KGB REFRESH Project - KGB F5 - IL KOREA RANGE
Proposed Launch Q1/Q2 2016
IL Korea
TIMELINE 5-Oct 9-Nov 16-Nov 23-Nov 30-Nov 7-Dec 14-Dec 21-Dec 28- Dec 4- Ja n 11-Jan 18-Jan 25-Jan 1-Feb 8-Feb 15-Feb 22-Feb 29-Feb 7-Mar 14-Mar 21-Mar 28-Mar 4-Apr 11-Apr 18-Apr 25-Apr 2-May 9-May 16-May 23-May
GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION
Gate 1 Approval D ecision to Charter Project 9 Oct
STAGE2 -Concept development& project feasibility
PROJECT TEAM CREATED/BRIEFED
LIQUID BRIEFED INTO R&D
LIQUID DEVELOPMENT
GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 27-Nov
PRELIMINARYBUSINESS CASE- INDICITIVECOSTCARD
Gate 2 Approval Decision to Develop
8-Dec
STAGE3A -CREATIVE Product development
PHASE1- INVESTIGATION:
INTERNAL BRAND WORKSHOP -APB & ILNZ 15-DecCOMPETITIVEOVERVIEW
BRAND DECONSTRUCTION
BRAND STRATEGYDOC (DRAFT)
PHASE2- PLAY & EXPLORE
CONCEPT EXPLORATION
PRE-PRODUCTION CONSULTATIONS
CONCEPT DEVELOPMENT
CUSTOMER ENGAGEMENT (APB & IL KOREA)
CUSTOMER FEEDBACK RECEIVED (AP B & IL KOREA)
TESTING IN MARKET -QUAL PREFERRED
TESTING IN MARKET - QUANT -IF TIME PERMITS
GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 2-Feb
Gate 3 Approval Decision to Launch
10-Feb
PHASE3 -DESIGN REFINEMENT
POST RESEARCH DESIGN DEVELOPMENT
PRE-PRODUCTION MEETING
APB (CLIENT) APPROVAL
BRAND WORKSHOP -KOREA 16-Feb
BRAND WORKSHOP -CHINA - ASAHICHINA TO MANAGE 17-Feb
PHASE4- PRODUCTION
DRAFTARTWORK
APB/ILNZAPPROVAL
PREPARATION OF MASTER ARTWORK FILES
COLOUR PROOFING
STAGE3B -APB Product development, testing & full costing.Manufacturing strategy
IL KOREA SKUs
PROJECTBRIEFED INTO GRAPHICS
ARTWORK DEVELOPMENTBASED ONFEEDBACK
ARTWORK (1ST ROUND) TO BECIRCUL ATED WITH OP'S FOR FEEDBACK & CHANGES
FINAL ARTWORK SIGN OFF
FINAL APPROVED ARTWORK TO BESENTTO PRINTERS FOR PREPRESS PRODUCTION
FINAL BOM REQUESTED
BOM FINALISED INCLUDING FINAL PACKAGING COSTS
PDF RECEIVED FOR APPROVAL
PDF SIGNED OFF
PROOF RECEIVED FOR APPROVAL - LABELS/SLEEVES,WRAPS,CARTONS
STAGE4 - Factory trials, graphics, customer approval
FINAL COSTCARD GENERATED WITH TERMS GENERATED FOR SIGN OFF ATGATE 4
GATEPAPER COMPLETEFOR PRE-READ DISTRIBUTION 2-Mar
PROOF SENTFROM ILNZTO APB FOR APPROVAL - WRAPS
PROOF SIGNED OFF -WRAPS AND CARTONS
Gate 4 Approval Decision to go to Market
10-Mar
COSTCARD TO BE CIRCULATED AND SIGNED
STAGE5 -COMMERCIALISATION
SHUTDOWN
BONNEYCREATIVEPROGRAM
GATE 3 toprovideapproval toproceedto final
stages.