top 10 commissioning · 2019-04-24 · commissioning plan witness factory testing submittal reviews...

20

Upload: others

Post on 22-Feb-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site
Page 2: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Top 10 Commissioning Mistakes

Johnathan Woodside, P.E., LEED AP O+M, GBE, GGP

Steven Metzgar, CxA, LEED AP BD+C, EMP

Page 3: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

What is Commissioning

A process of coordinating design and construction activities to ensure that; a design meets the owner’s project requirements, a design will function according to the design intent and the final product is completed and installed per the contract documents.

Page 4: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Design Phase

Gresham Smith Cx Process

Construction PhaseAcceptance Phase

Post Occupancy Phase

► Cx Specification

► Cx Design Review

► Commissioning Plan

► Witness Factory Testing

► Submittal Reviews

► Cx Kickoff Meeting

► Review Start-Up Plan

► Witness Start-Up

► Pre-Functional Check Site Visits

► Functional Performance Tests

► Training Personnel

► O&M Review

► Final Report

► Systems Manual

► Opposed Season Testing

► Warranty Review

► Lessons Learned Meeting

► Revise Final Report

Pre-Design Phase

► OPR Development/Review

► Project Approach

► Contract Scoping

► BOD Review

Page 5: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Common Mistakes

Page 6: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Chilled Water System

Page 7: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

CHW System DPnot verified with TAB

1

Page 8: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

2

CHW minimum flow bypass valve

Page 9: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Chiller did not have DP sensor, it only had pressure transducersfor reading DP

3

Page 10: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Heating Hot System

Page 11: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

4 Verify MinimumFlow

Master/Slave Control5

Page 12: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Isolation ValveOperation

Firing RateRamp Schedule

6

7

Page 13: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Control System

Page 14: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Read/WriteCapabilities

8

BACNet Capabilitywith Equipment

Page 15: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Design/Construction Phase

Page 16: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Equipment not installed accordingto design

9

Page 17: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Design build needs more attention, not less attention

10

Page 18: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Overall Picture

Commission entire system and not piecemeal.

Page 19: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Design Phase

Gresham Smith Cx Process

Construction PhaseAcceptance Phase

Post Occupancy Phase

► Cx Specification

► Cx Design Review

► Commissioning Plan

► Witness Factory Testing

► Submittal Reviews

► Cx Kickoff Meeting

► Review Start-Up Plan

► Witness Start-Up

► Pre-Functional Check Site Visits

► Functional Performance Tests

► Training Personnel

► O&M Review

► Final Report

► Systems Manual

► Opposed Season Testing

► Warranty Review

► Lessons Learned Meeting

► Revise Final Report

Pre-Design Phase

► OPR Development/Review

► Project Approach

► Contract Scoping

► BOD Review

Page 20: Top 10 Commissioning · 2019-04-24 · Commissioning Plan Witness Factory Testing Submittal Reviews Cx Kickoff Meeting Review Start-Up Plan Witness Start-Up Pre-Functional Check Site

Florida Water Resources ConferenceApril 17, 2018

Questions?