TMS is an “Add-In” software application designed to “Support & Report” the progress for any kind of project (from small and simple to large and complex) managed with Oracle Primavera P6 and/or Microsoft Project

TRANSCRIPT

Page 1: TMS (Technical Monitoring System)

echnical onitoring ystemAdd in Software for Oracle Primavera P6 & Microsoft Project

Page 2: TMS (Technical Monitoring System)

TMS is an «Add-In» software application designed to

the progress for any kind of project managed with

ORACLE® PRIMAVERA P6 or MICROSOFT PROJECT

2

Page 3: TMS (Technical Monitoring System)

Unique Features not available in your Planning

System

High level Support provided by a

Project Control Professional Team

Specific Module for Construction Progress Control

Integrates with other CLA

APPLICATIONS

High Quality Progress Reports in Excel™ Format

Software open and evolving

3

Page 4: TMS (Technical Monitoring System)

2) Create Calendar & Timescales

1) Define Weighting Structure

4) Calculate Baseline Progress

5) Define Alternative Views

6) Generate Baseline Reports

3) Get Baseline Data from Scheduling System

4

Page 5: TMS (Technical Monitoring System)

1) Define Work Class Library

2) Define C3 Settings

3) Autogenerate C3 Project Work Class Structure

4) Populate C3 Items details

ImportExport

5) Export Workbooks for External Data Entry

6) Import & Consolidate External Data Entry

Export File for Schedule Updating

SUBCONTRACTORSSUB1 SUB2 SUB3 SUB4

CLA Applications Software fromother vendors or in-house

5

The C3 Module can also work as a «Stand-alone Progress Data Collector» independent from the Scheduling System

Page 6: TMS (Technical Monitoring System)

Get quantities from CLA external applications or other vendors

Import Neutral Excel File Export Neutral Excel File

SEND Quantity Data to TMS selected work classes

GET Quantity Data from TMS selected Work Classes Validations

Checks

6

Page 7: TMS (Technical Monitoring System)

1) Get Current Data from Scheduling System

3) Calculate & Store Actual Progress

4) Calculate Forecast Progress

5) Generate Reports

2) Perform Inconsistency Checks

Engineering updated info Procurement updated info

Construction updated info from TMS C3 Module

Updated Current schedule

7

Page 8: TMS (Technical Monitoring System)

• One Original Baseline (BL1) Schedule

• One Revised Baseline (BL2) Schedule (if any)

• One Updated Schedule at each predefined cut off

The required Schedule info will be exported in Excel

using Oracle Primavera «P6 Report Wizard/Editor» or

Microsoft Project «Export Wizard»

8

Page 9: TMS (Technical Monitoring System)

9

Page 10: TMS (Technical Monitoring System)

10

Page 11: TMS (Technical Monitoring System)

• User-defined unlimited levels• Imposed or calculated weights from Schedule Data• Import/export in Excel™ format (97/2013)

11

Page 12: TMS (Technical Monitoring System)

12

Main WS Hierarchical Codes

Main WS Lowest Level Code (associated to the Schedule Activity)

Main WS Classification Codes (associated to the Main WS Lowest Levels)

Schedule Activity Codes (imported from the Scheduling System)

C3 Item Codes (Associated to the C3 Item Codes)

Page 13: TMS (Technical Monitoring System)

13

Page 14: TMS (Technical Monitoring System)

14

We can select from a different Cut off Types :

- Monthly (last day of each month)- Weekly (each specified day of the Week)- Daily ( All Calendar Days)- Every selected Day of each month- Every selected «last day of the week» (i.e.

Last Sunday) of each month

Page 15: TMS (Technical Monitoring System)

If you are a Consortium Leader and you need to consolidate Actual Progress of a Partner

(externally calculated) in the Overall Client Project Progress you can import Custom Actual

Progress in Excel format at the Lowest Level of your defined Weighting Structure

Planned Values are exported from TMS as a reference15

Page 16: TMS (Technical Monitoring System)

• Exported in Excel• Up to 10 Selectable distribution series• Selectable timescale & level of detail• Multiple progress views

16

Page 17: TMS (Technical Monitoring System)

• User Defined

• Cross Projects

• Project Specific

• Max 10 Steps

• Excel Import/Export

17

Page 18: TMS (Technical Monitoring System)

• Export in Excel of a protected workbook for external data entry• Automatic progress calculation at any level• Import & Consolidation of updated workbook in TMS

18

Page 19: TMS (Technical Monitoring System)

19

We can define unlimited number of UDP’s to be associated to each C3 Item.UDP are common to all C3 Items but we can define specific UDP to be applied only to a specific Work ClassWe can define the format for each UDP (Number, Date, Text)UDP can be exported from one project and imported in another project

Page 20: TMS (Technical Monitoring System)

You can compose the hierarchy, you can apply filters, you can select the columns, the columns order and the sort.Layout Specs are saved and you can export specs from one project and import them in another project

20

Page 21: TMS (Technical Monitoring System)

Hierarchical Layout

Flat Layout

21

Page 22: TMS (Technical Monitoring System)

22

You can create and save unlimited Distribution Profiles

You can globally apply the selected Profile to all Activities of a specific Main WS Node and to a specific Spread Type

Optionally, you can apply the selected profile only to Activities with duration more than «x» days

When you change the Percent Value the Chart is changing accordingly

Page 23: TMS (Technical Monitoring System)

23

Exported Excel File Format as required by :

Exported Excel File Format as required by :

From the C3 Module we can export two separated preformatted excel files ready to be imported as it is in Oracle P6 or MS Project with Actual Data for Schedule Updating

Page 24: TMS (Technical Monitoring System)

24

If «C3 Module only» is flagged not all icons are active but still we have a facility to Store Actuals at each Cut off and export Actuals for updating the Scheduling System

Page 25: TMS (Technical Monitoring System)

25

In a few minutes and in a 4 steps we are ready to start to collect progress:1) Create a Main WS2) Create a Cut off Calendar & Timescales3) Import Basic Data from Excel4) Autogenerate a Work Class Structure

TMS can be used also as

«Progress Data

Collector» without any

Schedule Link

Basic Data imported from Excel or manually inputted

«Excel Like» Commands available

Page 26: TMS (Technical Monitoring System)

26

Just Activate the «Chart Renderer» Command and click on a specific Main WS Level and the Pie chart will appear

A Tab with «Data» is also available in the Chart

Page 27: TMS (Technical Monitoring System)

27

Just Activate the «Chart Renderer» Command and click on a specific Progress View Level and the Progress Curves will appear

Available in all Progress Views combinations (Alternative Views)

Page 28: TMS (Technical Monitoring System)

28

We can edit for each Main WS Lowest level the Cumulated Stored Progress at each cut off, and, consequently, Weighting Factors and Units (Period & Cumulated) will be automatically recalculated

Page 29: TMS (Technical Monitoring System)

29

We can edit for each Schedule Activity the Cumulated Stored Progress % at each cut off, and, consequently, Weighting Factors and Units (Period & Cumulated) will be automatically recalculated

Option to recalculate the progress at Main WS Lowest level

Page 30: TMS (Technical Monitoring System)

30

We can edit for each Work Class the Cumulated Stored Progress % at each cut off, and, consequently, Weighting Factors and Units (Period & Cumulated) will be automatically recalculated

Page 31: TMS (Technical Monitoring System)

31

Backup includes TMS Project Files and All the Excel Working files (Qualification Templates and Export Files from Primavera P6 or MS Project)

When you restore a Project you can also restore «All» or «Selected Working Files» in the same Original Pathname or in another selected Pathname.Folders are automatically created if not existing

Page 32: TMS (Technical Monitoring System)

1. All Reports are in Excel Format (2003 / 2013)

2. Reports specs are saved (Report ready to run)

3. High Level of Customization

4. Multiple Progress Views (using Alternative WS)

5. Selectable Level of details

6. Selectable Baseline Comparison

7. Selectable Time interval (From – To)

8. Selectable Timescales (Weekly, Monthly, Custom)

9. Up to 10 Selectables Progress Series

32

Page 33: TMS (Technical Monitoring System)

33

Report Specs can be saved linked to the project

Report specs are maintained in Copy, Backup and Restore

Report Specs can be exported

Report Specs can be imported

Just select a Report and run it

Page 34: TMS (Technical Monitoring System)

• Selectable level of detail

• Selectable comparison

• Selectable period

• Selectable progress view34

Page 35: TMS (Technical Monitoring System)

• Drill down up to activity level

• Organized by subcontractors

• Grouped by work class35

Page 36: TMS (Technical Monitoring System)

• Up to 10 Selectable distribution series

• Selectable timescale

• Selectable content36

Page 37: TMS (Technical Monitoring System)

37

• Focus on Data Date• Selectable number of period before Data Date• Selectable Series & Timescales

Page 38: TMS (Technical Monitoring System)

38

• Long Periods representation• Current Status at Data Date• Selectable Series & Timescales

Page 39: TMS (Technical Monitoring System)

39

• Up to 10 Selectable Distribution Series

• Selectable Timescale & Level of Detail

• Multiple Progress Views

Page 40: TMS (Technical Monitoring System)

40

Old Historical Status New Revised Baseline

Page 41: TMS (Technical Monitoring System)

41

Page 42: TMS (Technical Monitoring System)

42

• Up to 8 Summary Bars with user defined content• Selectable timescale• Selectable series

Page 43: TMS (Technical Monitoring System)

43

Page 44: TMS (Technical Monitoring System)

44

Page 45: TMS (Technical Monitoring System)

45

We can select the type of Comparison and the TMS Project to be compared

Page 46: TMS (Technical Monitoring System)

46

Page 47: TMS (Technical Monitoring System)

47

Page 48: TMS (Technical Monitoring System)

48

Milestone can be organized by Activity Code or by Cut off DatesMilestones can be filtered by Activity Codes, by «Due but not Achieved»Milestones can be sorted by Activity ID, by Planned Dates or by Forecast DatesAdded Milestones in the Current Schedule are identified with «A»

Page 49: TMS (Technical Monitoring System)

49

Page 50: TMS (Technical Monitoring System)

50

Page 51: TMS (Technical Monitoring System)

51

Page 52: TMS (Technical Monitoring System)

52

Page 53: TMS (Technical Monitoring System)

Reports Multi-Language

Report Batch (One Run for Multiple Reports)

Actions Batch (Selected actions in one Run)

Direct Access to Primavera P6 (via API) and to MS Project

C3 Module via WEB (for Subcontractors)

Actual Resource Data Collection

Earned Value Management

53