tokyo - topical meeting, march 2006 1 peter-raymond kettle beam line update end-caps end-caps...
TRANSCRIPT
Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 11Peter-Raymond KettlePeter-Raymond Kettle
Beam Line UpdateBeam Line Update
• End-Caps End-Caps • Insertion SystemInsertion System• Target SystemTarget System• ScheduleSchedule
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 22
COBRA End-COBRA End-CapsCaps• Complex design He/Vacuum/NComplex design He/Vacuum/N22/Air interface/Air interface
• Materials minimized Al & CHMaterials minimized Al & CH22/EVAL (background)/EVAL (background)• Non-disruptive Access for Insertion System, Non-disruptive Access for Insertion System, Cables, Gas etc.Cables, Gas etc.Upstream End-Cap: Upstream End-Cap: Design CompletedDesign CompletedDownstream: Downstream: On ScheduleOn Schedule virtually completed virtually completed linked to Insertion System linked to Insertion System
USUSUSUS DSDSDSDS
ManufacturerManufacturerFound &Found &
Schedule Schedule Still as Still as plannedplanned
USUSUSUSDSDSDSDS
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 33
ManufacturerManufacturerspecialists in specialists in complex welding & complex welding & structural designstructural design
ManufacturerManufacturerspecialists in specialists in complex welding & complex welding & structural designstructural design
AMS-02 spectrometerAMS-02 spectrometerHe-vessel 2500 l He-vessel 2500 l Superfluid He for Superfluid He for ISS mission 2008ISS mission 2008
AMS-02 spectrometerAMS-02 spectrometerHe-vessel 2500 l He-vessel 2500 l Superfluid He for Superfluid He for ISS mission 2008ISS mission 2008
ISS
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 44
Insertion SystemInsertion System
Connects to acceleratorConnects to acceleratorBeam pipeBeam pipe
Gliding supportGliding supportringsrings
NBRNBR
RETRACTED into End-CapRETRACTED into End-Cap
ReplaceReplacewithwithwindowwindow
• Gas-tight to He-side CHGas-tight to He-side CH22/EVAL window/EVAL window• normally connected to motor-driven accelerator normally connected to motor-driven accelerator beam tubebeam tube• frictional hand-drive via electric drill/crank-handlefrictional hand-drive via electric drill/crank-handle
Detailed FEM study
Electric-drill or hand driveElectric-drill or hand drive
View from InsideCOBRA
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 55
Target Target SystemSystem
CHCH2 2 oror
RohacellRohacellCHCH2 2 oror
RohacellRohacell
Various solutions under study:Various solutions under study: UCI/PSI/KEKUCI/PSI/KEK
Permanent Muon TargetPermanent Muon Target• Rohacell foam/CHRohacell foam/CH2 2 combination combination • Complete Rohacell Complete Rohacell (too thick 2.3 - 5.3 mm)(too thick 2.3 - 5.3 mm)• CHCH22 or polystyrene Target + wire frame or polystyrene Target + wire frame
MOST LIKELY MATERIALMOST LIKELY MATERIALfor initial target PE (CHfor initial target PE (CH22=CH=CH22) a~ 0.15) a~ 0.15
or Polystyrene Cor Polystyrene C66HH55CH=CHCH=CH22 a~ 0.05 a~ 0.05
Ellipse: 6Ellipse: 6 major-axis 162 mm, minor axis 60 mmmajor-axis 162 mm, minor axis 60 mm thickness 150thickness 150µm CHµm CH22 equivalent equivalent
SupportSupport
• from DC frame- from DC frame- rotatable rotatable or translational or translational
Prototypes be investigated at UCIPrototypes be investigated at UCI
Target orientationTarget orientation
Monte-Carlo just about finishedMonte-Carlo just about finished
Various solutions under study:Various solutions under study: UCI/PSI/KEKUCI/PSI/KEK
Permanent Muon TargetPermanent Muon Target• Rohacell foam/CHRohacell foam/CH2 2 combination combination • Complete Rohacell Complete Rohacell (too thick 2.3 - 5.3 mm)(too thick 2.3 - 5.3 mm)• CHCH22 or polystyrene Target + wire frame or polystyrene Target + wire frame
MOST LIKELY MATERIALMOST LIKELY MATERIALfor initial target PE (CHfor initial target PE (CH22=CH=CH22) a~ 0.15) a~ 0.15
or Polystyrene Cor Polystyrene C66HH55CH=CHCH=CH22 a~ 0.05 a~ 0.05
Ellipse: 6Ellipse: 6 major-axis 162 mm, minor axis 60 mmmajor-axis 162 mm, minor axis 60 mm thickness 150thickness 150µm CHµm CH22 equivalent equivalent
SupportSupport
• from DC frame- from DC frame- rotatable rotatable or translational or translational
Prototypes be investigated at UCIPrototypes be investigated at UCI
Target orientationTarget orientation
Monte-Carlo just about finishedMonte-Carlo just about finished
DC Support Structure
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 66
Target Target ParkingParking
In-Beam PositionIn-Beam Position Parked PositionParked Position
DCDCStructureStructure
InsertionInsertionBellowsBellows
Target Parking possible by simple RotationTarget Parking possible by simple RotationTarget Parking possible by simple RotationTarget Parking possible by simple Rotation
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 77
Target Parking cont.Target Parking cont.
DC-extentDC-extent
InsertionInsertionBellowsBellows
TargetTarget
Simple target RotationSimple target Rotation possiblepossibleShown: Shown: = 0 = 0 ̊ Beam̊ Beam 52 ̊ Touching 52 ̊ Touching 80 ̊ Parked80 ̊ Parked
Peter-Raymond KettlePeter-Raymond Kettle Tokyo - Topical Meeting, March 2006Tokyo - Topical Meeting, March 2006 88
ScheduleSchedule
US: Manufacture ~ Beg. May EARLIER???US: Manufacture ~ Beg. May EARLIER???US: Manufacture ~ Beg. May EARLIER???US: Manufacture ~ Beg. May EARLIER???
DS: Manufacture ~ Mid June EARLIER ???DS: Manufacture ~ Mid June EARLIER ???DS: Manufacture ~ Mid June EARLIER ???DS: Manufacture ~ Mid June EARLIER ???