time/cost trade-off analysis kathy s. schwaig. a roadmap of the project planning process develop...
TRANSCRIPT
Time/Cost Trade-off Analysis
Kathy S. Schwaig
A Roadmap of the Project Planning Process
Develop project charterEstablish work breakdown structureAnalyze sequencing relationshipsEstimate “normal” activity durationsPerform network calculationsValidate/revise initial schedulePerform time-cost tradeoff analysisLoad resources to activitiesResolve any resource/workload imbalancesDevelop budget and cash flow plan based on analysis of direct and indirect costs
Validating the ScheduleOnce the project network has been drawn and analyzed, you should check to make sure the results make sense . . . this is called validationIs the project duration reasonable?Is the critical path where you would expect it to be?Are you missing any activities? Or precedence relationships?If you are using project management software, has the data been entered correctly?
Revising the ScheduleThe schedule may be revised for many reasons
To correct errorsTo reflect changes in assumptionsTo reflect reductions in project scope (i.e., elimination of activities)To reflect changes in the project calendarIn response to changes in the approach taken to complete an activityIn response to changes in precedence relationships
Time/Cost Trade-off AnalysisTime/cost trade-off analysis is the compression of the project schedule to achieve a more favorable outcome in terms of project duration, cost, and projected revenuesObjectives of time/cost trade-off analysis
Minimize total project costs
Compress project to an acceptable duration
Done by selectively crashing specific activities to shorten project duration
Time/Cost Trade-off AnalysisYou might think that total project costs will increase when we begin to crash activitiesBut, total project costs consist of both indirect (project-based) costs (PBC) and activity-based costs (ABC)
ABC goes up when we crash activities in an effort to finish the project earlyBut, PBC (the indirect costs) goes down if we finish the project early
Which Activities are the Best Candidates for Crashing?
Any activity that is on the critical pathActivities with relatively long durationsBottleneck activities (that appear on multiple critical paths)Activities that relatively low cost to crashActivities that are not likely to cause quality problems if crashedActivities that occur relatively early in the schedule and are labor intensive
Steps for Performing Time/Cost Trade-off Analysis
1. Estimate project-based (indirect) cost per unit time
2. Identify critical activities that are good candidates for crashing
3. Determine activity-based (direct) cost of crashing selected activities vs. indirect cost savings
4. Select activities to be crashed5. Recalculate the forward pass and
check for changes in critical path
Potential Problems with Crashing
Reduced flexibility and less margin for errorincreased risk of failure to complete project on timeRaises potential for poor qualityIncreases potential for staff burnout, stress, and turnover (from what Yourdon calls Death March projects)Raises activity-based costsMay negatively affect other projectsCreates unrealistic expectations for future projects
Crashing Example
Start
BN=9, $80,000C=6, $110,000
AN=7, $50,000C=5, $62,000
Finish
DN=8, $30,000C=6, $42,000
CN=10, $40,000C=9, $45,000
Crashing Example Cont’d
Costs to accelerate are:Activity A, $6,000/wkActivity B, $10,000/wkActivity C, $5,000/wkActivity D, $6,000/wkMakes sense to crash only those activities on the critical path(s) with the lowest acceleration cost per time period
Crashing Example Cont’d
Start
BN=9, $80,000C=6, $110,000
AN=7, $50,000C=5, $62,000
Finish
DN=8, $30,000C=6, $42,000
CN=10, $40,000C=9, $45,000
Step 1: Crash C by 1 week
Path C-D = 9 + 8 = 17
Crashing Example Cont’d
Start
BN=9, $80,000C=6, $110,000
AN=7, $50,000C=5, $62,000
Finish
DN=8, $30,000C=6, $42,000
CN=10, $40,000C=9, $45,000
Step 1: Crash C by 1 week
Step 2: Crash D by 1 week
Path C-D = 9 + 7 = 16
Crashing Example Cont’d
Start
BN=9, $80,000C=6, $110,000
AN=7, $50,000C=5, $62,000
Finish
DN=8, $30,000C=6, $42,000
CN=10, $40,000C=9, $45,000
Step 1: Crash C by 1 week
Step 2: Crash D by 1 week
Step 3: Crash D by 1 week AND crash A by 1 week. Why?