To Estimate or Not to Estimate,
Is that the Question?
#leanagileUS @mattphilipLeanAgileUS Conference, 27 Feb 2017
Hofstadter’s Law
“It always takes longer than you
expect, even when you take into
account Hofstadter’s Law.”
#leanagileUS @mattphilip
Parkinson’s Law
“Work expands so as to fill the
time available for its completion."
#leanagileUS @mattphilip
The Spectrum of Estimating
Never EstimateAnything
Always Estimate
Everything
Question purpose of estimatingInclude all sources of variation
Focus on characterizing workProbabilistic forecast
Use delivery dataLess effort spent
Estimation cultureConsider effort onlyDeterministic forecastUse intuitionHeavy effort involvedTasks in hours
#leanagileUS @mattphilip
What NoEstimates is not saying
• You are evil if you estimate
• All estimates are totally useless
• Stop doing your successful estimating practice
• Stop having the conversations to understand/analyze/break down work
• Work items must be the same size
• You must place your full faith and confidence in Monte Carlo forecasts
#leanagileUS @mattphilip
What NoEstimates is saying
• Know why you are estimating
• Discover for yourself how good you are at estimating (measure)
• Keep doing the things that help you understand the work
• Upfront estimates need to be held loosely
#leanagileUS @mattphilip
NoEstimates, Manifesto Style
… We have come to value:
Probabilistic over Deterministic
Delivery time over Development time
MVP scope over Full scope
Data over Intuition*
Reducing sources of variation over Improving estimating
That is, while there is value in the items on the right, we value the items on the left more.
*Neil Kil l ick uses “empiricism over guesswork”
#leanagileUS @mattphilip
Do You Assume Correlation?
Is the initial sizing a good predictor for when you can get your stuff? In our case, the surprising truth was ”no.”
-- Mattias Skarin, Real-World Kanban
#leanagileUS @mattphilip
What’s Going On?Low process efficiency (typically 5-15% in
software delivery) means that even if we
nailed the effort estimates … we would be
accurately predicting 5-15% of elapsed
delivery time!
-- Troy Magennis
#leanagileUS @mattphilip
Other Sources of Variation
Often system factors account for more of the elapsed delivery time than different
story sizes.
-- Troy Magennis
#leanagileUS @mattphilip
Sources of Variation
#leanagileUS @mattphilip
• WIP
• Technology/domain/product
• Team composition
• User, client and client representative
• Multitasking/focus factor
• Market and competitors
• System dependencies
• Team dependencies
• Specialization
• Waiting for availability
• Rework
• Steps/handoffs (50%*50%*50%...)
• Stages in team development (Tuckman)
• Selection policy
• Essential complication (How hard a problem
is on its own)
• Accidental complication (“How much we
suck at our jobs” -Rainsberger)
Keogh’s “Scale of Ignorance”
1. Just about everyone in the world has done this.
2. Lots of people have done this, including someone on our team.
3. Someone in our company has done this, or we have access to expertise.
4. Someone in the world did this, but not in our organization (and probably at a
competitor).
5. Nobody in the world has ever done this before.
#leanagileUS @mattphilip
What You Can Do About Variation
• Lower WIP
• ConWIP/System WIP
• Five Focusing Steps
• Blocker clustering
• Reduce workflow stages
• Explicit policies
• Cost of Delay scheduling, sequencing and selection
#leanagileUS @mattphilip
Lean
-Kan
ban
What You Can Do About Variation
• “Agile 101” (simple, decoupled design; thin vertical slices; pairing)
• Identify/make visible/measure dependencies
• Collaborate/Share work (Dimitar Bakardzhiev)
• Spike and stabilize (Dan North)
• Reduce accidental complexity (Liz Keogh)
#leanagileUS @mattphilip
Team
Why?
NoEstimates and the Business
• Determine what actions would be different based on the estimate
• Customer-based fitness criteria
• Budgeting: Team run rate
• Focus conversation on value, not cost
• MVP and product ownership
• Create probabilistic forecast ASAP (as soon as you have data) – together!
• Service-Delivery Reviews
• Teams: Keep teams together, dedicated (reduces context-switching, Tuckman stages)
#leanagileUS @mattphilip
To Estimate or Not to Estimate?
Never EstimateAnything
Always Estimate
Everything
Question purpose of estimatingInclude all sources of variation
Focus on characterizing workProbabilistic forecast
Use delivery dataLess effort spent
Estimation cultureConsider effort onlyDeterministic forecastUse intuitionHeavy effort involvedTasks in hours
#leanagileUS @mattphilip
A better question:What can you do to maximize value and
reduce risk in planning and delivery?
• noestimatesbook.com (Vasco Duarte)
• focusedobjective.com (Troy Magennis)
• actionableagile.com (Dan Vacanti)
• infoq.com/articles/noestimates-monte-carlo
(Dimitar Bakardzhiev)
• priceonomics.com/why-are-projects-always-
behind-schedule/
• scrumandkanban.co.uk/estimation-meets-
cynefin/
• ronjeffries.com
• lizkeogh.com
• neilkillick.com
• zuill.us
• mattphilip.wordpress.com/tag/noestimates
References and More Info
#leanagileUS @mattphilip