TRANSCRIPT
![Page 1: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/1.jpg)
INTRODUCTIONTo The
City Light Department
Presentation to the Budget CommitteeAugust 2010
![Page 2: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/2.jpg)
PRESENTATION OUTLINE
City Light at a Glance
- Physical Plant
- Budget and Organization
Trends
Benchmarks
Challenges
2
![Page 3: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/3.jpg)
Physical Plant
![Page 4: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/4.jpg)
At its most basic, City Light is charged with meeting the
electricity needs of its customers. To do this it
• Own and operates electricity generating plants
• Owns and operates an electricity delivery system
• Has long-term contracts to purchase electricity
• Continually trades electricity in the wholesale market
Although a City department in every respect, the revenues City Light
generates and the resources it owns can be used only for utility purposes
4
Function
![Page 5: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/5.jpg)
Transmission/Substations Distribution System Customer End SystemsGeneration
Substation Control System
Substation Control System
Distribution Network
MTR
MTR
MTR
7 dams
26 powerhouse
transformers
660 Circuit Miles
of Transmission
(20 miles UG)
2,400 mi. Distribution• 450 mi UG
• 160 mi UG Network
53,720 Transformers
170 Electric Feeders
108,000 Poles
84,000 Street Lights
Next slide …
Vertically Integrated Utility
5
![Page 6: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/6.jpg)
Transmission/Substations Distribution System Customer End SystemsGeneration
Substation Control System
Substation Control System
Distribution Network
MTR
MTR
MTR
7 dams
26 powerhouse
transformers
660 Circuit Miles
of Transmission
(20 miles UG)
2,400 mi. Distribution• 450 mi UG
• 160 mi UG Network
53,720 Transformers
170 Electric Feeders
108,000 Poles
84,000 Street Lights
Next slide …
Vertically Integrated Utility
6
$630 M $3,400 M $60 M$3,000 M
![Page 7: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/7.jpg)
7
Service Territory• 130-square-mile service
territory
• Seattle & seven franchise areas
• 15 major substations
• Service area population: 750,000
• 400,000 meters – 80% in Seattle
• 10th largest Public Power utility in the US and largest in the Northwest (by customers served)
![Page 8: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/8.jpg)
Generation Resources
Owned Hydro Plants
Long-term Hydro Contract
Treaty Rights From British Columbia
Long-term Green Power Contracts
Snake River
Boise River
Spokane River
Pend Oreille River
Columbia River
Skagit River
Cedar
River
Skagit
Projects
Newhalem
South Fork Tolt
Cedar Falls
Priest
Rapids
GCPHA
Projects
Lucky
Peak
Boundary
High Ross (Canada)
Stateline WindColumbia Ridge
Biomass
Bonneville Power
Administration (BPA) includes multiple projects
across the Pacific
Northwest
8
![Page 9: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/9.jpg)
9
Generation & DemandUnder Average Hydro Conditions
![Page 10: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/10.jpg)
Role of Wholesale Market
10
![Page 11: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/11.jpg)
Budget & Organization
![Page 12: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/12.jpg)
Organizational StructureJorge Carrasco
Chief of Staff
Vacant
Customer Service & Energy Delivery
Phillip West
Financial Service
Phillip Leiber
Power Supply & Environ’l Affairs
Steve Kern
Human Resources
DaVonna Johnson
Internal Compliance
Mike Haynes
Govt. & Legislative Affairs
Customer Care Finance Integrated Resource Planning
Talent Acquisition Security & Emergency Mgmt
Communications & Public Affairs
Energy Delivery (Operations)
Accounting Power Operations & Marketing
Labor Relations
Energy Delivery (Engineering)
Risk Mgmt & Strategic Planning
Conservation Resources
Safety
Asset Management Corporate Performance
Utility Support Services
Employee Relations
System Operations Information Technology
Power Contracts & Resource Acq’n
Environmental Affairs
Power Production
O&M: $3.1M $85.5M $28.9M $512.2M $6.5M $1.8M CIP: - $109.1M $6.4M $46.2M - $3.0M FTE: 20 1,068 205 475 58 15
![Page 13: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/13.jpg)
2010 Adopted Budget: USESTotal = $1.1 Billion; Amounts shown in Millions
13
** Includes short-term purchases,
excludes costs of owned generation.
![Page 14: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/14.jpg)
14
2010 Adopted Budget: SOURCESTotal = $1.1 Billion; Amounts shown in Millions
**Gross Revenues
14
![Page 15: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/15.jpg)
15
2010-2015 Six-Year CIP: USESTotal = 1.27 Billion; Amounts shown in Millions
![Page 16: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/16.jpg)
16
2010-2015 Six-Year CIP: SOURCESTotal = $1.2 Billion; Amounts shown in Millions
![Page 17: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/17.jpg)
Controllable O&MTotal = $159.6 Million; Amounts shown in Millions
17
![Page 18: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/18.jpg)
Trends
![Page 19: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/19.jpg)
19
Recent Rate History
Energy Crisis, 58%
Pass-through of
lower BPA costs
8.4% reduction
13.8% increase
Rates expressed in 2009 dollars
![Page 20: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/20.jpg)
20
Recent Load History
![Page 21: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/21.jpg)
21
Debt Outstanding
Energy Crisis
![Page 22: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/22.jpg)
Total Expenditures
22
![Page 23: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/23.jpg)
Administrative Costs
23
58% Inc. since 2000
![Page 24: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/24.jpg)
Authorized FTE
24
Note: Changes are exaggerated by vertical scale
![Page 25: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/25.jpg)
T&D Overtime Costs
25
![Page 26: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/26.jpg)
Benchmarks
![Page 27: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/27.jpg)
27
Rate ComparisonCents/kilowatt-hour
Includes 4.5%
Surcharge
![Page 28: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/28.jpg)
28
Bill Comparison
Large Biotech
![Page 29: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/29.jpg)
29
Bill Comparison
Box-store/Office Tower
![Page 30: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/30.jpg)
30
Bill Comparison
Medium Industrial
![Page 31: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/31.jpg)
31
Bill Comparison
Small Manufacturing
![Page 32: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/32.jpg)
T&D SystemExpense Per Customer
32
![Page 33: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/33.jpg)
33
T&D SystemExpense Per MWh of Load
![Page 34: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/34.jpg)
Challenges
![Page 35: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/35.jpg)
T&D Issues• Aging Distribution Infrastructure
• External Drivers: Utility Relocations & Regional
Transmission Issues
• System Enhancement
Generation Issues• Resource Acquisition Costs
• Boundary Relicensing Cost
Utility Wide: Aging workforce
35
Challenges
![Page 36: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/36.jpg)
36
Aging InfrastructurePoles, For Example
![Page 37: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/37.jpg)
37
External Cost Drivers
Total = $173 M
![Page 38: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/38.jpg)
System Enhancements
System Automation (SCADA)
Smart Meters
• 400,000+ Meters; ~ 40% over 30 years old
• Replacement cost > $100 million
Smart Grid
38
![Page 39: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/39.jpg)
T&D Issues• Aging Distribution Infrastructure
• External Drivers: Utility Relocations & Regional
Transmission Issues
• System Enhancement
Generation Issues• Resource Acquisition Costs
• Boundary Relicensing Cost
Utility Wide: Aging workforce
39
Challenges
![Page 40: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/40.jpg)
Boundary Dam License
Total Generating
Capacity: 1,070 MW
Produces around 27% of
City Light’s power
Critical to Meeting Daily
Load Peaks
Relicense Expense Will
Likely Double $/MWh
From the Plant
40
![Page 41: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/41.jpg)
Resource Acquisition
380,000 MWh of Renewable Energy or
Credits by 2016
$/MWh Typically 3-4 Times City Light’s
Current Average Power Costs
Will Add ~ 3% to Base Rates
41
![Page 42: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/42.jpg)
T&D Issues• Aging Distribution Infrastructure
• External Drivers: Utility Relocations & Regional
Transmission Issues
• System Enhancement
Generation Issues• Resource Acquisition Costs
• Boundary Relicensing Cost
Utility Wide: Aging workforce42
Challenges
![Page 43: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/43.jpg)
43
Workforce% of Workforce Eligible to Retire
![Page 44: To The City Light Departmentclerk.ci.seattle.wa.us/~public/meetingrecords/2010/budget20100816… · 8/16/2010 · At its most basic, City Light is charged with meeting the electricity](https://reader034.vdocuments.us/reader034/viewer/2022052010/6020b2f84e7b4753a27c4668/html5/thumbnails/44.jpg)
Questions?