 22 of 66 pages Date 19/02/2016
FINAL
2.2.4 Kidman Way / Tysons Road Intersection
The existing intersection of Tysons Road with Kidman Way is located approximately 19km south-east of
Goolgowi and is illustrated in Figures 2.12 to 2.13 below. Tysons Road meets Kidman Way on a straight
and flat section of road and offers a reasonably good level of visibility in either direction. The intersection is
sealed but unlinemarked and is controlled by a Give-Way sign. No turn bays are provided at the
intersection, however, a wide sealed shoulder in the form of a Basic Right Turn (BAR) treatment is provided
on the northbound carriageway of Kidman Way to allow through traffic to pass a vehicle waiting to turn right
at the intersection (see Figure 2.2). The intersection mouth is quite wide to accommodate the turn path
requirements of large heavy vehicles generated by existing developments that currently use the intersection
or previously used it (in the case of GrainCorp’s Tabbita Silo).
Figure 2.12: Tysons Road approach to Kidman Way (GrainCorp’s Tabbita Silo access on RHS in
foreground)
Figure 2.13: Tysons Road viewed from Kidman Way (GrainCorp’s Tabbita Silo access on LHS)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 23 of 66 pages Date 19/02/2016
FINAL
2.2.5 Adjacent Intersections on Kidman Way
Approximately 190m to the south-east of Tysons Road, Kidman Way intersects with the next side road
called Glen Roy Street on its western side. Glen Roy Street is a local unsealed rural road which forms an
uncontrolled T-intersection with Kidman Way. No widening or turn bay provision is provided at this
intersection.
Approximately 400m further to the north-west of Tysons Road, Kidman Way intersects with Tabbita Lane on
its western side at a Give-Way controlled T-intersection that includes left and right turn bays on Kidman Way
in an AUL/CHR configuration. Tabbita Lane is a 2-lane 2-way sealed rural road running east-west which
provides a connection at its western end to the Mid-Western Highway west of Goolgowi via Carrathool Road,
thereby providing an alternative route for locally-generated traffic that avoids the need to travel via Goolgowi.
2.3 Existing Land Use
The long-standing and existing use of the development site is associated with traditional agricultural
production, primarily dryland cropping.
The primary land use for the surrounding neighbourhood is also traditional agricultural production.
Additional land uses within the area include a privately owned and operational silo on Tysons Road (ROTY
Grain Store depot), located approximately 5.4km south-west of the Development Site; GrainCorp’s Tabbita
Silo which is currently closed, located near the intersection of Tysons Road with Kidman Way; and JBS
Australia’s Tabbita Feedlot (cattle feedlot) approximately 12km to the west of The Ranch Farm 5
development which is accessed from Tabbita Lane. There are also several other poultry developments
recently approved within the area, as discussed later.
The Ranch Farm 5 development is removed from any urban areas. Council has advised that Tabbita, which
is located approximately 5.5km south-west of the Development Site, comprises five residences.
2.4 Existing Traffic Volumes
2.4.1 Kidman Way near Tysons Road
Existing traffic volumes along Kidman Way in the vicinity of the proposed development have been derived
from traffic data provided by Roads and Maritime Services (RMS). RMS has a mobile counting site (station
no. 95255) on Kidman Way located approximately 700m south of Tysons Road. There are no major roads
located between the count site and Tysons Road, hence the traffic volumes and daily traffic flow profile at
the count site are expected to be representative of what also occurs on Kidman Way near its intersection
with Tysons Road.
The most recent traffic data available from the RMS mobile site dates back to the period from Tuesday 22
November 2011 to Tuesday 13 December 2011. The information provided to RoadNet includes hourly traffic
volumes in each direction of travel for each day of the week and daily volumes in each direction for each of
the 12 different vehicle types in accordance with the Austroads method of classification.
The data shows relatively low traffic volumes on Kidman Way over the survey period. Average traffic
volumes during the weekdays were approximately 1,100 vehicles per day (two-way), reducing at the
weekends to provide an overall 7-day average daily volume of 987 veh/day (two-way).
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 24 of 66 pages Date 19/02/2016
FINAL
A summary of the average hourly traffic profile for each direction of travel over the survey period is provided
in Figure 2.14 below.
Figure 2.14: Average hourly traffic volumes on Kidman Way (from RMS data)
Analysis of the data indicates:
Traffic volumes along Kidman Way generally increase during the morning to a peak of 75veh/hr between 8-9am and 9-10am, and then remain at a level between 60 and 70veh/hr during the middle part of the day before peaking again in the afternoon to 81veh/hr between 4-5pm. The volumes then reduce again with an overnight low of 3 veh/hr recorded between 1am and 4am.
Existing traffic volumes during the development peaks for The Ranch Farm 5 proposed development (i.e. around 7am and 4pm, corresponding to the start and end times for the daily farm workers shift) are approximately 51veh/hr and 81veh/hr respectively.
There is some variation throughout the day between northbound and southbound volumes, however, the directional split for the full 24 hr period is approximately 50:50.
Heavy vehicle numbers contribute up to approximately 20% of the total daily traffic volumes, however, during the night-time the proportion of heavy vehicles is expected to be much higher.
Weekday traffic volumes were observed to be slightly higher than weekend volumes over the survey period.
0
10
20
30
40
50
60
70
80
90
0.0
0
1.0
0
2.0
0
3.0
0
4.0
0
5.0
0
6.0
0
7.0
0
8.0
0
9.0
0
10
.00
11
.00
12
.00
13
.00
14
.00
15
.00
16
.00
17
.00
18
.00
19
.00
20
.00
21
.00
22
.00
23
.00
Northbound
Southbound
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 25 of 66 pages Date 19/02/2016
FINAL
An on-site traffic count was also conducted on Kidman Way at the intersection with Tysons Road as part of a
site visit on the afternoon of Thursday 4 June 2015 between 3:30pm and 5pm. The count indicated a two-
way peak hour volume along Kidman Way of 110veh/hr between 3:45 and 4:45pm, including 22 heavy
vehicles. Only 2 vehicles were observed to turn into Tysons Road and 1 vehicle out during the entire survey
period (i.e. 1.5hrs).
The volume of traffic observed along Kidman Way from the traffic survey is a little higher than that identified
from analysis of the RMS traffic data for the same time period, although the overall order of magnitude is
similar. Given the different times of year associated with each survey and the different baseline assumptions
(i.e. average 7-day traffic volume vs weekday spot count) this is to be expected. However, since the hourly
volumes are so low the differences are insignificant.
Importantly, the survey indicates that there is very little traffic currently using Tysons Road via its intersection
with Kidman Way during the afternoon peak period. This is consistent with site observations which confirm a
limited number of existing and operational access points along the length of Tysons Road as previously
discussed in Section 2.2.2.
For the purpose of this assessment, the highest average hourly traffic volume of 81veh/hr in 2011 (41veh/hr
southbound, 40veh/hr northbound) identified from analysis of the RMS data has been used, with an
allowance for traffic growth as discussed in Section 2.5, to represent the future traffic volumes along Kidman
Way at the Tysons Road intersection during each of the development peak hours. This equates to examining
the worst case (highest hourly volume) scenario on a typical (average) day. In addition, a nominal allowance
of 1veh/hr turning into Tysons Road from each direction and 1veh/hr turning out of Tysons Road in each
direction) during the development peak hours has been adopted, and 10veh/hr in and out (i.e. each way)
over a full day. These assumptions reflect the very low background traffic volumes observed to be currently
using this road.
2.4.2 Kidman Way – other locations
Existing traffic volumes along Kidman Way have also been examined at other locations within the study area
based on traffic data provided by RMS. A summary of those sites and the most recent period(s) for which
traffic data is available is provided below (Station no. 95255 discussed in the previous section is included for
comparison):
Station no. 95255 (Tabbita) – 24/7/2010 to 10/08/2010 and 22/11/2011 to 13/12/2011.
Station no. 95374 (west of Griffith) – 25/7/2010 to 12/08/2010.
Station no. 95641 (south of Willandra Avenue, Griffith) – 25/7/2010 to 10/8/2010.
The average daily traffic volumes and proportion of heavy vehicles recorded at these sites for each of the
time periods specified are summarised in Table 2.1 below.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 26 of 66 pages Date 19/02/2016
FINAL
Year Average Daily Traffic Volumes (veh/day) and % Heavy Vehicles
Station No.
95255 (Tabbita) 95374 (west of Griffith) 95641 (south of Griffith)
2010 816 (13.5%) 2,667 (11.7%) 5,800*
2011 987 (19.6%) - -
*Estimated from axle count of 6,743 axle pairs using factor of 0.86
Table 2.1 Average daily traffic volumes on Kidman Way
These numbers may have increased a little between the time the surveys were conducted and now,
however, they are expected to be broadly representative of the existing traffic conditions along Kidman Way.
The data indicates that the average daily traffic volumes along Kidman Way are quite low, ranging from
approximately 1,000 veh/day in the vicinity of Tabbita (i.e. near the proposed development site as previously
discussed in Section 2.4.1) to between approximately 3,000 and 6,000 veh/day within the immediate vicinity
of Griffith depending on the location. Corresponding numbers of heavy vehicles range from approximately
200 to 300 veh/day based on the available data.
2.5 Background Traffic Growth
A background linear traffic growth rate of 1.5% per annum (applied from the base year of 2011 for the traffic
data) has been adopted for both the peak hour and daily volumes for the purposes of this assessment.
Given the rural nature of the location of the proposed development and the relatively low levels of
development occurring as a whole within the region, a growth rate of 1.5% per annum over the longer term is
expected to provide a conservative basis against which the potential upgrades required on the external road
network as a result of the proposed development can be assessed.
Note that a separate assessment of the cumulative impacts of not only The Ranch Farm 5 development, but
also other developments recently completed (such as the Jeanella Poultry Production Complex) or proposed
which have/will add additional traffic to the local road network, is provided in Section 7.6. This includes the
other farms proposed as part of The Ranch Poultry Production Complex.
2.6 Existing Pedestrian and Cyclist Facilities
Given the rural location for this development proposal, all access to and from Tysons Road and the
proposed site is expected to be via vehicle. No pedestrian or cyclist movements have been observed to
currently occur in the area and none are expected as a result of the proposed development.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 27 of 66 pages Date 19/02/2016
FINAL
3. PROPOSED DEVELOPMENT
3.1 Development Description
VOAG 5 intends to develop an intensive poultry broiler production complex (The Ranch Farm 5) comprising
of 16 tunnel-ventilated fully-enclosed climate-controlled poultry sheds where broiler birds will be grown for
human consumption. The conceptual layout of the proposed development is shown in Appendix A. The key
development elements of the proposed farm include:
Table 3.1 Summary of The Ranch Farm 5 Proposed Development
Development Characteristic Proposed Development
Purpose Birds grown for human consumption
Number of poultry sheds 16, each measuring 176m long by 18m wide (3,168m2)
Type of poultry sheds Tunnel-ventilated, fully-enclosed, climate-controlled
Maximum shed population 50,000 birds
Maximum farm population 800,000 birds
Maximum bird density within sheds 18 birds per square metre (and will not exceed a density of 34kg/m2)
Hours of operation 24 hours a day, 7 days a week
Production cycle length Approximately 9 weeks (63 days), comprising 7.5 weeks (53 days) of bird occupation and a 1.5 week (10 days) cleaning phase.
Number of production cycles per year Approximately 5.7 on average
The proposed poultry development will operate 24 hours a day, 7 days a week. Each of the proposed
poultry sheds will have the capacity to house a maximum of 50,000 broilers at any one time, equating to a
total farm population of 800,000 broilers.
The proposed disturbance footprint (including access roads, servicing infrastructure and support
infrastructure) of The Ranch Farm 5 development will be relatively small at approximately 17ha and the
commercial activities associated with the poultry operation will be largely confined to this area.
In addition to poultry shedding, The Ranch Farm 5 will include:
The construction of two (2) dwellings within The Ranch Farm 5 site comprising of one residential dwelling and one rural workers dwelling, to accommodate the farm manager and assistant farm manager; and
The construction of ancillary infrastructure and improvements required to support the poultry production operation.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 28 of 66 pages Date 19/02/2016
FINAL
3.2 Vehicular Access and Internal Road Layout
Entry to The Ranch Poultry Production Complex which includes The Ranch Farm 5 will occur via a suitable
all-weather access road connecting to Tysons Road within the Carrathool LGA. The internal access road
will run parallel to the fenceline along the side of Tysons Road and then north generally parallel to Back
Hillston Road.
As mentioned in previous sections, development approval for the proposed upgrades at the Kidman Way /
Tysons Road intersection, the new site entrance onto Tysons Road and the internal access road to The
Ranch Farm 1 were previously sought and granted as part of the DA (DA 2016/017) and associated EIS
prepared and lodged for that development. Similarly, development approval for the construction and
operation of the additional section of internal access road between The Ranch Farm 1 and The Ranch Farm
2, and between The Ranch Farm 2 and The Ranch Farm 3, were sought and granted as part of DA
2016/022 and DA 2016/023 respectively.
The application for The Ranch Farm 5 is predicated on The Ranch Farm 4 being approved and developed
first, since that development will provide the section of internal access road between The Ranch Farm 3 and
The Ranch Farm 4. The DA and EIS for The Ranch Farm 5 seek approval for the construction and use of the
additional section of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
A conceptual layout of the proposed access arrangements and supporting infrastructure servicing the
development was provided previously in Figures 2.1(a) and 2.1(b). A plan showing the development layout
is also provided in Appendix A. The new section of internal access road proposed to connect The Ranch
Farm 5 to The Ranch Farm 4 has been located to avoid vegetation clearing, where possible. The Ranch
Farm 5 development will include a one-way system to enable traffic to enter, exit and manoeuvre around the
poultry sheds for loading, unloading and servicing activities in a forward direction, thereby minimising the
potential for traffic conflict and noise.
The roads will be constructed as all-weather rural-type roads able to carry the anticipated heavy vehicle
movements.
Parking will be available adjacent to the sheds to accommodate staff and visitor movements.
3.3 Pedestrians, Cyclists and Public Transport
No provision is made for external pedestrians, cyclists or public transport connections due to the remote
location of the site.
3.4 Development Traffic Generation
This section focuses on the traffic that would be generated by the proposed development once The Ranch
Farm 5 becomes operational. Construction traffic generated during the construction of the proposed
development is discussed in Section 6.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 29 of 66 pages Date 19/02/2016
FINAL
3.4.1 Traffic Generating Sources
While the proposed poultry development will operate 24 hours a day, seven days a week, the majority of
activities will occur between 7.00am and 7.00pm. As the birds reach their desired processing (slaughter)
weight they will be removed from the sheds and transported from the development site between the hours of
7pm and 4pm, although for reasons of livestock welfare they will generally be removed overnight and in the
morning when it is cooler and the birds are more settled.
There will typically be one daily shift for farm workers commencing at 7:00am and finishing at 4:00pm each
day.
It is estimated that approximately 75 percent of the total daily traffic generation will comprise of heavy
vehicles (primarily either semi-trailers or rigid trucks), while the remaining traffic will be light vehicles
(predominantly cars).
Light Vehicles
It is expected that the majority of light vehicles will travel to and from Goolgowi and the Griffith area
(particularly the latter where the majority of the local population resides) via Kidman Way to access the site.
Most inbound light vehicles will turn right into Tysons Road from Kidman Way and left into the proposed site
access road connecting to The Ranch Farm 5, while traffic exiting will turn right out of the site access road
and left onto Kidman Way from Tysons Road.
Some staff movements may have an origin or destination from/to points to the west of Goolgowi such as the
area around Gunbar, and would therefore be expected to use the shorter, more direct route provided by
Tabbita Lane to travel to/from the site rather than travelling via Goolgowi. However, in practice the distance
involved (e.g. approximately 46km from Gunbar) is expected to limit the number of such movements. A small
allowance for some traffic arriving and departing via Kidman Way to the north of Tysons Road has been
made in the traffic calculations, which allows for this option as well as the option of traffic arriving/departing
from/to Goolgowi.
While Old Hillston Road and its connection to Tysons Road theoretically provides an alternative route for
light vehicle traffic originating from locations further to the east of Goolgowi such as Rankin Springs, in
practice very little traffic would be expected to travel this distance (approximately 60km) to access the site on
a regular basis. Even then, the majority of that traffic would still be expected to use the higher standard and
faster State Highway network (i.e. the Mid-Western Highway and Kidman Way) to access the site rather than
the lower standard, slower dirt road option that Old Hillston Road offers. For the purpose of this
assessment, all light vehicle traffic movements to and from the development site are assessed to occur via
Kidman Way and its connection with Tysons Road.
The following issues have been considered when estimating traffic generation.
Most staff will travel to and from the site by car.
The number of staff is likely to vary seasonally i.e. there will be busy times when additional labour will be called upon.
The distance from towns to the site is likely to result in the occurrence of some car-pooling during busier times.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 30 of 66 pages Date 19/02/2016
FINAL
Staff numbers are low in relation to the number of birds on the site. It is proposed that there be:
- 1 full-time farm manager who lives on site.
- 1 full-time assistant farm manager who lives on site.
- 2 full-time equivalent farm hands.
Trucks
Trucks will travel to and from the site on a daily basis via the Kidman Way / Tysons Road intersection. All
trucks will be directed to use Kidman Way and its intersection with Tysons Road to access the site.
Practically all truck movements will be to and from the direction of Griffith and Hanwood (approximately 6
kilometres south of Griffith on Kidman Way) i.e. to/from the south-east. This means that they will turn right
into Tysons Road from Kidman Way and left out. The associated operational activities include:
Delivery of the shed floor bedding material in rigid trucks from a storage facility located near Hanwood, to the south-east of the site;
Delivery of day-old chicks from Baiada Poultry’s (Baiada) hatchery facility located approximately 3 kilometres west of Griffith on Snaldero Road in insulated pantechnicon trucks (south);
Delivery of feed from Baiada’s feedmill facility located approximately 1 kilometre south of Hanwood on the corner of Kidman Way and McWilliams Road in semi-trailers (south);
Delivery of bulk liquid petroleum gas (LPG) from Griffith in rigid trucks (south);
Removal of birds to Baiada’s processing complex located approximately 1 kilometre south of Hanwood on the corner of Kidman Way and Murphy Road in semi-trailers (south);
Removal of shed floor litter (spent bedding material) in semi-trailers to various locations;
Removal of dead birds to Baiada’s processing complex, which includes a protein recovery/rendering plant, located approximately 1 kilometre south of Hanwood on the corner of Kidman Way and Murphy Road in rigid trucks (south); and
Removal of general garbage in rigid trucks to disposal facilities located in the vicinity of Griffith (south).
The traffic volume calculations used in the traffic assessment are based on the largest truck being a semi-
trailer. However, it is possible that future contractors may use B-Doubles to service the site, which would
reduce the overall number of trips used in this traffic impact assessment.
Heavy vehicle trips will be mostly spread over the nine week production cycle and will be distributed
relatively evenly over the predicted delivery hours.
3.4.2 Traffic Generation volumes
Traffic generation for a typical 9 week production cycle and annually (based on 5.7 production cycles per
year) has been based on operational data provided by Baiada via SLR Consulting. A summary of the traffic
generation for The Ranch Farm 5 is provided in Table 3.2 on the next page.
It should be noted that in preparing these traffic generation estimates Baiada reviewed its core operational
data at its existing facilities for each of the key activities in which it is involved. As a result the heavy vehicle
traffic generation rates on a ‘per-shed’ basis over the 9 week production cycle, in particular, have changed
(increased) from what was previously adopted for assessment of The Ranch Farms 1 to 3. The revised
traffic generation volumes for the now-approved 8 shed developments for each of The Ranch Farms 1 to 3,
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 31 of 66 pages Date 19/02/2016
FINAL
which have been adopted going forward for assessing the traffic impacts of The Ranch Farm 5 development
proposal (on the basis that those developments will already be operational and therefore generating traffic
on the local road network prior to The Ranch Farm 5 becoming operational) are provided in Appendix B.
The changes made to the traffic generation rates equate to a small increase in the average total daily
predicted traffic generation for each of The Ranch Farms 1 to 3 from 7 vehicles per day (14 two-way trips) to
9 vehicles per day (18 two-way trips), while the forecast peak hour traffic generation remains unchanged.
Table 3.2 – Traffic Generation per Production Cycle and Year for The Ranch Farm 5 development
Activity Vehicle Type
Vehicles (Two Way Trips)
Traffic Per 9 Week
Production Cycle
(Trips)
Annual Traffic - 5.7
Production Cycles
(Trips)
Heavy Vehicles
Delivery of shed bedding material Twin axle rigid truck 30 (60) 171 (342)
Delivery of chicks Twin axle rigid truck 12 (24) 69 (138)
Delivery of feed Semi-trailer 180 (360) 1,026 (2,052)
Delivery of fuel Rigid tanker 2 (4) 12 (24)
Delivery of gas (LPG) Rigid tanker 4 (8) 23 (46)
Removal of birds Semi-trailer 180 (360) 1,026 (2,052)
Removal of birds – catching equipment
transporter Semi-trailer 40 (80) 228 (456)
Removal of birds – catching staff Bus 40 (80) 228 (456)
Removal of shed litter material Semi-trailer 72 (144) 410 (820)
Shed wash down equipment transporter Semi-trailer 40 (80) 228 (456)
Removal of dead birds Twin axle rigid truck 60 (120) 342 (684)
Removal of garbage Rigid truck 2 (4) 12 (24)
Heavy Vehicle Sub-Total 662 (1,324) 3,775 (7,550)
Light Vehicles
Staff visits Car 160 (320) 912 (1,824)
Tradesman Ute/Van 18 (36) 103 (206)
Catching equipment maintenance Van 8 (16) 46 (92)
Shed litter material removal contractors Car 20 (40) 114 (228)
Shed wash down contractors Car 8 (16) 46 (92)
Light Vehicle Sub-Total 214 (428) 1,221 (2,442)
TOTAL 876 (1,752) 4,996 (9,992)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 32 of 66 pages Date 19/02/2016
FINAL
Daily traffic generation and hourly volumes for The Ranch Farm 5 proposed development have been
calculated on the basis of 2 full-time equivalent staff. A few trucks will come and go as they are spread
evenly throughout daylight hours. The calculations are imprecise but only small numbers are involved.
On average there will be 30 movements per day (22 of these trucks).
The peak generating hours of the development will occur at the start and finish of the shift. It is estimated
that there would be 4 trips in the AM peak hour and 4 trips in the PM peak hour.
It is also estimated that approximately 70% of vehicle movements generated by the development will be into
the site in the morning, with 30% out, while the situation will be reversed in the afternoon (i.e. 30% in and
70% out).
Vehicle Type Vehicles Per Day
(Vehicle Trips)
AM Peak Hour
Movements
PM Peak Hour
Movements
Cars (LV) 4 (8) 3 (2 in, 1 out) 3 (1 in, 2 out)
Heavy Vehicles 11 (22) 1 (1 in, 0 out) 1 (0 in, 1 out)
Total 15 (30) 4 (3 in, 1 out) 4 (1 in, 3 out)
Table 3.3 – Traffic Generation per Day and in each Peak Hour for The Ranch Farm 5
For the purposes of this analysis it is assumed heavy vehicle trips will be spread evenly over the 9 week
cycle and will be distributed evenly over the main hours of activity between 7am and 7pm, equating to an
average of approximately 1 heavy vehicle trip per hour (including during the peak periods as shown in the
table above). The majority of light vehicle trips are associated with staff movements which occur
predominantly during the peak periods, equating to an average of 3 trips in each of the peak periods.
The trip generation volumes shown in Table 3.3 above represent the cycle-average or typical traffic volumes
that might arise on an average day in the production cycle while the chicks are being grown. However, it is
recognised that there are also peak traffic generating periods for the development associated with specific
activities such as bird placement at the beginning of the production cycle, live bird removal towards the end
of the cycle, and litter placement and removal which could potentially give rise to higher numbers of vehicle
movements, and in particular heavy vehicles, over those specific periods.
A more detailed examination of these peak activity periods is included later in Section 3.7, with the purpose
of testing the sensitivity of the results and conclusions drawn from using the cycle average trip generation
volumes which form the basis of the analysis in the following sections.
3.5 Future Design Year Volumes
A design horizon of 10 years from opening of the proposed development, which will be 2019 for The Ranch
Farm 5 development, has been adopted to assess the potential impacts of the development with respect to
any intersection upgrade requirements. Accordingly, a design year of 2029 has been adopted to determine
the future traffic volumes.
Average daily and peak hour background traffic volumes along Kidman Way obtained from the 2011 RMS
data, as discussed in Section 2.4.1, were factored up to 2029 using a linear growth rate of 1.5% per annum
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 33 of 66 pages Date 19/02/2016
FINAL
as discussed in Section 2.5. Existing background traffic volumes to/from Tysons Road were assumed to
remain unchanged. The peak and daily traffic volumes generated by The Ranch Farm 5 development, which
are summarised in Table 3.3 above, were superimposed with these volumes to provide the resulting future
design year volumes.
Figures 3.1 and 3.2 show the estimated daily traffic volumes and volumes at the peak generating times of
The Ranch Farm 5 development for the design year of 2029, including the counted volumes (with allowance
for future traffic growth) on Kidman Way. Some provision for traffic movements generated by the proposed
development arriving/departing from the north on Kidman Way has been included in the daily distribution,
however, as previously discussed the majority of traffic is expected to arrive/depart from/to the south.
Note that Figures 3.1 and 3.2 include traffic, in addition to The Ranch Farm 5 development traffic, generated
by The Ranch Farms 1 to 3, all of which will be operational prior to The Ranch Farm 5 becoming operational
as detailed in Section 1.1 (refer Section 4.1 for discussion of trip generation applicable to each of these
developments). They also include traffic generated by The Ranch Farm 4, which subject to approval would
also be operational prior to commencement of activities at The Ranch 5. These are necessary pre-requisites
to The Ranch Farm 5 development proceeding, since the new site access onto Tysons Road and the
internal access road between this site access and The Ranch Farm 1, as well as the internal access roads
between The Ranch Farms 1 and 2, The Ranch Farms 2 and 3, and The Ranch Farms 3 and 4 will all need
to have been constructed in accordance with the consent conditions for those developments first. As
previously stated, the DA and EIS for The Ranch Farm 5 seeks approval for the construction and use of the
additional section of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
Figure 3.1 Future (2029) peak hour traffic volumes on Kidman Way and Tysons Road, including estimated
traffic generated collectively by The Ranch Farms 1 to 3 (8 sheds each) and Farms 4 & 5 (16 sheds).
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 34 of 66 pages Date 19/02/2016
FINAL
Figure 3.2 Future (2029) daily traffic volumes on Kidman Way and Tysons Road, including estimated traffic
generated collectively by The Ranch Farms 1 to 3 (8 sheds each) and Farms 4 & 5 (16 sheds).
From Figures 3.1 and 3.2 it can be seen that the future traffic volumes, in terms of both background traffic
and traffic generated by the development, are very low even with the inclusion of traffic from the other
approved farms associated with The Ranch Poultry Production Complex. The resulting forecast traffic is
expected to be able to be easily accommodated by the surrounding road network.
A separate analysis of the cumulative traffic generated by all of the known developments in the area,
including full development of The Ranch Poultry Production Complex (i.e. all 5 farms) as well as other farms
recently approved or proposed, is provided in Section 4. The potential cumulative impacts arising from this
traffic is discussed in Section 7.6.
3.6 Heavy Vehicle Routes Servicing Development
Heavy vehicles will generally travel to and from the proposed development site from facilities in and around
Griffith and Hanwood (6km south of Griffith) on a daily basis.
Vehicles accessing facilities in Griffith will travel between the site and Griffith via Kidman Way and will then
be dispersed through the local road network. Similarly, delivery of day old chicks will occur in articulated or
rigid trucks via Kidman Way from a facility located approximately 3km west of Griffith.
Vehicles travelling to Hanwood will travel via Kidman Way south to Griffith, and then continue through Griffith
to Hanwood via Kidman Way. The reverse will occur when travelling from Hanwood to the development site.
Figure 3.3 shows the existing heavy vehicle route through Griffith via Kookora Street and Willandra Avenue.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 35 of 66 pages Date 19/02/2016
FINAL
Figure 3.3 – Heavy vehicle route through Griffith
Kidman Way is currently designated as a B-Double route. It is also an approved Road Train Route. As
discussed in Section 2.4.2, the daily volumes along this route are currently low, ranging between
approximately 1,000veh/day and 6,000veh/day depending on the location which includes approximately 200
to 300 heavy vehicles. The additional 22 heavy vehicle trips per day (1 in each of the peak hours for the
development) generated by The Ranch Farm 5 development along Kidman Way is not expected to have any
significant traffic impact, with the route having adequate facilities to accommodate the heavy vehicles
generated by the proposed development.
While the current assessment of traffic volumes generated by the development is based on the assumption
that the largest vehicles servicing the development will be semi-trailers, it is possible that future contractors
may use B-Doubles. The current heavy vehicle route servicing the development is suitable for this purpose.
3.7 Peak Activity Traffic Generation
Condition 34d) of DA 2016/022 and Condition 34e) of DA 2016/023 required the consideration of cumulative
peak traffic generation resulting from The Ranch Poultry Production Complex. This section has been
included, along with further analysis in Sections 5.1 and 7.6, to assess cumulative peak traffic resulting from
The Ranch Farms 1 to 5, and to identify operational measures to mitigate impacts, if necessary.
As previously discussed in Section 3.5, the trip generation volumes shown in Table 3.3 previously represent
the cycle-average or typical traffic volumes that might arise on an average day in the production cycle while
the chicks are being grown. However, there are also peak traffic generating periods for the development
associated with specific activities such as bird placement at the beginning of the production cycle, live bird
removal towards the end of the cycle, and litter placement and removal which could potentially give rise to
higher numbers of vehicle movements, and in particular heavy vehicles, over those specific periods.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 36 of 66 pages Date 19/02/2016
FINAL
An assessment of the peak activities during the production cycle has therefore been undertaken based on
additional data provided by Baiada/SLR for a 16-shed farm (i.e. The Ranch Farm 5). The resulting daily
traffic generation profile across the full 63 day production cycle is illustrated in Figure 3.4 below.
Figure 3.4 – Daily Traffic Flow Profile for The Ranch Farm 5
It is noted that the total vehicle movements over the course of the 63 day production cycle illustrated in
Figure 3.4 equate to the total trip generation of 876 vehicles per production cycle (1752 trips) provided
previously in Table 3.2.
As can be seen from Figure 3.4, the peak activity periods for The Ranch Farm 5 are associated with live bird
removal (peak traffic generation of 82 vehicles per day = 164 trips per day) on Day 54 of the production
cycle, and litter removal/shed cleanout (peak traffic generation of 85 vehicles per day = 170 trips per day) on
Day 57 of the production cycle. While these peak activity traffic volumes are similar to each other, the live
bird collection activities are skewed towards the night/early morning when conditions are cooler, while the
litter removal/shed cleanout activities are expected to be concentrated around daylight hours (say 7am to
7pm).
From a traffic operations/capacity perspective with respect to the adjoining state highway road network, the
peak daytime activities associated with the litter removal / shed cleanout represent the worst case. Assuming
a uniform distribution of traffic arrivals and departures from The Ranch Farm 5 development over the 12 hour
period from 7am to 7pm, the peak activity volume of 85 vehicles per day (170 trips per day) approximates to
7 vehicles per hour (14 trips per hour). These values compare to the 15 vehicles per day (30 trips per day)
and 4 trips in each of the AM and PM peak hours derived using the cycle average volumes (refer Table 3.3).
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 37 of 66 pages Date 19/02/2016
FINAL
By contrast, live bird removal is scheduled to occur between 7pm one day and 4pm the following day,
although for reasons of livestock welfare they would generally be removed overnight and in the morning
when it is cooler and the birds are more settled. Assuming 80% of the trips occur during 7pm to 9am and
the remaining 20% between 9am and 4pm, the peak activity volume of 82 vehicles per day (164 trips per
day) approximates to a maximum hourly volume of 5 vehicles per hour (10 trips per hour) during 7pm-9am
(when traffic volumes on the adjacent road network are for the majority of that period quite low) and only 3
vehicles per hour (6 trips per hour) during 9am-4pm. As can be seen, the additional trips in both periods are
lower than predicted to occur during the litter removal / shed cleanout phase.
It can be seen from the above assessments that while the daily peak activity volumes for both the live bird
removal phase and also the litter removal / shed cleanout phase are considerably higher than the cycle-
average volumes, the increase in hourly traffic volumes is relatively modest in both cases and is not
expected to result in any significant changes to the conclusions drawn based on using cycle-average
volumes.
However, as discussed in Section 5.1, a sensitivity test using the predicted peak activity traffic volumes for
litter removal / shed cleanout (i.e. the worst case scenario) has been used to confirm that the intersection
arrangements currently proposed at the Kidman Way / Tysons Road intersection in accordance with the
consent conditions for DA 2016/017 (i.e. The Ranch Farm 1) will continue to perform acceptably during
periods of peak activity associated with The Ranch Farm 5 development.
An assessment of the cumulative impacts arising from all of the approved/proposed developments known in
the study area has also been undertaken in conjunction with the worst case peak activity volumes for The
Ranch Farm 5, as discussed in Section 7.6.
It is important to note that only one peak activity is expected to arise at any given time from ANY of The
Ranch farms. This reflects practical constraints in relation to the physical resources that are at Baiada’s
disposal, which means that it is unable to undertake the peak traffic generating activities described above at
more than one location at a time.
For the purposes of this TIA it is also assumed that peak activities arising from other farms in the study area
(e.g. the Tabbita Lane, Maylands or Jeanella/Jeanella South farms) do not coincide with the peak activity
periods for The Ranch Farm 5. The daily traffic profile and peak activity periods for these other
developments are unknown. Furthermore, given that The Ranch Farm 5 production cycle extends over 63
days it seems unlikely that there would be many occurrences of peak activities overlapping, and on those
occasions when this might occur there is still considerable spare capacity available on the adjoining State
Highway network to accommodate short term fluctuations in traffic flow. This is discussed further in Section
5.1.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 38 of 66 pages Date 19/02/2016
FINAL
4. OTHER DEVELOPMENTS IN THE STUDY AREA
4.1 The Ranch Poultry Production Complex
As previously discussed in Section 1.1, The Ranch Farm 5 represents one of five separate farms being
proposed for development in the study area as part of The Ranch Poultry Production Complex. The Ranch
Farms 1 to 3 have already been approved for the development of 8 sheds each, and development consent
is now being sought for two more poultry farms, being The Ranch Farm 4 (the subject of a separate
development consent) and The Ranch Farm 5 (the subject of this TIA), which it is proposed will each have
16 sheds. Each of The Ranch Farms 4 and 5 will be the subject of a separate development application (DA)
and a separate Environmental Impact Statement (EIS) to be lodged with Council. The applications for The
Ranch Farm 4 and The Ranch Farm 5 are expected to be lodged concurrently in February 2016.
The locations of the five farms were previously shown in Figure 1.2. All five farms will be accessed via the
same internal site access road connection onto Tysons Road as previously discussed, which in turn will be
accessed exclusively from the intersection of Kidman Way and Tysons Road. Development approvals for
proposed upgrades at the Kidman Way / Tysons Road intersection, the new site entrance onto Tysons Road
and the internal access road to The Ranch Farm 1 were previously sought and granted as part of the DA
(DA 2016/017) and associated EIS prepared and lodged for The Ranch Farm 1 development. Similarly,
development approvals for the construction and operation of the additional sections of internal access road
between The Ranch Farm 1 and The Ranch Farm 2, and between The Ranch Farm 2 and The Ranch Farm
3, were sought and granted as part of DA 2016/022 for The Ranch Farm 2 and DA 2016/023 for The Ranch
Farm 3 respectively.
The application for The Ranch Farm 5 is predicated on The Ranch Farm 4 being approved and developed
first, since that development will provide the section of internal access road between The Ranch Farm 3 and
The Ranch Farm 4. The DA and EIS for The Ranch Farm 5 seek approval for the construction and use of the
additional section of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
It is proposed that each farm at The Ranch Poultry Production Complex will be constructed consecutively,
with indicative timeframes for the commencement of construction and operational activities at the five farms
(subject to obtaining the relevant approvals) as follows:
The Ranch Farm 1 – 8 sheds (approved) – commence construction: January 2016
– commence operation: July 2016
The Ranch Farm 2 – 8 sheds (approved) – commence construction: July 2016
– commence operation: January 2017
The Ranch Farm 3 – 8 sheds (approved) – commence construction: January 2017
– commence operation: July 2017
The Ranch Farm 4 – 16 sheds (proposed) – commence construction: July 2017
– commence operation: July 2018
The Ranch Farm 5 – 16 sheds (proposed) – commence construction: July 2018
– commence operation: July 2019
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 39 of 66 pages Date 19/02/2016
FINAL
In addition to the above, it is understood that further expansions to The Ranch Farms 1 to 3 are proposed to
be made in the future which if approved would see the size of each of these farms increase from the
currently approved capacity of 8 sheds up to 16 sheds each, making them the same size as proposed for
The Ranch Farms 4 and 5. Separate Development Briefing Papers for the expansion of each of these farms
were lodged with the Department of Planning and Environment (DP&E) on Monday 4 January 2016 to seek
the preparation of appropriately targeted Secretary’s Environmental Assessment Requirements (SEARs) for
each of the developments. At this stage it is proposed that the expansions to these farms will not occur until
all of the farms have been constructed in accordance with the above timetable. On this basis, the earliest
timing for the proposed Farm 1 to 3 Expansions would be as follows:
The Ranch Farm 1 Expansion – additional 8 sheds – commence construction: July 2019
– commence operation: January 2020
The Ranch Farm 2 Expansion – additional 8 sheds – commence construction: January 2020
– commence operation: July 2020
The Ranch Farm 3 Expansion – additional 8 sheds – commence construction: July 2020
– commence operation: January 2021
Taking the above into account, if all of the proposed developments are approved then ultimately each of the
five farms that comprise The Ranch Poultry Production Complex will be of the same size (i.e. 16 poultry
sheds, each with a maximum shed population of 50,000 birds resulting in a maximum farm population of
800,000 birds) and will have the same operational characteristics.
The traffic generation associated with each of the farms will therefore ultimately, once approved, be the
same as shown previously in Table 3.3 for The Ranch Farm 5. The total traffic generation arising from the
five farms collectively when fully developed (i.e. 16 sheds each) is summarised in Table 4.1. Note that these
volumes are cycle-average volumes.
Vehicle Type Vehicles Per Day
(Vehicle Trips)
AM Peak Hour
Movements
PM Peak Hour
Movements
Cars (LV) 20 (40) 15 (10 in, 5 out) 15 (5 in, 10 out)
Heavy Vehicles 55 (110) 5 (5 in, 0 out) 5 (0 in, 5 out)
Total 75 (150) 20 (15 in, 5 out) 20 (5 in, 15 out)
Table 4.1 – Traffic Generation per Day and in each Peak Hour for The Ranch Poultry Production
Complex (i.e. all five farms collectively comprising of 16 sheds each)
It should be noted that the volumes in the above table are different to those previously shown at the site
entrance on Figures 3.1 and 3.2, since the volumes shown on those figures include only the trip generation
associated with The Ranch Farm 5 plus what is currently approved for development (i.e. 8 sheds at each of
The Ranch Farms 1 to 3) or expected to be developed subject to approval (i.e. 16 sheds at The Ranch Farm
4), all of which would be operational prior to The Ranch Farm 4 development proceeding. The volumes in
the above table are provided for the purpose of assessing the cumulative impacts of all of the known
developments (approved and proposed) in the study area should they proceed (of which The Ranch Poultry
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 40 of 66 pages Date 19/02/2016
FINAL
Production Complex in its fully developed form comprises a part), rather than just the impacts arising from
the proposed development (i.e. The Ranch Farm 5) in isolation to which Figures 3.1 and 3.2 refer. An
assessment of both the individual and cumulative impacts of the subject development(s) is provided in
Section 5 and Section 7.6.
Details of other developments in the study area which are also relevant to the cumulative impact
assessment are provided in the following section.
4.2 Other Developments
In addition to The Ranch Poultry Production Complex, at the time of writing this report the following
developments had either been constructed or recently approved, or had been proposed (i.e. SEARS
requested/issued):
Jeanella Poultry Production Complex (ProTen Holdings P/L) - approved by Council in 2012 and
constructed in 2013. This site is operational and is located on the northern side of the Mid-Western
Highway, approximately 6km south-west of Goolgowi. It is accessed directly from the Mid-Western
Highway and comprises of 24 poultry sheds accommodating up to 1,284,000 birds. It’s
commencement of operations post-dates the most recent period for which RMS was able to provide
traffic data on Kidman Way (i.e. 2011, as previously discussed) and its traffic generation therefore
needs to be included when considering the potential cumulative impacts of the proposed
development with other known developments in the study area.
Jeanella South Poultry Production Complex (ProTen Holdings P/L) – approved by Council in
October 2015. It is located on the southern side of the Mid-Western Highway, approximately 7.5km
south-west of Goolgowi and 1.5km south of the existing Jeanella Poultry Production Complex.
Access to the development once operational will be provided from Merrondale Lane onto the Mid-
Western Highway, west of the existing access to the Jeanella Poultry Production Complex. The
development proposal comprises of 16 poultry sheds able to accommodate up to 856,000 birds.
Maylands Farm A (Lemic Holdings P/L) – approved by Council in August 2015. It is located on the
southern side of the Mid-Western Highway, approximately 7km north-east of Goolgowi. Access to
the development once operational will be provided from Youngs Lane onto the Mid-Western
Highway. The development will comprise 24 poultry sheds able to accommodate up to 1,360,800
birds.
Maylands Farm B (Lemic Holdings P/L) – approved by Council in December 2015. It is located on
the southern side of the Mid-Western Highway, approximately 8km north-east of Goolgowi on an
adjoining lot to Maylands Farm A. Access to the development once operational will be provided
from Youngs Lane onto the Mid-Western Highway. The development will comprise 24 poultry sheds
able to accommodate up to 1,360,800 birds.
Tabbita Poultry Farm 1 (NMS Enterprises P/L) – approved by Council in August 2015. It is located
on the northern side of Tabbita Lane to the west of its intersection with Kidman Way at Tabbita,
approximately 8km south-east of Goolgowi. Access to the development once operational will be
provided via Tabbita Lane and Kidman Way. The development proposal comprises of 20 poultry
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 41 of 66 pages Date 19/02/2016
FINAL
sheds able to accommodate up to 51,000 birds each, equating to a maximum population of
approximately 1,020,000 birds.
Tabbita Poultry Farm 2 (NMS Enterprises P/L) – approved by Council in September 2015, this
development is located on an adjoining lot to Tabbita Poultry Farm 1. It is located on the northern
side of Tabbita Lane to the west of its intersection with Kidman Way at Tabbita, approximately 8km
south-east of Goolgowi. Access to the development once operational will be provided via Tabbita
Lane and Kidman Way. The development proposal comprises of 20 poultry sheds able to
accommodate up to 51,000 birds each, equating to a maximum population of approximately
1,020,000 birds.
Tabbita Poultry Farm 3 (NMS Enterprises P/L) - approved by Council in December 2015, this
development is located on an adjoining lot to Tabbita Poultry Farms 1 and 2 on the northern side of
Tabbita Lane to the west of its intersection with Kidman Way at Tabbita, approximately 8km south-
east of Goolgowi. Access to the development once operational will be provided via Tabbita Lane
and Kidman Way. The development proposal comprises of 20 poultry sheds able to accommodate
up to 51,000 birds each, equating to a maximum population of approximately 1,020,000 birds.
Tabbita Poultry Farm 4 (NMS Enterprises P/L) – a Development Briefing Paper and request for
SEARs has been submitted to the DP&E for this proposed development. It is located on an
adjoining lot to Tabbita Poultry Farms 1, 2 and 3 on the northern side of Tabbita Lane to the west of
its intersection with Kidman Way at Tabbita, approximately 8km south-east of Goolgowi. Access to
the development once operational will be provided via Tabbita Lane and Kidman Way. The
development proposal comprises of 20 poultry sheds able to accommodate up to 51,000 birds
each, equating to a maximum population of approximately 1,020,000 birds.
Each of these developments, including the developments associated with The Ranch Poultry Production
Complex, is/will be serviced by vehicles that collectively use common sections of roads within the study area
for the delivery and removal of the raw input materials and production outputs. Tysons Road, and Kidman
Way to the north and south of Tysons Road, are of particular interest to this study.
Estimates of the traffic generation for The Ranch Poultry Production Complex as a whole (i.e. all five farms
in their ultimate configuration of 16 sheds per farm) were developed in Table 4.1. An assessment of the
traffic generation for each of the other developments listed above was produced separately (in some cases
by other parties) as part of their traffic impact assessment reports and has been extracted from those reports
without change for the purposes of this assessment. Details of those reports (in italics) are as follows:
Jeanella Poultry Production Complex: Traffic Impact Assessment – Proposed Poultry Broiler
Production Complex, Goolgowi, NSW (RoadNet, May 2012)
Jeanella South Poultry Production Complex: Traffic Impact Assessment – Proposed Jeanella
South Poultry Production Complex at Mid-Western Highway, Goolgowi (RoadNet, 30 July 2015)
Maylands Farm A: Traffic Impact Assessment – Proposed Maylands Poultry Farm at Mid-Western
Highway, Goolgowi (RoadNet, 18 June 2015)
Maylands Farm B: Traffic Impact Assessment – Maylands Poultry Complex – Farm B at Mid-
Western Highway, Goolgowi (RoadNet, 19 October 2015)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 42 of 66 pages Date 19/02/2016
FINAL
Tabbita Poultry Farm 1: Proposed Poultry Farm Development, Tabbita Lane, Tabbita, Traffic and
Parking Assessment Report (Varga Traffic Planning Pty Ltd, June 2014)
Tabbita Poultry Farm 2: Proposed Poultry Farm Development, Farm 2, Tabbita Lane, Tabbita,
Traffic and Parking Assessment Report (Varga Traffic Planning Pty Ltd, July 2015)
Tabbita Poultry Farm 3: Proposed Poultry Farm Development, Farm 3, Tabbita Lane, Tabbita,
Traffic and Parking Assessment Report (Varga Traffic Planning Pty Ltd, September 2015)
In the case of the proposed Tabbita Poultry Farm 4, at the time of writing this report there was no traffic
report available for this development to confirm its traffic generation. However, based on our understanding
that it will be the same size as the other approved poultry farm developments at Tabbita Lane (i.e. Tabbita
Poultry Farms 1 to 3), it is assumed that it will generate the same volume of traffic as those developments.
The following table summarises the total projected traffic generated by each of the developments, including
the five farms that make up The Ranch Poultry Production Complex in their fully developed form, and the
corresponding volumes using common sections of Tysons Road and Kidman Way. The distribution of traffic
for the 5 farms that make up The Ranch Poultry Production Complex is the same as that adopted for The
Ranch Farm 5 (refer Figures 3.1 and 3.2). For the other developments, as an approximation for this
assessment it is assumed all movements have an origin or destination to the south (i.e. in and around
Griffith).
Development Site
Estimated Daily Traffic Generation (two-way) – veh/day
(Heavy Vehicle volume in brackets)
Total Generated
Traffic
On Tysons Road
(east of Kidman Way)
On Kidman Way
(north of Tysons Road)
On Kidman Way
(south of Tysons Road)
The Ranch Poultry Production
Complex – 5 farms
150 (110) 150 (110) 10 (0) 140 (110)
Jeanella Poultry
Production Complex (existing)
38 (26) - 38 (26) 38 (26)
Jeanella South Poultry Farm 26 (16) - 26 (16) 26 (16)
Maylands Farm A 38 (30) - 38 (30) 38 (30)
Maylands Farm B 38 (30) - 38 (30) 38 (30)
Tabbita Poultry Farm 1 44 (28) - 44 (28) 44 (28)
Tabbita Poultry Farm 2 44 (28) - 44 (28) 44 (28)
Tabbita Poultry Farm 3 44 (28) - 44 (28) 44 (28)
Tabbita Poultry Farm 4 44 (28) - 44 (28) 44 (28)
Cumulative Volume 150 (110) 326 (214) 456 (324)
Table 4.2 – Cumulative Traffic Generated by Known Developments in Study Area
Based on the above assessment the known developments collectively result in an additional 150 trips per
day on Tysons Road; 326 trips per day on Kidman Way to the north of Tysons Road (150 trips per day north
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 43 of 66 pages Date 19/02/2016
FINAL
of Tabbita Lane after removing trips generated by Tabbita Poultry Farms 1 to 4, which have an origin or
destination on Tabbita Lane); and 456 trips per day on Kidman Way to the south of Tysons Road.
The existing volumes of traffic currently using these roads are low as previously discussed in Section 2.4.1
and the additional traffic generated by these developments is not expected to have any significant impact on
the operation of these roads. An assessment of the cumulative impacts of the developments is provided in
Section 7.6.
It should be noted that the volumes presented in Table 4.2 are the estimated cumulative average daily traffic
volumes on a typical day. In practice traffic volumes for each development will vary throughout their
production cycles, resulting in higher volumes on some days during periods of peak activity and lower
volumes at other times. However, it is not possible to assess those variations for all of the developments
since the required data simply isn’t available. It is also considered unlikely that each of the developments
shown in Table 4.2, which all have relatively long production cycles, would peak at the same time. This
reflects practical constraints in relation to the physical resources that are at Baiada’s disposal, which means
that it is unable to undertake the peak traffic generating activities described above at more than one location
at a time.
Taking the above into account, a sensitivity test which examines the cumulative impact arising from the
traffic generation presented in Table 4.2 above, but with the peak activity traffic generation for The Ranch
Farm 5 development (assessed in Section 3.7) used instead of its average traffic generation, has also been
examined as a worst case scenario. The results of that assessment are also presented in Section 7.6.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 44 of 66 pages Date 19/02/2016
FINAL
5. ACCESS REQUIREMENTS FOR THE PROPOSED DEVELOPMENT
5.1 Kidman Way / Tysons Road Intersection
Access to The Ranch Poultry Production Complex, which includes The Ranch Farm 5 development, is
proposed via an upgraded Kidman Way / Tysons Road intersection and a new access road connecting to
Tysons Road approximately 1km further to the east.
The proposed access road is sufficiently removed from the State Highway road network to allow adequate
room for traffic generated by The Ranch Farm 5 development and also The Ranch Poultry Production
Complex as a whole to manoeuvre or queue on the side road without impacting on Highway traffic.
The distance available between the existing railway level crossing on Tysons Road and Kidman Way
(approximately 150m) is also concluded to be adequate to safely accommodate any queuing that might
occur. The proposed development will generate just 30 trips per day on average including 22 heavy vehicle
movements, and 4 trips (1 heavy vehicle) during the development peak hours. The corresponding volumes
for The Ranch Poultry Production Complex (i.e. the 5 farms combined at full development = 16 sheds per
farm) are 150 trips per day on average including 110 heavy vehicle movements, and 20 trips (5 heavy
vehicles) during each of the development peaks. These volumes are still very low and, given the low
background traffic volumes currently occurring on Tysons Road and the low traffic volumes predicted to
occur on Kidman Way near Tysons Road in the future, they are not expected to cause any significant
operational issues (delays or queuing) at the Kidman Way / Tysons Road intersection.
An assessment of the intersection layout requirements at the Kidman Way / Tysons Road intersection to
accommodate the traffic collectively generated by The Ranch Farms 1, 2 and 3 was previously undertaken
as part of the TIA produced for the Ranch Farm 1 development (Traffic Impact Assessment – The Ranch
Poultry Production Complex – Farm 1 at Tysons Road (nr Kidman Way), Tabbita, NSW (RoadNet, 18
September 2015). The analysis was undertaken for a future design year of 2026 (the 10 year design horizon
for The Ranch Farm 1) and concluded that a BAL / BAR intersection layout (i.e. incorporating a basic left
turn treatment and a basic right turn treatment) would be suitable to accommodate the projected traffic
volumes arising from those 3 farms. The Ranch Farms 1 to 3 were subsequently approved by Council, with
the consent conditions for DA 2016/017 (i.e. The Ranch Farm 1) specifying the requirements at the Kidman
Way / Tysons Road intersection (refer Section 1.1.1 for details).
Since that time two additional farms (The Ranch Farms 4 and 5) have been proposed as part of The Ranch
Poultry Production Complex, as well as future expansions to The Ranch Farms 1 to 3 to increase their
capacity from 8 sheds per farm to 16 sheds per farm. Other poultry farms have also been approved or
proposed in the study area, including Maylands Farm B (approved) and Tabbita Poultry Farm 4 (proposed).
As a result of these changes, a further assessment of the requirements at the Kidman Way / Tysons Road is
considered to be appropriate to ensure that it can continue to service all of the future known developments in
the area.
The requirements for the layout of the Kidman Way / Tysons Road intersection have been re-assessed
using intersection warrants prescribed in Austroads Guide to Road Design, Part 4A: Unsignalised and
Signalised Intersections (AGRD Part 4A). The assessment has been based on peak hour traffic volume
forecasts for The Ranch Farm 5 design year of 2029 for the following scenarios:
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 45 of 66 pages Date 19/02/2016
FINAL
1) The Ranch Farm 5 development considered in ‘isolation’ - note that this scenario is based on the
future peak hour traffic volumes shown previously in Figure 3.1, which still assumes the Ranch
Farms 1 to 3 (8 sheds each) and The Ranch Farm 4 (16 sheds) are operational by the time The
Ranch Farm 5 development proceeds, and therefore generating traffic at this intersection in
addition to The Ranch Farm 5 development;
2) The Ranch Poultry Production Complex (i.e. the 5 farms collectively at full capacity of 16 sheds per
farm);
3) Total Cumulative Traffic - this scenario includes the traffic generated by other known developments
(approved or proposed) in the study area which will travel along Kidman Way through the subject
intersection, in addition to the traffic generated by the 5 farms at The Ranch Poultry Production
Complex. Peak hour volumes for the ‘other developments’ for this assessment (i.e. the farms that
are not part of The Ranch Poultry Production Complex) were assumed to be 10% of the predicted
daily trip generation shown in Table 4.2;
4) Total Cumulative Traffic including Peak Activity Traffic for The Ranch Farm 5 – this scenario is
similar to Scenario 3 above, but replaces the cycle-average traffic volumes for The Ranch Farm 5
with the peak activity traffic volumes associated with litter removal / shed cleanout as detailed in
Section 3.7. It is included as a sensitivity test to check that the proposed intersection arrangements
will continue to perform acceptably during periods of peak activity associated with The Ranch Farm
5 development.
The results are illustrated in Figure 5.1 below, with the red dots showing the left turn requirements for each
scenario, and the blue dots the right turn requirements (scenario nos. 1 - 4 are also annotated).
Figure 5.1: 2029 Access Turn Warrants (Extracted from Figure 4.9 from Austroads Guide to Road
Design, Part 4A: Unsignalised and Signalised Intersections)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 46 of 66 pages Date 19/02/2016
FINAL
Figure 5.1 indicates that under all of the scenarios considered, including the worst case scenario (Scenario
4) in which all of the cumulative traffic from other known developments in the study area is superimposed
with full development of The Ranch Poultry Production Complex AND peak activity traffic volumes for The
Ranch Farm 5, the layout required at the Kidman Way / Tysons Road intersection remains that of a basic
right turn treatment (BAR) and a basic left turn treatment (BAL). This is the minimum intersection
requirement indicated in AGRD Part 4A, and would typically be applied to any new intersection constructed
on the State-controlled road network.
Figure 5.1 also shows that there is still room for the major road hourly traffic volume to increase by a further
50% on the worst case (Scenario 4) levels before a higher level of intersection treatment would be required,
thereby indicating that the proposed layout provides considerable spare capacity to accommodate short term
fluctuations in traffic flow.
The results of the analysis confirm that the BAL / BAR intersection arrangements currently proposed for
implementation at the Kidman Way / Tysons Road intersection in accordance with the consent conditions for
DA 2016/017 (i.e. The Ranch Farm 1) will continue to perform acceptably in the future during periods of peak
activity associated with The Ranch Farm 5 development, even after allowing for traffic generated by all of the
other known developments in the study area including The Ranch Poultry Production Complex at full
development. Specific operational measures to mitigate the cumulative impacts of the developments during
periods of peak activity are therefore considered to be unnecessary.
The development application for The Ranch Farm 5 is predicated on the assumption that any upgrades
require to be made to the Kidman Way / Tysons Road intersection will be implemented as part of The Ranch
Farm 1 development, prior to The Ranch Farm 5 development proceeding. As previously indicated, the DA
and EIS for The Ranch Farm 5 seek approval for the construction and use of the additional section of
internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
Based on the above, the currently proposed intersection upgrades at the Kidman Way / Tysons Road
intersection are suitable to accommodate The Ranch Farm 5 development proposal.
5.2 Access Road and Driveway to Development
Access to The Ranch Poultry Production Complex, which includes The Ranch Farm 5 development, is
proposed via a new internal access road connecting to Tysons Road approximately 1km east of the existing
Kidman Way / Tysons Road intersection. The exact location of the access road will be subject to detailed
design, but the indicative location is shown on the plans in Appendix A.
The section of Tysons Road adjacent to where the proposed access road will connect is currently unsealed.
Traffic entering and exiting The Ranch Farm 5 development site from/to Kidman Way would be required to
travel along approximately 750m of unsealed road, with only the first 285m (approx.) of Tysons Road sealed
from its intersection with Kidman Way. The unsealed section of road in question was observed from the site
visit conducted to be in good condition, and of a width suitable to enable large heavy vehicles up to the size
of B-Doubles to safely pass each other. For these reasons Tysons Road in its current form was considered
to be suitable for the scale of development previously proposed at The Ranch Poultry Production Complex
(i.e. Farms 1 to 3). Apart from regular maintenance, no additional upgrades were therefore proposed in the
TIAs prepared for those developments.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 47 of 66 pages Date 19/02/2016
FINAL
However, as part of the consent conditions for The Ranch Farm 1, Council determined that Tysons Road
was to be upgraded from the end of the sealed section to the access gate of The Ranch Poultry Production
Complex “…with a finished 150mm gravel road-base at 6m wide and with a cross fall of 3%...”
With the addition of The Ranch Farms 4 and 5 to The Ranch Poultry Production Complex, and with the
future proposed expansion of The Ranch Farms 1 to 3 from 8 sheds to 16 sheds each, it is considered that
the potential impacts arising from the additional truck movements in terms of road deterioration and dust
generation warrant the provision of additional measures. As part of the development application for The
Ranch Farm 4 it has therefore been recommended that the unsealed section of Tysons Road between
Kidman Way and the proposed site access to The Ranch Poultry Production Complex (approx. 750m in
length), which will already have been upgraded in accordance with the consent conditions for The Ranch
Farm 1, be sealed prior to commencement of operations at The Ranch Farm 4 site.
Since it is intended that The Ranch Farm 4 will be operational before The Ranch Farm 5, this means that the
full length of Tysons Road between Kidman Way and the site access to The Ranch Poultry Production
Complex will be sealed prior to The Ranch Farm 5 development proceeding.
Development approvals for the new site entrance onto Tysons Road and the internal access road to The
Ranch Farm 1 were previously sought and granted as part of the DA (DA 2016/017) and associated EIS
prepared and lodged for that development. The consent conditions for that development specify the internal
access road and driveway requirements. No further assessment of the proposed site access driveway onto
Tysons Road is therefore required as part of this TIA.
Similarly, development approvals for the construction and operation of the additional sections of internal
access road between The Ranch Farm 1 and The Ranch Farm 2, and between The Ranch Farm 2 and The
Ranch Farm 3, were sought and granted (with associated consent conditions) as part of DA 2016/022 and
DA 2016/023 respectively. Approval for the construction and operation of the additional section of internal
access road between The Ranch Farm 3 and The Ranch Farm 4 has also been sought as part of the
application being lodged concurrently for The Ranch Farm 4.
The DA and EIS for The Ranch Farm 5 seek approval for the construction and use of the additional section
of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only. The internal access
requirements for The Ranch Farm 5 are discussed in the next section.
5.3 Internal Access Requirements
The anticipated internal access arrangements, as shown on the layout plan in Appendix A, will provide
adequate and suitable vehicular access to the proposed poultry sheds via the construction of new all-
weather crossovers and rural-type roads able to carry the anticipated heavy vehicle traffic.
The development will include a one-way system to enable traffic to enter, exit and manoeuvre around the
poultry sheds for loading, unloading and servicing activities in a forward direction, thereby minimising the
potential for traffic conflict and noise. The one-way system will connect directly to the internal 4m wide site
access road with passing bays providing access from the site onto Tysons Road.
The internal roads will be constructed to a suitable strength and width to accommodate the expected heavy
vehicles. Parking will be available adjacent to the sheds to accommodate staff and visitor movements.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 48 of 66 pages Date 19/02/2016
FINAL
6. CONSTRUCTION STAGING AND TRAFFIC
While construction planning details are still in the early stages for this development, the information in this
section seeks to provide a broad outline of the proposed construction activities and timing. A rough estimate
of the traffic volumes associated with the most intensive of the construction activities is also provided.
It is proposed that the five farms comprising The Ranch Poultry Production Complex will be constructed
consecutively, with indicative timeframes for the commencement of construction and operational activities at
each of the farms (subject to obtaining the relevant approvals) as follows:
The Ranch Farm 1 – 8 sheds (approved) – commence construction: January 2016
– commence operation: July 2016
The Ranch Farm 2 – 8 sheds (approved) – commence construction: July 2016
– commence operation: January 2017
The Ranch Farm 3 – 8 sheds (approved) – commence construction: January 2017
– commence operation: July 2017
The Ranch Farm 4 – 16 sheds (proposed) – commence construction: July 2017
– commence operation: July 2018
The Ranch Farm 5 – 16 sheds (proposed) – commence construction: July 2018
– commence operation: July 2019
The proposed expansions for Farms 1 to 3 discussed in previous sections of this report, subject to approval,
would not proceed until the above activities have been completed.
The Ranch Farm 5 development, which comprises of 16 poultry sheds and support infrastructure, is
expected to take about 12 months to construct and would commence operation in 2019 based on the above
schedule.
Access to the site during the construction stage will be provided via Kidman Way and Tysons Road, with the
proposed internal site access road extension between The Ranch Farm 4 and The Ranch Farm 5 (see
Section 5.2) to be constructed at commencement of the construction phase. This will connect to the sections
of new internal access road to be constructed in accordance with the recent development approvals granted
for The Ranch Farms 1 to 3, and pending approval for The Ranch Farm 4, as well as to the new site access
driveway onto Tysons Road to be constructed as part of The Ranch Farm 1 development, all of which will be
completed prior to commencement of construction activities for The Ranch Farm 5.
All construction-related traffic (including light vehicles associated with construction workers) will park within
the site during the construction phase.
The first stage of construction will comprise of undertaking the site earthworks, for which heavy earthmoving
equipment will need to be brought onto site. Once the earthmoving equipment is on site, workers will come
to and from the site daily.
Following substantial completion of the earthworks, construction of the poultry sheds will commence. Each
of the sheds will be 176m long x 18m wide (i.e. they will have an area of 3,168m2) and will be made up of
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 49 of 66 pages Date 19/02/2016
FINAL
concrete flooring, a fabricated structural steel framework, zincalume corrugated iron roof sheeting, and
insulated sandwich panel walls with a non-reflective colour-bond type material.
The concrete floor slab will be 100mm thick and will be poured over a duration of approximately 2 days for
each shed. It is proposed that the concrete will be transported to the site in ready mix batches.
Other building materials will generally be delivered on semi- trailers and in shipping containers over longer
periods of time and potentially throughout the duration of the construction period. At this stage no information
on quantities is available.
Equipment required for the fit-out of each shed will generally be delivered in shipping containers over a
period of a couple of weeks and stored on site until needed.
Given the limited information available on quantities at this stage it is not possible to accurately determine
the construction traffic volumes. However, the most intensive construction activity in terms of truck
movements to and from the site is expected to be associated with concrete deliveries.
Assuming an average quantity of 6m3 per concrete truck (typical) and a total volume of 3,168m2 x 100mm
depth = 317m3 of concrete required per shed, this equates to a total of 53 truckloads per shed (i.e. 106 trips
in/out). To complete a slab pour in 2 days would therefore require a total of approximately 53 trips per day
or approximately 5 trips per hour (average 2.5 in / 2.5 out) assuming a 10hr working day.
This level of activity would only arise during the slab pours. Apart from this there would be the odd truck
delivering other materials throughout the course of a typical day and a small number of light vehicle trips,
mostly concentrated around the construction shift start and end times, associated with construction workers.
Overall, it is concluded that the construction activities will generate only low traffic volumes, possibly in the
order of approximately 10-15 trips per day for The Ranch Farm 5 development excluding concrete deliveries,
and will occur for a duration of approximately 12 months. While higher volumes of traffic will occur during
the concrete pours, adding an additional 5 trips per hour on average, these will be concentrated over a
shorter period averaging 2 days per shed and will be able to be easily accommodated on the adjoining road
network.
The impacts arising from construction traffic are therefore expected to be low, and any mitigation treatments
identified in the previous TIAs produced for The Ranch Farm 1, The Ranch Farm 2, The Ranch Farm 3 and
The Ranch Farm 4 developments, or in this report, to address the operational traffic impacts of the
developments are expected to be sufficient to also address the construction traffic impacts.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 50 of 66 pages Date 19/02/2016
FINAL
7. IMPACTS ON ADJOINING ROAD NETWORK
7.1 Kidman Way
The additional traffic generated by the development proposal is minimal and will not have any significant
impact on the safety or operation of the external road network. The Ranch Farm 5 development is expected
to generate up to 30 vehicle trips per day on average, including 22 heavy vehicle trips per day (approx 1 per
peak hour) and 8 car trips per day (approx 3 per peak hour). The majority of this traffic is predicted to use the
section of Kidman Way to the south of Tysons Road, with only a very small volume of traffic generated by
the development predicted to use Kidman Way to the north of Tysons Road.
The forecast background traffic volumes on Kidman Way are low and the additional traffic generated by the
development can be easily accommodated.
The following table shows the future forecast daily background traffic volumes in 2029 along the section of
Kidman Way immediately to the south of Tysons Road, and the additional traffic generated by this
development proposal. The table excludes traffic generated by other developments that either currently
exist in the area, such as the Jeanella Poultry Production Complex, or which are proposed/approved
(including the other farms proposed as part of The Ranch Poultry Production Complex, Jeanella South
Poultry Farm, Maylands Farms A and B, and Tabbita Poultry Farms 1, 2, 3 and 4) as previously discussed in
Section 4. A separate discussion on the cumulative impacts of the proposed development with other
developments in the area is provided in Section 7.6.
Future Forecast Traffic Volumes on Kidman Way south of Tysons Road (2029)
Background Traffic
Vehicle Trips Per Day
Additional Generated Traffic
Vehicle Trips Per Day* Percentage Increase
Cars HVs Total Cars HVs Total Cars HVs Total
1013 251 1264 6 22 28 <1% 8.8% 2.2%
*excludes minor volume of traffic generated to/from Kidman Way north of Tysons Road
Table 7.1 – Percentage Increase in Vehicle Trips on External Road Network from The Ranch Farm 5
Car trips on Kidman Way immediately to the south of Tysons Road are expected to increase, on an average
day, by less than 1% with the proposed development, with most of these occurring around the start and end
of the farm workers shift (i.e. 7am and 4pm). The increase for heavy vehicles is a bit higher at 8.8%,
however, this is due to the relatively low volume of heavy vehicles in the background traffic. The increase in
heavy vehicles as a result of the proposed development is still only approximately 1 veh/hr during the peak
periods.
The volume of background traffic on Kidman Way is higher at locations closer to Griffith as discussed in
Section 2.4.2. The percentage increase in traffic arising from The Ranch Farm 5 development will therefore
be even less at those locations.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 51 of 66 pages Date 19/02/2016
FINAL
The above assessment is based on average daily traffic volumes over the production cycle. As discussed in
Section 3.7, it is recognised that there are also peak traffic generating periods for the development
associated with specific activities which could potentially give rise to higher numbers of vehicle movements,
and in particular heavy vehicles, over those specific periods. An assessment of peak activities during the
production cycle indicates that the litter removal / shed cleanout phase represents the worst case from a
potential traffic impact perspective, with a peak traffic generation of 85 vehicles per day (170 trips per day)
estimated on Day 57 of the production cycle. The composition of these trips is approximately 140 heavy
vehicle trips per day and 30 car trips per day.
Comparison of these peak activity volumes to the background volumes in Table 7.1 (i.e. assuming all peak
activity traffic has an origin/destination from/to the south as an approximation) indicates percentage
increases of 3% for cars, 56% for heavy vehicles and 13% for all vehicles combined. As expected the
biggest increase in traffic during the peak activity period is associated with the additional heavy vehicles,
which would increase from 251 trips/day to 391 trips/day. However, the resulting volume of heavy vehicles
is still very low, equating to an average of 5-10 trips per hour each way, which can easily be accommodated
on Kidman Way.
Overall, it is concluded that the additional trips generated by the proposed development are low and are not
expected to have any operational impacts on the external road network. Kidman Way is easily able to
accommodate the additional traffic generated by the proposal.
7.2 Heavy Vehicle Routes used by Development
As discussed in Section 3.6, heavy vehicles will generally travel to and from the site from facilities located in
and around Hanwood (6km south of Griffith) and Griffith via Kidman Way. The largest vehicles currently
expected to service the development are semi-trailers, however, it is possible that future contractors may
choose to use B-Doubles.
A designated B-double route currently exists along Kidman Way. Kidman Way is also an approved Road
Train Route. The daily volume of traffic along Kidman Way is currently low, ranging from approximately
1,000 veh/day in the vicinity of Tabbita (i.e. near the proposed development site) to between approximately
3,000 and 6,000 veh/day within the immediately vicinity of Griffith depending on the location. Corresponding
numbers of heavy vehicles range from approximately 200 to 300 veh/day based on the available data.
The additional 22 heavy vehicle trips per day on average (1 in each of the peak hours for the development)
along Kidman Way associated with The Ranch Farm 5 development proposal are not expected to have any
significant traffic impacts. Furthermore, even in the worst case during the litter removal / shed cleanout
phase, the corresponding peak activity trip generation of 140 heavy vehicle trips per day can be readily
accommodated on Kidman Way as discussed in the previous section and will only occur over a relatively
short period.
It is concluded that the routes that will be used by the development are suitable for the types of vehicle
movements that will be generated and have sufficient facilities to accommodate the additional heavy
vehicles generated by the proposal. No upgrades to roadways or intersections (other than those which have
already been proposed as part of The Ranch Farm 1 development proposal (DA 2016/017)) are anticipated
to be required on the external road network.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 52 of 66 pages Date 19/02/2016
FINAL
7.3 Intersections
7.3.1 Kidman Way / Tysons Road Intersection
As discussed in previous sections of this report, access to the proposed development and The Ranch
Poultry Production Complex as a whole will be achieved via Tysons Road and its existing intersection with
Kidman Way.
An assessment of the increase in traffic volumes that will occur on Kidman Way at this intersection was
provided in Section 7.1, which concluded that the additional trips generated by the proposed development
are low and not expected to have any adverse operational impacts on the external road network. It is
expected for the low volumes involved that the intersection will continue to operate at a level of service ‘A’
with minimal delays and queuing.
Nevertheless, a number of improvements to this intersection are proposed for implementation as part of the
consent conditions for The Ranch Farm 1 development (DA 2016/017) which include upgrading the layout to
provide a BAL / BAR configuration. The development application for The Ranch Farm 5 is predicated on the
assumption that any upgrades required to be made to the Kidman Way / Tysons Road intersection will be
implemented as part of The Ranch Farm 1 development, prior to The Ranch Farm 5 development
proceeding. As previously indicated, the DA and EIS for The Ranch Farm 5 seeks approval for the
construction and use of the additional section of internal access road between The Ranch Farm 4 and The
Ranch Farm 5 only.
As discussed in Section 5.1, the requirements for the layout of the Kidman Way / Tysons Road intersection
have been re-assessed using intersection warrants prescribed in Austroads Guide to Road Design, Part 4A:
Unsignalised and Signalised Intersections (AGRD Part 4A), in order to ensure that the approved layout will
be able to accommodate the traffic generated by additional developments previously unknown of which are
now proposed at The Ranch Poultry Production Complex and within the broader study area. A total of 4
separate scenarios have been considered in this process.
The analysis indicates that under all of the scenarios considered, including the worst case scenario
(Scenario 4) in which all of the cumulative traffic from other known developments in the study area is
superimposed with full development of The Ranch Poultry Production Complex AND peak activity traffic
volumes for The Ranch Farm 5, the layout required at the Kidman Way / Tysons Road intersection remains
a BAL / BAR. Furthermore, the analysis concludes that the major road hourly traffic volume could increase
by a further 50% on the worst case (Scenario 4) levels before a higher level of intersection treatment would
be required. The proposed layout therefore provides considerable spare capacity to accommodate short
term fluctuations in traffic flow.
The results of the analysis confirm that the BAL / BAR intersection arrangements currently proposed for
implementation at the Kidman Way / Tysons Road intersection will continue to perform acceptably in the
future during periods of peak activity associated with The Ranch Farm 5 development, even after allowing
for traffic generated by all of the other known developments in the study area including The Ranch Poultry
Production Complex at full development.
Based on the above, the currently proposed intersection upgrades at the Kidman Way / Tysons Road
intersection are suitable to accommodate The Ranch Farm 5 development proposal.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 53 of 66 pages Date 19/02/2016
FINAL
7.3.2 Proposed Site Access Driveway
As discussed in Section 5.2, the existing unsealed section of Tysons Road between the end of the existing
seal, located approximately 285m to the east of Kidman Way, and the proposed site access approximately
750m further to the east is in good condition and of a width suitable to enable large heavy vehicles up to the
size of B-Doubles to safely pass each other. Previous TIAs prepared for The Ranch Farms 1 to 3 have
therefore concluded that the existing formation is acceptable with regular maintenance without the need for
further improvements.
However, as part of the consent conditions for The Ranch Farm 1, Council determined that Tysons Road
was to be upgraded from the end of the sealed section to the access gate of The Ranch Poultry Production
Complex “…with a finished 150mm gravel road-base at 6m wide and with a cross fall of 3%...”
With the addition of The Ranch Farms 4 and 5 to The Ranch Poultry Production Complex, and with the
future proposed expansion of The Ranch Farms 1 to 3 from 8 sheds to 16 sheds each, it is considered that
the potential impacts arising from the additional truck movements in terms of road deterioration and dust
generation warrant the provision of additional measures.
As part of the development application for The Ranch Farm 4, it has therefore been recommended that the
unsealed section of Tysons Road between Kidman Way and the proposed site access to The Ranch Poultry
Production Complex (approx. 750m in length), which will already have been upgraded in accordance with
the consent conditions for The Ranch Farm 1, be sealed prior to commencement of operations at The Ranch
Farm 4 site.
Since it is intended that The Ranch Farm 4 will be operational before The Ranch Farm 5, this means that the
full length of Tysons Road between Kidman Way and the site access to The Ranch Poultry Production
Complex will be sealed prior to The Ranch Farm 5 development proceeding.
The future access driveway connecting the internal site access road to Tysons Road will be implemented as
part of The Ranch Farm 1 development, prior to The Ranch Farm 5 development proceeding. No further
assessment of the proposed site access driveway onto Tysons Road is therefore required as part of this TIA.
7.4 Pedestrians and Cyclists
The site is located in a lowly-populated rural area, removed from urban residential areas. It is unlikely staff
would travel to the site via bicycle or walking. Therefore the provision of cycle and pedestrian facilities to and
from the site is not considered necessary.
Within the site adequate provision should be made for pedestrians to move safely around the site.
7.5 Impacts during Construction
As discussed in detail in Section 6, there is not expected to be any significant impact to the external road
network during construction of the proposal.
Access to the site during the construction stage will be provided via Kidman Way and Tysons Road, with the
proposed internal site access road extension between The Ranch Farm 4 and The Ranch Farm 5 (see
Section 5.2) to be constructed at commencement of the construction phase. This will connect to the sections
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 54 of 66 pages Date 19/02/2016
FINAL
of new internal access road to be constructed in accordance with the recent development approvals for The
Ranch Farms 1 to 3, and pending approval for The Ranch Farm 4, as well as to the new site access
driveway onto Tysons Road to be constructed as part of The Ranch Farm 1 development, all of which will be
completed prior to commencement of construction activities for The Ranch Farm 5.
All construction-related traffic (including light vehicles associated with construction workers) will park within
the site during the construction phase.
Construction of the poultry sheds, internal roads and other infrastructure for The Ranch Farm 5 will generate
some heavy vehicle movements associated with deliveries of materials, equipment etc. This will also attract
construction employee trips to the site. The most intensive construction activity in terms of truck movements
to and from the site is expected to be associated with concrete deliveries during construction of the concrete
floor slabs for each poultry shed. It is estimated that a total of approximately 53 trips per day, or
approximately 5 trips per hour (average 2.5 in / 2.5 out), will occur for a duration of up to two days for the
construction of each concrete slab.
Apart from this there would be the odd truck delivering other materials throughout the course of a typical day
and a small number of light vehicle trips, mostly concentrated around the construction shift start and end
times, associated with construction workers.
Overall, it is concluded that the construction activities will generate only low traffic volumes, possibly in the
order of approximately 10-15 trips per day for The Ranch Farm 5 development excluding concrete deliveries,
and will occur for a duration of approximately 12 months. The impacts arising from construction traffic are
therefore expected to be low, and any mitigation treatments identified in the previous TIAs produced for The
Ranch Farm 1, The Ranch Farm 2, The Ranch Farm 3 and The Ranch Farm 4 developments, or in this
report, to address the operational traffic impacts of the development are expected to be sufficient to also
address the construction traffic impacts.
7.6 Cumulative Impacts of Developments
Previous sections have primarily considered the traffic impacts of The Ranch Farm 5 development in
isolation from other known developments in the area. This section examines the potential cumulative
impacts arising from all of the developments.
As discussed in detail in Section 4, a number of developments have either recently been approved and
constructed, or are proposed (i.e. development application lodged or imminent). These developments
include:
The Ranch Poultry Production Complex – Farms 1 to 5 (16 sheds/farm at full development)
Jeanella Poultry Production Complex (existing).
Jeanella South Poultry Production Complex.
Maylands Farm A.
Maylands Farm B.
Tabbita Poultry Farm 1.
Tabbita Poultry Farm 2.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 55 of 66 pages Date 19/02/2016
FINAL
Tabbita Poultry Farm 3.
Tabbita Poultry Farm 4.
The cumulative volume of traffic generated by these developments on Tysons Road and Kidman Way to the
north and south of Tysons Road was previously estimated and presented in Table 4.2. As stated previously,
the estimated volumes are based on traffic generation data prepared separately (in some cases by other
parties) as part of the TIAs for those developments, and have been adopted without change for the purposes
of this assessment.
Comparing these volumes to the future background traffic estimated to use these roads in the design year of
2029, the following changes in traffic are predicted:
Future Forecast Traffic Volumes (2029)
including Cumulative Traffic Generated by Developments
Background Traffic
Vehicle Trips Per Day1,2
Additional Generated Traffic
Vehicle Trips Per Day Percentage Increase
Cars HVs Total Cars HVs Total Cars HVs Total
Tysons Road (east of
Kidman Way) 10 10 20 40 110 150 400% 1100% 750%
Kidman Way (north of
Tysons Road) 1015 249 1264 112 214 326 11% 86% 26%
Kidman Way (south of
Tysons Road) 1013 251 1264 132 324 456 13% 129% 36%
1. Background traffic for Tysons Road estimated based on 2015 site observations.
2. Background traffic volumes for Kidman Way estimated using 2011 traffic count at Tabbita in Table 2.1 and 1.5% p.a. linear growth rate to design year of 2029, with small adjustments
north and south of Tysons Road to allow for estimated background turning volumes. Values south of Tysons Road same as presented in Table 7.1.
Table 7.2 – Cumulative Increase in Vehicle Trips on External Road Network from all Known Developments
The results show that all of the developments collectively still only result in an increase of 26-36% in the total
daily volumes on the subject sections of Kidman Way at the future design year of 2029. The forecast
percentage increase in heavy vehicle movements is substantially higher at 86% to 129%, however, the
resulting volumes are still very low and easily accommodated on Kidman Way which is a designated B-
Double and Road Train route.
Although there is a substantial increase in the volume of traffic predicted to use Tysons Road when
compared to the estimated current usage which is very low, the total predicted volume of 170 vehicles per
day (20 background trips + 150 generated trips associated with full development of The Ranch Poultry
Production Complex) is still extremely low and is not predicted to result in any capacity or operational issues,
particularly if the road is sealed as part of the recommendations made for The Ranch Farm 4 development
application.
The above assessment is based on average daily traffic volumes over the production cycle. If the worst
case peak activity scenario of litter removal / shed cleanout is considered as discussed previously in
Sections 3.7 and 7.1, a peak traffic generation of 85 vehicles per day (170 trips per day) is estimated to
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 56 of 66 pages Date 19/02/2016
FINAL
occur for The Ranch Farm 5 on Day 57 of the production cycle, comprising of approximately 140 heavy
vehicle trips per day and 30 car trips per day.
Assuming all peak activity traffic has an origin/destination from/to the south as an approximation,
comparison of these peak activity volumes (in combination with the other cumulative volumes previously
assessed for the other developments) to the background volumes in Table 7.1 indicates percentage
increases of 15% for cars, 176% for heavy vehicles and 47% for all vehicles combined. As expected the
biggest increase in traffic during the peak activity period is associated with the additional heavy vehicles,
which would increase from 251 trips/day to 693 trips/day on Kidman Way to the south of Tysons Road, with
all of the other cumulative development traffic included. However, the resulting volume of heavy vehicles is
still very low, equating to an average of 10-15 trips per hour each way, which can still easily be
accommodated on Kidman Way.
Based on the information that is available, the cumulative impacts of the known developments appear to be
acceptable even after allowing for the worst case peak activity traffic for The Ranch Farm 5 development,
and do not require additional improvements or upgrades beyond those already proposed in this TIA.
Furthermore, specific operational measures to mitigate the cumulative impacts of the developments during
periods of peak activity are considered to be unnecessary.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 57 of 66 pages Date 19/02/2016
FINAL
8. CONCLUSIONS
The proposed development involves the construction of an intensive poultry broiler production farm referred
to as The Ranch Farm 5, comprising of 16 tunnel-ventilated fully-enclosed climate-controlled poultry sheds
where broiler birds will be grown for human consumption. The development will be able to accommodate up
to approximately 800,000 broiler birds at any one time. Operations will occur 24 hours a day, 7 days a week.
The proposed development is one of five farms, collectively referred to as The Ranch Poultry Production
Complex, which are proposed for development on adjoining lots within the study area. Separate
development approvals for the first 3 farms known as The Ranch Farms 1, 2 and 3, each comprising of 8
poultry sheds, were granted by Carrathool Shire Council in December 2015. Separate DA’s and EIS’s are
now being prepared for The Ranch Farms 4 and 5, each of which will have 16 sheds, and these are
expected to be lodged concurrently in February 2016. Each of the farms will ultimately (with future proposed
expansions from 8 sheds to 16 sheds for The Ranch Farms 1, 2 and 3) be of the same size and have the
same operational characteristics.
Access to the proposed development and also The Ranch Poultry Production Complex as a whole is
proposed via a new internal 4m wide access road with passing bays which connects to Tysons Road (a local
rural road) approximately 1km east of the existing Kidman Way / Tysons Road intersection. The new site
entrance onto Tysons Road and the section of internal access road connecting this to The Ranch Farm 1 will
be constructed as part of The Ranch Farm 1 development, prior to The Ranch Farm 5 proceeding. No
further changes to the site access driveway are required to be made for The Ranch Farm 5 development.
Similarly, the additional sections of internal access road between The Ranch Farm 1 and The Ranch Farm
2, and between The Ranch Farm 2 and The Ranch Farm 3, will be constructed as part of The Ranch Farm 2
and The Ranch Farm 3 developments respectively, prior to The Ranch Farm 5 development proceeding.
The application for The Ranch Farm 5 is predicated on The Ranch Farm 4 being approved and developed
first, since that development will provide the section of internal access road between The Ranch Farm 3 and
The Ranch Farm 4. The DA and EIS for The Ranch Farm 5 seek approval for the construction and use of the
additional section of internal access road between The Ranch Farm 4 and The Ranch Farm 5 only.
It is anticipated that the direction of travel for heavy vehicles and the majority of staff vehicles will
predominantly be to and from Hanwood and Griffith to the south via Kidman Way, with most traffic turning
right into and left out of Tysons Road at its intersection with Kidman Way.
The Ranch Farm 5 development will generate an average of 30 vehicle trips per day (22 heavy vehicle trips
and 8 car trips) and 4 trips per hour during the peak generating times of the proposal (1 heavy vehicle trip
and 3 car trips). Existing and future background traffic volumes on Kidman Way are relatively low and
additional traffic from the proposal can be easily accommodated. It is not expected to cause any significant
impacts in terms of road safety or operation.
An assessment of the traffic generation arising from the peak activities that occur during the 63 day
production cycle for The Ranch Farm 5 has also been undertaken. The peak activity periods for The Ranch
Farm 5 are associated with live bird removal and litter removal/shed cleanout. Of these, the litter
removal/shed cleanout phase provides the worst case for assessing potential traffic impacts, with a peak
traffic generation of 85 vehicles per day (170 trips per day) estimated to occur on Day 57 of the production
cycle, with the majority of these trips occurring during daylight hours (say 7am to 7pm). Assuming a uniform
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 58 of 66 pages Date 19/02/2016
FINAL
distribution of traffic arrivals and departures from The Ranch Farm 5 development over this period, this
equates to approximately 7 vehicles per hour (14 trips per hour).
By contrast, live bird removal is scheduled to occur between 7pm one day and 4pm the following day,
although for reasons of livestock welfare they would generally be removed overnight and in the morning
when it is cooler and the birds are more settled. Assuming 80% of the trips occur during 7pm to 9am and
the remaining 20% between 9am and 4pm, the peak activity volume of 82 vehicles per day (164 trips per
day) on Day 54 approximates to a maximum hourly volume of 5 vehicles per hour (10 trips per hour) during
7pm-9am (when traffic volumes on the adjacent road network are for the majority of that period quite low)
and only 3 vehicles per hour (6 trips per hour) during 9am-4pm. The additional trips in both periods are lower
than those predicted to occur during the litter removal / shed cleanout phase.
While the daily peak activity volumes for both the live bird removal phase and also the litter removal / shed
cleanout phase are considerably higher than the cycle-average volumes, the increase in hourly traffic
volumes is relatively modest in both cases and is not expected to result in any significant changes to the
conclusions drawn based on using cycle-average volumes.
A number of improvements to the Kidman Way / Tysons Road intersection are proposed in accordance with
the consent conditions for The Ranch Farm 1 development (DA 2016/017), which include upgrading the
layout to provide a BAL / BAR configuration. The development application for The Ranch Farm 5 is
predicated on the assumption that any upgrades required to be made to this intersection will be implemented
prior to The Ranch Farm 5 development proceeding. The requirements for the layout of the intersection
have been re-assessed using intersection warrants prescribed in Austroads Guide to Road Design, Part 4A:
Unsignalised and Signalised Intersections (AGRD Part 4A), in order to ensure that the approved layout will
be able to accommodate the traffic generated by additional developments previously unknown which are
now proposed at The Ranch Poultry Production Complex and within the broader study area. A total of 4
separate scenarios were considered in this process.
The analysis indicates that under all of the scenarios considered, including the worst case scenario
(Scenario 4) in which all of the cumulative traffic from other known developments in the study area is
superimposed with full development of The Ranch Poultry Production Complex AND peak activity traffic
volumes for The Ranch Farm 5, the layout required at the Kidman Way / Tysons Road intersection remains
a BAL / BAR. Furthermore, the analysis concludes that the major road hourly traffic volume could increase
by a further 50% on the worst case (Scenario 4) levels before a higher level of intersection treatment would
be required. The proposed layout therefore provides considerable spare capacity to accommodate short
term fluctuations in traffic flow and is suitable without further change to accommodate The Ranch Farm 5
proposal.
As part of the application for The Ranch Farm 4, which is being lodged concurrently with The Ranch 5
application, it has been recommended that the unsealed section of Tysons Road between Kidman Way and
the proposed site access to The Ranch Poultry Production Complex (approx. 750m in length) be sealed prior
to commencement of operations at The Ranch Farm 4 site. Council has already determined as part of the
consent conditions for The Ranch Farm 1 that the subject section of Tysons Road should be upgraded to
provide a finished 150mm gravel road-base 6m in width with a crossfall of 3%. However, with the addition of
The Ranch Farms 4 and 5 to The Ranch Poultry Production Complex, and with the future proposed
expansion of The Ranch Farms 1 to 3 from 8 sheds to 16 sheds each, it is considered that the potential
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 59 of 66 pages Date 19/02/2016
FINAL
impacts arising from the additional truck movements in terms of road deterioration and dust generation
warrant the provision of additional measures.
Since it is intended that The Ranch Farm 4 will be operational before The Ranch Farm 5, this means that the
full length of Tysons Road between Kidman Way and the site access to The Ranch Poultry Production
Complex will be sealed prior to The Ranch Farm 5 development proceeding.
As mentioned previously the heavy vehicles servicing the site will generally travel to and from facilities in and
around Hanwood and Griffith to the south using Kidman Way. Kidman Way is a designated B-double and
Road Train route. It is suitable in its current form for the low daily volume of heavy vehicles generated by the
development proposal, without the need for further road or intersection improvements (other than those
which have already been proposed as part of The Ranch Farm 1 development proposal).
Internal roads for the development will be constructed to accommodate heavy vehicles and the operation will
allow one way traffic flow around the poultry sheds to avoid conflicts in servicing. The one-way system will
connect directly to the internal site access road providing access from the site onto Tysons Road.
Construction of the proposed development will generate some heavy vehicle movements associated with
deliveries of materials, equipment etc, in addition to generating additional light vehicle trips for staff. The
most intensive construction activity in terms of truck movements to and from the site is expected to be
associated with concrete deliveries during construction of the concrete floor slabs for each poultry shed. It is
estimated that a total of approximately 53 trips per day (approximately 5 trips per hour) will occur for a
duration of up to two days for the construction of each concrete slab.
Apart from this there would be the odd truck delivering other materials throughout the course of a typical day
and a small number of light vehicle trips, mostly concentrated around the construction shift start and end
times, associated with construction workers. All constructed-related traffic will park on site. Overall, it is
concluded that the construction activities will generate only low traffic volumes, possibly in the order of
approximately 10-15 trips per day for The Ranch Farm 5 development excluding concrete deliveries, and will
be for a relatively short term (i.e. duration of 12 months). The impacts arising from construction traffic are
therefore expected to be low and any mitigation treatments identified in the previous TIAs produced for The
Ranch Farms 1 to 4, or in this report, to address the operational traffic impacts of the development are
expected to be sufficient to also address the construction traffic impacts.
The cumulative traffic impacts of a number of known developments in the study area, including the existing
Jeanella Poultry Production Complex, the proposed Jeanella South Poultry Farm, Maylands Farms A and B,
Tabbita Poultry Farms 1, 2, 3 and 4 and the other four farms of The Ranch Poultry Production Complex at
full development have been examined in conjunction with The Ranch Farm 5 development proposal. The
analysis concludes that the resulting volumes on the relevant sections of those roads collectively used by
some or all of the developments (namely Tysons Road east of Kidman Way, Kidman Way north of Tysons
Road and Kidman Way south of Tysons Road) are still predicted to be relatively low at the design year of
2029 and easily accommodated by these roads.
Even when the assessment is undertaken with the peak activity traffic generation for The Ranch Farm 5
included, the resulting volume of heavy vehicles equates to an average of 10-15 trips per hour each way on
the section of Kidman Way to the south of Tysons Road, which is still able to be easily accommodated.
Based on the information available, the cumulative impacts of the known developments therefore appear to
be acceptable and do not require additional improvements or upgrades. Furthermore, specific operational
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 60 of 66 pages Date 19/02/2016
FINAL
measures to mitigate the cumulative impacts of the developments during periods of peak activity are
considered to be unnecessary.
Provided the recommendations made in this report and also in the previous applications for The Ranch
Farms 1 to 4 are met, the proposal for The Ranch Farm 5 is not expected to cause any significant impacts in
terms of road safety or operation, and there are no issues associated with traffic to reject the proposal.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 61 of 66 pages Date 19/02/2016
FINAL
9. RECOMMENDATIONS
1. Construct the internal roads proposed for The Ranch Farm 5 development, including the additional
section of internal site access road between The Ranch Farm 4 and The Ranch Farm 5, to a
suitable strength and width to accommodate the expected heavy vehicle movements and their turn
path requirements.
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 62 of 66 pages Date 19/02/2016
FINAL
APPENDIX A
PROPOSED DEVELOPMENT LOCATION AND LAYOUT
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 63 of 66 pages Date 19/02/2016
FINAL
Location Plan
“THE RANCH” FARM 5 SITE
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 64 of 66 pages Date 19/02/2016
FINAL
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 65 of 66 pages Date 19/02/2016
FINAL
APPENDIX B
REVISED TRIP GENERATION FOR THE RANCH FARMS 1, 2 AND 3 (8-SHED ONLY)
The Ranch Poultry Production Complex – Farm 5 Traffic Impact Assessment
Tysons Road (nr Kidman Way), Tabbita for Scolexia Pty Ltd
________________________________________________________________________________________________________________
15022G Page 66 of 66 pages Date 19/02/2016
FINAL
Table 1 - Estimated Operational Traffic Volumes – Production Cycle and Annual
The Ranch Farms 1, 2 and 3 (8 poultry sheds per farm)
Activity Vehicle Type
Vehicles (Two Way Vehicle Trips)
Production Cycle
(approx. 9 weeks)
Annual
(approx. 5.7 cycles)
Heavy Vehicles
Delivery of shed bedding material Twin axle rigid truck 15 (30) 86 (172)
Delivery of chicks Semi- trailer 6 (12) 34 (68)
Delivery of feed Semi-trailer 90 (180) 513 (1026)
Delivery of fuel Rigid tanker 1 (2) 6 (12)
Delivery of LPG Rigid tanker 2 (4) 11 (22)
Removal of birds Semi-trailer 90 (180) 513 (1026)
Removal of birds – catching equipment
transporter Semi-trailer 20 (40) 114 (228)
Removal of birds – catching staff Bus 20 (40) 114 (228)
Removal of shed litter material Semi-trailer 36 (72) 205 (410)
Shed wash down equipment transporter Semi-trailer 20 (40) 114 (228)
Removal of dead birds Twin axle rigid truck 30 (60) 171 (342)
Removal of garbage Rigid truck 1 (2) 6 (12)
Heavy Vehicle Sub-Total 331 (662) 1887 (3774)
Light Vehicles
Staff Visits Car 160 (320) 912 (1824)
Tradesman Ute / Van 9 (18) 51 (102)
Catching equipment maintenance Van 4 (8) 23 (46)
Shed litter material removal contractors Car 10 (20) 57 (114)
Shed wash down contractors Car 4 (8) 23 (46)
Light Vehicle Sub-Total 187 (374) 1066 (2132)
TOTAL 518 (1036) 2953 (5906)
Table 2 - Estimated Operational Traffic Volumes – Peak Hour and Daily
The Ranch Farms 1, 2 and 3 (8 poultry sheds per farm)
Vehicle Type Vehicles Per Day
(Vehicle Trips)
AM Peak Hour
Movements
PM Peak Hour
Movements
Cars (LV) 3 (6) 3 (2 in, 1 out) 3 (1 in, 2 out)
Heavy Vehicles 6 (12) 1 (1 in, 0 out) 1 (0 in, 1 out)
Total 9 (18) 4 (3 in, 1 out) 4 (1 in, 3 out)
NOTE: All traffic volumes presented in Tables 1 and 2 are provided on a per-farm basis.