    TOPIC 3

    CONSTRUCTION PROJECT SCHEDULING

  • 8/20/2019 Topic 3 Project Scheduling

    2/18

    Introduction

    •Determination of timing and sequenceactivities.

    •Should be detailed to:o show each WBS to be performed,o start and end date of each activities,relationship between activities

    o and expected duration of each activities

  • 8/20/2019 Topic 3 Project Scheduling

    3/18

    Advantages of good scheduling:o Reduce construction timeo Reduce cost of labor, overhead and interest on

    capitalo Provide continuous flow of worko

    Increase productivityo Provide specific milestones to work toward and

    indications of progress towards those goalso Provide control and management of material, m

    labot, time and equipment.

  • 8/20/2019 Topic 3 Project Scheduling

    4/18

    •Methods available in project schedulino Gantt Chart

    o Critical Path Method

  • 8/20/2019 Topic 3 Project Scheduling

    5/18

    Gantt Chart

    •Developed by Henry Gantt in 1917.•Is a list of activities displayed in a timeEach activity is represented by a bar. T

    position and length of the bar reflectsstart date, duration and end date of thactivity.

  • 8/20/2019 Topic 3 Project Scheduling

    6/18

    Gantt Chart

    •Gantt Chart represent:o The list of activities

    o Start and end date of each activities

    o The duration of each activities

    o The overlapping activities with its durat

    o The start and completion date of projec

  • 8/20/2019 Topic 3 Project Scheduling

    7/18

    Gantt Chart

    •Advantages:o easy to interpret and simple

    o widely used in construction project

    o easy to understand

    o visual clarity

    o does not require extensive interrelationactivities.

  • 8/20/2019 Topic 3 Project Scheduling

    8/18

    Gantt Chart

    •Disadvantages:o difficult for update status of project

    o does not show interdependency of activitie

    o does not integrate with cost or resources

    o limited application for detailed constructio

    o does not show the critical activities and flo

    o ineffective in forecasting effects of changes

  • 8/20/2019 Topic 3 Project Scheduling

    9/18

    Gantt Chart Example

  • 8/20/2019 Topic 3 Project Scheduling

    10/18

    Updating Gantt Chart

  • 8/20/2019 Topic 3 Project Scheduling

    11/18

    Critical Path Method CPM)

    •The basis of CPM is a logic diagram ornetwork which represent the activitiesconstruction project.

    •CPM is a method to determine the sta

    finish date for each activity, calculate tduration of project and identify the cractivities in project.

  • 8/20/2019 Topic 3 Project Scheduling

    12/18

    Advantages:o provides interrelationship of activities and

    scheduling of cost and resources.o provides more detailed information that is

    in project management.

    o

    can be used in simple or complex project.o The critical activities can be identified in th

    network those help managers in setting thepriorities in construction project.

    Critical Path Method CPM)

  • 8/20/2019 Topic 3 Project Scheduling

    13/18

    •Disadvantages:o requires an extensive description of theinterrelationship of activities.

    o requires more effort and training to bec

    an effective user.

    o CPM can become complex.

    Critical Path Method CPM)

  • 8/20/2019 Topic 3 Project Scheduling

    14/18

    •Method : Precedence Diagram Metho(PDM) and Arrow Diagram Method (A

    ADM PDM

    Critical Path Method CPM)

  • 8/20/2019 Topic 3 Project Scheduling

    15/18

    •ADM using arrows to represent theactivities and connecting them at nodshow the dependencies.

    •ADM uses only Finish-to-Start (FS)

    dependencies and may require the usedummy activities to define all logicalrelationship correctly.

    Critical Path Method CPM)-ADM

  • 8/20/2019 Topic 3 Project Scheduling

    16/18

    Critical Path Method CPM)-ADM

    Rules in developing ADM:o The network may have only one beginning node a

    ending node.o The logic states all activities coming into the node

    complete before any activities can start.o The logic must be exact regarding predecessors,

    successors and concurrent relationship.o There must be at least one continuous path from

    beginning of the project to the end of the project any dangling nodes.

    o Each activity must be represent by one arrow only

  • 8/20/2019 Topic 3 Project Scheduling

    17/18

    Critical Path Method CPM)-ADM

    •Example 1

    Num. Activity Duration (days) Pre

    1 Act. A 5

    2 Act. B 3

    3 Act. C 2

    4 Act. D 2

    5 Act. E 6

    6 Act. F 1

    7 Act. G 2

    8 Act. H 1 E

  • 8/20/2019 Topic 3 Project Scheduling

    18/18

    Critical Path Method CPM)-ADM

    •Example 2Num.

    Activity

    CodeActivity Name

    Duration

    (days)Predecesso

    1 A Initial Excavation 2 -

    2 B Continue excavation 2 A

    3 C Final excavation 2 B

    4 D Begin forms and rebar 4 A5 E Continue forms and rebar 4 B,D

    6 F Final forms and rebar 4 C,E

    7 G Initial concrete 2 D

    8 H Continue concrete 2 E,G

    9 I Final concrete 2 E,F,H

    10 J Erect steel column 9 I

    Total