8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
1/11
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 1
Tolerance Limits in Budgetingduring Procurement of Materials/Services
Applies to:
SAP Project System for Budgeting Tolerance limits with warning / error message - Version 6.0.
For more information, visit theSupplier Relationship Management homepage.
Summary
This Document describes the Tolerance Limits in Budgeting during procurement of Material or Services
Author: Ramalingeswara Rao Vengala
Company: Intelligroup Inc.
Created on:November 1st2010
Author Bio
Ramalingeswara Rao Vengala has a Bachelors degree in Engineering and worked as a Plant Managerbefore joined to SAP. He has been working as a Principal Consultant with Intelligroup Inc., USA. He hasexpertise in SAP Project System, Investment Management, Materials Management, WarehouseManagement, Document Management System and Easy DMS modules. He worked in many SAPimplementations and support Projects in India, Saudi Arabia, China, Egypt and USA.
https://www.sdn.sap.com/irj/sdn/bpx-srmhttps://www.sdn.sap.com/irj/sdn/bpx-srmhttps://www.sdn.sap.com/irj/sdn/bpx-srmhttps://www.sdn.sap.com/irj/sdn/bpx-srm -
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
2/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 2
Table of Contents
Project Systems Tolerance Limits in Budgeting during procurement of Materials / Services ......................... 3
Customization setting from Project System (PS) perspective ............................................................................ 4
Maintaining Planning Profile (SPRO) .............................................................................................................. 4
Maintaining Budget Profile .............................................................................................................................. 4
Maintaining Project Profile and assign Planning profile & Budget Profile ....................................................... 5
Defining Availability control for Budget profile with warning and error message ............................................ 5
Creating a Project ........................................................................................................................................... 6
Maintaining Cost Planning .............................................................................................................................. 7
Maintaining Original Budgeting (Budget has been assigned 110% of cost planning) .................................... 7
Related Content ................................................................................................................................................ 10
Disclaimer and Liability Notice .......................................................................................................................... 11
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
3/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 3
Project Systems Tolerance Limits in Budgeting during procurement of Materials /Services
Budget is an approved costs for a project and differs or same as with costs planning.
The below mentioned different types of Budget types can be used.
- Original Budget
Original Budget is initially allocated Budget.
- Budget Updates
Sometimes Budget needs to update from Original Budget
Availability control enables to control costs by issuing warning and error message during procurement ofmaterials or services
This paper is confined to the scope of Project systems (PS) with Budgeting control with Tolerance limits
The following settings can be done from the configuration
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
4/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 4
Customization setting from Project System (PS) perspective
Maintaining Planning Profile (SPRO)
Creating a new planning profile or changing existing ones by updating with necessary inputs
Project System ---- Costs --- Planned Costs --- Manual Costs Planning in WBS --- Hierarchical Cost Planning
--- Create / Change Planning Profile
Maintaining Budget Profile
Creating a new Budget profile or changing existing ones by updating with necessary inputs
Project System --- Costs --- Budget --- Maintain Budget Profiles
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
5/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 5
Maintaining Project Profile and assign Planning profile & Budget Profile
Project System --- Structures --- Operative Structures --- Work Breakdown Structure --- Create Project Profile
Defining Availability control for Budget profile with warning and error message
Project System --- Costs --- Budget --- Define Tolerance Limits
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
6/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 6
Creating a Project
T.Code: CJ01 / CJ20N
Cost planning acts as the base for an initial cost estimates to get approvals for Budgeting
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
7/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 7
Maintaining Cost Planning
T.Code: CJ40
Budget is the approved cost structure for a project
Maintaining Original Budgeting (Budget has been assigned 110% of cost planning)
T.Code: CJ30
Releasing the Budget is not the same as original Budget. You can release the Budget on total or annualvalues
Budget Release(Release is a Budget control though original Budget has been assigned $ 55,000 asBudget was released $ 40,000)
T.Code: CJ32
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
8/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 8
Create Purchase Requisition for a Material(As Availability control Tolerance has been maintained 90%warning for the Released Budget)
T.Code: ME51N
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
9/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 9
Create Purchase Requisition for a Material(As Availability control Tolerance has been maintained 100%error for the Released Budget)
T.Code: ME51N
Error Message as Budget was exceeded 0.50 USD
To correct the error message decrease the quantity of a material or updated the Released Budget
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
10/11
-
8/11/2019 Tolerance Limits in Budgeting During Procurement of Materials Services
11/11
Tolerance Limits in Budgeting during Procurement of Materials /Services
SAP DEVELOPER NETWORK |sdn.sap.com BUSINESS PROCESS EXPERT COMMUNITY| bpx.sap.com
2010 SAP AG 11
Disclaimer and Liability Notice
This document may discuss sample coding or other information that does not include SAP official interfaces and therefore is notsupported by SAP. Changes made based on this information are not supported and can be overwritten during an upgrade.
SAP will not be held liable for any damages caused by using or misusing the information, code or methods suggested in this document,and anyone using these methods does so at his/her own risk.
SAP offers no guarantees and assumes no responsibility or liability of any type with respect to the content of this technical article or
code sample, including any liability resulting from incompatibility between the content within this document and the materials andservices offered by SAP. You agree that you will not hold, or seek to hold, SAP responsible or liable with respect to the content of thisdocument.