    KGB REFRESH Project - KGB F5 - IL KOREA RANGE

    Proposed Launch Q1/Q2 2016

    IL Korea

    TIMELINE 5-Oct 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28- Dec 4- Ja n 11-Jan 18-Jan 25-Jan 1-Feb 8-Feb 15-Feb 22-Feb 29-Feb 7-Mar 14-Mar 21-Mar 28-Mar 4-Apr 11-Apr 18-Apr 25-Apr 2-May 9-May 16-May 23-May

    GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION

    Gate 1 Approval D ecision to Charter Project 9 Oct

    STAGE2 -Concept development& project feasibility

    PROJECT TEAM CREATED/BRIEFED

    LIQUID BRIEFED INTO R&D

    LIQUID DEVELOPMENT

    GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 27-Nov

    PRELIMINARYBUSINESS CASE- INDICITIVECOSTCARD

    Gate 2 Approval Decision to Develop

    8-Dec

    STAGE3A -CREATIVE Product development

    PHASE1- INVESTIGATION:

    INTERNAL BRAND WORKSHOP -APB & ILNZ 15-DecCOMPETITIVEOVERVIEW

    BRAND DECONSTRUCTION

    BRAND STRATEGYDOC (DRAFT)

    PHASE2- PLAY & EXPLORE

    CONCEPT EXPLORATION

    PRE-PRODUCTION CONSULTATIONS

    CONCEPT DEVELOPMENT

    CUSTOMER ENGAGEMENT (APB & IL KOREA)

    CUSTOMER FEEDBACK RECEIVED (AP B & IL KOREA)

    TESTING IN MARKET -QUAL PREFERRED

    TESTING IN MARKET - QUANT -IF TIME PERMITS

    GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 2-Feb

    Gate 3 Approval Decision to Launch

    10-Feb

    PHASE3 -DESIGN REFINEMENT

    POST RESEARCH DESIGN DEVELOPMENT

    PRE-PRODUCTION MEETING

    APB (CLIENT) APPROVAL

    BRAND WORKSHOP -KOREA 16-Feb

    BRAND WORKSHOP -CHINA - ASAHICHINA TO MANAGE 17-Feb

    PHASE4- PRODUCTION

    DRAFTARTWORK

    APB/ILNZAPPROVAL

    PREPARATION OF MASTER ARTWORK FILES

    COLOUR PROOFING

    STAGE3B -APB Product development, testing & full costing.Manufacturing strategy

    IL KOREA SKUs

    PROJECTBRIEFED INTO GRAPHICS

    ARTWORK DEVELOPMENTBASED ONFEEDBACK

    ARTWORK (1ST ROUND) TO BECIRCUL ATED WITH OP'S FOR FEEDBACK & CHANGES

    FINAL ARTWORK SIGN OFF

    FINAL APPROVED ARTWORK TO BESENTTO PRINTERS FOR PREPRESS PRODUCTION

    FINAL BOM REQUESTED

    BOM FINALISED INCLUDING FINAL PACKAGING COSTS

    PDF RECEIVED FOR APPROVAL

    PDF SIGNED OFF

    PROOF RECEIVED FOR APPROVAL - LABELS/SLEEVES,WRAPS,CARTONS

    STAGE4 - Factory trials, graphics, customer approval

    FINAL COSTCARD GENERATED WITH TERMS GENERATED FOR SIGN OFF ATGATE 4

    GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 2-Mar

    PROOF SENTFROM ILNZTO APB FOR APPROVAL - WRAPS

    PROOF SIGNED OFF -WRAPS AND CARTONS

    Gate 4 Approval Decision to go to Market

    10-Mar

    COSTCARD TO BE CIRCULATED AND SIGNED

    STAGE5 -COMMERCIALISATION

    SHUTDOWN

    BONNEYCREATIVEPROGRAM

    GATE 3 toprovideapproval toproceedto final

    stages.