TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

Upload: austen-mathews

Post on 11-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

TRACKING DSA PCO SUBMITTALS IN

EXPEDITION

byWendy Kaszycki, PE

Project Controls DirectorMarch 2, 2006

Page 2: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

2

Introduction

• What are PCOs?

• Background

• Why Track PCOs?

• Where Track?

• Who?

• How?

Page 3: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

3

What are PCOs?

• Preliminary Change Orders– Submitted to DSA to get preliminary

approval on changes to plans or specs– Required for Structural, Fire/Life Safety

and Accessability– Can be in the form of an RFC or sketch

Page 4: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

4

Background

• Title 24 requires all changes to plans and specs to have DSA approved CO prior to perform work

• Recognized as impractical, so DSA approves PCOs instead

• DSA Interpretative Regulation (IR) 6 further reduces this to only PCOs relating to Accessibility, Fire/Life Safety or Structural changes

Page 5: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

5

Problem

• Tracking DSA Submittals in Expedition was trained to OARs & PCs in August and September 2004

• Not all submittals being tracked in system

• Only 19 projects show PCO submittals in Expedition

Page 6: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

6

Why Track PCOs?

• DSA Form 6 – Documents whether project is constructed in

accordance with Plans & Specs– Assigns % complete in applicable categories– 100% complete required on Fire Alarm & Fire

Sprinklers in order to occupy• DSA approval on PCOs for all Fire Alarm & Fire Sprinkler

Safety changes

• Helps DSA manage workload and resources• DSA approval of COs is expedited if PCO has

been approved, thus speeding project certification

Page 7: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

7

Where Track?

• Policy– All DSA Submittals are to be tracked and

kept current using Expedition’s submittal package log

• Expedition is only system where PCOs can be uniformly tracked– PCOs not tracked in PIC– PCOs not tracked in DSA Tracker

Page 8: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

8

WHO?Responsibilities

• OAR/Project Team– Overall responsibility to log, track, monitor– Prepare/issue Log– Ensure Architect is sending required submittals to

DSA– Review status of PCO submittals in weekly

meetings

• Architect– Submits PCOs– Resolves all technical issues required for DSA

approval

Page 9: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

9

WHO?Responsibilities

• DSA– Reviews and approves all submittals to DSA

• General Contractor– Should not perform CO work until PCO is approved

• IOR– Generates DSA Form 6– If not “100/100”, requests Fire Department site visit

• OEHS– Completes Essential Safety Checklist prior to

School Occupancy

Page 10: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

10

Projects Tracking PCOs

Page 11: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

11

Valley Region – Open PCOs

Page 12: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

12

South Region – Open PCOs

Page 13: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

13

Central Region – Open PCOs

Page 14: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

14

Additions & Modulars – Open PCOs

Page 15: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

15

HOW?Expedition Submittal System

• Set up package called “DSA”• Enter each submittal • Track Type of submittal• Assign Priority

– High Priority if Fire Alarm/Fire Sprinkler PCO (critical/required for School Occupancy)

• Automatically tracks– Ball in Court– Days held– Overdue

Page 16: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

16

Expedition Submittal System

• Can track Multiple Reviewers • Tracks Multiple Review

Cycles/Revisions• Tracks Required Dates• Allows input of remarks/comments• Status• Automatically creates Transmittals• Automatically creates Dunning Letters

Page 17: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

17

Types of DSA Submittals

• Original Construction Documents• Revisions• Addenda• Deferred Submittals

– Elevator Rails– Sprinkler Systems– Storefronts, etc.

• PCOs (preliminary approval of change, can be in the form of an RFC)

• COs• Field Directives• CDAs (changes to scope on 17406 Projects)

Page 18: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

18

DSA Reviewers

• Accessibility

• Fire/Life Safety

• Structural

Page 19: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

19

Challenges

• Project Team/OARs need to input data as items occur, not when completed

• Architect and OAR being aware of when submittals are made

• OAR providing proper information to PC for input

Page 20: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

20

W I I F M

Page 21: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

21

W I I F MWhat’s

In

It

For

Me

Page 22: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

22

WIIFM

• One system to track all submittals during design & construction

• Provides log to discuss with A/E• Expedites project certification by DSA• Track by Project• Roll-up by Region• Exception Reporting

– High Priority– Held > X Days– Overdue

• Eliminates duplication of effort and/or several versions of logs with conflicting information

• SCHOOL OCCUPANCY!!!!!

Page 23: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

23

Sample Project Report

Page 24: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

24

Key Points to Remember

• Always Use Submittal Packages• Package called “DSA”• Add Submittals• Assign Type (“PCO”)• Assign Reasonable Priorities (High

for Fire Alarm/Fire Sprinkler PCOs)• Assign Status (NEW)

Page 25: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

25

Key Points to Remember

• Use Status– “NEW” – upon creation– “RRR” – if DSA reviews and returns for

revision– “APP” – after DSA approval

(Submittals show up as “UNS” (Unsubmitted) if status is not properly selected)

Page 26: TRACKING DSA PCO SUBMITTALS IN EXPEDITION by Wendy Kaszycki, PE Project Controls Director March 2, 2006

26

Questions?