TITLE TEXT Long Range Planning and Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019

Upload: others

Post on 02-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXT

Long Range Planning and Construction UpdatePresented By: Ed Holder and Scott Nielsen

February 12, 2019

Page 2: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Middle School/High School Projectso Schematic Designs

• Available for view in Johannsen Support Services Center (JSSC) Lobby through February 15 and posted online

• Shared with local municipal partners

• Next steps– Design continues to develop more detailed

construction documents– We will update the Board and community with more

detailed design documents later this spring

Page 3: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Site Plan: Prospect Site

Page 4: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Site Plan: Wellington Site

Page 5: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Middle School/High School Floorplan

Page 6: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Middle School/High School Projectso Athletics Complex at Prospect Site

• Design for a 4,000 seat district stadium at Prospect underway

• Planning a 2,500 seat stadium at Wellington– This will allow Wellington to host home games

o Lighting at the Prospect and Wellington Sites• Athletics complex will be lit • Area at and around the school will also be lit • PSD will use directional lighting and LED technology

o Closing on the Wellington Property: January 25, 2019

Page 7: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Middle School/High School Projectso Construction Management General Contractor

(CMGC) to Manage Projects• Advantages include:

– Consistent management– Access to resources, including dedicated subcontractor

pool – Potential for acceleration of completion timelines on

new construction

o Anticipated opening: Fall 2022• The Athletics Complex at the Prospect Site is anticipated to

open in Fall 2021

Page 8: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Zach Elementary School Additiono Schematic Design

• Available for view in Johannsen Support Services Center (JSSC) Lobby through February 15 and posted online

o Construction of addition to replace existing modulars will take place while school is in session• One modular will be removed before the 2019-2020 school

year • Two modulars will likely remain on site for the 2019-2020

school year, with at least one being removed for the 2020-2021 year

Page 9: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Zach Elementary School Additiono Construction Management General Contractor

(CMGC) for Project

o Anticipated completion: late 2019• Design work: Fall 2018• Construction begins: Spring 2019

Page 10: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Zach Elementary School Addition

Page 11: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• Southeast Elementary Schoolo Infrastructure Projects Continue

o HCM Selected as Architect and Approved by Board of Education on January 22, 2019

o Design is underway and will continue through early 2020

o Anticipated opening: Fall 2021

Page 12: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTOngoing Facilities Update

• $40 Million in Ongoing Facilities Improvementso Project List Finalized

o Project Timelines and Budget Codes Underway

o Purchasing for Furniture Proceeding• Shared with Office Managers and Principals on February 5

o Projects administered by Operations will be implemented over a three to four year period

Page 13: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTNew Construction Updates

• PSD Futures Labo 2019-2020 Programming at Fort Collins High

School • Entrepreneurship• iOS App Development• Unmanned Aerial Systems (Drones)• AP Seminar

o Anticipated Enrollment for 2019-2020: Up to 100 Students

o Programming Slated to Expand in 2020-2021

o Continuing to Explore Permanent Facility Options

Page 14: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTInterim Growth Management

• Modular Placements for 2019-2020:o Riffenburgh Elementary School

• Possible Modular Placements for 2020-2021 Will Continue to be Monitored

• Longer Term Growth Management Options Under Consideration

Page 15: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates

TITLE TEXTLooking Ahead

• Growth is anticipated to continue in the district

• District leadership is meeting internally to discuss potential long-term facility needs – the next long range plan

• The next 2016 bond program update to the Board is scheduled for April 2019

Page 16: TITLE TEXT Long Range Planning and Construction Update€¦ · Construction Update Presented By: Ed Holder and Scott Nielsen February 12, 2019. TITLE TEXTNew Construction Updates