tm financing transit p3s 101 and 1001 · tm financing transit p3s 101 and 1001 partnerships in...

35
B r i n g i n g B u s i n e s s t o G o v e r n m e n t TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President [email protected] 4733 Bethesda Ave, Suite 600 Bethesda, MD 20814 www.imggroup.com 301-907-2900

Upload: others

Post on 27-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

B r i n g i n g B u s i n e s s t o G o v e r n m e n t TM

Financing Transit P3s 101 and 1001 Partnerships in Transit September 18 2008

Sasha Page Vice President SPageIMGgroupcom

4733 Bethesda Ave Suite 600 Bethesda MD 20814 wwwimggroupcom

301-907-2900

Contents

Understand todayrsquos issues

Define the P3 project

Define the nature of the P3

Maximize innovative finance sources

Case studies

September 18 2008 Financing Transit P3s Page 2

UNDERSTAND TODAYrsquoS ISSUES

September 18 2008 Financing Transit P3s Page 3

Infrastructure needs are increasing

Summary of Range of ldquoHighrdquo Average Annual Capital Investment Levels Analyzed for All Modes (Billions of Constant Dollars)

1The estimated ldquoCurrently Sustainablerdquo funding for highways and transit is based on short-term Federal Highway Trust Fund revenue projections and assumes State local and private funding remains steady in constant dollar terms (ie growth equals inflation) while the estimate for freight rail assumes that private freight rail capital investment keeps pace with revenue growth The amount shown for intercity passenger rail assumes estimated current capital investment by Amtrak and State governments remains steady in constant dollar terms 2 The combined figures do not account for cross-modal impacts

Source National Surface Transportation Policy and Revenue Study Commission Transportation for Tomorrow December 2007 p 6

September 18 2008 Financing Transit P3s Page 4

Grant funding is declining

Projections of Highway and Transit The major source of Account Balances Through 2012 funding for highway and

transit transportation infrastructure fuel taxes is declining

The Highway Account Balance (Trust Fund) is in deficit transit by 2012 or sooner

Source National Surface Transportation Policy and RevenueStudy Commission Transportation for Tomorrow December2007 p 40

September 18 2008 Financing Transit P3s Page 5

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 2: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Contents

Understand todayrsquos issues

Define the P3 project

Define the nature of the P3

Maximize innovative finance sources

Case studies

September 18 2008 Financing Transit P3s Page 2

UNDERSTAND TODAYrsquoS ISSUES

September 18 2008 Financing Transit P3s Page 3

Infrastructure needs are increasing

Summary of Range of ldquoHighrdquo Average Annual Capital Investment Levels Analyzed for All Modes (Billions of Constant Dollars)

1The estimated ldquoCurrently Sustainablerdquo funding for highways and transit is based on short-term Federal Highway Trust Fund revenue projections and assumes State local and private funding remains steady in constant dollar terms (ie growth equals inflation) while the estimate for freight rail assumes that private freight rail capital investment keeps pace with revenue growth The amount shown for intercity passenger rail assumes estimated current capital investment by Amtrak and State governments remains steady in constant dollar terms 2 The combined figures do not account for cross-modal impacts

Source National Surface Transportation Policy and Revenue Study Commission Transportation for Tomorrow December 2007 p 6

September 18 2008 Financing Transit P3s Page 4

Grant funding is declining

Projections of Highway and Transit The major source of Account Balances Through 2012 funding for highway and

transit transportation infrastructure fuel taxes is declining

The Highway Account Balance (Trust Fund) is in deficit transit by 2012 or sooner

Source National Surface Transportation Policy and RevenueStudy Commission Transportation for Tomorrow December2007 p 40

September 18 2008 Financing Transit P3s Page 5

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 3: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

UNDERSTAND TODAYrsquoS ISSUES

September 18 2008 Financing Transit P3s Page 3

Infrastructure needs are increasing

Summary of Range of ldquoHighrdquo Average Annual Capital Investment Levels Analyzed for All Modes (Billions of Constant Dollars)

1The estimated ldquoCurrently Sustainablerdquo funding for highways and transit is based on short-term Federal Highway Trust Fund revenue projections and assumes State local and private funding remains steady in constant dollar terms (ie growth equals inflation) while the estimate for freight rail assumes that private freight rail capital investment keeps pace with revenue growth The amount shown for intercity passenger rail assumes estimated current capital investment by Amtrak and State governments remains steady in constant dollar terms 2 The combined figures do not account for cross-modal impacts

Source National Surface Transportation Policy and Revenue Study Commission Transportation for Tomorrow December 2007 p 6

September 18 2008 Financing Transit P3s Page 4

Grant funding is declining

Projections of Highway and Transit The major source of Account Balances Through 2012 funding for highway and

transit transportation infrastructure fuel taxes is declining

The Highway Account Balance (Trust Fund) is in deficit transit by 2012 or sooner

Source National Surface Transportation Policy and RevenueStudy Commission Transportation for Tomorrow December2007 p 40

September 18 2008 Financing Transit P3s Page 5

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 4: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Infrastructure needs are increasing

Summary of Range of ldquoHighrdquo Average Annual Capital Investment Levels Analyzed for All Modes (Billions of Constant Dollars)

1The estimated ldquoCurrently Sustainablerdquo funding for highways and transit is based on short-term Federal Highway Trust Fund revenue projections and assumes State local and private funding remains steady in constant dollar terms (ie growth equals inflation) while the estimate for freight rail assumes that private freight rail capital investment keeps pace with revenue growth The amount shown for intercity passenger rail assumes estimated current capital investment by Amtrak and State governments remains steady in constant dollar terms 2 The combined figures do not account for cross-modal impacts

Source National Surface Transportation Policy and Revenue Study Commission Transportation for Tomorrow December 2007 p 6

September 18 2008 Financing Transit P3s Page 4

Grant funding is declining

Projections of Highway and Transit The major source of Account Balances Through 2012 funding for highway and

transit transportation infrastructure fuel taxes is declining

The Highway Account Balance (Trust Fund) is in deficit transit by 2012 or sooner

Source National Surface Transportation Policy and RevenueStudy Commission Transportation for Tomorrow December2007 p 40

September 18 2008 Financing Transit P3s Page 5

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 5: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Grant funding is declining

Projections of Highway and Transit The major source of Account Balances Through 2012 funding for highway and

transit transportation infrastructure fuel taxes is declining

The Highway Account Balance (Trust Fund) is in deficit transit by 2012 or sooner

Source National Surface Transportation Policy and RevenueStudy Commission Transportation for Tomorrow December2007 p 40

September 18 2008 Financing Transit P3s Page 5

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 6: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Capital costs are increasing

September 18 2008 Financing Transit P3s Page 6

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 7: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Oil prices were increasing

Monthly Refiner Cost of Crude Oil Composite

-

2000

4000

6000

8000

10000

12000

14000

Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08

Do

llar

s p

er B

arre

l

Source wwweiadoegovpuboil_gaspetroleumdata_publicationspetroleum_marketing_monthly currenttxttables01txt

September 18 2008 Financing Transit P3s Page 7

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 8: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Other trends influence demand for transit Road congestion is increasing

Increased environmental sensitivity

Desire to reduce dependence on foreign oil

Aging population points to smaller homes reduced car use and new urbanist approaches

September 18 2008 Financing Transit P3s Page 8

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 9: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

DEFINE THE P3 PROJECT

September 18 2008 Financing Transit P3s Page 9

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 10: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Streamline the capital program

September 18 2008 Financing Transit P3s Page 10

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 11: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Agree on realistic OampM costs

Client

September 18 2008 Financing Transit P3s Page 11

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 12: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Assume defensible ridership forecasts and revenues

Last forecasted fare increase

Fare increases are assumed between years 2009 to 2025

Client

Client without fare increase

September 18 2008 Financing Transit P3s Page 12

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 13: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Settle on appropriate recovery ratio targets

September 18 2008 Financing Transit P3s Page 13

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 14: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

DEFINE THE NATURE OF THE P3

September 18 2008 Financing Transit P3s Page 14

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 15: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Position the P3 on the risk transfer spectrum

Project Debt

Vendor Innovative Finance

Design-Build Contracts

RISK TRANSFER TO PRIVATE PARTNER

Operations

Private Concession

September 18 2008 Financing Transit P3s Page 15

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 16: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Properly allocating P3 risk improves a P3srsquo long-term success

Contractor Developer or

Partner

Public Partners

Pre-Development Phase X

Financial Plan X X

Public Funding Risks X

Revenue amp Debt Financing Risks X X

ROW Cost Risks X

DBOM Terms amp Conditions X

Construction Cost Risks X

OperatingPerformance Risks X

Maintenance Risks X

September 18 2008 Financing Transit P3s Page 16

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 17: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

A concession is the most complex P3 but best for financial risk transfer Concession agreement

20-30 year term Shareholders Debt

Define municipal contribution fare-setting amp operations design parameters

Benefits Encourages efficiency and

innovation Can enable faster project

delivery

Special Purpose Vehicle

Developer Civil

Municipality

OampM

Allows for transfer of key risks Avoid cost overruns delays

September 18 2008 Financing Transit P3s Page 17

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 18: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Equity helps make (greenfield) projects ldquopushing the enveloperdquo feasible

Greenfield Project Cash flows With and Without Equity

Due to ramp-up characteristics financing with ldquopublicrdquo debt is not feasible

Using equity early debt service obligations are reduced

Dividends (EBITDA) repay equity later in project

September 18 2008 Financing Transit P3s Page 18

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 19: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

19

Debt Service Reserves

Capital Expenditures

Equity Distributions

Senior Debt Service

Major Maintenance Reserve

Subordinated Debt Service

Typical Cash Flow ldquoWaterfallrdquo

Not only are dividends deferred but equityrsquos repayment is subordinate

Gross Revenues

OampM Costs

Equity is paid at the bottom of the (annual) cash waterfall

Non-payment of dividends does cause project default

September 18 2008 Financing Transit P3s Page 19

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 20: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

P3s are highly structured financings--to ensure all parties pay and are paid

Example of Combining Senior Debt TIFIA and Private Equity

September 18 2008 Financing Transit P3s Page 20

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 21: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

MAXIMIZE INNOVATIVE FINANCE SOURCES

September 18 2008 Financing Transit P3s Page 21

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 22: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Innovative finance often complements P3 financings This chart shows the effect of different financing vehicles on

dedicated local fee receipts of $99 million annually in 2010

September 18 2008 Financing Transit P3s Page 22

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 23: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

TIFIA loans can be used for up to 33 of project costs and requires at least as much senior debt (investment grade)

Today TIFIA is the best money around for innovative and P3 transit projects The Transportation Infrastructure Finance and Innovation Act

(TIFIA) is ldquodesigned to fill market gaps and leverage substantial private co-investment providing supplemental and subordinate capital and credit rather than grantsrdquo

Designed for major transportation investments of national significance including inter-modal facilities border crossing infrastructure highway corridors and transit and passenger rail facilities

September 18 2008 Financing Transit P3s Page 23

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 24: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

TIFIA is the best money for innovative and P3 transit projects (contrsquod) TIFIA typically provides favorable loan terms such as

Subordinate loans and guarantees Long-term (35-year-plus) fixed-rate debt 10 year principal grace

periods and Treasury rates 110 coverage requirement Rate fixed at financial close -- no-cost interest rate hedge

Flexibility in program design allows innovation Back-loaded debt service structures Lower payment default triggers

Tren Urbano received a TIFIA loan for $300 million A (somewhat) subordinate and patient investor ldquoUltimate Recoveryrdquo DS approach Loan Life Coverage Ratio

September 18 2008 Financing Transit P3s Page 24

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 25: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

A rental car fee-backed TIFIA loan helped fund the Warwick Intermodal Facility $200 M facility for rental car parking commuter rail bus station and

future Amtrak facility Located on former super fund site with opportunities for future office

hotel and other real estate growth

Funded with rental car charges other facility fees federal and state grants

Warwick Intermodal Center

Funding Sources

FHWA

Grants 40

State Grants

10

Rental Car

Charges

13

TIFIA Loan

19

Tax-Exempt

Bond

Proceeds

18

September 18 2008 Financing Transit P3s Page 25

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 26: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

PABs allow P3s to access the tax-exempt market Private Activity Bonds (PABs) are subject to federal (USDOT) or state

allocation ( volume caps) Total Amount of $15 billion in SAFETEA-LU authorized PABS to be

allocated by USDOT are not subject to state volume caps Can be combined with other financing mechanisms like TIFIA and

availability payments Allows private sector to finance public use projects at cost similar to

public entities Limited availability due to state limitations if not able to access

SAFETEA-LU authority

September 18 2008 Financing Transit P3s Page 26

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 27: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

PABs TIFIA and equity make a great combination

Capital Beltway Funding Sources ($ M) Dec 2007

Private Activity Bonds benchmark of 36 for 20 years + margin of 175 for 7 years (535) total 40 years

TIFIA 445 40 years lt than 25 of interest paid can cause default

PABs amp TIFIA no principal repayment first 25 years

Source ldquoCapital Beltwayrdquo Investor Briefing Transurban December 21 2007 wwwtransurbancomautransurban_onlinetu_nav_blacknsfalltitleinvestors-presentations-2007open

September 18 2008 Financing Transit P3s Page 27

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 28: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

RRIF offers rail projects loans on less subsidized terms Railroad Rehabilitation amp Improvement Financing (RRIF) is a

revolving loan and loan guarantee program administered by FRA that is legislatively enabled to issue up to $35 B

Can fund up to 100 percent of project costs and allows for 5-year repayment grace period

Funding may be used to

Acquire improve or rehabilitate

Develop or establish new intermodal or railroad facilities

Refinance outstanding debt

Eligible applicants state amp local governments railroads government sponsored authorities joint ventures

September 18 2008 Financing Transit P3s Page 28

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 29: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

CASE STUDIES

September 18 2008 Financing Transit P3s Page 29

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 30: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

CA High-Speed Rail (HSR) combines P3 innovative and grant funding

September 18 2008 Financing Transit P3s Page 30

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 31: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

HSRrsquos $30 B expected to be sourced from state feds private companies locals

Funding Sources Amount (in $B)

Public-Private Partnerships (P3) $5 to $75

State Support $9 to $125

Federal Support $10 to $125

Local Partnerships $2 to $4

Additional Funding Sources

Environmental ldquoBenefit Capturerdquo

Additional Local Corridor Cost Sharing

$05 to

$1 to $3

Total Funding $275 to $395 All figures are in 2006 dollars

September 18 2008 Financing Transit P3s Page 31

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 32: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Backed by container charges Alameda Corridor was an early innovative financing

Project Alameda Corridor Freight Project Los Angeles County CA

Description 20 mile rail cargo route connecting Ports of Los Angeles and Long Beach and rail yards near downtown LA Eliminates 200 surface street railroad crossings smoothes port cargo flow and congestion $25 billion cost Includes bull North-end grade separations and bridge replacements bull Mid-corridor 10-mile trench 50 ft wide 33 ft deep accommodating grade separated rail line ($712 million) bull South end grade separations and bridge replacements

Sponsor Alameda Corridor Transportation Authority a joint powers agency of the cities and Ports of LAand Long Beach

Type of Finance

$12 billion in revenue-backed bonds $400 million USDOT loan $394 million in grants from Ports of Long Beach and Los Angeles $347 million from Los Angeles County MTA $160 million in interest other resources

Revenues Corridor use fees and container charges

September 18 2008 Financing Transit P3s Page 32

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 33: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Alameda Corridor was an early innovative financing (contrsquod) Delivery Method

Design-Build (DB) for mid-corridor Design-Bid-Build for north and south ends

Partner Port of Los Angeles and Port of Long Beach

Project Advisors

Nossaman Guthner Knox amp Elliott LLP Aramax (formerly OMelveny amp Myers) OBrien Partners Inc

Lenders USDOT and Bondholders

Physical Status

Project opened April 15 2002

September 18 2008 Financing Transit P3s Page 33

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 34: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

IMG Group overview

Headquartered in Washington DC metro area IMGrsquos Value Positioning

Multi-disciplined team of 25 seasoned professionals with more than 150 years of

Investors infrastructure experience as authority directors city managers facility operators and financial executives

Infrastructure Developers amp Management Advisors 200+ engagements for 100+ public and private Operators Group Inc

sector agencies authorities and investors

$100+ billion (B) of deals across the Asset infrastructure lifecycle - feasibility Stakeholders

development construction finance upgrade and mature operations

Experience across 22+ US states the Americas Europe Africa and Asia

IMG Capital launched in January 2008 to serve as international investment division for investor advisory and buy-side origination

September 18 2008 Financing Transit P3s Page 34

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35

Page 35: TM Financing Transit P3s 101 and 1001 · TM Financing Transit P3s 101 and 1001 Partnerships in Transit September 18, 2008 Sasha Page, Vice President ... Levels Analyzed for All Modes

Contact

Sasha N Page

Vice President Finance

Infrastructure Management Group Inc

4733 Bethesda Avenue Suite 600

Bethesda MD 20814

Phone (301) 280-0155 Fax (301) 907-2906

Cell 301-675-3102 SPageIMGgroupcom

September 18 2008 Financing Transit P3s Page 35