tmhs capital construction program sid sanders, vice ...€¦ · project scope 24 floor tower tpc $...
TRANSCRIPT
Rice Building InstituteSeptember 13, 2007
Sid Sanders, Vice President
Facilities Planning and Construction
TMHS Capital Construction Program
Methodist System Overview
San Jacinto
Willowbrook
Sugar Land
Medical Center
Overview of Capital Design and Construction Program
Capital Construction Program Overview(Major Projects)
Projects under Construction• Outpatient Clinic Building $331 M 1,600,000 GSF • Sugar Land Hospital Expansion $235 M 431,000 GSF• Research Institute Laboratory Building $218 M 420,000 GSF • Willowbrook Hospital Expansion $260 M 555,000 GSF
Projects in Design• Sugar Land MOB and Garage $61 M 158,000 GSF
Projects in Programming• West Houston Hospital and MOB $310 M• North Campus Hospital Expansion Unbudgeted
Projects in Conceptual Evaluation• Radiation Oncology Center Unbudgeted• Imaging Center Unbudgeted
Project Scope24 Floor towerTPC $ 331 M 760,000 GSF occupied space 846,000 GSF parking – 1370 spaces
Outpatient Clinic Building
The Methodist Hospital Research InstituteProject Scope425,000 GSF TPC $218 MSurgical Training Vivarium BSL 3 labsOfficeImaging center
TMHRITMHRI
Sugar Land Expansion
Project Scope432,000 GSF Hospital TPC $296 M158,000 GSF MOB 188 Beds950 Car Garage
Willowbrook Expansion
Project Scope555,000 GSF TPC $260 M240 Beds
North Campus Expansion Massing Concept
North Campus Expansion
PotentialProject Scope1.8 M GSF
West Houston Hospital
Project Scope200 Beds
Construction Procurement StrategyGoals• Complete a state-of-the-art Hospital and Research Facility • Optimize expenditures to maximize Clinical and Research
capability of the Facility• Meet or accelerate proposed construction schedule• Maintain project cost transparency and accountability
Challenges• Aggressive schedule• Aggressive program w/ little recent experience• Highly complex project with thousands of design decisions,
developing technologies and hundred of suppliers and subcontractors
• Price volatility• Limited supply of key subcontractors & skilled labor
Project Organization
Roles and Responsibilities
Project Director – Methodist Employee• Organizes the Methodist User Groups• Insures that the Project Meets the Goals of the
Institution• Assists the Project Manager as Needed
Project Manager – Contract Employee• Organizes all the of Consultant and Vendor Teams• Develops Overall Project Schedule• Develops Overall Project Budget• Insures the Coordinated Execution and Delivery of
the Project
Roles and Responsibilities
Architect – Consultant• Develops the Project Program and Design• Develops the Documents to Execute the Project• Coordinates the Design of all Specialty Consultants
Construction Manager – Consultant/Vendor• Responsible for Overall Construction of the Project• Develops GMP(s)• Responsible for Construction Buy-out
Construction Procurement Strategy
Use Construction Manager at Risk
Allows for aggressive scheduling and early project deliveryAllows just-in-time decision making on program elementsAllows for Guaranteed Maximum Price (GMP)Allows for high degree of collaboration and constructabilityAllows for best-value selection of major subcontractors during buy-out.
Project Life Cycle
PROGRAM
PRELIM.DESIGN
CONCEPT
PROJECT LIFE CYCLEPROJECT LIFE CYCLE
PRO
JEC
TPR
OJE
CT
EX
PEN
DIT
UR
ES
EX
PEN
DIT
UR
ES
FINALDESIGN
BUY-OUT
CONSTRUCTIONFURN./ COMM.
LE
VE
L o
f L
EV
EL
of
INFL
UE
NC
EIN
FLU
EN
CE
Selection of Construction Manager
Cost Curve
Influence Curve
Construction Procurement Strategy
CM-R Part I – Pre-Construction Service
Collaboration in design as member of project teamEvaluation of project constructabilityMaintenance and acceleration of scheduleForecasting costs using market informationContinually optimize project budget with design alternativesAssess early selection of subcontractorsNegotiation of a comprehensive Guaranteed Maximum Price (GMP)
Construction Procurement Strategy
CM-R Part II – Construction Service
All costs of work are competitively procured using best-value selectionIncorporate design-assist subcontractors previously selectedBid package strategy allows for optimal decision-making on technology procurementAccelerates scheduleAllows early involvement of major subcontractors and manufacturersAllows best-value selection of subcontractors
Construction Procurement Strategy
Part I Services• Pre-Construction Services – Lump sum
Part II Services – Guaranteed Maximum Price • Construction Phase Fee – Lump sum• General Conditions – Open book, Not-to-Exceed • Cost of Work – Open book, competitively procured• Buy-out Contingency – Joint controlled, Not-to-Exceed• Special Allowances – Owner controlled, lump sum - specified
All savings revert to owner
Construction Procurement strategyCM-R Contract Elements
Project Life Cycle
PROGRAM
PRELIM.DESIGN
CONCEPT
PROJECT LIFE CYCLEPROJECT LIFE CYCLE
PRO
JEC
TPR
OJE
CT
EX
PEN
DIT
UR
ES
EX
PEN
DIT
UR
ES
FINALDESIGN
BUY-OUT
CONSTRUCTIONFURN./ COMM.
LE
VE
L o
f L
EV
EL
of
INFL
UE
NC
EIN
FLU
EN
CE
Selection of Construction Manager
Cost Curve
Influence Curve
Construction Procurement Strategy
Problems with this ProcessCritical innovation and creativity exist in the SC and MFG FirmsStandard CM-R procurement leaves out the scoping and design documentation of projectThe procurement “below” the CM-R tends to become design-bid-build (slowest & least innovative procurement)Key parts of project are redrawn in shop drawing process by selected SC & MFG
Construction Procurement StrategyLimitation of CM-R Procurement – Key Subcontractors (SC) and Manufacturers (MFG) are not Selected until Design & Documents are Completed during the Buy-Out
Conundrum• Capital Projects take 3 to 5 years to complete• Reimbursement environment changes• Market changes• Diagnostic/treatment technology changes• Clinical therapies change
More information is needed earlier in project conceptualizationOnce commitment is made time-to-market is criticalMaximizing facility flexibility is essential
Construction Procurement Strategy
Project Life Cycle
PROGRAM
PRELIM.DESIGN
PROJECT LIFE CYCLEPROJECT LIFE CYCLE
PRO
JEC
TPR
OJE
CT
EX
PEN
DIT
UR
ES
EX
PEN
DIT
UR
ES
FINALDESIGN
BUY-OUT
CONSTRUCTION
FURN./ COMM.
LE
VE
L o
f L
EV
EL
of
INFL
UE
NC
EIN
FLU
EN
CE
Selection of Construction Manager
Cost Curve
Influence Curve
Construction Procurement Strategy
Construction Procurement StrategyConstruction Manager at Risk (CM-R) with Design-Assist
SubcontractorsGoal: Move up key subcontractors in process as Design-Assist agents
Project Management
Team
ConstructionManager
A/E
Subcontractor SubcontractorSubcontractor
Methodist
Challenges to Early SC Selection
How to keep early selection SC competitive in final pricingDesign team and construction team naturally revert to traditional rolesReluctance to step out of traditional roles due to unknown risk issuesMany SCs do not have design assist capabilityMany CMRs and SCs are reluctant to commit to GMPs until construction documents are well developed
Emerging Opportunities
Integrating design of multiple-disciplines thru object-based 3D modeling• Use of collision detection software in design• Integrating shop drawings with CDs
Use of building information modeling (BIM)• Still more promise than reality
Off site fabrication of subsystems